Case Study: Adaptative Overcurrent Protection Scheme Applied To An Industrial Plant With Cogeneration Units
Case Study: Adaptative Overcurrent Protection Scheme Applied To An Industrial Plant With Cogeneration Units
T he increase usage of microprocessor-based relays in the II. OVERCURRENT COORDINATION – BASIC PRINCIPLES
different power industry segments has been stimulated by The design of a new electrical system must be followed by a
advancements in microelectronic technology, high reliability set of technical studies to define the equipment ratings,
level, programming flexibility, good operational performance establish protection device settings and determine feasible
and low cost/benefit ratio ([1]). Several protection and control operating conditions. Such studies always consist of power
functions grouped in an unique device allow the design of flow and short circuit calculations, motor starting, arc flash
compact switchgears and the creation of specific protection hazard and overcurrent coordination ([2]-[3]). Overcurrent
schemes composed by the association of two or more coordination studies – the focus of this work – should
protection functions. Moreover, the microprocessor-based consider the components short-circuit and nominal ratings,
relays metering and oscilography functions, their low burdens, and short-circuit currents. Then, the overcurrent protection
programmable logic, communication capabilities, and devices can be adjusted and coordinated to clear a fault
different groups of settings for each protection characteristic without extensive damages to the electrical system
complete the main functions of such devices. Therefore, it can components. Moreover, two basic overcurrent coordination
be noted that a protection system composed by characteristics must be observed:
microprocessor-based relays can improve the reliability and • The faulted portion of the electrical system should be fast
safety of a power system, since fault clearing times can be removed from service;
reduced, false operation cases can be minimized and fault • Only a minimum portion should be removed from service
diagnostic can be provided by the analysis of oscilography in a faulted system. This is called selectivity.
records. Nevertheless, in many situations all the To coordinate two overcurrent protection devices in series,
functionalities of digital relays are not properly used, the one nearest to the fault location must be the first line of
consequently the advantages of their application are not fully defense against damages caused by the abnormal condition –
explored. This may occur due to the lack of personnel capable this is the primary protection. The other device, characterized
of handling with the large amount of parameters of digital as back up protection, is adjusted to operate if the primary
protection fails to clear the fault. Moreover, back up
protection must operate at a selected time interval after the
primary protection operates – this is the coordination time
Antonio H. M. Soares is with School of Engineering of São Carlos/USP. (e- interval. In case of relay-to-relay coordination, such interval
mail: [email protected]).
Jose C. M. Vieira is with School of Engineering of São Carlos/USP. (e-mail: should consider the circuit breaker opening time, the relay
[email protected]). overtravel, relay tolerance and setting errors. When
Authorized licensed use limited to: Petrobras. Downloaded on June 25, 2009 at 09:41 from IEEE Xplore. Restrictions apply.
2
coordinating electromechanical overcurrent relays, the desired substation busbar through a feeder and a 40MVA transformer
coordination time interval is in the range 0.3 to 0.4 seconds, (TR-4). This branch will be referred in this work as
on the other hand, when coordinating static or interconnection branch. The transformers TR-AUX1 and TR-
microprocessor-based relays, this range can be 0.2 to 0.3 AUX2 provide ancillary services to the cogeneration facility.
seconds ([4]). The total industry load is about 55MVA, which is supplied
Further guidelines to set overcurrent relays can be easily by the transformers TR-1, TR-2 and TR-3. During normal
found in technical literature ([2], [4]). Some important aspects operating condition, all generators are in service.
that must be taken into account are: Nevertheless, abnormal conditions that result in the
disconnection of one or more generators must be considered,
• Nominal ratings of equipments and conductors; because the short-circuit levels can change significantly. Such
• Maximum and minimum short-circuit currents; abnormal conditions comprise faults or maintenance services.
• Short-circuit withstanding capabilities of equipments and All the relays presented in Fig. 1 are microprocessor-based
conductors; ones, except R-TR3, which is an electromechanical
• The types of the relays to be coordinated overcurrent relay. Moreover, only the phase overcurrent
(microprocessor, static and electromechanical); protection functions of the microprocessor-based relays
• Motor start up and transformers inrush currents. (ANSI 50 and ANSI 51) are covered in this work. The
interconnection branch relays settings presented in this work
The overcurrent coordination analysis is graphically were calculated to detect faults at both 138kV and 11.5kV
executed by using a time overcurrent plot, in which the levels. The short-circuit current flowing through this branch
operating characteristics (curves) of devices and the for faults at both voltage levels is high enough to trip the
equipments overcurrent withstanding curves are plotted. interconnection branch relays. Consequently, the relays’
Further details are given in the following sections. overcurrent units were not configured with directional feature.
