100% found this document useful (2 votes)
656 views61 pages

COST CONTROL & Cash Flow

The document discusses project cost control and outlines objectives like accurately following the project plan, monitoring progress, providing reports on actual versus planned progress, forecasting cost at completion, and taking corrective actions. It describes measuring work progress using various approaches like units completed, incremental milestones, and weighted equivalent units. It also discusses cost and schedule control techniques like the S-curve method and earned value analysis to track variances from the plan.

Uploaded by

Manoj Ek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
656 views61 pages

COST CONTROL & Cash Flow

The document discusses project cost control and outlines objectives like accurately following the project plan, monitoring progress, providing reports on actual versus planned progress, forecasting cost at completion, and taking corrective actions. It describes measuring work progress using various approaches like units completed, incremental milestones, and weighted equivalent units. It also discusses cost and schedule control techniques like the S-curve method and earned value analysis to track variances from the plan.

Uploaded by

Manoj Ek
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 61

COST CONTROL

Where we are?

Contractor/Owner

▪ Schedule Updating
▪ Progress Evaluation
▪ Time& Cost Control

CONCEPT DESIGN BIDDING CONSTRUCTION O&M


General Background

Planning

Plan i.e., a new


Updating
T Plan to
follow
Correction
action

M
$ Q
Const-
ruction

Variances
in time &
cost
Evaluation &
Control
Control measurements Construction
Objectives of Project Control

◼ Accurately follow the project plan;


◼ Monitor actual site execution and keep track of resources;
◼ Provide detailed progress reports, comparing actual
versus planned progress;
◼ At any stage during construction, forecast the cost at
completion; and
◼ Take corrective actions at any stage to bring time and
cost closer to the plan.
Project Control
◼ Divided into four main aspects:
◼ Measuring Work Progress
◼ Activity and Project Levels
◼ Cost & Schedule Control
(Variance Analysis)
◼ Forecasting at completion
◼ Schedule Updating
1. Measuring Work Progress

◼ Step 1 Focus on activity level, then

◼ Step 2 The project level


The 5 Common Approaches

◼ Step 1: Activity level


1. Units completed
2. Incremental Milestone
3. Supervisor Opinion
4. Cost Ratio
5. Weighted of Equivalent Units
Units completed

◼ For activities that involve repeated


production of easily measured units of
work (e.g., pile driving)
◼ % Complete =
Units Completed / Total Units
Incremental Milestone
◼ For activities that include subtasks that must be
handled in sequence. Each milestone is assigned a
certain percentage as a rule of credit. E.g.,
Installation of Major Equipment:

◼ Received & Inspection 15%


◼ Setting Complete 35%
◼ Alignment Complete 50%
◼ Internals Installed 75%
◼ Testing Complete 90%
◼ Accepted by Owner 100%
Cost Ratio

◼ For activities that are budgeted based


on a bulk allocations of dollars and
involve long time (e.g., Project
management, quality assurance).
◼ % Complete = Actual Cost (or
hrs) of Work to Date/Forecast at
Completion
Weighted of Equivalent Units
(1) Subtask Unit (2) (3) Quantity (4)
Weight Total Quantity to Date Earned Tons
Cost/total

0.02 Run Found. Bolts Each 200 200 10.4


0.02 Shim % 100 100 10.4
0.05 Shakeout % 100 100 26
0.06 Columns Each 84 74 27.5*
0.11 Beams Each 859 45 3
0.10 Cross Braces Each 837 0 0
0.20 Girts & Sag rods Bay 38 0 0
0.09 Plumb & Align % 100 5 2.3
0.30 Connections Each 2977 74 3.9
0.05 Punch List % 100 0 0
1.0 83.5

Example: Structural Steel Erection. Total Steel Tons =520


Example

Earned Tons to date (4) =

(Quantity to Date (3) / Total Quantity (2)) * weight (1) *


Total Steel Tons
= (74/84) * 0.06 *520 = 27.5 tons

% Complete =
Summation (Earned Tons)/ Total Steel Tons
= 83.5 / 520 =16.1 %
Example Step 2: Project level

Task Budget Weight Bar Charts: Actual versus Planned

A $30K 0.3
10% 40% 40% 10%

B $20K 0.2
70% 30%

C $10K 0.1
40% 60%

D $40K 0.4
40% 60%

$100K 1.0 1 2 3 4 5 week No.

