The inspection notice from DEWA lists 24 comments about electrical installation deficiencies found at a villa project. The contractor is requested to complete all rectification work and submit for re-inspection and approval before power can be released to the property. Contact is provided to coordinate final inspection with DEWA.

Uploaded by

rmtaqui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
881 views2 pages

Sample Dewa Inspection Comments

The inspection notice from DEWA lists 24 comments about electrical installation deficiencies found at a villa project. The contractor is requested to complete all rectification work and submit for re-inspection and approval before power can be released to the property. Contact is provided to coordinate final inspection with DEWA.

Uploaded by

rmtaqui
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Application No : :

Date Of Inspection 22.10.2018

Inspection Notice
(LV Installation)

Project Type : VILLA-


Plot No, Area
Owner

Contractor Details :
Name
PO Box, City
Email
Fax :

Following comments were noted by our Engineer during inspection of the Electrical Installation at the
above Project.
1 . Provide main earth-pits (man-hole) with inspection cover and 3 meters long copper earth
electrode, as specified in the approved drawing
2 . Terminate Main ECC on the electrode and coat the termination with corrosion resistant paint.
Test and ensure that the earth resistance is less than 1 Ohm (submit test certificate)
3 . Terminate the ECCs on the earth electrodes using adequately sized individual clamps
4 . Terminate Earth Continuity Conductors (ECC) with copper lugs on main earth bus in MDB/kWh
meter enclosure
5 . Connect the ECC to the water heaters and GI boxes with copper lugs
6 . Provide inter-connection between the earth electrodes with ECC (________________)sq. mm,
Cu/PVC, Y/G) as per the approved drawings
7 . Provide 10mA ELCB for the Jacuzzi pump and provide separate DP switch outside the bathroom.
8 . Provide ELCB AND U.V.relay notices, as applicable ,and also necessary permanent identification
labels for KWH meters, circuits etc. in MDBs/SMDBs/DBs.
9 . Provide permanent identification for Local Isolators of Split unit / Package unit A/Cs, Lift
Machines , Water Pumps, __________________________ etc. with DB & circuit reference.
10 . Provide conduit (25mm) between water meter cabinet and Electrical meter cabinet with pull rope
for DEWA IMS.
11 . Conceal the KWH meter cabinet as per DEWA standard and regulation.
12 . Provide transparent shroud for CT links inside meter cabinet.
13 . Provide mechanical protection for MDB-EXT.
14 . Provide cable gland box below MDBs.
15 . Provide cable gland inspection cover for the incoming cable of DBs.
16 . Provide UVR + timer in DB-Laundry.
17 . Provide DB-GFP and DB-FFP as per DEWA approval.
18 . Complete the installation and connection of Sauna and Steam as per the approved drawings and

Page 1 / 2
DEWA Regulations.
19 . Remove ELCB and provide ELS + Alarm for Sump pump.
20 . Complete the termination and connection from A/C machine to isolator with suitable cable gland
/ brass adaptor as per DEWA standard.
21 . Complete the installation and connection of Remaining Light Fittings as per the approved
drawings and DEWA Regulations.
22 . Submit DMCC / concerned authority completion certificate.
23 . Submit A/C power factor letter from the A/C supplier for the Air-conditioning equipment installed
at site (Note: AC power factor to be verified before submitting to DEWA).
24 . Submit the UAE National Declaration form for release of supply to villa.

You are requested to complete the installation/rectification and submit application for re-inspection
/ final inspection of your works.

Further, please coordinate with our Inspection Engineer to release electric supply to the project.

Contact Name : Mr. JAVED RIYAZ SIDDIQUI


Telephone No : 043229265

Yours faithfully,

For DUBAI ELECTRICITY AND WATER AUTHORITY