We Are Intechopen, The World'S Leading Publisher of Open Access Books Built by Scientists, For Scientists
We Are Intechopen, The World'S Leading Publisher of Open Access Books Built by Scientists, For Scientists
We Are Intechopen, The World'S Leading Publisher of Open Access Books Built by Scientists, For Scientists
4,800
Open access books available
123,000
International authors and editors
140M Downloads
154
Countries delivered to
TOP 1%
most cited scientists
12.2%
Contributors from top 500 universities
Designing a Tunnel
Spiros Massinas
Abstract
Designing a tunnel is always a challenge. For shallow tunnels under cities due to
the presence of buildings, bridges, important avenues, antiquities, etc. at the sur-
face and other infrastructures in the vicinity of underground tunnels, parameters
like vibrations and ground settlements must be tightly controlled. Urban tunnels
are often made in soils with very low values of overburden. Risks of collapse and
large deformations at the surface are high; thus negative impact on old buildings are
likely to occur if appropriate measures are not taken in advance, when designing
and constructing the tunnel. For deep tunnels with high overburden and low rock
mass properties, squeezing conditions and excessive loads around the excavation
can jeopardize the stability of the tunnel, leading to extensive collapse. The aim of
the chapter is to give details on advance computational modelling and analytical
methodologies, which can be used in order to design shallow and deep tunnels
and to present real case studies from around the world, from very shallow tunnels
in India with only 4.5 m overburden to a deep tunnel in Venezuela with extreme
squeezing conditions under 1300 m overburden.
1. Introduction
The aim of the current chapter is to give details and guidance in designing
underground tunnels, to be constructed with tunnel boring machines (TBM).
In the sequence of paragraphs to follow, the reader will get a grasp of tunnelling
principles and theory related to mountainous and urban tunnelling—deep and
shallow tunnels will be explained (paragraph 2).
In paragraph 3, details for designing mechanized constructed (TBM) Metro tun-
nels in urban environment will be given, and real cases from India will be presented.
Special case for monument underpass with earth pressure balance machine (EPBM)
under extreme low overburden will also be discussed, and the real case study from
Chandpole Gate in Jaipur will be presented.
Mountainous and deep tunnels design will be presented in paragraph 4.
Squeezing and non-squeezing conditions will be explained, and methods of design-
ing will be given, along with examples from around the world.
The final paragraph will summarize the primary conclusions from the presented
design methodologies. It is noted that all the examples presented herein are real
cases of tunnels already constructed, with the personal involvement of the author in
their designs elaboration.
1
Tunnel Engineering - Selected Topics
2. Tunnelling principles
Tunnelling is divided in two general categories: the deep tunnel case and the
shallow tunnel case (Figure 1). The most common example of a shallow tunnel is
the Metro Lines in a big city. For example, underground tunnels realize the con-
nection between the underground stations. Since the stations are constructed, as
underground structures, to serve the surface mass transit system, the depth of the
train platform from the surface is limited to meters; in a normal typical station,
the platform depth can vary from 15 to 25 m, while for other cases like flagship
stations connecting different Metro Lines, platforms can be in different levels, and
consequently their depth can reach and even exceed 40 m. Therefore, the tunnels
connecting the stations can also vary in depth, and the typical overburden height
(distance between the tunnel crown and the surface) can be 10–20 m, while for
deeper sections can reach or even exceed 35 m. Of course along a Metro Line, there
are always unique cases where the tunnel depth can be very limited, and thus the
overburden height can be even less than a tunnel diameter (e.g., 5 m); for such a
special case, the real case study from Chandpole Gate in Jaipur will be presented in
the following paragraphs. Therefore, from a mathematical perspective, in shallow
tunnelling, two boundaries are introduced, the tunnel geometry (circular or not)
and the surface (Figure 1).
On the contrary, for a deep tunnel case, the problem can be described only by
one boundary, the tunnel geometry (Figure 1). Furthermore, the influence of the
variation of the in situ stress with the depth is more intense and critical in a shallow
tunnel rather than in a deeper tunnel case. In the latter, the in situ stress difference
between tunnel crown and invert is insignificant compared to the absolute value of
the in situ stress at this depth. To understand the main difference between shallow
and deep tunnel, a characteristic example of a motorway with multiple tunnels
crossing a mountainous terrain can be used. In such a case where the tunnel pierces
a mountain, the overburden height can be decades of meters (120, 150 m, etc.) or
even hundreds of meters and even can exceed 1000 m; a real case study for a very
deep tunnel in Venezuela will be presented later on.
The first to differentiate the shallow from the deep tunnel, covering, also, the
intermediate zone between deep and shallow tunnels, was Bray [2]. In order to do
so, he introduced the dimensionless ratio of the depth (from tunnel center—di) to
the radius (ri) of a tunnel. For a ratio (di/ri) equal or greater to 25—e.g., a tunnel
with radius 5 and 120 m overburden height—the deep tunnel case is described,
while the shallow tunnel is defined by a ratio (di/ri) smaller or equal to 7—e.g., a
Figure 1.
Shallow and deep tunnels [1].
2
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
tunnel with radius 5 and 25 m overburden. For the intermediate values of the ratio,
thus between 7 and 25, a transition zone is defined. The stress distribution around
an underground cavity either shallow or deep is the key factor to design a tunnel.
In a similar fashion to the lines of flow in the current of a river, which are devi-
ated by the pier of a bridge and increase in speed as they run around it, the flow
lines of the stress field in a rock mass are deviated by the opening of a cavity (tun-
nel) and are channelled around it to create a zone of increased stress around the
walls of the excavation. The channelling of the flow of stresses around the cavity
introduces the arch effect (Figure 2).
Arch effect can occur, depending on the size of the stresses (overburden height)
and the geomechanical properties of the rock mass (strength and deformation
properties), (a) close to the profile of the tunnel, (b) far from the profile of the
tunnel, and (c) not at all.
Case (a) occurs when the rock mass around the tunnel withstands the deviated
stress flow, responding elastically in terms of strength and deformation. In case (b),
due to the low properties of the rock mass, the ground around the excavation is not
able to withstand the deviated stress flow and thus responds nonelastically, plasticiz-
ing and deforming in proportion to the volume of ground involved in the plasticiza-
tion phenomenon. The latter, that often causes an increase in the volume of the
ground affected, propagates radially and deviates the channelling of the stresses out-
wards into the rock mass until the triaxial stress state is compatible with the strength
properties of the rock mass. In this situation, the arch effect is formed far from the
line of the excavation and the ground around the tunnel which has been plasticized
(plastic zone), contributing to the final tunnel stability with its own residual strength
giving rise to deformations, which is often sufficient to compromise the safety of
the excavation. With proper support measures, the ground can be “helped”; the
plasticization phenomena can be limited, and thus the formation of the arch effect by
natural means can be produced, and the tunnel stability can be ensured. In the third
case (c), the ground around the cavity is completely unable to withstand the deviated
stress flow and responds in the failure range producing the collapse of the tunnel. In
such case the arch effect cannot be formed naturally, and thus pre-support measures
must be used before the excavation, in order artificially to initiate the arch effect.
The reaction is the deformation response of the medium (ground) to the
action of excavation (tunnelling). It is always generated ahead of the excavation
face within the area that is disturbed, following the generation of greater stress in
the medium around the cavity. The deformation response always depends on the
Figure 2.
Flow lines in the current of a river around a pier (left) and stress field flow lines around a tunnel [1].
3
Tunnel Engineering - Selected Topics
medium’s properties and its stress state and is affected by the tunnel’s face advance.
As the face advances, the tunnel passes from a triaxial to a plane stress state. In
case that the progressive decrease in the confinement pressure at the face (σ3 = 0)
produces stress in the elastic range ahead of the face, then the excavation face
remains stable with limited and absolutely negligible deformation. In this case the
channelling of stresses around the cavity (arch effect) is produced by natural means
close to the profile of the excavation, and no artificial support is required to secure
the tunnel stability. If, on the other hand, the progressive decrease in the stress state
at the face (σ3 = 0) produces stress in the elastoplastic range ahead of the face, then
elastic-plastic deformation of the face will give rise to a condition of short-term sta-
bility. This means that in the absence of any intervention, plasticization is triggered,
which, by propagating radially and longitudinally from the walls of the excavation,
produces a shift of the “arch effect” away from the tunnel further into the rock
mass. This shift from the theoretical profile of the tunnel can only be controlled by
intervention to stabilize the ground.
