Proposed Library Block-Main Campus For Rongo University
Proposed Library Block-Main Campus For Rongo University
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
1 PROPOSED LIBRARY BLOCK‐MAIN CAMPUS FOR 456 days Tue 1/1/19 Tue 9/29/20
RONGO UNIVERSITY
2 SITE CLEARANCE 14 days Tue 1/1/19 Fri 1/18/19
3 SITE MOBILIZATION 21 days Thu 1/10/19 Thu 2/7/19
4 SITE OFFICES 21 days Thu 1/10/19 Thu 2/7/19 2SS+7 days
5 PLANT AND EQUIPMENT 21 days Thu 1/10/19 Thu 2/7/19 4SS
6 DRAWING AND DETAILS 45 days Thu 1/10/19 Wed 3/13/19
7 ARCHITECTURAL DRAWINGS 45 days Thu 1/10/19 Wed 3/13/19 4SS
8 STRUCTURAL AND CIVIL DRAWINGS 45 days Thu 1/10/19 Wed 3/13/19 4SS
9 SERVICE LAYOUTS 45 days Thu 1/10/19 Wed 3/13/19 4SS
10 SHELL CONSTRUCTION 434 days Thu 1/17/19 Tue 9/15/20
11 BASEMENT & SUBSTRUCTURES 53 days Thu 1/17/19 Mon 4/1/19
12 SETTING OUT 2 days Thu 1/17/19 Fri 1/18/19 4SS+5 days
13 APPROVAL 1 day Mon 1/21/19 Mon 1/21/19 12
14 EXCAVATION 15 days Mon 1/21/19 Fri 2/8/19 12
15 HARDCORE FILLING BELOW BLINDING 12 days Mon 1/28/19 Tue 2/12/19 14FF+2 days
16 ANTI TERMITE TREATMENT 10 days Wed 1/30/19 Tue 2/12/19 15FF
17 BLINDING 10 days Fri 2/1/19 Thu 2/14/19 16FF+2 days
18 FOUNDATION FOR COLUMNS, LIFTS, 39 days Wed 2/6/19 Mon 4/1/19
SHEAR WALL, RAMPS & STAIRCASE
19 FORMWORK 7 days Fri 2/8/19 Mon 2/18/19 17FF+2 days
20 REINFORCEMENT 10 days Wed 2/6/19 Tue 2/19/19 19FF+1 day
21 APPROVAL 10 days Thu 2/7/19 Wed 2/20/19 20FF+1 day
22 CONCRETE 7 days Wed 2/13/19 Thu 2/21/19 21FF+1 day
23 BASEMENT 25 days Tue 2/26/19 Mon 4/1/19
24 COLUMNS, LIFTS, SHEAR WALL, 15 days Tue 2/26/19 Mon 3/18/19
RAMPS & STAIRCASE
25 REINFORCEMENT 12 days Tue 2/26/19 Wed 3/13/19 22FS+2 days
26 FORMWORK 10 days Mon 3/4/19 Fri 3/15/19 25FF+2 days
27 CONCRETE 10 days Tue 3/5/19 Mon 3/18/19 26FF+1 day
28 BEAMS, SLAB 18 days Thu 3/7/19 Mon 4/1/19
29 FORMWORK 15 days Thu 3/7/19 Wed 3/27/19 27SS+2 days
30 REINFORCEMENT 15 days Fri 3/8/19 Thu 3/28/19 29FF+1 day
31 APPROVAL 12 days Wed 3/13/19 Thu 3/28/19 30FF
32 CONCRETE 2 days Fri 3/29/19 Mon 4/1/19 31
33 SUPERSTRUCTURE 208 days Fri 4/5/19 Tue 1/21/20
34 GROUND FLOOR 28 days Fri 4/5/19 Tue 5/14/19
35 COLUMN, LIFT AND STAIRCASE 23 days Fri 4/5/19 Tue 5/7/19
36 REINFORCEMENT 20 days Fri 4/5/19 Thu 5/2/19 32FS+3 days
37 FORMWORK 18 days Thu 4/11/19 Mon 5/6/19 36FF+2 days
38 CONCRETE 18 days Fri 4/12/19 Tue 5/7/19 37FF+1 day
Page 1
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
39 BEAMS, SLAB 21 days Tue 4/16/19 Tue 5/14/19
40 FORMWORK 18 days Tue 4/16/19 Thu 5/9/19 38SS+2 days
41 REINFORCEMENT 18 days Wed 4/17/19 Fri 5/10/19 40FF+1 day
42 APPROVAL 12 days Thu 4/25/19 Fri 5/10/19 41FF
