Floor Installation of The Agru Sure Grip Concrete Protective Liner Floor Standard Method
Floor Installation of The Agru Sure Grip Concrete Protective Liner Floor Standard Method
Floor Installation of The Agru Sure Grip Concrete Protective Liner Floor Standard Method
A squared timber is best suitable for this (10 times 10 cm, length approx. 1.5 m). The
installer rams the plate with the front side of the squared timber into the concrete
carefully.
The plate is then covered with form work boards and load is applied (30-40 kg/m²). Plastic
buckets filled with sand or water (10 l of volume) or sand bags are suitable for this
purpose.
The load should be kept until the concrete is cured.
The next step is to check if there are any hollow spaces where the CPL studs are not
embedded. Use a plastic hammer to knock on the lining over the whole surface. Hollow
spots can be recognized by listenining to the sound when knocking. The spots have to be
backfilled with grout mortar.
After careful preparation of the welding areas the extrusion welding and testing of seams
can take place.
Note:
As only T-intersections are accepted, the liners ha
havve to be laid accordingly
accordingly..
T E C H N I S C H E I N F O R M A T I O N
floor plaster
concrete foundation
lean concrete support
approx. 80mm
floor plaster
concrete foundation
Layout plan of a circular basin floor - the support for the concrete protective liner at the outside(cicumference) is made of lean
concreteTo cover the floor at the inside, steel profiles are to be attached to the concrete foundation
Floor Installation:
After primer-coating (adhesive for bonding to the floor plaster) is performed the floor
panel reinforcement is brought in place and concreting is started
Floor plaster is ruled in at a slightly raised level (2-3 mm/ 0.078-0.118 in.)
Afterwards the CPL is laid and slightly manuallytamped orvibrarted using timber.
Note:Studs have to be removedto fit to the
After Laying the CPL the panels are covered with wooden boards and evenly weighted
(weight / m²: 30-40kg/ 66-88 lb.). Bags or plastic buckets filled with water or sand can
be used for this purpose.
The weight must not be removed until the concrete is cured sufficiently.
T E C H N I S C H E I N F O R M A T I O N
After floor concrete is cured the weight and boards can be removed
and extrusion welding and testing of seams is performed
floor plaster
floor plaster
concrete foundation
floor plaster
extrusion welding
concrete
floor plaster
concrete foundation
wire nail
(bottom fixation of the wall steel profile- screw or shoot profile
liner on the formwork) support for the liners to the foundation