CMP 2101: Software Engineering
1.2. Process Models
Process models are general approaches for organizing a project into activities. They are a
strategy employed in software engineering that encompasses or specifies the process, tools
and methods that support the engineering process. Process models for software engineering
are chosen depending on:
• nature of the project or application at hand; large and complex, small, enterprise,
custom e.t.c;
• methods ; technical how-to's for building software; a broad array of tasks that include
requirements analysis, design, program construction, testing, and support;
• and tools (automated and semi-automated)to be used and the controls and deliverables
required.
Strengths
• It allows for compartmentalization and managerial control as scheduling is easily set.
• Milestones are easily monitored and managed using step deliverables.
• Works well for small projects.
• It is easy to use and understand
• It provides structure for inexperienced staff
3
CMP 2101: Software Engineering
Weaknesses
• The waterfall method is inflexible as ideally it discourages revisiting and revising a phase
once it's complete.
• Highly risky and not good for long or complex models which would normally require re-
visiting of phases.
• It is usually difficult for the client to state all the requirements explicitly and so
requirements may not be known well, thus it is not good for changing requirements.
• A working version of the system is only available late in the project time-span, thus
requiring customer patience as they cannot preview the product.
• It is a documentation-heavy approach, requiring documentation at every phase.
• Can give a false impression of progress – Poor progress visibility.
• Does not reflect problem-solving nature of software development – iterations of phases is
not possible.
• Requirements for the system are determined and often "frozen" at the beginning of the
development project thus the cost of changing the requirements at a later stage in the
project can be very high.
A. Incremental Model/Delivery
This type of process model combines elements of linear sequential model applied repetitively
with the iterative philosophy of prototyping. The software specification, design and
implementation are broken down into a series of increments and each are developed in turn.
Customers outline the services to be provides and identify the most and least important, then
a number of delivery increments are then defined, each increment providing a subset of the
system functionality.
The model is designed, implemented and tested as a series of incremental builds until the
product is finished.
4
CMP 2101: Software Engineering
The first increment is often the “core product”, and subsequent iterations are the supporting
functionalities or the add-on features that a customer would like to see.
B. Spiral Model
Originally proposed by Barry Boehm in his article “A Spiral Model of Software Development
and Enhancement” from 1985, this model represents the process as a spiral rather than a
sequence of activities with back tracking. It couples the iterative nature of prototyping with
the controlled and systematic aspects of the linear sequential model. The development of the
system progresses outwards in a spiral from an initial outline through to the final developed
system. Each loop in the spiral represents a phase in the process.
There are no fixed phases e.g. specification, design in this model as loops are chosen
depending on what is required. Risks are addressed and resolved throughout the process.
• Risk assessment and reduction: A detailed analysis is carried out for each of the
identified project risks and steps are taken to reduce the risk. In case the risks indicate any
kind of uncertainty in requirements, prototyping may be used to proceed with the available
data and find out possible solution in order to deal with the potential changes in the
requirements E.g. for the risk of inappropriate requirements, a prototype system may be
developed.
5
CMP 2101: Software Engineering
• Development and Validation: After risk evaluation, a development model is chosen. E.g.
If user interface risks are dominant, an appropriate development model might be
evolutionary prototyping, if the main identified risk is sub-system integration, the most
appropriate model would be waterfall model. The output of this phase is passed through all
the phases iteratively in order to obtain improvements in the same.
• Planning: The project is reviewed and a decision made to continue with a further loop of
the spiral. If it is decided to continue, plans are drawn up or the next phase of the project.
6
CMP 2101: Software Engineering
The RAD model encompasses the following phases:
a) Business modeling
The information flow among business functions is modeled in a way that the following
questions are answered:
What information drives the business process?
What information is generated?
Who generates it?
Where does the information go?
Who processes it?
b) Data modeling
The information flow defined as part of the business modeling phase is refined into a set
of data objects that are needed to support the business. The characteristics (called
attributes) of each object are identified and the relationships between these objects are
defined.
c) Process modeling
The data objects defined in the data-modeling phase are transformed to achieve the
information flow necessary to implement a business function. Processing descriptions are
created for adding, modifying, deleting, or retrieving a data object.
d) Application generation
RAD assumes the use of the RAD fourth generation techniques and tools like Visual
Basic, Visual C++, Delphi etc rather than creating software using conventional third
generation programming languages. The RAD works to reuse existing program
components (when possible) or create reusable components (when necessary). In all
cases, automated tools are used to facilitate construction of the software.
7
CMP 2101: Software Engineering
Applicable:
• Primarily for information systems applications.
• Where requirements are well understood.
• If a business application can be modularized so that each major function can be
completed within the development cycle.
RAD Advantages
• A system can be developed in a short time.
• There is early visibility due to prototyping.
• The methodology provides greater flexibility because the developers can redesign
almost at will.
• Reduced manual coding since automation tools, code generators and code reuse are
involved. This also means less defects possible
• Increased user involvement because they are represented on the team at all times.
RAD Disadvantages
• Requires sufficient human resources to create the right number of RAD teams, for large
but scalable projects.
• Requires committed developers and customers to the ‘rapid-fire’ activities to get a
system complete in a short time frame otherwise RAD fails.
• If a system cannot be properly modularized, building components for RAD will be
problematic.
• It is not appropriate when technical risks are high, e.g. when a new application makes
heavy use of new technology.
