Proposed Library Block-Main Campus For Rongo University

The document outlines the proposed schedule for construction of a new library block at Rongo University over 456 days from January 2019 to September 2020. It involves site clearance, mobilization, drawing and detailing, shell construction including the basement, superstructure of 3 floors, and services layout. Key activities include excavation, reinforcement, formwork and concrete works for the foundations, columns, beams, slabs and other structural elements.

Uploaded by

Shreekant Kerai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
89 views4 pages

Proposed Library Block-Main Campus For Rongo University

The document outlines the proposed schedule for construction of a new library block at Rongo University over 456 days from January 2019 to September 2020. It involves site clearance, mobilization, drawing and detailing, shell construction including the basement, superstructure of 3 floors, and services layout. Key activities include excavation, reinforcement, formwork and concrete works for the foundations, columns, beams, slabs and other structural elements.

Uploaded by

Shreekant Kerai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY

ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
1 PROPOSED LIBRARY BLOCK‐MAIN CAMPUS FOR  456 days Tue 1/1/19 Tue 9/29/20
RONGO UNIVERSITY
2 SITE CLEARANCE 14 days Tue 1/1/19 Fri 1/18/19
3 SITE MOBILIZATION 21 days Thu 1/10/19 Thu 2/7/19
4 SITE OFFICES 21 days Thu 1/10/19 Thu 2/7/19 2SS+7 days
5 PLANT AND EQUIPMENT 21 days Thu 1/10/19 Thu 2/7/19 4SS
6 DRAWING AND DETAILS 45 days Thu 1/10/19 Wed 3/13/19
7 ARCHITECTURAL DRAWINGS 45 days Thu 1/10/19 Wed 3/13/19 4SS
8 STRUCTURAL AND CIVIL DRAWINGS 45 days Thu 1/10/19 Wed 3/13/19 4SS
9 SERVICE LAYOUTS 45 days Thu 1/10/19 Wed 3/13/19 4SS
10 SHELL CONSTRUCTION 434 days Thu 1/17/19 Tue 9/15/20
11 BASEMENT & SUBSTRUCTURES 53 days Thu 1/17/19 Mon 4/1/19
12 SETTING OUT 2 days Thu 1/17/19 Fri 1/18/19 4SS+5 days
13 APPROVAL 1 day Mon 1/21/19 Mon 1/21/19 12
14 EXCAVATION 15 days Mon 1/21/19 Fri 2/8/19 12
15 HARDCORE FILLING BELOW BLINDING 12 days Mon 1/28/19 Tue 2/12/19 14FF+2 days
16 ANTI TERMITE TREATMENT 10 days Wed 1/30/19 Tue 2/12/19 15FF
17 BLINDING 10 days Fri 2/1/19 Thu 2/14/19 16FF+2 days
18 FOUNDATION FOR COLUMNS, LIFTS,  39 days Wed 2/6/19 Mon 4/1/19
SHEAR WALL, RAMPS & STAIRCASE
19 FORMWORK 7 days Fri 2/8/19 Mon 2/18/19 17FF+2 days
20 REINFORCEMENT 10 days Wed 2/6/19 Tue 2/19/19 19FF+1 day
21 APPROVAL 10 days Thu 2/7/19 Wed 2/20/19 20FF+1 day
22 CONCRETE 7 days Wed 2/13/19 Thu 2/21/19 21FF+1 day
23  BASEMENT 25 days Tue 2/26/19 Mon 4/1/19
24 COLUMNS, LIFTS, SHEAR WALL,  15 days Tue 2/26/19 Mon 3/18/19
RAMPS & STAIRCASE
25 REINFORCEMENT 12 days Tue 2/26/19 Wed 3/13/19 22FS+2 days
26 FORMWORK 10 days Mon 3/4/19 Fri 3/15/19 25FF+2 days
27 CONCRETE 10 days Tue 3/5/19 Mon 3/18/19 26FF+1 day
28 BEAMS, SLAB 18 days Thu 3/7/19 Mon 4/1/19
29 FORMWORK 15 days Thu 3/7/19 Wed 3/27/19 27SS+2 days
30 REINFORCEMENT 15 days Fri 3/8/19 Thu 3/28/19 29FF+1 day
31 APPROVAL 12 days Wed 3/13/19 Thu 3/28/19 30FF
32 CONCRETE 2 days Fri 3/29/19 Mon 4/1/19 31
33 SUPERSTRUCTURE 208 days Fri 4/5/19 Tue 1/21/20
34 GROUND FLOOR 28 days Fri 4/5/19 Tue 5/14/19
35 COLUMN, LIFT AND STAIRCASE 23 days Fri 4/5/19 Tue 5/7/19
36 REINFORCEMENT 20 days Fri 4/5/19 Thu 5/2/19 32FS+3 days
37 FORMWORK 18 days Thu 4/11/19 Mon 5/6/19 36FF+2 days
38 CONCRETE 18 days Fri 4/12/19 Tue 5/7/19 37FF+1 day