Actual Plan
Example

◼ It is required to calculate
◼ The project % complete at the end of each week
◼ The Earned Value (i.e., the budgeted cost of actual
cost) in the second period.
Solution: Main considerations

◼ Deal with planned separately from actual


progress;
◼ The planned % complete at the end of each
week is prorated with activity duration; and
◼ The weight of each activity is calculated as
the activity’s total budget in proportion to the
total project budget.
Solution
Task Budget Weight Cumulative % complete at end of Week No.

1 2 3 4 5
A $30,000 30%* Plan 0.333 0.666 1.0 1.0 1.0
Actual 0.1 0.5 0.9 1.0 1.0
B $20,000 20% Plan 0.25 0.75 1.0 1.0 1.0

Task Budget Weight


Actual 0 0.7 1.0 1.0
Bar Charts: Actual versus Planned
1.0
C $10,000 10% Plan 0 0 0.25 0.75 1.0
33.3% 33.3% 33.3%

A $30K 0.3 Actual 0 0 0.4 1.0 1.0


D $40,000 40% Plan 0
10% 0
40% 0 10%
40% 0.5 1.0
Actual 0 0 0 0.4 0.6
Project % Complete
◼ The Actual Project % complete at
end of week 2 =

= 0.5*0.3(A) + 0.7*0.2(B) + 0*0.1(C)


+ 0*0.4(D) = 0.29 = 29%
Project % Complete

Cumulative % complete at end of


Week No.

1 2 3 4 5

Plan 0.15 0.35 0.525 0.775 1.0

Actual 0.03 0.29 0.51 0.76 1.0


Comparison
100% $100,000

80% $80,000
% Complete

Budget ($)
60% $60,000

40% Plan $40,000

20% Actual $20,000

0% $0
0 1 2 3 4 5 6
Week No.
2. Cost & Schedule Control

1. S-Curve Method

2. Double S-Curve Method

3. The Earned Value Technique


S-Curve Method
Direct+
Indirect 100%
cost

Plot the S-Curve


Early Start Average
as an envelope
bounded by the
early-start S-
Late Start
Actual Curve and the
late-start S-Curve.

Time

Project Time-Cost Envelope


S-Curve Method

◼ The shape and width of the project’s time-cost


envelope depend on the relative amount of float each
activity in the network has. The wide envelope
indicates more flexibility than a narrow envelope.
◼ At any reporting period, if the actual cost point is
above the average S-Curve, then we can assume that
we have additional project expenses.
◼ One of the drawbacks is that it does not tell if these
extra expenses are due to a fast execution of more
work than planned.
Double S-Curve Method
E
100%
Direct+
e Planned
Indirect Early-Start
cost Actual Costs CV
Costs

Work Hours
D
C
100%

Cumulative Cost
a
and Working
B
A
Hours (the
Planned
Hours amount of work
Actual
Hours done)
Time
SV Now
Double S-Curve Method
◼ Although the plot covering the drawback of the
previous technique, it can be misleading and requires
extra care. One can conclude that the project exhibits
a cost overrun equal to the distance between points
“E and e”, and slow work progress (delay) by the
distance between points “A and a”, which is wrong;
but
◼ Point A shows the level of work done till time “NOW”
Double S-Curve Method
◼ Using the horizontal line, point B shows the time at which
the current level of work was supposed to be completed;
◼ Using a vertical line from point B, point C is the level of
planned cost that correspond to the amount;
◼ Using the horizontal line from point C, point D is the
planned cost for the work done at time ”NOW”; and
◼ Recalculating the cost overrun of the project based on the
amount of work done at time “NOW” (the distance
between points E and D), which is much larger than the
cost overrun assumed earlier.
The Earned Value Technique
$