Therefore, in respect to the in situ ground properties, the in situ stress field, and
the applied support measures/pressure, the stress redistribution remains within the
elastic domain, or a phenomenon of plasticization is triggered which may result to
the formation of a plastic domain around the tunnel. Extent/width and shape of the
plastic zone around the cavity are the main parameters for calculating/evaluating
the stability conditions of an underground excavation. The impact of this mecha-
nism is different in a shallow and a deep tunnel.
In a shallow tunnel, the overburden height is limited. Therefore, any under-
ground deformation that may result from the soil plasticization will affect the
development of the surface settlements. In case that the extent of the plastic zone
gives rise to excessive surface settlements (Figure 3), damages on the surface
structures can also be significant or even severe. For a shallow tunnel design, the
key parameter is to minimize the magnitude of the developed surface settlements,
and thus the redistribution of the stresses around the tunnel needs to be controlled
accordingly by designing and applying proper support measures and consequently
proper support pressure (Pi). However, for the deep tunnel case the redistribution
of the stresses around the excavation can be the main challenge. The increased
overburden height combined with low ground mass properties can give rise to
excessive loads exerted around the excavation and thus can lead to tunnel collapse,
if non-proper design of the support measures is elaborated. In such difficult cases,
safe tunnel advance can only be achieved with controlled plasticization of the
Figure 3.
Impact of plastic zone formation around a shallow (left) and a deep (right) tunnel.
4
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
a. Analytic
b. Computational
Analytic methods are related with the use of closed form solutions, while the
finite element method (FEM) and the finite difference method (FDM) describe
the computational procedures. Finally, combination of closed form solutions with
FEM or FDM modelling can be more beneficial than the other two methods along;
closed form solution can give the opportunity to the designer for quick and accurate
calculations and thus to be properly “guided” in the elaboration of the final FEM/
FDM modelling. Indeed, empirical methods (e.g., Protodiakonov, Terzaghi, etc.)
are also used in some cases for solving tunnelling problems.
5
Tunnel Engineering - Selected Topics
Figure 4.
Geological map of Delhi (Source: Geological Survey of India) (Delhi Metro Phase 3 area marked with blue circle).
the actual depth of the bedrock (Figure 5), to quantify the risk from having mixed
face conditions (soft soil with hard rock), and finally to determine the arrangement of
the EPB-TBM cutterhead (to be designed for mixed face conditions) (Figure 6).
For another case, where the stratigraphy is uniform along the entire alignment, the
boreholes can be in greater distance. Let us investigate another example, again from
India but from another area, the state of Rajasthan and the Jaipur Metro Phase 1B.
6
7
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 5.
Geological longitudinal section of shallow tunnel in Delhi Metro Phase 3 (CC23), with boreholes [3]—Delhi silt marked with yellow color and quartzite rock with magenta.
8
Quaternary sediment occupies the major northeastern part of Jaipur, but hill-
ocks and ridge are present around the city (Figure 7). Granite gneisses occupy the
southern part of the district. Other important lithological unites exposed in Jaipur
are limestone, sandstone, etc. Soil alluvium is the main formation along the align-
ment of the project, in the form of sand to silty sand with gravels. The uniformity
on the geological conditions dictated the determination of a geotechnical campaign
with boreholes in greater distances varying from 100 to 150 m (Figure 8).
On the contrary to the Delhi Metro, the EPB-TBM for Jaipur is designed with
an open spoke-type cutterhead with opening ratio of 60%, suitable for the sandy
formations (Figure 9). The increased opening ratio of the cutterhead is more suit-
able in applying uniformly the earth pressure on the excavation face but is essential
to maintain always the pressure in every stroke of the machine as it moves forward,
in order to avoid face instabilities and excessive surface settlements.
For both cases, Delhi and Jaipur Metro, the water table is revealed below the
tunnel invert.
Following the geotechnical campaign and the laboratory tests on the samples,
which are taken from the executed boreholes, the geotechnical model will be deter-
mined along with the characteristic geotechnical parameters of the soil formations.
The modulus of elasticity (E), the effective cohesion (c′), effective friction angle
(φ′ or phi), and the unit weight (γ) of the soil formations are the main geomechani-
cal properties required for designing the tunnel excavation. While the effective
cohesion and friction angle are critical parameters that will govern the extent of the
plastic zone shape, the modulus of elasticity controls the magnitude of the surface
settlements, and the tunnel depth is the geometrical parameter that will affect the
shape of the surface settlement trough.
When tunnelling with EPB shields, the surface settlement development is
related with the machine operation in conjunction with the soil properties. The
so-called volume loss, resulted from the face extrusion (face loss), the steering gap
closure (radial loss on the shield), and the annular void between the segmental
lining and the soil, are basic key parameters that will affect the magnitude of the
soil’s deformations. It is obvious that the soil properties are the governing factors for
determining the operation parameters of the TBM, in order to keep the volume loss
within acceptable limits, to control the plastic zone formation, and thus to mini-
mize the surface settlements.
Since the tunnel excavation with EPB shields is a short-term procedure, the
properties of the soil should be addressed in a careful manner in order to describe
the actual geotechnical conditions. Continuous support on the tunnel face is applied
by using the freshly excavated soil, which completely fills up the work chamber
(muck). The supporting pressure is achieved through control of the incoming and
outgoing materials in the chamber, i.e., through regulation of the screw conveyor
rotation speed and of the excavation advance rate.
Underestimation of the mechanical characteristics of the soil medium and
especially underestimation of the modulus of elasticity E can lead to the calculation
of unreasonable and extremely high values of support pressure, with detrimental
effect on the operation of the machine, as demonstrated below:
a. The muck exhibits a shear resistance that, for a given internal friction angle,
increases with the support pressure. Since muck with shear resistance does not
behave like a fluid, the stress field in the work chamber, and thus the distribution
of the support pressure along the tunnel face, is not under control (Figure 10a).
9
10
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 8.
Geological longitudinal section of shallow tunnel in Jaipur Metro Phase 1B, with boreholes [4]—Silty sand along the entire alignment marked with orange color.
12
Figure 10.
Typical problems caused by high support pressure in EPB shields.
b. For a full work chamber, the cutting wheel not only separates the ground from
the tunnel face but also shears the compacted muck during the rotation. The
larger the support pressures in the work chamber, the larger the shear resist-
ance that must be overcome (Figure 10b). Thus, larger support pressures result
in greater torque and in excessive cutterwear.
c. For high support pressures and low clay percentages, arching of the muck
occurs at the entrance to the screw conveyor and inhibits further discharge. In
case that the excavation continues with impeded discharge, the muck becomes
further compacted. It will be obvious that a silty, sandy soil is especially
susceptible to arching and that the cutting wheel could then be brought to a
complete halt due to the very high necessary torque (Figure 10c).
Table 1.
Consistency of soil formation based on SPT N values as per CIRIA, R143.
13
Tunnel Engineering - Selected Topics
Figure 11.
Characteristic plots showing the variation on SPT N value with depth along the tunnel alignment. Delhi Metro
(CC23), left plot; Jaipur Metro Phase 1B, right plot.
In order to establish the representative SPT N60 values along the tunnel, the
respective values should be plotted versus depth for the entire alignment consider-
ing the results from all the boreholes (Figure 11).
Further plots can also be prepared for different stretches, e.g., considering the
boreholes results of the same stretch (between two stations). With this approach
the entire tunnel stretch can be divided in sub-areas, and different fit lines can
be determined as linear equations linking the representative N value with depth
(e.g., N = 2.8z + 5, whereas z = depth below ground surface). Therefore, by con-
sidering the CIRIA report, the modulus of elasticity can be calculated versus the
SPT N60 values. As an example, for silts, sandy silts, and silty sands, the equation
E = 0.7–1.0 N60 can determine the modulus of elasticity. For the derivation of the
cohesion and friction angle, consolidated undrained triaxial strength tests (CU)
when possible and direct shear strength tests can be used.
As already mentioned, underestimation of the soil properties when calculating
the EPB pressure can lead to excessive problems during construction of the tunnel.
Therefore, it is essential to study in detail the soil behavior not only through the
results of the laboratory tests but also by investigating physical exposed open cuts
in order to understand the “stand-up time” of the formations. “Stand-up time” is
the short-term stability of the soil without the application of support measures and
mainly reveals the existence of increased shear strength on the formation which
sometimes is difficult to be determined by laboratory tests.
As a conclusive remark, it is worth mentioning that when designing the excava-
tion of a tunnel with shield machine, it is proper to use the upper values of the soil
parameters, while when designing the permanent lining, lower values can be used
with caution to avoid unnecessary overdesign.
