Thrustboring Construction Company (TCC LTD.) : An Introduction Prepared BY
Thrustboring Construction Company (TCC LTD.) : An Introduction Prepared BY
18/08/2007
An Introduction prepared
BY
c Keywords.
Pipe Jacking.
Auger Boring.
Micro Tunneling.
Conclusion.
Open Cut is the method by which access is gained by excavation from the ground level to
the required underground level for installation, maintenance, or inspection of pipes,
conduits, cables, etc.
m Manentry is the term applied for any trenchless technique, which requires an operative to
enter a pipe, duct or bore. The minimum size for which this is permissible is generally
defined by national health and safety legislation (>go0 mm in the UK).
Basic problem with traditional trench construction work for utilities is that only a relatively small
Proportion of the cross sectional area of the trench is occupied by the utility pipe or cable. On
the other hand, trenchless technique methods employ minimum excavation approach. This
means less removal of soil, minimum replacement of bacMill and shorter time for the work.
'I
I 18/08/2007
Therefore, trenchless technology methods, in general, provide safer job sites to the public,
more environmentally friendly and these projects are much economical in difficutt soil
conditions and in urban areas. The following picture shows the general discomfort caused by
an open cut in a populated area.
Some advantages of trenchless construction techniques compared with traditional open cut
approach:-
m More environmentallyfriendly.
THRUSTBORING CONSTRUCTION COMPANY LTD. P.O. BOX 31803, AL-KHOBAR 31952 KSA
PHONE+96638682100 FAX+9@38682096 [email protected]
TRENCHLESS TECHNIQUES PAGE 4 OF 9
1wwm7
In N. America, the impetus was quite different from that in Japan. The need for long pipelines,
crossing environmentally sensitive tenitories, encouraged the use of Horizontal Directional
Drilling (HDD). The need was initially to drill a pilot hole under obstacles and then to enlarge it
to a size allowing product pipe installation. Steerable HDD rigs enabled contractors to drive a
hole from surface to surface under obstacles with a minimum damage to the environment. This
technology has also reduced the pipe installation times and expenditures compared to
traditional open cut.
The aim of any trenchless technique is to build a line in ground with a minimum excavation
on surface. The most popular techniques implemented in pipelining and utility construction
industries are as follows:-
Pipejacking
Augerboring
Microtunnelling
The jacking shield consists of steel cylinder from which operator's carry out excavation by hand
held tools. Spoil is hauled to surface by means of trolley or suction systems. When enough
excavation is done in front of the tunnel, pipes are pushed forward by hydraulic jacks, which
are located in the thrusting pit. When all length of a pipe segment is entered in to the ground,
jacking cylinders are retreated and a new pipe segment is added to the string at the drive shaft.
Being the simplest technique, pipejacking is only applicable in stable ground without saturated
soils. The drives are limited in length and steering is done manually.
THRUSTBORING CONSTRUCTION COMPANY LTD. p.0. BOX 31803, AL-KHOBAR 31952 KSA
F'HONE + 966 3 868 2100 FAX + 9663 868 2096 E-MAIL [email protected]
TRENCHLESS TECHNIQUES PAGE 5 OF 9
181WMO7
40-60 metres
Data Diameters 0900 mm (036")and above
L
Materials RCP, Steel and Vitrified Clay
Augerboring is a non man-enfq technique and consists of a cutting head attached to a helical
auger. The rotation of auger flights simultaneously rotates cutting head and removes spoil from
the tunnel. As the cutting head advances, pipes are driven into ground by means of surface
jacks. Augerboring systems are non-steerable so the line and level of boring are set at the
drive pit by guidance rails. Any deflection of the tunnel axis from planned alignment is usually
not correctable. Augerboring technique is most suitable for short crossing with cohesive soil.
Auger Flights.
. ..
. . ... ..
Cutting Head Casing P i p .. .
.. ..
.. ..
Although it is still used in some places because of low investment cost, augerboring technique
has some disadvantages. It can not be applied in saturated soils because of ground collapse
risk. In addition to that, this technique may over excavate the annular space that may settle
with time and damage the nearby structures and installation itself. The following table shows
an overview of augerboring technique.
Advantages No disruption to traffic. Low noise level. Applicable only above water
table. Good performance in cohesive soils. Non man-entry pipes can
be installed.
Limitations Drive and reception shafts are required. Large boulders are problem.
Can not'be steered. Risk of ground settlement.
Technical Lengths Up to 50 metres
Data Diameters 0300 to 0 1500 mm
Materials Steel Pipes only
THRUSTBORING CONSTRUCTION COMPANY LTD. p.0. BOX 31803, AL-KHOBAR 31952 KSA
PHONE + 966 3 868 21 00 FAX + 9663 868 2 ~ 9 6 E-MAIL thrustboringaal-tamimi.com
TRENCHLESS TECHNIQUES PAGE 6 OF 9
18/08/2307
A hydraulically driven tunneling head is rotated by hydraulic motors and thrust against ground
by means of surface jacks. Excavated material is transported from tunnel face into settlement
tank as slurry, where it is re-circulated afier solids are removed. Steering of cutting head is
done by means of remotely controlled articulated joints and using laser guidance control
system monitors the accuracy of the bore.
Advantages Minimal damage on surface & environment. Noise level & traffic
disruption is minimal. Applicable below water table. Non man-entry
pipes can be installed. Steerable, therefore accurate installation of the
product pipes.