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: Project PROGRAM
Date: Mon 11/26/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
39  BEAMS, SLAB 21 days Tue 4/16/19 Tue 5/14/19
40   FORMWORK 18 days Tue 4/16/19 Thu 5/9/19 38SS+2 days
41   REINFORCEMENT 18 days Wed 4/17/19 Fri 5/10/19 40FF+1 day
42   APPROVAL 12 days Thu 4/25/19 Fri 5/10/19 41FF
43   CONCRETE 2 days Mon 5/13/19 Tue 5/14/19 42
44 1st FLOOR 42 days Mon 5/20/19 Tue 7/16/19
45  COLUMN, LIFT AND STAIRCASE 23 days Mon 5/20/19 Wed 6/19/19
46  REINFORCEMENT 20 days Mon 5/20/19 Fri 6/14/19 43FS+3 days
47  FORMWORK 18 days Fri 5/24/19 Tue 6/18/19 46FF+2 days
48  CONCRETE 18 days Mon 5/27/19 Wed 6/19/19 47FF+1 day
49   BEAMS, SLAB 21 days Tue 6/18/19 Tue 7/16/19
50    FORMWORK 18 days Tue 6/18/19 Thu 7/11/19 48FS‐2 days
51    REINFORCEMENT 18 days Wed 6/19/19 Fri 7/12/19 50FF+1 day
52    APPROVAL 12 days Thu 6/27/19 Fri 7/12/19 51FF
53    CONCRETE 2 days Mon 7/15/19 Tue 7/16/19 52
54 2nd FLOOR 42 days Mon 7/22/19 Tue 9/17/19
55   COLUMN, LIFT AND STAIRCASE 23 days Mon 7/22/19 Wed 8/21/19
56   REINFORCEMENT 20 days Mon 7/22/19 Fri 8/16/19 53FS+3 days
57   FORMWORK 18 days Fri 7/26/19 Tue 8/20/19 56FF+2 days
58   CONCRETE 18 days Mon 7/29/19 Wed 8/21/19 57FF+1 day
59    BEAMS, SLAB 21 days Tue 8/20/19 Tue 9/17/19
60     FORMWORK 18 days Tue 8/20/19 Thu 9/12/19 58FS‐2 days
61     REINFORCEMENT 18 days Wed 8/21/19 Fri 9/13/19 60FF+1 day
62     APPROVAL 12 days Thu 8/29/19 Fri 9/13/19 61FF
63     CONCRETE 2 days Mon 9/16/19 Tue 9/17/19 62
64 3rd FLOOR 42 days Mon 9/23/19 Tue 11/19/19
65    COLUMN, LIFT AND STAIRCASE 23 days Mon 9/23/19 Wed 10/23/19
66    REINFORCEMENT 20 days Mon 9/23/19 Fri 10/18/19 63FS+3 days
67    FORMWORK 18 days Fri 9/27/19 Tue 10/22/19 66FF+2 days
68    CONCRETE 18 days Mon 9/30/19 Wed 10/23/19 67FF+1 day
69     BEAMS, SLAB 21 days Tue 10/22/19 Tue 11/19/19
70      FORMWORK 18 days Tue 10/22/19 Thu 11/14/19 68FS‐2 days
71      REINFORCEMENT 18 days Wed 10/23/19 Fri 11/15/19 70FF+1 day
72      APPROVAL 12 days Thu 10/31/19 Fri 11/15/19 71FF
73      CONCRETE 2 days Mon 11/18/19 Tue 11/19/19 72
74 4th FLOOR 42 days Mon 11/25/19 Tue 1/21/20
75     COLUMN, LIFT AND STAIRCASE 23 days Mon 11/25/19 Wed 12/25/19
76     REINFORCEMENT 20 days Mon 11/25/19 Fri 12/20/19 73FS+3 days
77     FORMWORK 18 days Fri 11/29/19 Tue 12/24/19 76FF+2 days
78     CONCRETE 18 days Mon 12/2/19 Wed 12/25/19 77FF+1 day
79      BEAMS, SLAB 21 days Tue 12/24/19 Tue 1/21/20
Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: Project PROGRAM
Date: Mon 11/26/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 2
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
80       FORMWORK 18 days Tue 12/24/19 Thu 1/16/20 78FS‐2 days
81       REINFORCEMENT 18 days Wed 12/25/19 Fri 1/17/20 80FF+1 day
82       APPROVAL 12 days Thu 1/2/20 Fri 1/17/20 81FF
83       CONCRETE 2 days Mon 1/20/20 Tue 1/21/20 82
84 WALLING AND PARTITION 230 days Wed 5/15/19 Tue 3/31/20
85 PARKING BASEMENT  15 days Wed 5/15/19 Tue 6/4/19 43
86 GROUND FLOOR 25 days Wed 7/17/19 Tue 8/20/19 53
87 1st FLOOR 25 days Wed 9/18/19 Tue 10/22/19 63
88 2nd FLOOR 25 days Wed 11/20/19 Tue 12/24/19 73