The tunnel boring machines that provide immediate peripheral and frontal
support simultaneously belong to the closed-face group. They excavate and support
both the tunnel walls and the face at the same time. Except for mechanical support
machines, they all have the, so-called, cutterhead chamber at the front, separated by
the remaining part of the machine by a bulkhead, where a confinement pressure is
maintained in order to actively support the excavation and/or balance the hydrostatic
pressure of the groundwater. The TBM is moving forward through hydraulic cylinders
that are pushing the already erected segmental lining (Figure 12). Respective video
for the operation of an EPB can be found in the following link from Herrenknecht:
https://www.herrenknecht.com/en/products/productdetail/epb-shield/.
14
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Figure 12.
Typical view of earth pressure balance (EPB) shield (Source: Herrenknecht).
With earth pressure balance shields, the cohesive soil loosened by the cutting
wheel serves to support the tunnel face, unlike other shields which are dependent on
a secondary support medium (e.g., slurry shields). The area of the shield in which
the cutting wheel rotates is known as the excavation chamber and is separated from
the section of the shield under atmospheric pressure by the pressure bulkhead. The
soil is loosened by the cutters on the cutting wheel, falls through the openings of the
cutting wheel into the excavation chamber, and mixes with the plastic soil already
there. Uncontrolled penetration of the soil from the tunnel face into the excavation
chamber is prevented because the force of the thrust cylinders is transmitted from
the pressure bulkhead onto the soil. A state of equilibrium is reached when the soil
in the excavation chamber cannot be compacted any further by the native earth and
water pressure. The excavated material is removed from the excavation chamber
by an auger conveyor (screw of Archimedes). The amount of material removed
is controlled by the speed of the auger and the cross section of the opening of the
upper auger conveyor driver. The auger conveyor conveys the excavated material to
the first of a series of conveyor belts. The excavated material is conveyed on these
belts to the so-called reversible conveyor from which the transportation gantries in
the backup areas are loaded when the conveyor belt is put into reverse. The tunnels
are normally lined with steel- or fiber-reinforced lining segments, which are posi-
tioned under atmospheric pressure conditions by means of erectors in the area of the
shield behind the pressure bulkhead and then temporarily bolted in place. Mortar is
continuously forced into the remaining gap between the segments’ outer side and the
rock through injection openings in the tailskin or openings directly in the segments.
The principle of EPB-TBM operation is that pressurizing the spoil held in the
cutterhead chamber to balance the earth pressure exerted holds up the excavation. If
necessary, the bulkhead spoil can be made more plastic by injecting additives from
the openings in the cutterhead chamber, the pressure bulkhead, and the muck-
extraction screw conveyor. By reducing friction, the additives reduce the torque
required to churn the spoil, thus liberating more torque to work on the face. They
also help maintain a constant confinement pressure at the face. The hydrostatic pres-
sure is withstanding by forming a plug of confined earth in the chamber and screw
conveyor; the pressure gradient between the face and the spoil discharge point is
balanced by pressure losses in the extraction and pressure relief device (Figure 13).
Face support is uniform. It is obtained by means of the excavated spoil and addi-
tives. Injecting products through the shield can enhance additional peripheral support.
For manual work to proceed in the cutterhead chamber, it may be necessary to create
a sealing cake at the face through controlled substitution (without loss of confinement
pressure) of the spoil in the chamber with bentonite slurry. The architecture of this type
of TBM allows for rapid changeover from closed mode to open mode operation and vice
versa. The tunnel lining is erected inside the TBM tail skin, with a tail skin seal, ensuring
there are no leaks. Back grout is injected behind the lining as the TBM advances.
15
Tunnel Engineering - Selected Topics
Figure 13.
Earth pressure balance principle (Source: Herrenknecht).
• Shield loss (radial ground movement into the gap created by the TBM overcut)
Since the above ground losses are related with the cavity displacements, conse-
quently this is the mechanism that will give rise to the development of the surface
settlements. Designing a TBM tunnel means control of the volume loss, and this can
be achieved with:
• The earth pressure support that is applied at the tunnel face is also transferred
to the shield gap (thus around the shield), through the cutterhead openings,
and therefore reduces the shield’s radial displacements
• Injecting products (e.g., bentonite) through the shield openings can also
enhance additional peripheral support
• Tail skin grouting to seal the gap between erected segments and the tunnel’s exca-
vated profile will minimize the so-called development of secondary settlements
16
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Figure 14.
Overview of a TBM tunnel interstation design.
17
Tunnel Engineering - Selected Topics
According to the analysis methodology that is related with the control of the
induced surface settlements, the following basic phases are considered in a TBM TID:
ii. Diagnostic phase: The tunnel face and cavity behavior is examined along the tun-
nel alignment for different overburden heights, since the face and cavity stabil-
ity affects the development of the ground displacements and hence the induced
surface settlements. Therefore in a TID, three different categories need to be
considered in order to describe the excavation face reaction:
• Elastic
• Elastoplastic
• Stable
18
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
• Unstable
iii. Therapy phase: According to the results derived from the previous phase (II),
the required parameters (e.g., support pressure, TBM operation parameters) are
determined in order to secure the face and cavity stability and thus to minimize
the induced surface settlements.
After studying the tunnel alignment, the designer will define the critical
sections of the project, which is a combination of ground properties, water table
height, overburden height, axial distance between the two tunnel bores (in cases
of twin bore tunnels), locations of the existing buildings, and important struc-
tures. The outcome of the study will determine the tunnel sections of the TID. In
detail the characteristic tunnel sections that need to be used in a TID will include
mainly the following cases:
During the tunnel excavation, the development of the surface settlements will
be recorded through an established geomechanical monitoring program, in order to
check the predictions of the TID and to calibrate if required the operation param-
eters of the EPB machines (e.g., support pressure).
The tunnel face and cavity reaction is always related with the following main key
parameters:
• Ground mass geotechnical properties and water table level. “Output” of the GIR
19
Tunnel Engineering - Selected Topics
U2 3.8 Delhi silt At Existing bridge and “Nala” (water canal) with
surface bridge’s foundation level 3.8 m above tunnel
crown
Table 2.
Critical sections along CC23 of Delhi Metro Phase 3.
CH 4.5 Silty sand Nil Chandpole Gate with foundation level 4.5 m
above tunnel crown
Table 3.
Critical sections along Jaipur Metro Phase 1b.
20
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Characteristic N60 value 2.8z + 5, z = depth below ground surface (m) 3.2z + 5, z = depth
below ground
surface (m)
Modulus of elasticity, E 1.0 × N60 1.0 × N60
[MPa]
Effective friction angle, Depth 0–15 m 30 Depth 27
φ′ [°] 0–10 m
Depth 15–25 m 32 Depth 30
>10 m
Depth 25–>30 m 34
Effective cohesion, c′ Depth 0–7.5 m 0 Depth 5
[kPa] 0–>25 m
Depth 7.5–15 m 10
Depth 15–25 m 20
Depth 25–>30 m 30
3
Unit weight, γ [kN/m ] 20 19
Coefficient of earth 0.61 0.57
pressure at rest, Ko
Poisson’s ration, v 0.3 0.4
Table 4.
Geotechnical design parameters.
Figure 15.
CC23 Delhi Metro. Calculation of plastic zone width according to Massinas and Sakellariou solution [6] for
different tunnel depths (as per sections of Table 2). Proposed range of support pressure also shaded with orange
color.
According to the international literature and case studies from various projects
around the world, the applied support pressure for the tunnel construction with TBM
shields is considered according to the earth pressure at rest and active earth pressure
or according to Anagnostou and Kovari [5]. Recently, the Massinas and Sakellariou
[6] analytic solution is also used to determine the required support pressure for EPB
21
Tunnel Engineering - Selected Topics
Figure 16.
CC23 Delhi Metro. Calculated EPB support pressure for different overburden heights as per the critical sections
F1–F8 of Table 2. Pressures Pr and Pa are calculated based on earth pressure at rest and active earth pressure,
respectively. Psm (min) and (max) give the range of calculated support pressure based on Massinas and
Sakellariou closed form solution [6].
shields [7, 8]). Considering the geotechnical parameters of the soil, the Massinas
and Sakellariou solution [6] is used to calculate the min and max value of the sup-
port pressure (Figure 15). The proposed range of pressure, given by Massinas and
Sakellariou, coincides with minimum plastic zone width (less than 0.5–1 m). Since
the aim is to minimize the induced surface settlements, controlling the plastic zone
formation to minimum width can determine the required value of support pressure.
Considering also earth pressure at rest (Ko) and active (Ka), the EPB support
pressure is calculated for all the different sections F1–F8 of Table 2, for CC23 Delhi
Metro. All the calculation results are plotted in the diagram of Figure 16.
