Project Milestones Project Milestones

This document provides a critical path schedule for the completion of Site No. 250 - Prototype No. 48 for the Al Mujahidin Department Branch in the Abha-Jazan Zone. It outlines the engineering works including design adaptation, design submittals, and design approval from April 2015 to July 2015. The construction period is scheduled from July 2015 to October 2016, including milestones for the main building, warehouse, and main entrance. Testing and commissioning is scheduled for November 2016 with the project scheduled to close out between December 2016 and March 2017.

Uploaded by

Faheem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
137 views6 pages

Project Milestones Project Milestones

This document provides a critical path schedule for the completion of Site No. 250 - Prototype No. 48 for the Al Mujahidin Department Branch in the Abha-Jazan Zone. It outlines the engineering works including design adaptation, design submittals, and design approval from April 2015 to July 2015. The construction period is scheduled from July 2015 to October 2016, including milestones for the main building, warehouse, and main entrance. Testing and commissioning is scheduled for November 2016 with the project scheduled to close out between December 2016 and March 2017.

Uploaded by

Faheem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

Site No.250-Prototype no.

48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
610 9-Apr-15
KAP5-Site No.250-(AL-MUJAHIDIN DEPARTMENT BRANCH COMPLETION)-Prototype no.48-ASIR Zone 29-Mar-17 0 2,017,800.54 9-Apr-15 29-Mar-17

610 9-Apr-15 29-Mar-17 0 0.00 9-Apr-15 29-Mar-17


Project Milestones
General Milestones 610 9-Apr-15 29-Mar-17 0 0.00 9-Apr-15 29-Mar-17

249.D2.GN.MS.1020 Project start date milestone 0 9-Apr-15 0 0.00


249.D2.GN.MS.1030 Site handing over milestone 0 9-Apr-15 0 0.00
249.D2.GN.MS.1310 Project finish date milestone 0 29-Mar-17 0 0.00
Engineering Works Milestones 94 9-Apr-15 11-Jul-15 0 0.00 9-Apr-15 11-Jul-15

249.D2.GN.MS.1010 Design Start Date Milestone 0 9-Apr-15 0 0.00


249.D2.GN.MS.1060 Design Finish Date Milestone 0 11-Jul-15 0 0.00
Construction Milestones 402 12-Jul-15 31-Oct-16 0 0.00 12-Jul-15 31-Oct-16

Main Building Milestones 0 12-Jul-15 12-Jul-15 0 0.00 12-Jul-15 12-Jul-15


249.D2.GN.MS.1090 Main Building Start Date 0 12-Jul-15 0 0.00
Ware house Milestones 398 16-Jul-15 31-Oct-16 0 0.00 16-Jul-15 31-Oct-16
249.D2.GN.MS.1120 Ware house Start Date 0 16-Jul-15 0 0.00
249.D2.GN.MS.1200 Ware house Finish Date 0 31-Oct-16 0 0.00
Main Entrance Milestones 0 31-Oct-16 31-Oct-16 0 0.00 31-Oct-16 31-Oct-16
249.D2.GN.MS.1220 Main Entrance Finish Date 0 31-Oct-16 0 0.00
Testing & Commissioning Milestones 0 1-Nov-16 1-Nov-16 0 0.00 1-Nov-16 1-Nov-16

249.D2.GN.MS.1250 Testing & Commissioning Start Date Milestone 0 1-Nov-16 0 0.00


Handing Over & Project Close Out Milestones 81 26-Dec-16 29-Mar-17 0 0.00 26-Dec-16 29-Mar-17

249.D2.GN.MS.1270 Close Out Start Date Milestone 0 26-Dec-16 0 0.00


249.D2.GN.MS.1300 Close Out Finish Date Milestone 0 29-Mar-17 0 0.00
94 9-Apr-15 11-Jul-15 0 0.00 9-Apr-15 11-Jul-15
Engineering Works
Design Work 94 9-Apr-15 11-Jul-15 0 0.00 9-Apr-15 11-Jul-15

Site Adaptation 30 9-Apr-15 8-May-15 0 0.00 9-Apr-15 8-May-15


249.D2.EN.DE.1010 Design Adaptation 30 9-Apr-15 8-May-15 0 0.00 9-Apr-15 8-May-15
Design Work 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Main Building 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1020 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1170 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1520 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1680 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.1970 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2110 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2180 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 17 25-Jun-15 11-Jul-15 0 0.00 25-Jun-15 11-Jul-15
249.D2.EN.DE.2400 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2530 Approve of Substation 7 5-Jul-15 11-Jul-15 0 0.00 5-Jul-15 11-Jul-15
Barracks 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1030 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1200 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1530 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1690 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2000 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2120 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2190 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 17 25-Jun-15 11-Jul-15 0 0.00 25-Jun-15 11-Jul-15
249.D2.EN.DE.2410 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2540 Approve of Substation 7 5-Jul-15 11-Jul-15 0 0.00 5-Jul-15 11-Jul-15
Electricity room 54 9-May-15 1-Jul-15 0 0.00 9-May-15 1-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1040 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1220 Submit Fire protection drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1540 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1700 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2020 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2130 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2200 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2430 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
Mosque 54 9-May-15 1-Jul-15 0 0.00 9-May-15 1-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15