Limitations Drive arld reception shafts are required. Capital investment is high
g
Technical Lengths Up to 300 metres.
Data Diameters 0300 to 02000 mm
0 Materials
Horizontal Directional Drilling is used to install flexible pipes with minimum damage at the
surface. This technique was adopted from oil & gas well drilling industry to install pipelines
under major obstacles like rivers, estuaries, main highways, etc. Most commonly used pipe
materials are Carbon Steel and High Density Poly Ethylene (HDPE).
The following figure explains fundamental stages of HDD technique. Sequence of diagrams
shows (1) Pilot hole drilling, (2) Back reaming and (3) Pipe pulling stages. First, a pilot hole is
drilled with pre-established geometrical specifications under the obstacle by means of a
steerable drilling head. Then, this head is changed with a reaming assembly and pulled back to
enlarge the diameter of hole. When the bore is enlarged to a suitable size, product pipe is
installed by pulling from exit to entry side.
As can be deducted from this figure, a HDD installation can be constructed with a minimum
damage on the ground and usually the fastest and friendly method in environmentally sensitive
areas.
I
When hole is enlarged, produd
pipe is attached to drilling rod
and pulled from exit side.
THRUSTBORING CONSTRUCTION COMPANY LTD. P.O. BOX 31803, AL-KHOBAR 31952 KSA
PHONE + 966 3 868 2100 FAX+ 9663 2096 [email protected]
TRENCHLESS TECHNIQUES PAGE 8 OF 9
18/08/2007
Advantages The least possible damage on the surface. Ground water level is
insigniticant. Curved, deep and small size installations can be made.
Very- quick
. process and therefore most econornical and
( environmentally friendly.
Limitations 1 Skilled operators are required. Only flexible pipes can be installed:
I 1 underground strikes are possible therefore utility mapping is 1
necessary.
Technical Lengths Up to 1500 metres.
Data Diameters 050 to 0750 mm
Materials Steel or HDPE
Although trenchless applications are relatively new techniques, today there are too many
variations of them. The previous sections briefly introduced the main characteristics of some
commonly used techniques. It must be dear that today there is many hybridtypes of trenchless
applications in the market with varying success rates.
The following table compares some of the features of various trenchless techniques. Each
technique has its own weak and strong points. Before deciding for a trenchless application,
pipe characteristics and soil particulars have to be analyzed thoroughly. Then, the best method
for a trenchless installation can be judged.
Trenchless techniques are the safest and most environmentally friendly methods compared
to traditional open cut approach. Besides that, these techniques are the only cost effective
solutions when applied in densely populated u&an areas, under roads wifh heavy M c ,
around sensitive areas like hospitals, fire sfafiom, airports, etc. It is important to consider
the friendliness to environmental systems brought up by any trenchless technique.
However, the indirect cost of a trenching to public should also be considered in making
econornical decisions.
THRUSTBORING CONSTRUCTION COMPANY LTD. P.O. BOX 31803, AL-MOBAR 31952 KSA
PHONE+966386821M3 FAX+96638682@36 E-MA1L [email protected]
TRENCHLESS TECHNIQUES PAGE 9 OF 9
18J081M07
Contrary to common beliefs, trenchless techniques are not the last option selections. In fad,
in many circumstances application of this technology provides safer, quicker and more
economical alternatives. This technology is developed to install suburt8ce utilities by
working on ground surface with minimum interference on the surface in order to provide a
safer working environment.
All trenchless techniques are based on the minimum excavation principle. This principle
implies minimum amount of spoil & backtill material, almost no reinstatement efforts, shortest
installation times, most friendly approach to nearby structures and less impad on society &
environment. Therefore, preference has to be given to the trenchless technology
applications, whenever economical terms justify it.
THRUSTBORING CONSTRUCTION COMPANY LTD. P.O. BOX 31803, AL-KHOBAR 31952 KSA
PHONE + 966 3 868 2100 FAX + 966 3 868 2096 EMI L thntstbon'[email protected]
Sheet Piligag Set-up
107.) Name of Project TB WORKS FOR WASTE WATER PROJECT FOR PLANS 1/55
DAMMAM
Client / Owner Ministry of Water & Electricity - Dammam
Main Contractor : Saeed R Al-Zahrani Trad. Est. (SRACO)
Method Microtunnelling (MT)
Pipe Size 0 SOOmm FRP 1 030" Steel Sleeve Pipe
Total Length 55 Lm
Year 2006
Total Est. Contract Value SAR 223,000.00
I 100.) Name of Project : TB WORKS FOR ROAD CROSSING EXIT - 13, RIYADH
RING ROAD
Client I Owner Ministry of Water Works
I Main Contractor
Method
Pipe Size
: Shibh Al-Jazira Contracting Est.
Microtunnelling (MT)
0300mm, 0350 1024" & 0450mm, 0500 1030" Steel Pipes
Total Length 480.49m
I Year
Total Est. Contract Value
2006
SAR 1,468,099.00
89.) Name of Project : TB WORKS FOR INST'LN OF WATER MAIN LINE - MAKKAH
Client I Owner Ministry of Water Works
Main Contractor : Al-Angari Projects & Trading Co.
Method Microtunnelling (MT) / Pipe Jacking (PJ)
Pipe Size 02400mm RC Jacking Pipes
Total Length 50m
Year 2005
Total Est. Contract Value SAR 525,000.00