04A - 1352 Pipe Drainage
04A - 1352 Pipe Drainage
04A - 1352 Pipe Drainage
1 GENERAL
1.1 RESPONSIBILITIES
General
Requirement: Provide the pipework for the drainage system, as documented.
1.2 CROSS REFERENCES
General
Requirement: This worksection is not a self-contained specification. In addition to the requirements of
this worksection, conform to the following:
- 0136 General requirements (Construction).
- 0152 Schedule of rates (Construction).
- 0161 Quality management (Construction).
- 0319 Auxiliary concrete works
- 1101 Traffic management.
- 1171 Subsurface drainage.
- 1351 Stormwater drainage (Construction).
- 1354 Drainage structures.
- 1392 Trenchless conduit installation.
- [complete/delete]
1.3 INTERPRETATIONS
Definitions
General: For the purposes of this worksection the following definitions apply:
- Effective pipe length: The centre-line length dimension specified by the manufacturer and subject to
permissible tolerances.
1.4 SUBMISSIONS
Execution
Invert protection to steel pipes: Submit cement slurry application procedure.
Products and materials
Product conformity: Submit manufacturer’s certificate of conformance to the relevant standard for each
batch of pipes before dispatch to site. Identify the item, source and record the inspection and test
records that verify conformity.
Manufacturer’s data and installation recommendations: Submit in conformance with AS/NZS 2041.4
Appendix A and AS/NZS 2041.6 Appendix A, AS/NZS 4058 Appendix B and AS 4139 Appendix A, as
appropriate.
Samples
Components: Submit pipes and fittings.
Pre-treatment: If necessary to represent the condition and grading when compacted and in service,
pre-treat samples.
Tests
2 MATERIALS
3 EXECUTION
3.1 ESTABLISHMENT
General
Excavation: To the 1351 Stormwater drainage (Construction) worksection.
Excavation drainage: Dewater the excavation to permit the compaction of the foundation, the bedding
and backfilling, as documented.
Tolerances dimensions: Provide culverts within 10 mm of the grade line and within 10 mm of the
horizontal alignment, as documented.
Subsurface drain location: At the discharge end of culverts terminating at pits and headwalls, provide a
3 m length of 100 mm diameter subsurface drain, as follows:
- Position in the trench 100 mm above the invert level of the pipe.
- Discharge through the wall of the pit or headwall.
- Seal the subsurface drainage pipe at the upstream end and enclose in a seamless tubular filter
fabric to the 1171 Subsurface drainage worksection.
Damage
Pipeline components: Inspect all pipe line components for damage and flaws immediately before
installation.
Damaged components: Repair damaged components in conformance with manufacture’s
requirements. Replace units components, if unable to repair satisfactorily.
3.2 INSTALLATION
Concrete pipes
Standard: To AS/NZS 3725.
Positioning of pipes: Lay pipes as follows:
- Install with the socket end upstream.
- Install pipes with markings indicating the crown or invert in conformance with the markings.
Minimum pipe length: 1.2 m.
Stiffening of pipes: If required by the manufacturer, provide temporary stiffening struts to the interior
before back filling.
Lifting holes: Before backfilling, seal lifting holes in all pipes with approved plastic preformed plugs or a
3:1 sand cement mortar.
Bulkhead locations: Construct bulkheads to the 1354 Drainage structures worksection on all lines
where the pipe gradient exceeds 5%.
Anchor blocks: Provide anchor blocks at a maximum spacing of 3 m and at bends or junctions for all
stormwater pipes laid on a grade more than 20% and as documented.
Joints for concrete pipes
Joint testing: Test joints, as follows:
- Precast concrete pipes: To AS/NZS 4058 Appendix H.
- Fibre reinforced concrete pipes: To AS 4139 Appendix L.
Skid rings: To the manufacturer’s recommendations, including the use of lubricants, if wedge shaped
‘skid’ rubber rings are required.
Flush or butt joints: Seal the joints with proprietary rubber sleeves to the manufacturer’s
recommendations.
Other joints: Provide direct side connections to other pipes, as documented.
Flexible plastic pipes
Standard: To AS/NZS 2566.2.
Positioning of pipes: Install pipes with markings indicating the crown or invert, or the direction of flow in
conformance with the markings.
Bulkheads: If required, provide bulkheads or trenchstops to AS/NZS 2566.2 Table 5.7 or as
documented.
Flotation prevention: To AS/NZS 2566.2 clause 5.5.3.
Corrugated metal pipes and structures
Standard: To AS/NZS 2041.2.
Joints to helically formed sinusoidal pipes: Provide as follows:
- Re-roll both ends with 4 annular corrugations of pitch 68 mm.
- Semi-corrugated coupling bands
- Rubber ring joint seals, as documented.
Joint protection: Provide non-woven geotextile material to prevent loss of sand backfill or bedding into
the pipe in to the requirements for geotextiles in the 1171 Subsurface drainage worksection and as
follows:
- Extent: All joints or lap joints, except rubber ring joint coupling bands.
- Geotextile material: Minimum 250 mm wide and minimum 270 grams/m2.
Bedding: Provide non-erodible poured concrete bedding to the bottom third of the pipe circumference
to provide external protection of corrugations, as documented.
Invert protection for steel pipes
Surface preparation: Remove any foreign material and if corrosion has occurred, remove all loose
scale.
Extent: Place sprayed concrete to a minimum thickness of 100 mm over the crest of the corrugations
to cover the bottom third of the pipe circumference symmetrically about the invert centreline of the
pipe, as documented.
Sprayed concrete: To the 0319 Auxiliary concrete works worksection.
Reinforcement: Fabric of hard drawn steel wire 4 mm diameter with 200 mm square mesh, securely
supported at a central location within the sprayed concrete by non-metallic supports on the pipe side
of the fabric and as follows:
- Laps in fabric: 300 mm.
- Cover to the fabric: 50 mm.
Cement slurry application: Immediately after placement of the sprayed concrete, remove all free water
and coat the surface with cement slurry.
Water flow: Prevent the flow of water over the surface of the sprayed concrete for 24 hours after the
placement of sprayed concrete.
Bedding: Provide non-erodible poured concrete bedding to the bottom third of the pipe circumference
to provide external protection of corrugations, as documented.
3.3 COMPLETION
Pipework installation
Progressive inspections: Inspect each section of installed and jointed pipework before commencement
of trench backfilling.
4 ANNEXURE
Product conformity
Conformity of
components
Damage
Elastomeric seal.
Joints for concrete
pipes Check V ring joints
Pipework installation
*H = Hold point
W = Witness point
4.2 ANNEXURE - PAY ITEMS
Pay items Unit of measurement Schedule rate scope
1352.1 Supply and install pipe Linear m of pipe drainage culvert: The Schedule rate for this Pay Item to
drainage culverts, pipes, structures. be a rate for each type, class and size
- Measured on centreline of each of pipe culvert.
type, class and size of stormwater
drainage pipe culvert. All costs associated with all activities
- The plan length between centres of including:
gully pits or faces of headwalls.
- Supply.
- Survey and setting out.
- Bedding.
4.3 ANNEXURE - REFERENCED DOCUMENTS
The following documents are incorporated into this worksection by reference:
AS/NZS 1260 2017 PVC-U pipes and fittings for drain, waste and vent application
AS/NZS 5065 2005 Polyethylene and polypropylene pipes and fittings for drainage
and sewerage applications