Scaffold VOC questions with answers

1. As soon as the first section of scaffold has been erected, a Scafftag holder
displaying “Do Not Use” is to be placed in visible locations on ALL access points.
True / False

2. mingling of separate scaffold systems permitted? Yes / No


Explain why?

(if no) Different scaffold systems are not manufactured to be mixed with each other.
(if yes) can mix only if have manufactures approval.

3. Identify 4 hazards that must be considered when planning to erect a scaffold

1. Ground stability
2. Manual handling techniques
3. Other work groups
4. Competent workers
5. Working at heights etc.

4. Fall protection is required when working above 1.8m with no handrails in place.

True / False

5. What is the minimum number of planks that must be installed when moving to a
higher level that is not reachable from the full working deck? 1, 2, 3, 4,

6. Describe a method of reducing risk from manual handling when erecting and
dismantling a scaffold.

1. Stretch and flex before work


2. Mechanical aid
3. Ask a mate to help
7. During the erection and dismantling process, it is acceptable to stand on mid-rails or
hand rails if necessary?
True / False

8. Tube, coupler and fabricated frame scaffolds shall be designed by a registered


Professional Engineer when the height exceeds.

1
1. 34m
2. 36m distance a ladder should extend above the scaffold platform?
9. What is the minimum
3. 38m
1. 200mm
2. 600mm
3. 910mm

10.A complete scaffolding handrail consists of toe board (not less than 100mm), hand
rail (not less than 960mm and not more than 1200mm) with a middle rail centered
between toe board and hand rail.
True / False

11. A barricade is needed when there is risk of falling objects.


True / False

12.A scaffold is required to be tied to a secure structure when the height is ……………
times the base width

1. 6 times
2. 1 times
3. 3 times

13.Who is authorized to inspect and tag scaffolds on site?.......scaffold inspector............


a) Worker
b) Scaffolder
c) Inspector

14.When should you inspect your harness and lanyard?..before each use...............

15.Footings shall be level, sound, rigid, and capable of supporting the loaded scaffold
without settling or displacement.
True / False

16.It is acceptable to throw material from one level to another.


True / False

17.Which of the following is NOT the correct coupler to use as a safety/check coupler?

1. Single/putlog coupler
2. Double coupler
3. Swivel coupler

2
18.The height to base width ratio of a mobile scaffold during movement is.
1. 2-1
2. 3-1
3. 4-1

19.Braces shall only be installed if the scaffold is above 3m in height.


True / False

20.A complete scaffold platform should have no holes/openings.


True / False

21.The maximum lift/bay height should not be more than…………2……meters.

1. 3
2. 1.5
3. 2

22.It is acceptable to use damaged scaffold wood if the damage is only on half
damaged.
True / False

23.What is the weight for the weight for the light duty scaffold
1- 150 KG
2- 200 KG
3- 250 KG

24.The scaffold wood should be at least ……….past the supporting tube.


1- 15 cm
2- 20 cm
3- 25 cm

25.The toe board height shouldn’t be less than ……….


1- 10 cm
2- 15 cm
3- 20 cm

26.The least width for the scaffold wood is………


1- 20.5 cm
2- 22.5 cm
3- 24 cm