Faults at 11.5kV region were not covered in this work, but
III. ELECTRICAL SYSTEM they were part of the complete coordination study made for
the industrial plant of Fig. 1.
The electrical system studied in this work comprised an
The software DIgSILENT PowerFactory ([5]) was
industrial plant located in the southeast of Brazil. In this plant,
employed to perform the short-circuit calculations and the
there is a cogeneration facility of 41.88MVA composed by
overcurrent coordination study.
two steam-turbine generators and one gas-turbine generator.
The single line diagram of the system and the relays location
IV. OVERCURRENT COORDINATION PROBLEMS
are presented in Fig. 1. Only the relays analyzed in this paper
are shown. All the relays are identified by the letter “R”. In this section, the problems encountered during the
Thus, the name R-G1 means relay protecting generator 1. overcurrent coordination study are presented. In all the cases
analyzed, the coordination among R-TR3 and all the relays in
the cogeneration facility is verified in case of a solid three-
DIgSILENT
External Grid
R-Sec-TR-4
protection devices in an electrical system and overcurrent
Sec-TR1/TR2
Sec-TR3 ground fault protection. Nevertheless, the idea of this work is
R-F2-COGEN
to use only the part of the coordination study that presented
serious coordination problems. Such part comprises the
R-F1-COGEN
Bus COGEN - 11.5 kV generators, interconnection branch and TR-3. The adaptative
R-G1 R-G2 R-G3
protection scheme was also employed to overcurrent ground
fault protection, and it was not shown here due to lack of
Bus G1 Bus G2 Bus G3
TR-AUX1 TR-AUX2
space.
G
~
G
~
G
~
A. Scenario 1 – All the generators in service
M M
G1 G2 G3
Fig. 2 shows the relays’ curves and short-circuit currents
~ ~
Fig. 1 Single line diagram of the electrical system. for the above-referred fault. The short-circuit currents are
plotted in vertical lines and their values are referred to
The generators are described below: 138kV. The relays and equipments are identified in the
• G1: steam-turbine – 12.50MVA – 11.5kV; graphic by an information box attached to their curves. From
• G2: steam-turbine – 12.50MVA – 11.5kV; Fig. 2 it can be seen that the total short-circuit current
• G3: gas turbine – 16.88MVA – 11.5kV. (symmetrical and initial value) is about 10.1kA and the
The cogeneration facility is connected to the 138kV instantaneous unit of R-TR3 operates in about 30ms. The
Authorized licensed use limited to: Petrobras. Downloaded on June 25, 2009 at 09:41 from IEEE Xplore. Restrictions apply.
3
DIgSILENT
Total short-circuit current x=9850.000 pri.A
100
[s] R-Pri-TR-4
R-F1-COGEN TR-4
R-F2-COGEN Through fault
R-G1 protective curve
R-G2 0.01
10
138.00 kV 10 100 1000 10000 [pri.A] 100000
R-G3
11.50 kV 1000 10000 100000 1000000
R-Sec-TR-4
Fig. 3 Time overcurrent plot of scenario 2: G3 out of service.
1
R-TR3
Interconnection branch x=530.000 pri.A
G1/G2 contribution x=182.000 pri.A
DIgSILENT
Total short-circuit current x=9668.000 pri.A
R-Pri-TR-4 100
G3 contribution x=252.000 pri.A
R-Sec-TR-4
0.1 [s]
R-G1 R-F1-COGEN
or R-F2-COGEN TR-4
R-G2 Through fault
10
protective curve
0.01
138.00 kV 10 100 1000 10000 [pri.A] 100000
R-Pri-TR-4
11.50 kV 1000 10000 100000 1000000 1
R-TR3
G1 or G2 contribution x=182.000 pri.A
0.1
B. Scenario 2 – Two generators in service
If one of the generators is out of service, the current
flowing in the interconnection branch in case of a three-phase 0.01
fault at primary side of TR-3 is smaller than in scenario 1. It 138.00 kV 10 100 1000 10000 [pri.A] 100000
Authorized licensed use limited to: Petrobras. Downloaded on June 25, 2009 at 09:41 from IEEE Xplore. Restrictions apply.