89 3rd FLOOR 25 days Wed 1/22/20 Tue 2/25/20 83
90 4th FLOOR 25 days Wed 2/26/20 Tue 3/31/20 89
91 RENDERING WORK 240 days Mon 6/10/19 Fri 5/8/20
92 PARKING BASEMENT  15 days Mon 6/10/19 Fri 6/28/19 85FS+3 days
93 GROUND FLOOR 25 days Mon 8/26/19 Fri 9/27/19 86FS+3 days
94 1st FLOOR 25 days Mon 10/28/19 Fri 11/29/19 87FS+3 days
95 2nd FLOOR 25 days Mon 12/30/19 Fri 1/31/20 88FS+3 days
96 3rd FLOOR 25 days Mon 3/2/20 Fri 4/3/20 89FS+3 days
97 4th FLOOR 25 days Mon 4/6/20 Fri 5/8/20 90FS+3 days
98 FINISHES 241 days Mon 9/30/19 Mon 8/31/20
99 EXTERNAL FINISHES 100 days Wed 4/1/20 Tue 8/18/20 90
100 INTERNAL FINISHES 241 days Mon 9/30/19 Mon 8/31/20
101 CEILING FINISHES 190 days Mon 9/30/19 Fri 6/19/20
102 PARKING BASEMENT  15 days Mon 9/30/19 Fri 10/18/19 93
103 GROUND FLOOR 15 days Mon 12/2/19 Fri 12/20/19 94
104 1st FLOOR 15 days Mon 2/3/20 Fri 2/21/20 95
105 2nd FLOOR 15 days Mon 4/6/20 Fri 4/24/20 96
106 3rd FLOOR 15 days Mon 5/11/20 Fri 5/29/20 97
107 4th FLOOR 15 days Mon 6/1/20 Fri 6/19/20 106
108 FLOOR FINISHES 190 days Mon 10/21/19 Fri 7/10/20
109 PARKING BASEMENT  15 days Mon 10/21/19 Fri 11/8/19 102
110 GROUND FLOOR 15 days Mon 12/23/19 Fri 1/10/20 103
111 1st FLOOR 15 days Mon 2/24/20 Fri 3/13/20 104
112 2nd FLOOR 15 days Mon 4/27/20 Fri 5/15/20 105
113 3rd FLOOR 15 days Mon 6/1/20 Fri 6/19/20 106
114 4th FLOOR 15 days Mon 6/22/20 Fri 7/10/20 107
115 DOOR AND WINDOW 193 days Mon 11/11/19 Wed 8/5/20
116 PARKING BASEMENT  15 days Mon 11/11/19 Fri 11/29/19 109
117 GROUND FLOOR 18 days Mon 1/13/20 Wed 2/5/20 110
118 1st FLOOR 18 days Mon 3/16/20 Wed 4/8/20 111
119 2nd FLOOR 18 days Mon 5/18/20 Wed 6/10/20 112
120 3rd FLOOR 18 days Mon 6/22/20 Wed 7/15/20 113
Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: Project PROGRAM
Date: Mon 11/26/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 3
PROPOSED LIBRARY BLOCK-MAIN CAMPUS FOR RONGO UNIVERSITY
ID Task Task Name Duration Start Finish Predecessors Half 1, 2019 Half 2, 2019 Half 1, 2020 Half 2, 2020
Mode D J F M A M J J A S O N D J F M A M J J A S O
121 4th FLOOR 18 days Mon 7/13/20 Wed 8/5/20 114
122 WALL FINISHES 196 days Mon 12/2/19 Mon 8/31/20
123 PARKING BASEMENT  15 days Mon 12/2/19 Fri 12/20/19 116
124 GROUND FLOOR 18 days Thu 2/6/20 Mon 3/2/20 117
125 1st FLOOR 18 days Thu 4/9/20 Mon 5/4/20 118
126 2nd FLOOR 18 days Thu 6/11/20 Mon 7/6/20 119
127 3rd FLOOR 18 days Thu 7/16/20 Mon 8/10/20 120
128 4th FLOOR 18 days Thu 8/6/20 Mon 8/31/20 121
129 EXTERNAL WORKS AND SERVICES 120 days Wed 4/1/20 Tue 9/15/20
130 OAVED AREAS & CARPARKS 60 days Wed 4/1/20 Tue 6/23/20 90
131 STORM WATER DRAINAGE 30 days Wed 6/24/20 Tue 8/4/20 130
132 FOUL WATER DRAINAGE 30 days Wed 8/5/20 Tue 9/15/20 131
133 LANDSCAPPING 30 days Wed 6/24/20 Tue 8/4/20 131SS
134 GENERATOR ROOM 30 days Wed 6/24/20 Tue 8/4/20 131SS
135 SNAGGING & DESNAGGING 30 days Wed 8/5/20 Tue 9/15/20 134
136 CLEANING AND HANDOVER 30 days Wed 8/19/20 Tue 9/29/20 135FF+10 days

Task Project Summary Manual Task Start-only Deadline

Split Inactive Task Duration-only Finish-only Progress


Project: Project PROGRAM
Date: Mon 11/26/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 4