It is obvious that the calculation of Pr by considering the earth pressure at rest
leads to non-pragmatic values, not feasible for the tunnel construction. On the other
hand, the active earth pressure seems to give more realistic results since Pa is almost
coincide with the upper values of the pressures range, as calculated according to
Massinas and Sakellariou solution. Most realistic results can be derived by Massinas
and Sakellariou analytic solution; since the soil-tunnel-surface interaction is consid-
ered and the plastic zone width is derived, therefore the proposed support pressure to
be applied by the EPB is concluded, and the input for part B is defined. More details
for the application of Massinas and Sakellariou method can be found in Refs. [6–8].
For the special case U1, the bored tunnels of CC23 (Line-8) underpass the existing
tunnels of Line-2 as shown in Figure 17. The objective of securing the safe operation
of the existing Metro Line-2 is related with the reduction of the soil deformations and
thus minimizing the displacement of the existing segmental lining. In order to exam-
ine the soil-structure interaction by calculating the plastic zone formation around the
tunnel and calculating the EPB support pressure (Psm) range, again the method of
Massinas and Sakellariou needs to be applied, with the assumptions that follow.
The presence of the existing Line-2 is taken into consideration by assuming as
an upper boundary of the semi-infinite space its invert foundation level; thus a total
overburden of 4 m (conservatively instead of 4.5 m) is considered, to examine the
interaction between the new and the existing tunnel (Figure 18—left); the total
earth pressure (due to gravity) at the real depth of the tunnel is taken into account,
by applying a uniform load (Po) at the upper boundary of the half-space.
22
23
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 17.
CC23 Delhi Metro. Key plan and typical cross section of Line-8 bored tunnels under existing Metro tunnels of Line-2 [6, 7].
Tunnel Engineering - Selected Topics
Figure 18.
CC23 Delhi Metro. Physical and analytical model for calculating the required support pressure of Line-8 TBM
under the existing Metro tunnels of Line-2 (left). Analytic calculation of plastic zone width (right) [6, 7].
By using the analytic solution formula [6], the calculation of the plastic zone
shape around the tunnel is performed for different values of the support pressure
(Figure 18—right). Minimum plastic zone of less than 0.5 m is derived for support
pressure range of 1.8–2.2 bar, while for 2.4 bar, the soil around the cavity remains
within the elastic domain. Therefore by considering a support pressure within the
range of 1.8–2.2 bar, the stress redistribution remains within the elastic domain, and
thus minimum displacements are expected to be developed. The above-derived con-
clusion is the initial observation for the tunnel interactions and is further analyzed
(part B of TID) in full detail through 3D elastic-plastic FDM multistaged simula-
tions with powerful software Fast Lagrangian Analysis of Continua in 3 Dimensions
(FLAC3D) [9].
For the second special case U2 of CC23 Line-8, the TBM working on the up
line underpass the existing Nala, while for the construction of the down line, the
TBM will underpass both the abutments of the existing bridge as well as the Nala.
Therefore, the critical area is approximately 50 m, starting from the neutral zone
(cut and cover structure). Typical plan view of the horizontal alignment and the
longitudinal sections of the down line tunnel is given in Figure 19.
Special survey on the bridge’s foundation (trial pit) revealed pad foundation
with thickness of approximately 2.33 m. The bridge is new, and the span is approx.
26 m with general dimensions in plan 35 × 14 m (length × width). The superstruc-
ture is made of prestressed reinforced concrete box and lay on the abutments
through bearings, as presented in Figure 20.
As in the previous case U1, also for this critical section U2, the presence of the
existing bridge is considered by assuming as an upper boundary of the semi-infinite
space its foundation level; thus a total overburden of 4 m is considered, to examine
the interaction between the bridge and the tunnel. Furthermore, the total earth
pressure (due to gravity) at the real depth of the tunnel is also taken into account,
and a total uniform load (Po) at the upper boundary of the half-space is applied
(Figure 20—right). Considering the longitudinal section of the tunnel, different
overburden heights are considered for the analytic calculations in order to determine
the required support pressure. Table 5 summarizes the calculated support pressure
as per TID—part A for different overburden heights along the bridge and Nala area.
For the calculation of Psm pressures, the same principle, as in previous case U1,
is used. Thus, the required pressure is calculated in order to keep the plastic zone
width around the tunnel below 0.5 m. As per part B of TID, further analysis of the
24
25
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 19.
CC23 Delhi Metro Line-8. Horizontal alignment (left) of up and down lines in Nala (water canal) area. Longitudinal section (right) of down line shows tunnel under the bridge abutments and
the Nala [10].
Tunnel Engineering - Selected Topics
Figure 20.
CC23 Delhi Metro Line-8. Cross section of Line-8 tunnels under existing bridge (left). Physical and analytical
model for calculating the required support pressure of Line-8 TBM under the existing bridge (right) [10].
Table 5.
Support pressure along tunnel alignment, for different overburden heights.
26
27
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 21.
Jaipur Metro Phase 1b. Horizontal alignment and typical cross section of TBM tunnels under Chandpole Gate [8].
Tunnel Engineering - Selected Topics
Figure 22.
Jaipur Metro Phase 1b. Physical and analytical model for TBM support pressure calculation under Chandpole
Gate (left). Analytic calculation of plastic zone width (right) [8].
Table 6.
Critical sections along CC23 of Delhi Metro Phase 3 with proposed support pressure for settlement analysis.
the significance and vulnerability of the structure. Additionally, the loading of the
structure itself and the long period of its application was naturally assumed to have
made the soil below the Gate compact. This assumption could be partly verified
by the soil inspection in the trial pits. In the light of the above considerations, the
designer and the contractor decided to underpass the structure without any pre-
treatment of the soil, relying on the appropriate TBM operation, mainly in terms of
applied face pressure and annular gap grouting application.
Following the same procedure as for the Delhi Metro cases, the presence of the
existing Gate was considered by assuming its foundation level as an upper bound-
ary of the semi-infinite space. Thus a total overburden of 4.5 m has been consid-
ered to examine the interaction between the Gate and the tunnel, as presented in
Figure 22. Furthermore, the total earth pressure (due to gravity) at the real depth
28
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Table 7.
Critical sections along Jaipur Metro Phase 1b with proposed support pressure for settlement analysis.
of the tunnel is also considered, and a total uniform load (Po) at the upper bound-
ary of the half-space is applied. The comparison between the physical model of
the problem and its equivalent model for the analytical calculations is illustrated
in Figure 22 along with the results derived by the application of Massinas and
Sakellariou analytic solution.
A minimum plastic zone width (<0.5 m) is calculated for a mean support pres-
sure within the range of 1.4–1.5 bar, while for 1.6 bar, the soil around the excavation
remains within the elastic domain. The value of 1.5 bar was selected for the execu-
tion of 3D numerical analyses for settlement prediction.
To summarize the results from part A of TID, Tables 6 and 7 give the final
proposed TBM support pressures used for the settlement analysis in part B of TID.
For all the above cases as summarized in Tables 6 and 7, the adopted support
pressure for the settlements analysis is based on the calculation results as per
Massinas and Sakellariou solution [6]. Comparing the two tables, it is obvious
that for the case of Jaipur Metro Phase 1b, higher pressures are considered, which
resulted from the requirement to keep the plastic zone width around the tunnel less
than 0.5 m since the entire tunnel alignment is very shallow (7–12 m) compared to
CC23 Delhi Metro.
Furthermore, even along the Jaipur Metro Phase 1b, the tunnel alignment is
below the busy roadway; in close vicinity with the tunnel’s sides, the very old build-
ings of the “Pink City” and other important monuments exist (Figure 23), and thus
the settlement needs to be kept to absolute minimum values to avoid any damages.
Figure 23.
Jaipur Metro Phase 1b. Important monuments of the “Pink City” along the tunnel alignment [12].
29
Tunnel Engineering - Selected Topics
Figure 24.
Typical FDM models used for settlement analysis. CC23 Delhi Metro on the left and Jaipur Metro Phase 1b on
the right [11, 12].
Figure 25.
Section U1: underpass of Line-2. Typical FDM model used for the settlement analysis. CC23 Delhi Metro [14].
30
31
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 26.
Section U2: underpass of bridge and Nala. Typical FDM model used for the settlement analysis (left). Additional support measures for soil strengthening under the bridge’s abutment (right).
CC23 Delhi Metro [10].
Tunnel Engineering - Selected Topics
Figure 27.
Section CH: underpass of Chandpole Gate. Typical FDM model used for the settlement analysis. Jaipur Metro
Phase 1b [15].