4
be readily implemented because the microprocessor-based the algorithm sends a signal to the relays, activating the
relays used have four groups of settings for each protection selected settings. After that, the system returns to the
function. Moreover, by activating logical inputs, the desired monitoring function (breaker status reading).
group of settings can be selected. TABLE II
CONTROL LOGIC TABLE
A. Adaptative overcurrent protection scheme Groups
Breaker Status
G1 G2 G3
The first step of the proposed solution was to establish how Group 1 1 1 1
many groups of settings were necessary, according to the Group 2 1 0 1
operating scenarios. This is shown in Table I. Group 2 1 1 0
Group 2 0 1 1
TABLE I - GROUPS OF SETTINGS Group 3 1 0 0
Group 3 0 1 0
Group Scenarios
Group 3 0 0 1
Group 1 1 – all generators in service
Authorized licensed use limited to: Petrobras. Downloaded on June 25, 2009 at 09:41 from IEEE Xplore. Restrictions apply.
5
comparison to Group 1 settings: the pickup changed from Finally, to fully explore all the functionalities of
200A to 130A, both values referred to 138kV. microprocessor-based relays and reach their maximum
Fig. 7 shows the settings of Group 3, considering only G1 efficiency, it is desired that protection technicians and
or G2 in service. The relays whose settings were modified are engineers have a thorough knowledge, with some background
identified by “Sc3” after their names. The settings in power system, programming skills, relay software
corresponding to Group 1 (scenario 1) are also presented for operation, digital electronic, protection and computer
comparison reasons. Observe that the coordination time networks.
interval between R-TR3 and the interconnection branch relays
is about 1.5 seconds for a solid three-phase fault at the VIII. REFERENCES
primary side of TR-3. In this case, the pickups of the
interconnection branch relays were adjusted in 60A (referred [1] A. T. Johns and S. K. Salman, Digital Protection for Power Systems.
to 138kV), which has increased the relays sensibility in London: Peter Peregrinus Ltd., 1995, p. 203.
comparison to the situation presented in Fig. 4. [2] T. P. Smith, “Power system studies for cement plants,” IEEE Industry
Applications Magazine, vol. 13, no. 4, pp. 56-65, July-Aug. 2007.
[3] IEEE Recommended Practice for Industrial and Commercial Power
DIgSILENT
100
Interconnection branch x=360.000 pri.A
System Analysis, IEEE Std 399-1997, Sep. 1997.
Total short-circuit current x=9850.000 pri.A [4] IEEE Recommended Practice for Protection and Coordination of
[s]
R-G1 Industrial and Commercial Power Systems, IEEE Std 242-2001, 2001.
R-G2
[5] DIgSILENT User’s Manual, 2003.
10 R-Pri-TR-4 [6] A. Y. Abdelaziz, H. E. A. Talaat, A. I. Nosseir, and A. A. Hajjar, “An
R-Sec-TR-4
R-F1-COGEN
adaptative protection scheme for optimal coordination of overcurrent
R-Pri-TR-4 (Sc2)
R-F2-COGEN
relays,” Electric Power Systems Research, vol. 61, pp. 1-9, 2002.
R-Sec-TR-4 (Sc2)
IX. BIOGRAPHIES
0.1
Fig. 6 Time overcurrent plot - Group 2 settings. Jose C. M. Vieira (S’98-M’07) graduated in Electric Engineering from Federal
University of Uberlandia, Uberlandia, Brazil in 1996, received his M.Sc. and
DIgSILENT
100
G1 or G2 contribution x=182.000 pri.A Total short-circuit current x=9668.000 pri.A Ph.D. degrees from State University of Campinas, Campinas, Brazil in 1999 and
R-G1 2006, respectively. From 1999 to 2003, he was with Figener, Sao Paulo, Brazil,
or
[s] R-G2 R-Pri-TR-4 as a Consulting Engineer. From 2006 to 2007 he was a Post-Doctoral Fellow at
R-Sec-TR-4
University of Campinas. At present, he is an Assistant Professor at School of
10 R-F1-COGEN
R-F2-COGEN
Engineering of Sao Carlos, in Sao Carlos, Brazil. His research interests are
R-Pri-TR-4 (Sc3) distributed generation, power system control, dynamics and protection.
RF-Sec-TR-4 (Sc3)
R-TR3
1
R-F1-COGEN (Sc3)
R-F2-COGEN (Sc3)
0.1
0.01
138.00 kV 10 100 1000 10000 [pri.A] 100000
VII. CONCLUSIONS
This paper presented and adaptative overcurrent protection
system, which has used the communication, logic and control
functionalities of microprocessor-based relays. The proposed
solution was simple and efficient and guaranteed the relays
overcurrent coordination for all the operating scenarios
analyzed. It is worth pointing out that the results shown here
were part of the whole overcurrent coordination study, thus
other factors not reported in this paper were considered in
defining the settings of each scenario.
Authorized licensed use limited to: Petrobras. Downloaded on June 25, 2009 at 09:41 from IEEE Xplore. Restrictions apply.