43 CONCRETE 2 days Mon 5/13/19 Tue 5/14/19 42
44 1st FLOOR 42 days Mon 5/20/19 Tue 7/16/19
45 COLUMN, LIFT AND STAIRCASE 23 days Mon 5/20/19 Wed 6/19/19
46 REINFORCEMENT 20 days Mon 5/20/19 Fri 6/14/19 43FS+3 days
47 FORMWORK 18 days Fri 5/24/19 Tue 6/18/19 46FF+2 days
48 CONCRETE 18 days Mon 5/27/19 Wed 6/19/19 47FF+1 day
49 BEAMS, SLAB 21 days Tue 6/18/19 Tue 7/16/19
50 FORMWORK 18 days Tue 6/18/19 Thu 7/11/19 48FS‐2 days
51 REINFORCEMENT 18 days Wed 6/19/19 Fri 7/12/19 50FF+1 day
52 APPROVAL 12 days Thu 6/27/19 Fri 7/12/19 51FF
53 CONCRETE 2 days Mon 7/15/19 Tue 7/16/19 52
54 2nd FLOOR 42 days Mon 7/22/19 Tue 9/17/19
55 COLUMN, LIFT AND STAIRCASE 23 days Mon 7/22/19 Wed 8/21/19
56 REINFORCEMENT 20 days Mon 7/22/19 Fri 8/16/19 53FS+3 days
57 FORMWORK 18 days Fri 7/26/19 Tue 8/20/19 56FF+2 days
58 CONCRETE 18 days Mon 7/29/19 Wed 8/21/19 57FF+1 day
59 BEAMS, SLAB 21 days Tue 8/20/19 Tue 9/17/19
60 FORMWORK 18 days Tue 8/20/19 Thu 9/12/19 58FS‐2 days
61 REINFORCEMENT 18 days Wed 8/21/19 Fri 9/13/19 60FF+1 day
62 APPROVAL 12 days Thu 8/29/19 Fri 9/13/19 61FF
63 CONCRETE 2 days Mon 9/16/19 Tue 9/17/19 62
64 3rd FLOOR 42 days Mon 9/23/19 Tue 11/19/19
65 COLUMN, LIFT AND STAIRCASE 23 days Mon 9/23/19 Wed 10/23/19
66 REINFORCEMENT 20 days Mon 9/23/19 Fri 10/18/19 63FS+3 days
67 FORMWORK 18 days Fri 9/27/19 Tue 10/22/19 66FF+2 days
68 CONCRETE 18 days Mon 9/30/19 Wed 10/23/19 67FF+1 day
69 BEAMS, SLAB 21 days Tue 10/22/19 Tue 11/19/19
70 FORMWORK 18 days Tue 10/22/19 Thu 11/14/19 68FS‐2 days
71 REINFORCEMENT 18 days Wed 10/23/19 Fri 11/15/19 70FF+1 day
72 APPROVAL 12 days Thu 10/31/19 Fri 11/15/19 71FF
73 CONCRETE 2 days Mon 11/18/19 Tue 11/19/19 72
74 4th FLOOR 42 days Mon 11/25/19 Tue 1/21/20
75 COLUMN, LIFT AND STAIRCASE 23 days Mon 11/25/19 Wed 12/25/19
76 REINFORCEMENT 20 days Mon 11/25/19 Fri 12/20/19 73FS+3 days
77 FORMWORK 18 days Fri 11/29/19 Tue 12/24/19 76FF+2 days
78 CONCRETE 18 days Mon 12/2/19 Wed 12/25/19 77FF+1 day
79 BEAMS, SLAB 21 days Tue 12/24/19 Tue 1/21/20
Task Project Summary Manual Task Start-only Deadline
Page 2
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
80 FORMWORK 18 days Tue 12/24/19 Thu 1/16/20 78FS‐2 days
81 REINFORCEMENT 18 days Wed 12/25/19 Fri 1/17/20 80FF+1 day
82 APPROVAL 12 days Thu 1/2/20 Fri 1/17/20 81FF
83 CONCRETE 2 days Mon 1/20/20 Tue 1/21/20 82
84 WALLING AND PARTITION 230 days Wed 5/15/19 Tue 3/31/20
85 PARKING BASEMENT 15 days Wed 5/15/19 Tue 6/4/19 43
86 GROUND FLOOR 25 days Wed 7/17/19 Tue 8/20/19 53
87 1st FLOOR 25 days Wed 9/18/19 Tue 10/22/19 63
88 2nd FLOOR 25 days Wed 11/20/19 Tue 12/24/19 73
89 3rd FLOOR 25 days Wed 1/22/20 Tue 2/25/20 83