For the settlement analysis at bridge and Nala area (U2), the 3D model consid-
ered the cut and cover structure of the neutral station the bridge’s foundation. The
anaglyph of the Nala with the physical slopes is also detailed simulated (Figure 26).
Due to the fact that the tunnel excavation below the Nala area and the bridge would
start from neutral station, additional support measures are required for strength-
ening the soil (in front of the launching area) during the TBMs entrance in the
ground, since at this stage there will not be adequate support pressure. Therefore,
fully grouted self-drilling bolts 14 m in length 32 mm in diameter are foreseen to
be installed perpendicular to the face wall of the neutral station, around the tun-
nel excavation area (Figure 26). The respective support measures have been also
simulated in the respective 3D analysis as illustrated in Figure 26.
The last simulation (CH) is related with the settlement analysis of Chandpole
Gate during the TBM tunnel boring below the monument. Detailed 3D model
prepared simulating the Gate’s foundations and the sequential construction of the
tunnels with the two TBM shields (Figure 27).
In all the 3D analyses, the exact geometry of the segments and the annular gap
of the tail shield grouting were simulated as presented in Figure 28. The excava-
tion simulation is sequential, and in each step certain actions are considered. The
advance of the TBM can be simulated either by considering the total length of the
shield (e.g., 9 m in length) as one excavation step or slower advance of the shield
equal to one segment can also be considered in the simulation. In the first case, the
total load cases can be reduced, and thus the calculation time can be significantly
Figure 28.
Typical 3D view (left) of segmental lining and grout for backfilling the annular gap simulation. Typical 3D
view (right) of segmental lining (blue) and grout (red) applied on soil (white) [11, 12].
32
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
minimized. Both methods of simulating the TBM advancement will give reliable
results. It is preferable in cases of critical underpasses (e.g., U1, U2, and CH) for the
excavation step to follow each segment length. Therefore, in such cases the analysis
can commence with an initial excavation step equal to the shield’s length, and as
the TBM simulation reaches the important structure, the excavation step is to be
reduced and should follow the segment length.
In each excavation step simulation, the EPB mean support pressure (as calcu-
lated in part A of TID) is applied at the tunnel face. Around the shield the same
pressure with the face can be applied either with a triangular distribution reaching
zero value on the tail of the shield or uniformly up to the half-length of the shield.
Both methods are feasible, and the designer can decide based on the abilities of the
software that he uses. In the previous step (behind the excavation), green grout (a
modulus of elasticity equal to 1 GPa or less can be used) to simulate the backfill on
the annular gap is applied along with the segmental lining. Two steps behind, the
grout mature is simulated by applying its final properties (modulus of elasticity
equal to 10 GPa). There are also other methods to simulate the TBM excavation, for
example, interface elements can be used in order to simulate the behavior of the
shield gap or the annular gap around the segments. Those methods need advance
modelling and increased computational time, which are more appropriate for
academic research and are not common practice in the design industry, since there
are many unknown parameters that need to be defined in order to assign the correct
properties to the interface elements.
In order for the calculated surface settlements to reach equilibrium behind the
shield, a minimum excavation simulation of total tunnel length equal to 5 x diam-
eters is mandatory. For special cases additional excavation length may be required
to be simulated. In Table 8 the total simulated length of tunnel excavation is given
for all the performed 3D analyses along with geometrical required information.
In all the 3D analyses performed (Table 8), the plastic zone width was calculated
below 0.5–1.0 m (Figure 29). It is obvious that this value was expected as it was
initially derived based on Massinas and Sakellariou solution [6].
As it is evident from the diagram in Figure 30, the simulated support pressure
(Pfdm, black dotted line) in the FDM 3D analysis is within the lower range of the
Massinas and Sakellariou support pressure. The higher the overburden, the higher
the pressure required to support the tunnel excavation, following second-order
polynomial curve (e.g., the equation of trendline is y = 8.89x2–0.4x + 5.67). On the
contrary, the calculation of the support pressure, based on the earth pressure at
rest, follows, as expected, linear line that results to unrealistic values, the applica-
tion of them can jeopardize the effective operation of the TBM.
Table 8.
3D models simulation properties.
33
34
Figure 30.
CC23 Delhi Metro. Calculated EPB support pressure for different overburden height as per critical sections
F1–F8 of Table 2 and including the results from the 3D FDM analysis (P fdm).
Figure 31.
CC23 Delhi Metro. Maximum calculated surface settlements after first (left) and second (right) bore
excavation simulations for sections F1–F8 of Table 2 (horizontal axis in m and vertical axis in mm).
35
Tunnel Engineering - Selected Topics
Figure 32.
CC23 Delhi Metro. Percentage of maximum developed surface settlements after first (left) bore excavation
simulation for sections F1–F8 of Table 2. Diagrammatic comparison of maximum calculated surface
settlements after the first and second bore excavations (right).
(11 m overburden), while for the deepest part of the alignment (25 m overburden),
60% of the total settlements are calculated (Figure 32). Of course the two bores’
axial distance is another parameter which affects the surface settlements develop-
ment range, but for shallow tunnelling in Metro projects, optimum value for the
dimensionless ratio of the tunnels’ axial distance to the diameter of the tunnel
varies between 2.2 and 2.5. Even greater values than 2.5 can be applied, but it is
economically preferable to keep the above range for the following reasons:
• Reduces the tunnel influence zone width, thus the surface monitoring is
applied to less area.
• In case that the alignment does not permit reduction on the bores’ axial
distance before entering the station, results in wider station island platform.
• In case that the tunnel alignment permits the axial distance reduction before
entering the station, additional complication is added in TBM alignment
survey and navigation.
36
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Figure 33.
Jaipur Metro Phase 1b. 3D FDM calculated surface settlements after the first and second bore excavation
simulations versus actual final monitored surface settlements [8].
After the first bore excavation simulation, the maximum surface settlement is
calculated as 5 mm, while the second bore excavation only increases the surface
settlement to 4 mm above the second bore without giving rise to the total maximum
settlements. As already discussed in Figure 32 (left), the shallow depth can give rise
to the absolute maximum value of the surface settlements after the first bore excava-
tion. The section CH, which is a case with extreme low overburden height, shows that
even 100% of the final value of the surface settlements can be developed only during
the first bore excavation, while the second tunnel construction can extend only the
shape of the settlement trough without increasing the absolute maximum value. This
is also visible from the actual monitored results; thus after the first bore construction
(Figure 34), the maximum measured settlements at the Gate area are 6 mm, while
after the second TBM underpass (Figure 33), only extent of the trough above its axis
is measured, with absolute maximum value of the settlements equal to 2 mm.
Indeed, the application of the design support pressure (Figure 35—left) during
the construction is the key factor along with the adequate tail shield grouting, in
order to control the soil’s settlements; the secret is to keep the chamber pressure
constant in each stroke of the TBM, thus in each excavation step as the shield is
moving forward (Figure 35—right).
To understand how the earth pressure is properly applied in the excavation
chamber, the respective plots during the calibration of the TBM 1 are given in
Figure 36. As it can be seen from the left diagram of Figure 36, during the calibra-
tion stage, the pressure drops at the beginning of the excavation for the construc-
tion of ring 78. This means that the chamber pressure during the last stroke of the
previous ring 77 is not kept constant and as per the design requirements.
Therefore, at the beginning of ring 78 excavation, the support pressure inside
the chamber is zero, and only after the excavation advanced 250 mm the pressure
starts to rise. After the calibration stage, the support pressure inside the excavation
chamber (Figure 35, right; and Figure 36, right) is kept constant along the entire
excavation length. Along the calibration area, the maximum measured surface
settlements were in the order of 10–14 mm. During the excavation simulation of
the first tunnel, the maximum calculated deflection of the Gate’s foundation (above
the tunnel) is 1/1300, while the maximum differential settlement between the two
foundations of the Gate is calculated 5 mm with an angular distortion of 1/1200.
37
38
Figure 35.
Jaipur Metro Phase 1b. Variation of average face pressure per ring excavation versus the design range (as per
section CH analysis), for TBM 1 (up line) and TBM 2 (down line) (left) [8].
Figure 36.
Jaipur Metro Phase 1b. Variation of face pressure of middle sensors along excavation of last ring of calibration
drive (left) and first ring under the Gate (right) vs. the machine stroke [8].
Along the alignment of Jaipur Metro (3D FDM analysis J1–J3 as per Table 7), the
maximum calculated surface settlements are in the order of 9–10 mm (Figure 37).
As it is evident from Figures 23 and 37, all the buildings along the alignment are at
8 m distance from the tunnel bore axis. No structures are aligned above the tunnel
centerline (except Chandpole Gate). Therefore, at the building location, the maxi-
mum calculated surface settlements are 4–5 mm. Maximum differential settlements
are calculated 2 mm with an angular distortion of 1/2000.