Primary Baseline Remaining Work Summary Page 1 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone
Site No.250-Prototype no.48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
249.D2.EN.DE.1050 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1240 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1550 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1710 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2040 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2140 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2210 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2450 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
Ware house 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1060 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1260 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1560 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1720 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2060 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2150 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2220 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 17 25-Jun-15 11-Jul-15 0 0.00 25-Jun-15 11-Jul-15
249.D2.EN.DE.2470 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2570 Approve of Substation 7 5-Jul-15 11-Jul-15 0 0.00 5-Jul-15 11-Jul-15
Main Entrance 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1080 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1290 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1580 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1740 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2090 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2170 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2240 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 17 25-Jun-15 11-Jul-15 0 0.00 25-Jun-15 11-Jul-15
249.D2.EN.DE.2520 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2590 Approve of Substation 7 5-Jul-15 11-Jul-15 0 0.00 5-Jul-15 11-Jul-15
Kiosk 64 9-May-15 11-Jul-15 0 0.00 9-May-15 11-Jul-15
Design Submittal 47 9-May-15 24-Jun-15 0 0.00 9-May-15 24-Jun-15
249.D2.EN.DE.1070 Submit Architectural drawings (1st Stage) 10 9-May-15 18-May-15 0 0.00 9-May-15 18-May-15
249.D2.EN.DE.1280 Submit Plumbing drawings 10 19-May-15 28-May-15 0 0.00 19-May-15 28-May-15
249.D2.EN.DE.1570 Submit HVAC drawings 10 26-May-15 4-Jun-15 0 0.00 26-May-15 4-Jun-15
249.D2.EN.DE.1730 Submit Electrical drawings 10 29-May-15 7-Jun-15 0 0.00 29-May-15 7-Jun-15
249.D2.EN.DE.2080 Submit Architectural drawings (2nd Stage) 10 8-Jun-15 17-Jun-15 0 0.00 8-Jun-15 17-Jun-15
249.D2.EN.DE.2160 Submit Architectural drawings (3rd Stage) 10 11-Jun-15 20-Jun-15 0 0.00 11-Jun-15 20-Jun-15
249.D2.EN.DE.2230 Submit Architectural drawings (4th Stage) 10 15-Jun-15 24-Jun-15 0 0.00 15-Jun-15 24-Jun-15
Design Approval 17 25-Jun-15 11-Jul-15 0 0.00 25-Jun-15 11-Jul-15
249.D2.EN.DE.2490 Approve Architectural drawings (4th stage) 7 25-Jun-15 1-Jul-15 0 0.00 25-Jun-15 1-Jul-15
249.D2.EN.DE.2580 Approve of Substation 7 5-Jul-15 11-Jul-15 0 0.00 5-Jul-15 11-Jul-15
402 12-Jul-15 31-Oct-16 0 2,017,800.54 12-Jul-15 31-Oct-16
Construction
Division2-Site Works 84 12-Jul-15 26-Oct-15 0 43,318.76 12-Jul-15 26-Oct-15

Main Building 4 12-Jul-15 15-Jul-15 0 1,843.20 12-Jul-15 15-Jul-15


249.D2.CN.02.MB.1010 Excavation Works 4 12-Jul-15 15-Jul-15 0 1,843.20 12-Jul-15 15-Jul-15
Ware house 80 16-Jul-15 26-Oct-15 0 41,475.56 16-Jul-15 26-Oct-15
249.D2.CN.02.WH.1010 Excavation Works 6 16-Jul-15 26-Jul-15 0 6,912.00 16-Jul-15 26-Jul-15
249.D2.CN.02.WH.1020 Protection from Termi nates Works Phase1 2 27-Jul-15 28-Jul-15 0 0.00 27-Jul-15 28-Jul-15
249.D2.CN.02.WH.1030 Masonry Works under S.O.G 4 29-Aug-15 1-Sep-15 0 0.00 29-Aug-15 1-Sep-15
249.D2.CN.02.WH.1040 Backfilling Works Phase1 6 9-Sep-15 15-Sep-15 0 0.00 9-Sep-15 15-Sep-15
249.D2.CN.02.WH.1050 Backfilling Phase 2 6 17-Oct-15 22-Oct-15 0 23,155.20 17-Oct-15 22-Oct-15
249.D2.CN.02.WH.1060 Gravel Layer 3 24-Oct-15 26-Oct-15 0 11,408.36 24-Oct-15 26-Oct-15
Division3-Concrete 353 29-Jul-15 18-Sep-16 0 1,285,477.55 29-Jul-15 18-Sep-16

Main Building 79 8-Nov-15 7-Feb-16 0 214,746.25 8-Nov-15 7-Feb-16


Sub structure 10 8-Nov-15 18-Nov-15 0 32,409.90 8-Nov-15 18-Nov-15
Foundation 10 8-Nov-15 18-Nov-15 0 32,409.90 8-Nov-15 18-Nov-15
249.D2.CN.03.MB.1060 SOG 150 mm 10 8-Nov-15 18-Nov-15 0 32,409.90 8-Nov-15 18-Nov-15
Super structure 69 19-Nov-15 7-Feb-16 0 182,336.35 19-Nov-15 7-Feb-16
Ground floor 22 19-Nov-15 14-Dec-15 0 90,051.83 19-Nov-15 14-Dec-15
249.D2.CN.03.MB.1070 Columns Works 8 19-Nov-15 28-Nov-15 0 15,628.83 19-Nov-15 28-Nov-15
249.D2.CN.03.MB.1080 Slab Works 14 29-Nov-15 14-Dec-15 0 74,423.00 29-Nov-15 14-Dec-15