90 4th FLOOR 25 days Wed 2/26/20 Tue 3/31/20 89
91 RENDERING WORK 240 days Mon 6/10/19 Fri 5/8/20
92 PARKING BASEMENT 15 days Mon 6/10/19 Fri 6/28/19 85FS+3 days
93 GROUND FLOOR 25 days Mon 8/26/19 Fri 9/27/19 86FS+3 days
94 1st FLOOR 25 days Mon 10/28/19 Fri 11/29/19 87FS+3 days
95 2nd FLOOR 25 days Mon 12/30/19 Fri 1/31/20 88FS+3 days
96 3rd FLOOR 25 days Mon 3/2/20 Fri 4/3/20 89FS+3 days
97 4th FLOOR 25 days Mon 4/6/20 Fri 5/8/20 90FS+3 days
98 FINISHES 241 days Mon 9/30/19 Mon 8/31/20
99 EXTERNAL FINISHES 100 days Wed 4/1/20 Tue 8/18/20 90
100 INTERNAL FINISHES 241 days Mon 9/30/19 Mon 8/31/20
101 CEILING FINISHES 190 days Mon 9/30/19 Fri 6/19/20
102 PARKING BASEMENT 15 days Mon 9/30/19 Fri 10/18/19 93
103 GROUND FLOOR 15 days Mon 12/2/19 Fri 12/20/19 94
104 1st FLOOR 15 days Mon 2/3/20 Fri 2/21/20 95
105 2nd FLOOR 15 days Mon 4/6/20 Fri 4/24/20 96
106 3rd FLOOR 15 days Mon 5/11/20 Fri 5/29/20 97
107 4th FLOOR 15 days Mon 6/1/20 Fri 6/19/20 106
108 FLOOR FINISHES 190 days Mon 10/21/19 Fri 7/10/20
109 PARKING BASEMENT 15 days Mon 10/21/19 Fri 11/8/19 102
110 GROUND FLOOR 15 days Mon 12/23/19 Fri 1/10/20 103
111 1st FLOOR 15 days Mon 2/24/20 Fri 3/13/20 104
112 2nd FLOOR 15 days Mon 4/27/20 Fri 5/15/20 105
113 3rd FLOOR 15 days Mon 6/1/20 Fri 6/19/20 106
114 4th FLOOR 15 days Mon 6/22/20 Fri 7/10/20 107
115 DOOR AND WINDOW 193 days Mon 11/11/19 Wed 8/5/20
116 PARKING BASEMENT 15 days Mon 11/11/19 Fri 11/29/19 109
117 GROUND FLOOR 18 days Mon 1/13/20 Wed 2/5/20 110
118 1st FLOOR 18 days Mon 3/16/20 Wed 4/8/20 111
119 2nd FLOOR 18 days Mon 5/18/20 Wed 6/10/20 112
120 3rd FLOOR 18 days Mon 6/22/20 Wed 7/15/20 113
Task Project Summary Manual Task Start-only Deadline
Page 3
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
121 4th FLOOR 18 days Mon 7/13/20 Wed 8/5/20 114
122 WALL FINISHES 196 days Mon 12/2/19 Mon 8/31/20
123 PARKING BASEMENT 15 days Mon 12/2/19 Fri 12/20/19 116
124 GROUND FLOOR 18 days Thu 2/6/20 Mon 3/2/20 117
125 1st FLOOR 18 days Thu 4/9/20 Mon 5/4/20 118
126 2nd FLOOR 18 days Thu 6/11/20 Mon 7/6/20 119
127 3rd FLOOR 18 days Thu 7/16/20 Mon 8/10/20 120
128 4th FLOOR 18 days Thu 8/6/20 Mon 8/31/20 121
129 EXTERNAL WORKS AND SERVICES 120 days Wed 4/1/20 Tue 9/15/20
130 OAVED AREAS & CARPARKS 60 days Wed 4/1/20 Tue 6/23/20 90
131 STORM WATER DRAINAGE 30 days Wed 6/24/20 Tue 8/4/20 130
132 FOUL WATER DRAINAGE 30 days Wed 8/5/20 Tue 9/15/20 131
133 LANDSCAPPING 30 days Wed 6/24/20 Tue 8/4/20 131SS
134 GENERATOR ROOM 30 days Wed 6/24/20 Tue 8/4/20 131SS
135 SNAGGING & DESNAGGING 30 days Wed 8/5/20 Tue 9/15/20 134
136 CLEANING AND HANDOVER 30 days Wed 8/19/20 Tue 9/29/20 135FF+10 days
Page 4