1.3.4. V-Model
This model is presumed to be the extension of the waterfall model. The only difference is that
instead of moving down in a linear way, the process steps are bent upwards after the
coding phase (implementation), to form the typical V shape.
The horizontal and vertical axes represents time or project completeness (left-to-right) and
level of abstraction (coarsest-grain abstraction uppermost), respectively.
8
CMP 2101: Software Engineering
Figure 5: V-Model
Advantages
• It is simple and easy to use.
• Each phase has specific deliverables.
• Higher chance of success over the waterfall model due to the development of test plans
early on during the life cycle.
• Works well for small projects where requirements are easily understood.
Disadvantages
• Very rigid, like the waterfall model.
• Adjusting scope is difficult and expensive.
• Software is developed during the implementation phase, so no early prototypes of the
software are produced.
• This model doesn’t provide a clear path for problems found during testing phases.
• It does not easily handle concurrent events.
• It does not contain risk analysis activities.
9
CMP 2101: Software Engineering
Prototyping Model is used for:
• Understanding the requirements for the user interface
• Examining feasibility of a proposed design approach
• Exploring system performance issues
Disadvantages:
• Clients usually treat the prototype as the final solution or expect only a few changes to the
prototype and thus try to rush through, giving little consideration to the quality
requirements for the solution.
• On the other hand there is the temptation for the development team to loose focus of the
real purpose of the prototype and thus compromise the quality of the product e.g. using an
inappropriate programming language.
• Prototype is only a partial specification and not the product itself.
This process recognizes that the traditional waterfall approach can be inefficient because it
idles key team members for extended periods of time. Many feel that the waterfall approach
also introduces a lot of risk because it defers testing and integration until the end of the
project lifecycle.
RUP is highly flexible in its developmental path, as any stage can be updated at any time. It
uses an iterative, incremental approach for object -oriented development.
Different process stakeholders may see the RUP from different perspectives which also
double as its definition. Below are three examples of typical perspectives into a RUP based
process:
• A dynamic perspective.
• A static perspective.
• A practice perspective.
A. Dynamic perspective
This shows the phases of the model over time. It is four phased:
1. Inception
This phase centres on assessing needs, requirements, viability and feasibility of the
program or project as the developers define the scope of the project and its business case.
2. Elaboration
The developers analyze the project's needs in greater detail and define its architectural
foundation. They measure the architecture of the system's appropriateness based on the
project needs.
3. Construction
In this phase, the actual software system is made by developing components and features.
It also includes the first release of the developed software.
4. Transition
10
CMP 2101: Software Engineering
This stage marks the end of the development cycle, if all objectives are met. It includes
training of the end users, beta testing and the final implementation of the system.
Each phase is organised into a number of separate iterations which must satisfy certain
criteria. At the end of each iteration, RUP provides a prototype.
B. A static perspective
This perspective shows the process activities (workflows) that are enacted within the phases.
A workflow is a set of activities.
Sample core workflows include:
• Business modeling – Requirements capture
• Requirements – Use case model
• Analysis – Analysis model(i.e conceptual object model)
• Design – Design model(e.g classes, use case realizations)
• Implementation – Implementation model (components)
• Test – Test model (test cases)
C. A static perspective
This suggests good practices to be used during the process:
• Develop software iteratively
• Manage requirements
• Use component-based architectures
• Visually model software
• Verify software quality
• Control changes to software
11
CMP 2101: Software Engineering
1.3.7. Agile Development
This model appeared in the 90’s as a reaction to the strict Waterfall method. Software is
developed progressively with each new release adding more capabilities and it eemphasizes
flexibility during the software development process.
It reduces risk by breaking projects into small, time-limited modules ("iterations"), each of
which is approached like a small, self-contained mini-project, lasting only a few weeks
(analysis, design, production, testing and documentation). It is intended that even though
iterations may not add enough functionality to warrant releasing the product, there will be a
new software release at the end of every iteration. In addition, at the end of each iteration, the
project's priorities, direction and progress are re-evaluated.
Key Emphases:
• Two-person(pair) programming teams - Two programmers work together on the problem
exchanging information and insight and sharing skills and the advantages of this pair
programming setup include:
1. There is more and better communication among the developers.
2. Higher levels of productivity
3. Higher quality code
4. Reinforcement of code-and-test discipline with test suites designed first before any
coding has to be done.
12
CMP 2101: Software Engineering
• Customer on-site during development (part of developer team)
All phases of the life cycle converge into a series of activities based on coding, testing,
listening, and designing.
Coding and testing are closely related parts of the process and the programmers write code
and develop tests for it too and this code is tested immediately after it is written; if the test is
successful, development proceeds; otherwise rework code. It is emphasised that testing is
only to be done not on everything, but on those things that can break or go wrong.
Strengths
• Empowers developers to confidently respond to the changing customer requirements, even
late in the lifecycle.
• Emphasizes collaborative teamwork as the team self organizes around the problem at
hand.
Weaknesses
• Detailed specifications are not created or preserved.
• Programmers are required to work in pairs - not all software developers expect to be asked
to work this way.
• Most of the design activity takes place on the fly and incrementally, starting with "the
simplest thing that could possibly work" and adding complexity only when it's required by
failing tests. This could result in more re-design effort than only re-designing when
requirements change.
The role of the ‘customer representative is attached to the project’ can become a single-point-
of-failure for the project and some people have found it to be a source of stress.