Primary Baseline Remaining Work Summary Page 2 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone
Site No.250-Prototype no.48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
First floor 14 9-Jan-16 24-Jan-16 0 74,423.00 9-Jan-16 24-Jan-16
249.D2.CN.03.MB.1100 Slab Works 14 9-Jan-16 24-Jan-16 0 74,423.00 9-Jan-16 24-Jan-16
Roof 12 25-Jan-16 7-Feb-16 0 17,861.52 25-Jan-16 7-Feb-16
249.D2.CN.03.MB.1110 Columns Works 4 25-Jan-16 28-Jan-16 0 1,488.46 25-Jan-16 28-Jan-16
249.D2.CN.03.MB.1120 Slab Works 8 30-Jan-16 7-Feb-16 0 16,373.06 30-Jan-16 7-Feb-16
Barracks 15 2-Apr-16 18-Apr-16 0 61,026.86 2-Apr-16 18-Apr-16
Super structure 15 2-Apr-16 18-Apr-16 0 61,026.86 2-Apr-16 18-Apr-16
Ground floor 15 2-Apr-16 18-Apr-16 0 61,026.86 2-Apr-16 18-Apr-16
249.D2.CN.03.BA.1070 Columns Works 5 2-Apr-16 6-Apr-16 0 8,930.76 2-Apr-16 6-Apr-16
249.D2.CN.03.BA.1080 Slab Works 10 7-Apr-16 18-Apr-16 0 52,096.10 7-Apr-16 18-Apr-16
Electricity room 11 7-Jun-16 19-Jun-16 0 38,699.96 7-Jun-16 19-Jun-16
Super structure 11 7-Jun-16 19-Jun-16 0 38,699.96 7-Jun-16 19-Jun-16
Ground floor 11 7-Jun-16 19-Jun-16 0 38,699.96 7-Jun-16 19-Jun-16
249.D2.CN.03.ER.1070 Columns Works 4 7-Jun-16 11-Jun-16 0 16,373.06 7-Jun-16 11-Jun-16
249.D2.CN.03.ER.1080 Slab Works 7 12-Jun-16 19-Jun-16 0 22,326.90 12-Jun-16 19-Jun-16
Mosque 14 5-May-16 21-May-16 0 72,934.54 5-May-16 21-May-16
Super structure 14 5-May-16 21-May-16 0 72,934.54 5-May-16 21-May-16
Ground floor 14 5-May-16 21-May-16 0 72,934.54 5-May-16 21-May-16
249.D2.CN.03.MQ.1070 Columns Works 5 5-May-16 10-May-16 0 13,396.14 5-May-16 10-May-16
249.D2.CN.03.MQ.1080 Slab Works 9 11-May-16 21-May-16 0 59,538.40 11-May-16 21-May-16
Ware house 207 29-Jul-15 31-Mar-16 0 883,137.32 29-Jul-15 31-Mar-16
Sub structure 92 29-Jul-15 18-Nov-15 0 445,530.08 29-Jul-15 18-Nov-15
Foundation 92 29-Jul-15 18-Nov-15 0 445,530.08 29-Jul-15 18-Nov-15
249.D2.CN.03.WH.1010 PC Footing Works 4 29-Jul-15 2-Aug-15 0 34,666.45 29-Jul-15 2-Aug-15
249.D2.CN.03.WH.1020 RC Footing Works 12 5-Aug-15 18-Aug-15 0 106,113.15 5-Aug-15 18-Aug-15
249.D2.CN.03.WH.1030 RC Neck Columns 6 22-Aug-15 27-Aug-15 0 26,888.40 22-Aug-15 27-Aug-15
249.D2.CN.03.WH.1040 Under Ground Beams 15 16-Sep-15 8-Oct-15 0 173,430.18 16-Sep-15 8-Oct-15
249.D2.CN.03.WH.1050 S.O.G 50 mm 2 27-Oct-15 28-Oct-15 0 0.00 27-Oct-15 28-Oct-15
249.D2.CN.03.WH.1060 SOG 150 mm 12 5-Nov-15 18-Nov-15 0 104,431.90 5-Nov-15 18-Nov-15
Super structure 32 24-Feb-16 31-Mar-16 0 437,607.24 24-Feb-16 31-Mar-16
Ground floor 32 24-Feb-16 31-Mar-16 0 437,607.24 24-Feb-16 31-Mar-16
249.D2.CN.03.WH.1070 Columns Works 8 24-Feb-16 3-Mar-16 0 58,049.94 24-Feb-16 3-Mar-16
249.D2.CN.03.WH.1080 Slab Works 24 5-Mar-16 31-Mar-16 0 379,557.30 5-Mar-16 31-Mar-16
Main Entrance 64 6-Jul-16 18-Sep-16 0 14,932.62 6-Jul-16 18-Sep-16
Super structure 64 6-Jul-16 18-Sep-16 0 14,932.62 6-Jul-16 18-Sep-16
Ground floor 11 6-Jul-16 18-Jul-16 0 11,907.68 6-Jul-16 18-Jul-16
249.D2.CN.03.ME.1070 Columns Works 4 6-Jul-16 10-Jul-16 0 4,465.38 6-Jul-16 10-Jul-16
249.D2.CN.03.ME.1080 Slab Works 7 11-Jul-16 18-Jul-16 0 7,442.30 11-Jul-16 18-Jul-16
Roof 5 13-Sep-16 18-Sep-16 0 3,024.94 13-Sep-16 18-Sep-16
249.D2.CN.03.ME.1090 Concrete Threshold 5 13-Sep-16 18-Sep-16 0 3,024.94 13-Sep-16 18-Sep-16
Division4-Masonry 120 26-Apr-16 12-Sep-16 0 140,931.62 26-Apr-16 12-Sep-16