For the case U1 of CC23 Delhi Metro, two analyses were performed. The first
(as presented) includes the station structure, while the second is also performed
without simulating the station. The purpose of the second analysis is to examine the
effect of the station’s stiffness on the development of the surface settlements. The
presence of the stiffness of the existing tunnels and the Hauz Khas station affects
the magnitude and the shape of the calculated surface settlements. In the first case,
where the station is not simulated, the stiffness of the existing tunnels (Yellow
Line) contributes to the development of the surface settlements by reducing their
magnitude of approx. 10–15%.
This is evident in the diagram of Figure 38 (left), where the maximum calcu-
lated surface settlements which are 30 m before the Yellow Metro Line is approx.
5 and 9 mm after the first and second bore excavations, respectively, while at a
section just above and parallel with the up line axis of the Yellow Line, the surface
settlements are calculated 4.5 and 8 mm, respectively. Therefore, a vertical shift
on the settlement trough is observed, due to the stiffness of the existing tunnels,
without affecting the overall shape of the trough but only the maximum value on
39
40
the settlement curve. On the other examined case, the simulation of the station
has a more clear influence on both the shape and the magnitude of the surface
settlements. As it is evident from Figure 38 (right), both vertical and horizontal
shift of the settlements curve is observed. The vertical shift is affecting the mag-
nitude of the maximum calculated settlements which is in the order of approx. 3
and 6 mm after the first and second bore excavations, respectively. Thus, a reduc-
tion of approx. 30–40% is observed from the maximum values (5 and 9 mm)
of the surface settlements. After the first bore underpass simulation, vertical
displacements are calculated at the crown of the existing tunnels, with maximum
values within the range of 3 and 5 mm (for both examined cases). After the
second bore excavation, a slight increase on the crown vertical displacements is
calculated, and the final maximum values are in the order of 7 and 8.5 mm (for
the cases with and without station simulation, respectively). Again, the stiffness
of the simulated station reduces the actual values of the crown displacements by
producing vertical and horizontal eccentricity in the calculated curves, almost in
the same degree as in the surface settlements which are presented before.
The maximum vertical displacements at the invert of the existing tunnels are
calculated within the range of 3.5 mm (case with no station) and 6 mm (case with
station) after the first bore excavation, with a maximum angular distortion in
the order of 0.25‰ (no station simulation) having a peak value of 0.3‰ (station
simulated) at the area which is in close vicinity with the station.
The advance of the second bore below the existing tunnels increases the invert
displacements to 7 mm for the case where the station has been simulated and to
8.5 mm at the second case without the station been simulated, as it is evident in
Figure 39. An increase on the differential displacements is also calculated with a
maximum slope value reaching 0.4‰ (Figure 40). To sum up, for the case of U1 sec-
tion, the maximum vertical displacements at the crown and the invert of the existing
tunnels are calculated within the range of 3.5–6 mm with a maximum angular distor-
tion of 0.3–0.35‰, after the first bore excavation simulation. The completion of the
second bore excavation simulation gives rise to maximum vertical displacements
at crown and invert equal to 7 and 8.5 mm, respectively, with a maximum angular
distortion reaching the value of 0.4‰. The maximum horizontal displacements are
calculated lower than 1 mm. The most critical aspect in U1 underpass is the execution
of works with the existing tunnels under operation. Therefore minimum required
displacements and differential settlements are acceptable at the track slab of the
under operation tunnels. Details will be presented in the following chapter.
The case U2 of CC23 Delhi Metro was another critical underpass since in close
vicinity with the tunnel launching shaft was the existing bridge and the water canal.
The plastic zone width as it is evident in Figure 41 is calculated less than 0.5 m width.
Figure 38.
Calculated surface settlements (m) at sections along the existing yellow line and 30 m before—case without
station simulation in the left diagram and case with station simulation in the right diagram.
41
Tunnel Engineering - Selected Topics
Figure 39.
Calculated max vertical displacements (m) at the invert of the existing up line of yellow line for both
examined cases—with (left above) and without (right above) station simulation.
Figure 40.
Calculated max differential displacements at the invert of the existing up line of yellow line for both examined
cases.
The maximum calculated surface settlements are in the order of 8–9 mm with
a maximum deflection of 1/1000. At the area of the existing bridge, the surface
settlements and angular distortion are calculated 2–8 mm and 1/1000, respectively.
At the foundation level of the bridge (~4 m above tunnels crown), the maximum
calculated vertical subsurface displacements are 10 mm with maximum angular
distortion of 1/700 (Figure 42).
42
43
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Figure 41.
Calculated plastic zone width (left) and surface settlements (right) for case U2 of CC23 Delhi Metro [10].
44
DOI: http://dx.doi.org/10.5772/intechopen.90182
Designing a Tunnel
Damage Negligible Low Slight Medium High
category
0 < Iv < 20 20 < Iv < 40 40 < Iv < 60 60 < Iv < 80 80 < Iv < 100
Slight 10–50 1/500–1/200 8–40 1/625– 6.7–33 1/750– 5.7–28.5 1/875– 5–25 1/1000–
1/250 1/300 1/350 1/400
Moderate 50–75 1/200–1/50 40–60 1/250– 33–50 1/300– 28.5–43 1/350– 25–37.5 1/400–
1/63 1/75 1/88 1/100
Severe >75 >1/50 >60 >1/63 >50 >1/75 >43 >1/84 >37.5 >1/100
Table 9.
Relation between buildings’ categories of damage and vulnerability index.
Tunnel Engineering - Selected Topics
related with “Negligible” damage even in the case of “Highly” vulnerable structures.
For the case of the bridge (U2), “Negligible” damage category is expected as per the
calculated results presented synoptically in Table 10.
Following the damage assessment of the buildings within the influence zone of
the tunnels, the trigger and alarm levels are mandatory to be established in order to
monitor the actual the surface settlements and compare them with the calculated
ones. Examples from real established trigger and alarm levels are given in Table 11
for the critical sections U1, U2, and CH.
Concluding, the derived support pressures as per part A of TID resulted in
acceptable surface settlements (calculated in part B), and consequently the build-
ing risk assessment (part C) proved that no additional measures are required to be
Table 10.
Synoptic presentation of calculated surface settlements.
Table 11.
Established trigger and alarm levels for sections U1, U2, and CH.
46
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
taken, in order to protect the existing surface and subsurface structures which are
within the influence zone of the Metro tunnels.
Figure 43.
Approximate relationship between strain and the degree of difficulty associated with tunnelling through
squeezing rock, for unsupported tunnels [17].
Figure 44.
Comparison between rigid (red line) and yielding (blue line) support [18].
47
Tunnel Engineering - Selected Topics
As it is evident from the curve of Figure 43, the smaller the ratio σcm/Po, the
higher the strain, and thus critical in the tunnel design is the control of the rock
mass deformations around the cavity. Therefore, in case of deep tunnels with high
overburden and low rock mass properties, controlled plasticization is almost man-
datory in order to reduce the exerted loads around the excavation. By intervening
with application of proper yielding support measures, the rock mass is deformed
plastically under controllable manner. This solution involves the introduction of
deformable elements into the lining. These elements are allowed to deform by a
predetermined amount, and when this limit is reached, the support system becomes
rigid and starts to carry the full support load. This process allows progressive failure
to occur, and a plastic zone is formed in the rock mass immediately surrounding the
tunnel. This progressive failure results in a redistribution of the stresses in the rock,
surrounding the tunnel, and in a significant reduction in the capacity of the support
system required to stabilize the tunnel.
The concept is illustrated in Figure 44. Different behavior patterns of rigid (red
line) and yielding (blue line) supports are compared. As the rigid support system
is installed at a roof displacement of 100 mm, the rock mass loads are that high that
the system fails. On the other hand, when a flexible yield support is installed at the
same initial crown displacement (100 mm), the controllable deformation of the rock
(to 300 mm) through the yielding joints reduces the loads transferred to the support
after “locking” of the sliding joints (Figure 44, right), without failure of the system.
In the following paragraphs the case study from one of the most difficult tunnels
around the world will be analyzed, and details from the design of critical sections
will be presented.
48
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
49
Tunnel Engineering - Selected Topics
occurs when the rock mass surrounding the tunnel is overstressed and a “plastic
zone” develops, as described previously. Unless adequate support measures are
introduced, this squeezing can develop into uncontrolled closure and eventually
collapse of the tunnel. The primary cause of squeezing is, as already described, a
combination of a weak rock mass subjected to high in situ stresses due to a high
overburden cover. The process is exacerbated by the presence of water and by
gradual deterioration or “creep” of the rock mass.
