COST CONTROL & Cash Flow
COST CONTROL & Cash Flow
Where we are?
Contractor/Owner
▪ Schedule Updating
▪ Progress Evaluation
▪ Time& Cost Control
Planning
M
$ Q
Const-
ruction
Variances
in time &
cost
Evaluation &
Control
Control measurements Construction
Objectives of Project Control
% Complete =
Summation (Earned Tons)/ Total Steel Tons
= 83.5 / 520 =16.1 %
Example Step 2: Project level
A $30K 0.3
10% 40% 40% 10%
B $20K 0.2
70% 30%
C $10K 0.1
40% 60%
D $40K 0.4
40% 60%
Actual Plan
Example
◼ It is required to calculate
◼ The project % complete at the end of each week
◼ The Earned Value (i.e., the budgeted cost of actual
cost) in the second period.
Solution: Main considerations
1 2 3 4 5
A $30,000 30%* Plan 0.333 0.666 1.0 1.0 1.0
Actual 0.1 0.5 0.9 1.0 1.0
B $20,000 20% Plan 0.25 0.75 1.0 1.0 1.0
1 2 3 4 5
80% $80,000
% Complete
Budget ($)
60% $60,000
0% $0
0 1 2 3 4 5 6
Week No.
2. Cost & Schedule Control
1. S-Curve Method
Time
Work Hours
D
C
100%
Cumulative Cost
a
and Working
B
A
Hours (the
Planned
Hours amount of work
Actual
Hours done)
Time
SV Now
Double S-Curve Method
◼ Although the plot covering the drawback of the
previous technique, it can be misleading and requires
extra care. One can conclude that the project exhibits
a cost overrun equal to the distance between points
“E and e”, and slow work progress (delay) by the
distance between points “A and a”, which is wrong;
but
◼ Point A shows the level of work done till time “NOW”
Double S-Curve Method
◼ Using the horizontal line, point B shows the time at which
the current level of work was supposed to be completed;
◼ Using a vertical line from point B, point C is the level of
planned cost that correspond to the amount;
◼ Using the horizontal line from point C, point D is the
planned cost for the work done at time ”NOW”; and
◼ Recalculating the cost overrun of the project based on the
amount of work done at time “NOW” (the distance
between points E and D), which is much larger than the
cost overrun assumed earlier.
The Earned Value Technique
$
BCWS
Earned
Value
Measures
Cost Variance
ACWP
Schedule
Variance
Time
BCWP (EV) Now
Time Variance
The Earned Value Technique
◼ Budgeted Cost of Work Scheduled (BCWS):
measures What is Planned in terms of budget cost of
the work that should take place (i.e., according to the
baseline schedule of the work).
◼ Budgeted Cost of Work Performed (BCWP) –
Earned Value: measures What is Done in terms of
budget cost of the work that has actually been
accomplished to date.
◼ Actual Cost of Work Performed (ACWP): measures
What is Paid in terms of actual cost of the work that
has actually been accomplished to date.
The Earned Value Technique
BC WP
Schedule Performance Index (SPI) =
BC WS
BC WP
Cost Performance Index (CPI) =
AC WP
Project Performance Indices
SPI
Schedule Schedule
Advantage >1 Advantage
Cost Overrun Cost Saving
CPI
<1 1 >1
◼ A 32-day project
◼ Indirect cost = $500/day (total = ?)
◼ Indirect cost is distributed in a balanced way
◼ Reporting Period = 8 days
Example
$2,000 / $125,000
1.6 x $16,000
$500/day x 32 days
Example
1 2 3 4
100% cost
100% cost
100% cost
4/8=50%
2/10
Example
1 Budget Cost for period 1 =
1x$2,256
+ 1x$11,280
+ 1x$4,512
+ 0.5x$20,304
+ 0x$22,560
+ 0.2x$16,920
+ 0.125x$13,536
+ 0x$18,048
+ 0x$11,280
+ 1x$11,280
+ 0x$9,024 =$44,556
Example BCWS
BCWS
1 2 3 4
BCWS 44,556 53,016 24,929 18,499
$150,000
$141,000
$122,501
$100,000
$97,572
Cost
$50,000
$44,556
$- $-
0 8 16 24 32
Time
Example Now
Example ACWP
ACWP
1 2 3 4
ACWP 38,659.72 46,777.78
$150,000
BCWS $141,000
$122,501
$100,000
$97,572
Cost
$85,438
$50,000
$44,556
ACWP
$38,660
$- $-
0 8 16 24 32
Time
Example BCWP
BCWP
1 2 3 4
BCWP 38,634 53,016
$150,000
BCWS $141,000
$122,501
$100,000
$97,572
$91,650
Cost
$85,438
$50,000
$44,556
ACWP
$38,660
$38,634
BCWP
$- $-
0 8 16 24 32
Time
3. Forecasting at Completion
◼ The Estimate at completion (EAC) =
BCWS at completion + (ACWP – BCWP)
at present
◼ EAC = 141,000 + (85,438 – 91,650)
= $134,788
Cash Flow
profit
Max. amount of cash
needed, at period 5
Expense
S-Curve
Income profile
1 2 3 4 5 6 7
Cash Flow Example
1.6 x $16,000
$500/day x 32 days
Cash Flow Example
1 2 3 4
100% cost
100% cost
100% cost
4/8=50%
2/10
Cash Flow Example
1 Direct Cost for period 1 =
1x$2,000
+ 1x$10,000
+ 1x$4,000
+ 0.5x$18,000
+ 0x$20,000
+ 0.2x$15,000
+ 0.125x$12,000
+ 0x$16,000
+ 0x$10,000
+ 1x$10,000
+ 0x$8,000 =$39,500
Cash Flow step3