Ware house 18 26-Apr-16 16-May-16 0 133,009.15 26-Apr-16 16-May-16


Super structure 18 26-Apr-16 16-May-16 0 133,009.15 26-Apr-16 16-May-16
Ground floor 18 26-Apr-16 16-May-16 0 133,009.15 26-Apr-16 16-May-16
249.D2.CN.04.WH.1010 Masonary Works 18 26-Apr-16 16-May-16 0 133,009.15 26-Apr-16 16-May-16
Main Entrance 27 13-Aug-16 12-Sep-16 0 7,922.47 13-Aug-16 12-Sep-16
Super structure 27 13-Aug-16 12-Sep-16 0 7,922.47 13-Aug-16 12-Sep-16
Ground floor 4 13-Aug-16 16-Aug-16 0 4,681.46 13-Aug-16 16-Aug-16
249.D2.CN.04.ME.1010 Masonary Works 4 13-Aug-16 16-Aug-16 0 4,681.46 13-Aug-16 16-Aug-16
Roof 2 11-Sep-16 12-Sep-16 0 3,241.01 11-Sep-16 12-Sep-16
249.D2.CN.04.ME.1020 Masonary Works 2 11-Sep-16 12-Sep-16 0 3,241.01 11-Sep-16 12-Sep-16
Division5-Metals 3 3-Oct-16 5-Oct-16 0 1,440.45 3-Oct-16 5-Oct-16

Main Entrance 3 3-Oct-16 5-Oct-16 0 1,440.45 3-Oct-16 5-Oct-16


Super structure 3 3-Oct-16 5-Oct-16 0 1,440.45 3-Oct-16 5-Oct-16
Roof 3 3-Oct-16 5-Oct-16 0 1,440.45 3-Oct-16 5-Oct-16
249.D2.CN.05.ME.1020 Ladder Hook Installation 3 3-Oct-16 5-Oct-16 0 1,440.45 3-Oct-16 5-Oct-16
Division7-Thermal & Moisture Protection 335 2-Sep-15 2-Oct-16 0 44,250.58 2-Sep-15 2-Oct-16

Ware house 254 2-Sep-15 29-Jun-16 0 42,089.91 2-Sep-15 29-Jun-16


Sub structure 50 2-Sep-15 4-Nov-15 0 41,532.94 2-Sep-15 4-Nov-15
Foundation 50 2-Sep-15 4-Nov-15 0 41,532.94 2-Sep-15 4-Nov-15
249.D2.CN.07.WH.1010 Bituminous Water proofing Works of neck columns 6 2-Sep-15 8-Sep-15 0 0.00 2-Sep-15 8-Sep-15
249.D2.CN.07.WH.1020 Bituminous Water proofing Works of Ground Beams 6 10-Oct-15 15-Oct-15 0 31,929.95 10-Oct-15 15-Oct-15
249.D2.CN.07.WH.1030 Water Vapour Barriers 6 29-Oct-15 4-Nov-15 0 9,602.99 29-Oct-15 4-Nov-15
Super structure 6 23-Jun-16 29-Jun-16 0 556.97 23-Jun-16 29-Jun-16
Ground floor 6 23-Jun-16 29-Jun-16 0 556.97 23-Jun-16 29-Jun-16
249.D2.CN.07.WH.1050 Waterproofing Works for Wet Area 6 23-Jun-16 29-Jun-16 0 556.97 23-Jun-16 29-Jun-16
Main Entrance 12 19-Sep-16 2-Oct-16 0 2,160.67 19-Sep-16 2-Oct-16

Primary Baseline Remaining Work Summary Page 3 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone
Site No.250-Prototype no.48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Super structure 12 19-Sep-16 2-Oct-16 0 2,160.67 19-Sep-16 2-Oct-16
Roof 12 19-Sep-16 2-Oct-16 0 2,160.67 19-Sep-16 2-Oct-16
249.D2.CN.07.ME.1060 Concrete Screed 3 19-Sep-16 21-Sep-16 0 540.17 19-Sep-16 21-Sep-16
249.D2.CN.07.ME.1070 Waterproofing Works for Wet Area 3 22-Sep-16 25-Sep-16 0 540.17 22-Sep-16 25-Sep-16
249.D2.CN.07.ME.1080 Cement Tiling 3 26-Sep-16 28-Sep-16 0 540.17 26-Sep-16 28-Sep-16
249.D2.CN.07.ME.1090 Gravel Layer 3 29-Sep-16 2-Oct-16 0 540.17 29-Sep-16 2-Oct-16
Division8-Doors & Windows 20 4-Sep-16 26-Sep-16 0 7,643.98 4-Sep-16 26-Sep-16