In the case of the graphitic phyllite, shown at the Salida heading in Figure 46, the
tectonically disturbed rock mass makes it very difficult to collect samples for labora-
tory testing, and, consequently, very little reliable rock mass strength data is available.
The choice of an appropriate intact strength from results such as those presented
in Figure 46 is a highly subjective process. Anisotropic and foliated rocks such as
slates, schists, and phyllites, whose behavior is dominated by closely spaced planes
of weakness, cleavage, or schistosity, present particular difficulties in the determi-
nation of the uniaxial compressive strengths. Salcedo has reported the results of a
set of directional uniaxial compressive tests on a graphitic phyllite from Venezuela.
It will be noted that the uniaxial compressive strength of this material varies by
a factor of about 5, depending upon the direction of loading. Evidence of the
behavior of this graphitic phyllite in the field suggests that the rock mass properties
are dependent upon the strength parallel to schistosity rather than that normal to
it. In the case of Yacambu-Quibor, the many years of experience of the behavior
of the tunnel gives adequate information to calibrate the rock mass strength to a
certain degree. It is recommended that the parameter that should be varied in this
calibration is the intact rock strength σci since this is both logical from a mechanics
point of view and it has a very significant numerical influence on the estimated
rock mass strength. For the good siliceous phyllites, the intact rock strength σci was
determined as 40–50 MPa, while for the more carbonaceous and foliated phyllites
(graphitic phyllite), the intact rock strength varies from 15 to 30 MPa.
Approximately 5 km of tunnel remained to be excavated, and it is anticipated that
a significant portion of this length will be in graphitic phyllite and that this will be
under the high overburden cover (up to 1200 m). The Turbio fault, which is clearly
defined on surface, may extend to tunnel depth, and provision had to be made for
Figure 46.
Tectonically deformed graphitic phyllite exposed in excavated face of Salida heading of Yacambu-Quibor tunnel
on 24 November 2003 (left) and influence of loading direction on strength of graphitic phyllite (right) [18].
50
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
excavating through and stabilizing the tunnel in this fault. It is also possible that
high pressure water and methane gas could be encountered in excavating through
the Turbio fault. Therefore, for designing the remaining un-excavated part (approx.
5 km), the information from two critical stations at KP 6+540 and KP 11+700 along
the excavated tunnel (Figure 47) were used in order to design the most adequate
support measures and excavation profile as well as the final lining of the tunnel.
The support types along the tunnel were divided into two main categories. Three
full face horseshoe types S1, S2 and S3 for their application in silicified phyllite with
GSI values greater than 50 (Rock mass types A, B and C) were foreseen, for fault
zones and areas with large intrusions of graphitic phyllite at the excavation face
(Rock mass types D1 and D2) with GSI values even low to 25 (Figure 48).
The flexible support types (S4 and S5) consist of shotcrete with total final thick-
ness up to 60 cm (to act also as final lining), steel sets with sliding joints embed-
ded in the shotcrete lining placed in axial distances of 0.6–1.0 m, and 10–12 fully
grouted rock bolts installed every round length. Two sliding joints were foreseen
for class S4 at the vaulted area (Figure 49), while three flexible joints were equally
spaced in category S5. In both flexible support classes, the sliding joints gap was
30 cm as shown in the detail of Figure 49.
In order to investigate the behavior of the tunnel and the reaction of the flexible
support class, to be used in the Turbio fault area, the particular case of the support
near station 11+700 in the Salida heading was considered, and detailed 3D FEM
analysis is elaborated. Near the station the conditions were as follows:
An intact rock strength of 20 MPa is considered, and the following rock mass
properties are considered in the simulation:
It is well noticed that the ratio σcm/Po (<0.1) for the above case reveals extreme
squeezing conditions. Following the above, support type S4 has been examined.
For the simulation, SOFiSTiK [19] software was used. Large model is constructed
51
52
53
54
Figure 50.
3D finite element model of Yacambu-Quibor tunnel temporary support with sliding joints and roof
displacement (ratio) versus tunnel advance [18].
55
56
Table 12.
Simulation results from 2D models S4–1 and S4–4.
57
58
• In the area of the fault zone, support type S4 with 40 cm of shotcrete in horse-
shoe geometry with 4.60 m diameter (minimum internal diameter of 3.80 m).
• In the area before and after the fault zone, support type S4 in circular
geometry.
The type S4 (horseshoe and circular geometry) has been examined in detail in
this paragraph by 2D finite element analysis in order to investigate the implementa-
tion of type S4 section (horseshoe and circular geometry) during the long-term
operation of the project as well as to use the findings for the un-excavated part of
the tunnel.
Considering the event near the station KP 6+540, the conditions were consid-
ered as follows:
An intact rock strength of 15 MPa is considered, and the following rock mass
properties are adopted in the simulations:
59
Tunnel Engineering - Selected Topics
Figure 53.
Inward radial displacement as per convergence-confinement method for unsupported tunnel [21].
Table 13.
2D FEM analysis for tunnel station KP 6+540.
Figure 54.
Modulus of elasticity reduction as per convergence-confinement method [21].
The initial rock deformations 45 cm (S4a–c), 80 cm (S4b–c, S4b–h), and
100 cm (S4c–h) are investigated in Load Case LC1, by considering an initial
reduction in elasticity modulus of the core of the order of 98% (45 cm), 99.3%
(80 cm), and 99.5% (100 cm), respectively, as per Panet curves. In the next step,
the installation of a temporary support shell with minimum stiffness is simulated
60
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
Figure 55.
Model S4a–c and S4b–c, calculated plastic zone (top-left and bottom-left, respectively) and axial force (12,500
and 8500 kN, respectively) distribution (top-right and bottom-right, respectively) within the final shotcrete
shell [21].
61
Tunnel Engineering - Selected Topics
(Young modulus and ultimate shear strength are derived by the taken GSI = 25,
mi = 10, and σci = 15 MPa).
Load Case LC4 is used as a long-term behavior calculation step. The thickness of
the final lining is reduced to 40 cm for S4a–c and S4b–c and to 35 cm for S4b-h and
S4c-h due to the risk of weathering of the external shotcrete layer. Rockbolts are
considered as not functional.
Four (4) different models have been elaborated in order to investigate the sensi-
tivity of the reinforcement results (for the final lining of S4, in either a circular and a
horseshoe geometry), in comparison with the initial rock mass deformation (45, 80,
100 cm) due to the tunnel sliding that occurred near station at KP 6+540. In all mod-
els the detailed construction sequence has been analyzed along with the respective
initial rock mass deformation. In the first model S4a–c the initial rock mass conver-
gence that is simulated, before the installation of the temporary support, is 45 cm.
At the second model (S4b–c), it is assumed that the reported deformation of
45 cm (ING-03-52) does not include initial deformation occurred before the slide
(estimated of the order of 30–35 cm), and therefore the total deformation is of the
order of 80 cm. The resultant axial forces, regarding the first approach, are higher
than the axial forces that are calculated with the second model (Figure 55).
The second approach as mentioned above considers both convergences that are
produced by (a) relaxation of the rock mass (30–35 cm) which is supposed to be
occurred before the excavation and (b) additional measured displacement of the
rock mass (before and after the fault zone) due to tunnel failure. The corresponding
values of the axial and shear forces along with the moments that are developed in
the flexible temporary lining is a result of the shell’s displacement. Thus, the lower
the displacement of the shell, the lower the axial and shear forces and moments.
In a long-term basis, the stresses that were developed in the temporary lining are
redistributed within the total thickness of the final lining. Considering the behavior
of the tunnel near station 6+540, where no important shell displacements were
occurred after the installation of the first 15 cm of shotcrete, it is assumed that the
initial rock mass convergence before the installation of the shell was about 80 cm.
For models S4b–h and S4c–h, the radial initial displacement of the rock mass is
estimated at about 80–100 cm, due to the fact that the area, which is investigated, is the
fault zone, where the tunnel failed. The results for these analyses are unfavorable. In
both approaches the bending moments and shear forces, in the connection area of the
vault with the invert, are extremely higher than the previous model S4b–c (Figure 56).
Figure 56.
Model S4b–c, calculated plastic zone (left), axial force (9000 kN) distribution (middle), and bending
moments (max 1300 kN m—right) within the final shotcrete shell [21].
62
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
The reason for the unfavorable results is the “bad” geometry of the horseshoe
support class (see Figure 48). Even in cases that further failure has not been observed
in the areas of adjustment to KP 6+540, where the horseshoe geometry was applied, a
decision had to be made in order to secure the tunnel lining on a long-term basis.