BCWS

Earned
Value
Measures

Cost Variance
ACWP
Schedule
Variance

Time
BCWP (EV) Now

Time Variance
The Earned Value Technique
◼ Budgeted Cost of Work Scheduled (BCWS):
measures What is Planned in terms of budget cost of
the work that should take place (i.e., according to the
baseline schedule of the work).
◼ Budgeted Cost of Work Performed (BCWP) –
Earned Value: measures What is Done in terms of
budget cost of the work that has actually been
accomplished to date.
◼ Actual Cost of Work Performed (ACWP): measures
What is Paid in terms of actual cost of the work that
has actually been accomplished to date.
The Earned Value Technique

BC WP
Schedule Performance Index (SPI) =
BC WS

BC WP
Cost Performance Index (CPI) =
AC WP
Project Performance Indices
SPI

Schedule Schedule
Advantage >1 Advantage
Cost Overrun Cost Saving

CPI
<1 1 >1

Schedule Delay Schedule Delay


Cost Overrun <1 Cost Saving
Solved Example
◼ Find the early & late times for the following
project.
Act no. Act. Duration Predecessor Res.
1 A 0 ---- 0
2 B 2 1 0
3 C 5 1 2
4 D 3 1 2
5 E 2 2 1
6 F 6 2 2
7 G 6 3 3
8 H 6 4 1
9 I 4 4 0
Solved Example
Act no. Act. Duration Predecessor Res.
10 J 2 5, 6 4
11 K 7 6, 7 2
12 L 3 2, 8 2
13 M 2 2, 8, 9 4
14 N 2 10, 11, 12, 13 0

◼ Draw the project BCWS, BCWP and ACWP


curves to the end of week 5, give the
following .
Solved Example
◼ Progress report at end of week 5.

Activity ES Projected completion


B 0 3
C 0 5
D 0 4
E 2 5
H 3 9
I 3 8
Solved Example
◼ Budget values for the project
Act. Total Cost
B 24,000
C 145,000
D 84,000
E 126,000
F 168,000
G 126,000
H 78,000
Solved Example
Act. Total Cost
I 80,000
J 216,000
K 84,000
E 70,000
L 228,000
M 120,000
N 36,000
Actual cost to end of week 5
Week 1 2 3 4 5

Cost (000) L.E 72 72 125 130 65


529
Cumulative cost (LE) *100 1600
1400
1200
1000 BCWS
800 BCWP
600 SV = 92
ACWP
400
CV= 27
200
0
1 4 7 10 13 16 19
Weeks
Example

◼ A 32-day project
◼ Indirect cost = $500/day (total = ?)
◼ Indirect cost is distributed in a balanced way
◼ Reporting Period = 8 days
Example
$2,000 / $125,000

1.6 x $16,000

$500/day x 32 days
Example
1 2 3 4

100% cost
100% cost
100% cost
4/8=50%

2/10
Example
1 Budget Cost for period 1 =
1x$2,256
+ 1x$11,280
+ 1x$4,512
+ 0.5x$20,304
+ 0x$22,560
+ 0.2x$16,920
+ 0.125x$13,536
+ 0x$18,048
+ 0x$11,280
+ 1x$11,280
+ 0x$9,024 =$44,556
Example BCWS