Ware house 20 4-Sep-16 26-Sep-16 0 7,643.98 4-Sep-16 26-Sep-16


Super structure 20 4-Sep-16 26-Sep-16 0 7,643.98 4-Sep-16 26-Sep-16
Ground floor 20 4-Sep-16 26-Sep-16 0 7,643.98 4-Sep-16 26-Sep-16
249.D2.CN.08.WH.1070 Wooden Doors Works 8 4-Sep-16 12-Sep-16 0 7,643.98 4-Sep-16 12-Sep-16
249.D2.CN.08.WH.1030 Doors Coating 6 13-Sep-16 19-Sep-16 0 0.00 13-Sep-16 19-Sep-16
249.D2.CN.08.WH.1040 Doors Accessories 6 20-Sep-16 26-Sep-16 0 0.00 20-Sep-16 26-Sep-16
Division9-Finishes 126 31-May-16 24-Oct-16 0 231,596.35 31-May-16 24-Oct-16

Ware house 112 31-May-16 8-Oct-16 0 216,001.09 31-May-16 8-Oct-16


Super structure 112 31-May-16 8-Oct-16 0 216,001.09 31-May-16 8-Oct-16
Ground floor 112 31-May-16 8-Oct-16 0 216,001.09 31-May-16 8-Oct-16
249.D2.CN.09.WH.1010 Plaster Works 20 31-May-16 22-Jun-16 0 71,984.04 31-May-16 22-Jun-16
249.D2.CN.09.WH.1020 Ceramic For Walls 6 30-Jun-16 6-Jul-16 0 7,754.42 30-Jun-16 6-Jul-16
249.D2.CN.09.WH.1050 Putty Coat Painting Works 12 14-Jul-16 27-Jul-16 0 0.00 14-Jul-16 27-Jul-16
249.D2.CN.09.WH.1060 Epoxy Paint on Concrete Screed 12 28-Jul-16 10-Aug-16 0 56,177.51 28-Jul-16 10-Aug-16
249.D2.CN.09.WH.1090 60*60 Isolated Panels for Ceiling 10 11-Aug-16 22-Aug-16 0 26,408.23 11-Aug-16 22-Aug-16
249.D2.CN.09.WH.1110 1st and 2nd Coat Painting Works 10 23-Aug-16 3-Sep-16 0 0.00 23-Aug-16 3-Sep-16
249.D2.CN.09.WH.1140 Final Coat Paintings 10 27-Sep-16 8-Oct-16 0 53,676.89 27-Sep-16 8-Oct-16
Main Entrance 16 6-Oct-16 24-Oct-16 0 15,595.26 6-Oct-16 24-Oct-16
Super structure 16 6-Oct-16 24-Oct-16 0 15,595.26 6-Oct-16 24-Oct-16
Roof 2 6-Oct-16 8-Oct-16 0 403.33 6-Oct-16 8-Oct-16
249.D2.CN.09.ME.1120 Concrete Threshold Painting 2 6-Oct-16 8-Oct-16 0 403.33 6-Oct-16 8-Oct-16
Elevation 14 9-Oct-16 24-Oct-16 0 15,191.93 9-Oct-16 24-Oct-16
249.D2.CN.09.ME.1130 External Plastering Works 5 9-Oct-16 13-Oct-16 0 5,492.91 9-Oct-16 13-Oct-16
249.D2.CN.09.ME.1140 External Painting Works 4 17-Oct-16 20-Oct-16 0 1,488.46 17-Oct-16 20-Oct-16
249.D2.CN.09.ME.1150 External Granite Skirting 3 22-Oct-16 24-Oct-16 0 8,210.56 22-Oct-16 24-Oct-16
Division10-Specialties 6 13-Oct-16 19-Oct-16 0 4,839.91 13-Oct-16 19-Oct-16

Ware house 6 13-Oct-16 19-Oct-16 0 4,839.91 13-Oct-16 19-Oct-16


Super structure 6 13-Oct-16 19-Oct-16 0 4,839.91 13-Oct-16 19-Oct-16
Ground floor 6 13-Oct-16 19-Oct-16 0 4,839.91 13-Oct-16 19-Oct-16
249.D2.CN.10.WH.1010 Bathroom Accessories 6 13-Oct-16 19-Oct-16 0 4,839.91 13-Oct-16 19-Oct-16
Division12-Furniture 10 20-Oct-16 31-Oct-16 0 247,133.05 20-Oct-16 31-Oct-16