Figure 57.
Calculated required reinforcement for long-term tunnel operation. Model S4b–c (left) with max 14 cm2 and
model S4b–h (right) with 43 cm2 at crown and max 140 cm2 [21].
Figure 58.
Conversion of horseshoe tunnel excavation profile to equivalent circular final lining for long-term tunnel
operation [21].
63
Tunnel Engineering - Selected Topics
Table 14.
Support classes and application criteria for GSI 25–35.
From the detailed FEM analysis results, it was clear that a circular geometry
for the final lining during the long-term operation of the tunnel was able to
withstand the rock load with a minimum required reinforcement of 14 cm2
(Figure 57), while the horseshoe geometry was unfavorably affecting the capacity
of the final lining. Therefore, special reinforcement arrangement was applied in
order to convert the tunnel excavation profile to an equivalent circular final lining
(Figure 58).
The detailed analysis and back-analysis of the tunnel in the two critical stations
at KP 11+700 and KP 6+540 describe the behavior of the excavation and conse-
quently the support classes, under the worst geotechnical conditions which are
governed by the presence of very weak carbonaceous and foliated phyllites (gra-
phitic phyllite) with GSI <35 and intact rock strength from 15 to 30 MPa.
The tunnel excavation under maximum overburden height and in the presence
of rock with GSI value of 35 and intact rock strength of 20 MPa can lead to a total
radial closure of 300–350 mm. For the extreme case of GSI = 25 and σci = 15 MPa,
the total radial closure can be in the order of 650–750 mm. For both cases, the
circular excavation profile of S4 and S5 support classes is suitable and needs to be
implemented in order to secure the long-term operation of the final lining. Table 14
summarizes the findings from the parametric analysis.
As it is shown in detail in the respective chapters, the tunnel excavation under
extreme squeezing conditions is only feasible by applying a flexible support cat-
egory with sliding joints in a circular excavation profile.
5. Conclusions
In the present chapter of the book, the shallow and deep tunnel cases are
explained in detail, and methods of designing are presented. For the reader and the
tunnel designer, the following conclusions are summarized for the shallow and deep
tunnel problems.
64
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
The general geological formations of the under-study area will be the governing
parameter for establishing the density of the investigation boreholes and the density
and type of laboratory tests.
Knowledge of the geological-geotechnical conditions will determine the type of
the TBM shield to be used as well as the cutterhead design.
Combination of analytic solutions and computational advance modelling (FEM
or FDM) is the most adequate method to be used in the design, since it reduces the
time required for executing the calculations.
TBM tunnel interstation design is mandatory to be followed in Metro projects,
due to the existence of surface and subsurface structures. The aim of the design to
control the surface settlements and thus the operation of the TBM shields need to
be determined by the designer.
Conservatism in determining the geotechnical properties of the soil must be
avoided since it will result in overdesigning the permanent segmental lining of the
tunnel and will also lead to unreasonably high support pressures with immediate
detrimental effect on the operation of the machine.
The discrete parts A, B, and C determined the TBM TID and as such need to be
strictly followed.
The application of the design support pressure (as derived from the TID) is the
key factor along with the adequate tail shield grouting, in order to control the soil’s
settlements. The adequate application is to keep the chamber pressure constant in
each stroke of the TBM, thus in each excavation step, as the shield is moving for-
ward. Grouting from the tail shield of the TBM must be performed, and the amount
and pressure of grout injected into the annular gap must be controlled by the pilot
of the machine, and the consumed volume must always be monitored per ring along
with the applied grouting pressure. Grouting amount in general should be 1.1–1.2
times of the interspace cubage. Secondary grouting from the segments should be
performed based always on the live monitoring data.
Anisotropic and foliated rocks such as graphitic phyllites, when met under high
in situ pressure, can always lead to extreme squeezing problems.
For extreme squeezing conditions only, flexible supports can secure the stability
of the underground excavation. Any other type of stiff support will result in failure.
Long-term behavior of weak rocks should always be investigated when perma-
nent lining is designed.
The most adequate excavation profile is the circular geometry. Horseshoe
geometries should be avoided since the resultant bending moments will lead to
undesignable conditions. Larger tunnels (>5 m diameter) should be designed with a
geometry as close as possible to a circle.
For larger tunnel diameters to be constructed in extreme squeezing conditions with
increased number of sliding joints (or lining stress controllers (LSC)), 3D FEM or FDM
computational analysis will be required with advance modelling of the sliding interface
in order to investigate the closure sequence of the joints in relation to the advance of the
tunnel face. Using the results from the 3D analysis, relaxation factors can be used in 2D
modelling, and the temporary support measures dimensioning can be achieved.
Acknowledgements
65
Tunnel Engineering - Selected Topics
demanding and difficult projects around the globe. Special thanks also to Dr. Evert
Hoek for his valuable guidance in my early years as a designer in the Yacambu-
Quibor tunnel project.
To download the chapter with high resolution images, please use the following
link: https://cdn.intechopen.com/public/docs/70605.pdf
Author details
Spiros Massinas1,2,3,4,5
© 2019 The Author(s). Licensee IntechOpen. This chapter is distributed under the terms
of the Creative Commons Attribution License (http://creativecommons.org/licenses/
by/3.0), which permits unrestricted use, distribution, and reproduction in any medium,
provided the original work is properly cited.
66
Designing a Tunnel
DOI: http://dx.doi.org/10.5772/intechopen.90182
References
[1] Massinas S. Analytic solution for EPB machines under low overburden:
shallow tunneling problems in elastic- The case of Chandpole Gate in Jaipur
plastic half space [thesis]. National Metro, India. Geotechnical & Geological
Technical University of Athens; 2019 Engineering. 2018. DOI: 10.1007/
s10706-018-0565-0
[2] Bray JW. Some applications of
elasticity theory. In: Brown ET, editor. [9] FLAC3D, Fast Lagrangian Analysis
Analytical and Computational of Continua in 3 Dimensions, Itasca
Methods in Engineering Rock Consulting Group, Inc. US Minneapolis.
Mechanics. London: Allen & Unwin; Available from: www.itascacg.com
1987. pp. 32-94
[10] Omikron Kappa—Indus
[3] Omikron Kappa—Indus Consultrans JV. Design of under passing
Consultrans JV. Geotechnical existing bridge at Nala area. CC23 Delhi
interpretation report for tunnels. CC23 Metro; 2013
Delhi Metro; 2013
[11] Omikron Kappa—Indus
[4] Omikron Kappa—Indus Consultrans JV. TBM tunnel interstation
Consultrans JV. Geotechnical design—Assessment and protection of
interpretation report for tunnels, existing buildings. CC23 Delhi Metro;
stations and shafts. Jaipur Metro Phase 2013
1B; 2014
[12] Omikron Kappa—Indus
[5] Anagnostou G, Kovari K. Face Consultrans JV. TBM tunnel interstation
stability conditions with earth design—Assessment and protection of
pressure balance shields. Tunnelling existing buildings. Jaipur Metro Phase
and Underground Space Technology. 1B; 2014
1996;9:165-174
[13] Massinas S, Sakellariou M. A
[6] Massinas S, Sakellariou M. Closed parametric study of tunneling-
form solution for plastic zone formation induced surface settlements under
around a circular tunnel in half space 3D conditions. In: Proceedings of
obeying Mohr-coulomb criterion. 2nd International Conference “From
Geotechnique. 2009;59(8):691-701. Scientific Computing to Computational
DOI: 10.1680/geot.8.069 Engineering”; 5-8 July 2006; Athens,
Greece
[7] Massinas S, Daljeet S, Saini MIS,
Bhardwaj V, Aishwarya K. Settlement [14] Omikron Kappa—Indus
analysis and monitoring Consultrans JV. Design of under passing
instrumentation of Delhi Metro’s existing mMetro line (yellow) near
operational Line-2 tunnels during Hauz Khas—Stage 3 analysis. CC23
TBM of new Line-8 underpass. In: Delhi Metro; 2013
Proceedings of the ITA WTC 2015
Congress; 22-28 May 2015; [15] Omikron Kappa—Indus
Lacroma Valamar Congress Center, Consultrans JV. Under passing scheme
Dubrovnik, Croatia for Chandpole gGate. Jaipur Metro
Phase 1B; 2014
[8] Massinas S, Prountzopoulos G,
Bhardwaj V, Saxena A, Clark J, [16] Chiriotti E, Marchionni V,
Sakellariou M. Design aspects of under- Grasso P. Porto Light Metro System,
passing a city’s heritage landmark with Lines C, S and J. Compendium to the
67
Tunnel Engineering - Selected Topics
68