BCWS

1 2 3 4
BCWS 44,556 53,016 24,929 18,499

Cumulative 44,556 97,572 122,501 141,000


Example BCWS

$150,000

$141,000
$122,501
$100,000
$97,572
Cost

$50,000
$44,556

$- $-
0 8 16 24 32
Time
Example Now
Example ACWP

ACWP

1 2 3 4
ACWP 38,659.72 46,777.78

Cumulative 38,659.72 85,437.5


Example ACWP

$150,000

BCWS $141,000
$122,501
$100,000
$97,572
Cost

$85,438
$50,000
$44,556
ACWP
$38,660

$- $-
0 8 16 24 32
Time
Example BCWP

BCWP

1 2 3 4
BCWP 38,634 53,016

Cumulative 38,634 91,650


Example BCWP

$150,000

BCWS $141,000
$122,501
$100,000
$97,572
$91,650
Cost

$85,438
$50,000
$44,556
ACWP
$38,660
$38,634
BCWP
$- $-
0 8 16 24 32
Time
3. Forecasting at Completion
◼ The Estimate at completion (EAC) =
BCWS at completion + (ACWP – BCWP)
at present
◼ EAC = 141,000 + (85,438 – 91,650)
= $134,788
Cash Flow
profit
Max. amount of cash
needed, at period 5
Expense
S-Curve

Income profile

1 2 3 4 5 6 7
Cash Flow Example

◼ The 32-day network


◼ Indirect cost = $500/day (total = ?)
◼ Contractor’s optimum Markup = 5%
◼ For bid prices, Indirect cost will be distributed in a balanced way
◼ Retainage amount = 10%; all withheld money will be paid back with
the last payment
◼ Owner’s payment delay of any invoice is one period (e.g., 1st period
invoice will be paid at the END of the 2nd period
◼ Time Period =8 days and the interest per period is 1%
Cash Flow Example

◼ Step 1: Project Network and Bar Chart

◼ Step 2: Assessment of Costs, Expenses, and Bid Prices

◼ Step 3: Cash Flow Calculations

◼ Step 4: Plotting the Overdraft Profile

◼ Step 5: Interpreting the Results


Cash Flow step1
$2,000 / $125,000

1.6 x $16,000

$500/day x 32 days
Cash Flow Example
1 2 3 4

100% cost
100% cost
100% cost
4/8=50%

2/10
Cash Flow Example
1 Direct Cost for period 1 =
1x$2,000
+ 1x$10,000
+ 1x$4,000
+ 0.5x$18,000
+ 0x$20,000
+ 0.2x$15,000
+ 0.125x$12,000
+ 0x$16,000
+ 0x$10,000
+ 1x$10,000
+ 0x$8,000 =$39,500
Cash Flow step3

X $1000 1st 2nd 3rd 4th 5th Ret.


(1)
39.5 47 22.1 16.4 0
Direct Expense
(2)
4 4 4 4 0
Indirect Expense
(3)
43.5 51 26.1 20.4 0
Total Expense
(4)
43.5 94.5 120.6 141 141
Cumul. Expense
Cash Flow step3
X $1000 1st 2nd 3rd 4th 5th Ret.
(5)
46.78 55.67 26.18 19.42 0
Budget Value
(6) = (5)x10% Sum
4.678 5.567 2.618 1.942 0
Retainage 14.81
(7) =(5)-(6)
42.11 50.1 23.56 17.48 0 14.81
Amount Payable
(8) Payment 14.81
Received
(9) Cumul.
0 42.11 92.21 115.8 133.2 148.1
Owner payment
Cash Flow step3
X $1000 1st 2nd
(3) Total Expense 43.5 51
(7) Payment Received 42.1

(10) Overdraft before -51


interest -43.5 -43.935
=-94.935
(11) = (10)x 1%
-0.435 -0.949
Interest on overdraft
(12) Total Overdraft -43.935 -95.884
Cash Flow step3

X $1000 1st 2nd 3rd 4th 5th


(10) -28.21
-43.5 -94.94 -79.88 -50.98 -27.93 +17.48
+14.81
(11)
-.435 -.949 -.799 -.510 -.279

(12)= (10)+(11) -43.9 -95.9 -80.7 -51.5 -28.2 4.078

You might also like