Ware house 10 20-Oct-16 31-Oct-16 0 233,496.80 20-Oct-16 31-Oct-16


Super structure 10 20-Oct-16 31-Oct-16 0 233,496.80 20-Oct-16 31-Oct-16
Ground floor 10 20-Oct-16 31-Oct-16 0 233,496.80 20-Oct-16 31-Oct-16
249.D2.CN.12.WH.1010 Furniture Installation 10 20-Oct-16 31-Oct-16 0 233,496.80 20-Oct-16 31-Oct-16
Main Entrance 6 25-Oct-16 31-Oct-16 0 13,636.25 25-Oct-16 31-Oct-16
Super structure 6 25-Oct-16 31-Oct-16 0 13,636.25 25-Oct-16 31-Oct-16
Ground floor 6 25-Oct-16 31-Oct-16 0 13,636.25 25-Oct-16 31-Oct-16
249.D2.CN.12.ME.1010 Furniture Installation 6 25-Oct-16 31-Oct-16 0 13,636.25 25-Oct-16 31-Oct-16
Division16-Mechanical 87 7-Jul-16 16-Oct-16 0 11,168.28 7-Jul-16 16-Oct-16

Ware house 84 7-Jul-16 12-Oct-16 0 11,168.28 7-Jul-16 12-Oct-16


Super structure 84 7-Jul-16 12-Oct-16 0 11,168.28 7-Jul-16 12-Oct-16
Ground floor 84 7-Jul-16 12-Oct-16 0 11,168.28 7-Jul-16 12-Oct-16
Plumbing 84 7-Jul-16 12-Oct-16 0 11,168.28 7-Jul-16 12-Oct-16
Drainage 84 7-Jul-16 12-Oct-16 0 8,955.75 7-Jul-16 12-Oct-16
249.D2.CN.16.WH.1120 2nd Fix ( Valves , Gullytrap, Accessori es ) for G.F 6 7-Jul-16 13-Jul-16 0 858.51 7-Jul-16 13-Jul-16
249.D2.CN.16.WH.1200 3rd Fix (Saintary fixture, wiring, Cleanout , Ventilation cover , Accessories )4for G.F9-Oct-16 12-Oct-16 0 8,097.24 9-Oct-16 12-Oct-16
Water Supply 84 7-Jul-16 12-Oct-16 0 2,212.53 7-Jul-16 12-Oct-16
249.D2.CN.16.WH.1130 2nd Fix (Pipes Installation , Valves , Accessories ) for G .F 6 7-Jul-16 13-Jul-16 0 1,290.64 7-Jul-16 13-Jul-16
249.D2.CN.16.WH.1210 3rd Fix (Saintary fixture, Water heater , wiring, Cleanout , Accessories ) for4G.F 9-Oct-16 12-Oct-16 0 921.89 9-Oct-16 12-Oct-16
Main Entrance 2 15-Oct-16 16-Oct-16 0 0.00 15-Oct-16 16-Oct-16
Super structure 2 15-Oct-16 16-Oct-16 0 0.00 15-Oct-16 16-Oct-16
Roof 2 15-Oct-16 16-Oct-16 0 0.00 15-Oct-16 16-Oct-16
Drainage 2 15-Oct-16 16-Oct-16 0 0.00 15-Oct-16 16-Oct-16
249.D2.CN.16.ME.1170 3rd Fix ( Ventilation cover , Accessories ) for R.F 2 15-Oct-16 16-Oct-16 0 0.00 15-Oct-16 16-Oct-16
Division17-Electrical 12 17-May-16 30-May-16 0 0.00 17-May-16 30-May-16

Ware house 12 17-May-16 30-May-16 0 0.00 17-May-16 30-May-16


Super structure 12 17-May-16 30-May-16 0 0.00 17-May-16 30-May-16
Ground floor 12 17-May-16 30-May-16 0 0.00 17-May-16 30-May-16
Lightining Layout 6 24-May-16 30-May-16 0 0.00 24-May-16 30-May-16

Primary Baseline Remaining Work Summary Page 4 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone
Site No.250-Prototype no.48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
249.D2.CN.17.WH.1080 LIGHTINING SYSTEM , installing cable from roof floor to grounding pit at down
6 of24-May-16
building 30-May-16 0 0.00 24-May-16 30-May-16
Earthing Layout 6 24-May-16 30-May-16 0 0.00 24-May-16 30-May-16
249.D2.CN.17.WH.1090 EARTHING SYSTEM , grounding copper rod arround the building and connected
6 to
24-May-16
each other with cable 30-May-16 0 0.00 24-May-16 30-May-16
Lighting Layout 6 17-May-16 23-May-16 0 0.00 17-May-16 23-May-16
249.D2.CN.17.WH.1050 1st Fix ( Pipes , Box , sleves , Fittings ) for F.F 6 17-May-16 23-May-16 0 0.00 17-May-16 23-May-16
47 1-Nov-16 25-Dec-16 0 0.00 1-Nov-16 25-Dec-16
Testing & Commissioning
Main Building 47 1-Nov-16 25-Dec-16 0 0.00 1-Nov-16 25-Dec-16

Water Supply 6 1-Nov-16 7-Nov-16 0 0.00 1-Nov-16 7-Nov-16


249.D2.TC.MB.1080 Water heaters Check 2 1-Nov-16 2-Nov-16 0 0.00 1-Nov-16 2-Nov-16
249.D2.TC.MB.1090 Commision Sanitary ware 4 3-Nov-16 7-Nov-16 0 0.00 3-Nov-16 7-Nov-16
Drainage 2 8-Nov-16 9-Nov-16 0 0.00 8-Nov-16 9-Nov-16
249.D2.TC.MB.1100 Commision Bath Tubs 2 8-Nov-16 9-Nov-16 0 0.00 8-Nov-16 9-Nov-16
Fire Protection 12 10-Nov-16 23-Nov-16 0 0.00 10-Nov-16 23-Nov-16
249.D2.TC.MB.1110 Commision Fire Fighting Pump 4 10-Nov-16 14-Nov-16 0 0.00 10-Nov-16 14-Nov-16
249.D2.TC.MB.1120 Commision pressurized Fire Fighting Pump 4 15-Nov-16 19-Nov-16 0 0.00 15-Nov-16 19-Nov-16
249.D2.TC.MB.1130 Commision of PRV & FHC 4 20-Nov-16 23-Nov-16 0 0.00 20-Nov-16 23-Nov-16
Electrical 17 24-Nov-16 13-Dec-16 0 0.00 24-Nov-16 13-Dec-16
249.D2.TC.MB.1140 Lightning & Earthing protection resistance test 5 24-Nov-16 29-Nov-16 0 0.00 24-Nov-16 29-Nov-16
249.D2.TC.MB.1150 Commision of VFD 5 30-Nov-16 5-Dec-16 0 0.00 30-Nov-16 5-Dec-16
249.D2.TC.MB.1160 Commision of Low current final Fixure 2 6-Dec-16 7-Dec-16 0 0.00 6-Dec-16 7-Dec-16
249.D2.TC.MB.1170 Commision of Lighting Fixture 5 8-Dec-16 13-Dec-16 0 0.00 8-Dec-16 13-Dec-16
HVAC 10 14-Dec-16 25-Dec-16 0 0.00 14-Dec-16 25-Dec-16
249.D2.TC.MB.1180 Commision of Eqipment 5 14-Dec-16 19-Dec-16 0 0.00 14-Dec-16 19-Dec-16
249.D2.TC.MB.1190 Main supply valve adjusting 5 20-Dec-16 25-Dec-16 0 0.00 20-Dec-16 25-Dec-16
81 26-Dec-16 29-Mar-17 0 0.00 26-Dec-16 29-Mar-17
Handing Over & Project Close Out
As Built 81 26-Dec-16 29-Mar-17 0 0.00 26-Dec-16 29-Mar-17

Structural 6 26-Dec-16 1-Jan-17 0 0.00 26-Dec-16 1-Jan-17


Main Building 6 26-Dec-16 1-Jan-17 0 0.00 26-Dec-16 1-Jan-17
Foundation 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1010 Concrete Dimension of Plain Concrete Footing 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1020 Concrete Dimension of Reinforced Concrete Footing 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1030 RFT. Details of Reinforced Concrete Footing 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1040 SOG 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
Ground floor 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1060 RFT. details of Columns 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1080 RFT. details of Slabs 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1050 Concrete Dimension of Columns 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1070 Concrete Dimension of Slabs 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
First floor 6 26-Dec-16 1-Jan-17 0 0.00 26-Dec-16 1-Jan-17
249.D2.EN.AD.MB.1090 Concrete Dimension of Columns 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1110 Concrete Dimension of Slabs 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1100 RFT. Detail of Columns 3 26-Dec-16 28-Dec-16 0 0.00 26-Dec-16 28-Dec-16
249.D2.EN.AD.MB.1120 RFT. Details of Slabs 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
Roof 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
249.D2.EN.AD.MB.1130 Concrete Dimension of Columns 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
249.D2.EN.AD.MB.1140 RFT. Details of Columns 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
249.D2.EN.AD.MB.1160 RFT. Details of Slabs 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
249.D2.EN.AD.MB.1150 Concrete Dimension of Slabs 3 29-Dec-16 1-Jan-17 0 0.00 29-Dec-16 1-Jan-17
Architectural 43 2-Jan-17 20-Feb-17 0 0.00 2-Jan-17 20-Feb-17
Main Building 43 2-Jan-17 20-Feb-17 0 0.00 2-Jan-17 20-Feb-17
Ground floor 15 2-Jan-17 18-Jan-17 0 0.00 2-Jan-17 18-Jan-17
249.D2.EN.AD.MB.1170 Finishing Floor Plans 3 2-Jan-17 4-Jan-17 0 0.00 2-Jan-17 4-Jan-17
249.D2.EN.AD.MB.1180 Masonary Works 3 5-Jan-17 8-Jan-17 0 0.00 5-Jan-17 8-Jan-17
249.D2.EN.AD.MB.1190 Plan + Interior Elevation of Wet Area 3 9-Jan-17 11-Jan-17 0 0.00 9-Jan-17 11-Jan-17
249.D2.EN.AD.MB.1200 Looking Up Celling 3 12-Jan-17 15-Jan-17 0 0.00 12-Jan-17 15-Jan-17
249.D2.EN.AD.MB.1210 Furniture Plan 3 16-Jan-17 18-Jan-17 0 0.00 16-Jan-17 18-Jan-17
First floor 15 19-Jan-17 5-Feb-17 0 0.00 19-Jan-17 5-Feb-17
249.D2.EN.AD.MB.1220 Finishing Floor Plans 3 19-Jan-17 22-Jan-17 0 0.00 19-Jan-17 22-Jan-17
249.D2.EN.AD.MB.1230 Masonary Works 3 23-Jan-17 25-Jan-17 0 0.00 23-Jan-17 25-Jan-17
249.D2.EN.AD.MB.1240 Plan + Interior Elevation of Wet Area 3 26-Jan-17 29-Jan-17 0 0.00 26-Jan-17 29-Jan-17
249.D2.EN.AD.MB.1250 Looking Up Celling 3 30-Jan-17 1-Feb-17 0 0.00 30-Jan-17 1-Feb-17
249.D2.EN.AD.MB.1260 Furniture Plan 3 2-Feb-17 5-Feb-17 0 0.00 2-Feb-17 5-Feb-17
Roof 6 6-Feb-17 12-Feb-17 0 0.00 6-Feb-17 12-Feb-17
249.D2.EN.AD.MB.1270 Finishing Floor Plans 3 6-Feb-17 8-Feb-17 0 0.00 6-Feb-17 8-Feb-17
249.D2.EN.AD.MB.1280 Masonary Works 3 9-Feb-17 12-Feb-17 0 0.00 9-Feb-17 12-Feb-17

Primary Baseline Remaining Work Summary Page 5 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone
Site No.250-Prototype no.48-Al Mujahididn Department Branch Completion

ABHA-JAZAN Zone

Critical Path

Activity ID Activity Name Original Early Start Early Finish Total Float Budgeted Total 2015 2016 2017
Duration CostFeb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
Elevation 7 13-Feb-17 20-Feb-17 0 0.00 13-Feb-17 20-Feb-17
249.D2.EN.AD.MB.1290 Elevation General Details 4 13-Feb-17 16-Feb-17 0 0.00 13-Feb-17 16-Feb-17
249.D2.EN.AD.MB.1300 Cladding Details 3 18-Feb-17 20-Feb-17 0 0.00 18-Feb-17 20-Feb-17
Electrical 8 21-Feb-17 1-Mar-17 0 0.00 21-Feb-17 1-Mar-17
Main Building 8 21-Feb-17 1-Mar-17 0 0.00 21-Feb-17 1-Mar-17
Ground floor 4 21-Feb-17 25-Feb-17 0 0.00 21-Feb-17 25-Feb-17
249.D2.EN.AD.MB.1310 Electrical Shop Drawings 4 21-Feb-17 25-Feb-17 0 0.00 21-Feb-17 25-Feb-17
First floor 4 26-Feb-17 1-Mar-17 0 0.00 26-Feb-17 1-Mar-17
249.D2.EN.AD.MB.1320 Electrical Shop Drawings 4 26-Feb-17 1-Mar-17 0 0.00 26-Feb-17 1-Mar-17
Mechanical 24 2-Mar-17 29-Mar-17 0 0.00 2-Mar-17 29-Mar-17
Plumbing 8 2-Mar-17 11-Mar-17 0 0.00 2-Mar-17 11-Mar-17
Main Building 8 2-Mar-17 11-Mar-17 0 0.00 2-Mar-17 11-Mar-17
Ground floor 4 2-Mar-17 6-Mar-17 0 0.00 2-Mar-17 6-Mar-17
249.D2.EN.AD.MB.1330 Plumbing Shop Drawings 4 2-Mar-17 6-Mar-17 0 0.00 2-Mar-17 6-Mar-17
First floor 4 7-Mar-17 11-Mar-17 0 0.00 7-Mar-17 11-Mar-17
249.D2.EN.AD.MB.1340 Plumbing Shop Drawings 4 7-Mar-17 11-Mar-17 0 0.00 7-Mar-17 11-Mar-17
Fire fighting 8 12-Mar-17 20-Mar-17 0 0.00 12-Mar-17 20-Mar-17
Main Building 8 12-Mar-17 20-Mar-17 0 0.00 12-Mar-17 20-Mar-17
Ground floor 4 12-Mar-17 15-Mar-17 0 0.00 12-Mar-17 15-Mar-17
249.D2.EN.AD.MB.1350 Fire Fighting Shop Drawings 4 12-Mar-17 15-Mar-17 0 0.00 12-Mar-17 15-Mar-17
First floor 4 16-Mar-17 20-Mar-17 0 0.00 16-Mar-17 20-Mar-17
249.D2.EN.AD.MB.1360 Fire Fighting Shop Drawings 4 16-Mar-17 20-Mar-17 0 0.00 16-Mar-17 20-Mar-17
HVAC 8 21-Mar-17 29-Mar-17 0 0.00 21-Mar-17 29-Mar-17
Main Building 8 21-Mar-17 29-Mar-17 0 0.00 21-Mar-17 29-Mar-17
Ground floor 4 21-Mar-17 25-Mar-17 0 0.00 21-Mar-17 25-Mar-17
249.D2.EN.AD.MB.1370 HVAC Shop Drawings 4 21-Mar-17 25-Mar-17 0 0.00 21-Mar-17 25-Mar-17
First floor 4 26-Mar-17 29-Mar-17 0 0.00 26-Mar-17 29-Mar-17
249.D2.EN.AD.MB.1380 HVAC Shop Drawings 4 26-Mar-17 29-Mar-17 0 0.00 26-Mar-17 29-Mar-17

Primary Baseline Remaining Work Summary Page 6 of 6 Date Revision Checked Approved
12-Jul-15 Site no.250 (Rev00) A.Hashem M.Reda
Tertiary Baseline Critical Remaining Work
Actual Work Milestone