Installation of Control Valves - MV - 39 and 40

Download as pdf or txt
Download as pdf or txt
You are on page 1of 4

Installation of Valves MV 039 and MV 040 in SBR Blowers Manifold 

With reference to the above‐mentioned valves are clarifications are as under: 

A. Clauses in Particular Specifications PS6 Process Equipment state as below: 
 
Clause PS 6.1 ‐ This section demonstrates only the minimum requirement for the works; 
however, the EPC Contractor undertakes all things necessary for the design, construct, 
commission and handover the project and ready for the use of the Owner/End User. 
 
And  
 
Clause  PS  6.1.2  ‐  The  following  Particular  Specifications  detail  the  particular 
requirements of the process equipment the Contractor shall provide for the Plant and 
should be read in conjunction with other sections of these Particular Specifications, the 
Haya Standard Specifications and the Haya Design Manual. 
 
And  
 
Clause  PS  6.1.3  ‐  The  Contractor’s  process  designs  and  equipment  selections  should 
provide  all  the  operational  flexibility,  functionality,  and  redundancies  as  shown  in  the 
P&IDs that are included with the Contract Drawings and as described herein. 
 
And  
 
Clause  PS  6.1.4  The  Contractor  shall  be  responsible  for  providing  all  structures, 
buildings,  civil  works,  materials,  equipment,  and  instrumentation  necessary  for 
completing  the  Plant  to  meet  the  required  functionality  of  process  equipment  as 
described herein. 
 
And  
 
Clause PS 6.1.5 This section demonstrate only the minimum requirement for the works; 
however, the EPC Contractor undertakes all things necessary for the design, construct, 
commission and handover the project and ready for the use of the Owner/End User. 
 
And  

All  mechanical  and  process  equipment  installed  in  or  on  pipelines  (air,  water, 
wastewater,  sludge  etc.)  including  but  not  limited  to  valves,  pumps  and  flow  meters 
shall include dismantling joints to allow removal of the item without the requirement to 
dismantle the adjacent pipework.  
 

Page 1 of 4 
 
And  
 
Clause  PS  6.1.11  Apart  from  this  specification,  the  detailed  study  and  scope  of  works 
shall  be  read  and  included  from  the  attached  Preliminary  Design  Report  Rev  –  07  for 
Process Equipment and Tender Drawings.  
 
Clause  PS  6.1.12  the  preliminary  design  and  the  engineering  documents  shall  be 
considered for guidance only.  
 
B. Clauses in Particular Specifications PS7 ICA state as below:  
 
Clause PS 7.1.1: 
 
This  specification  describes  the  minimum  requirement  and  generic  in  all  required 
facilities for ICA systems, the Contractor is responsible to ensure that all necessary 
ICA hardware & software units are provided to make the system complete and meet 
requirements and control functions for expansion of A’Seeb sewage treatment plant 
and related pumping stations to support increasing plant capacity to 80,000 cum/d.  
 
AND 
 
ICA  system  shall  be  expanded  to  cover  demands  of  Phase‐II  in  control  and 
monitoring  of  the  A'Seeb  STP,  Main  pumping  stations  (MPS‐l,  MPS‐2)  and  two  TE 
pump  stations  (Al‐Khoudh  and  Mobellah)  and  other  works  listed  under  scope  of 
work  section,  in  addition  to  all  related  ICA  works  resulted  by 
process/mechanical/operation  requirements.  The  Contractor  must  consider  any 
related integration with Al Ansab existing STP to supervisory control and monitoring 
process facilities for first & second phases. 
 
AND 
 
The  contractor  shall  furnish  all  equipment,  provide  needed  engineering  to 
accomplish the functional and technical requirements in all contract documents and 
drawings,  including  but  not  limited  to  design  assistance,  coordination  with  on‐site 
area,  detailed  system  design,  in  addition  to  supply,  shipment,  storage,  job  site 
delivery,  programming  and  configuration,  installation,  commissioning,  training, 
calibration, testing, and start‐up works. 
 
AND 

It  is  not  the  intention  to  specify  all  details  of  design  completely,  construction  and 
installation herein. Nevertheless, the equipment and installation shall conform to a 
high  standard  of  engineering  design  and  workmanship  in  all  respects  and  shall  be 
capable of performing in a continuous operation.  Items not specifically mentioned 
but required to make the system complete shall be treated as included, supplied, 
and installed under contractor scope of work. 

Page 2 of 4 
 
 
C. Clause  PS  7.1.2  Contractor  scope  is  derived  from  any  obligation  mentioned  in  all  particular 
specifications,  drawings,  or  any  further  requirement  arisen  in  detailed  engineering  to  fulfil 
complete process demands in plant expansion.  
 
D. Under  PS  7.1.3  ‐  Miscellaneous  Works  ‐  Any  other  work  under  tender  documents  (specs, 
drawings, and bills of quantity). 
 
E. Clauses in SCHEDULE 19a ‐ PRICING PREAMBLES. 
 
Clause 1.2 The Price Schedules herein, including all notes and instructions, form an integral 
part  of  the  Contract  Documents.  However,  the  descriptions  contained  in  the  Schedule  of 
Prices  for  each  item  are  not  necessarily  complete.  The  Contractor  is  referred  to  the 
Conditions of Contract and other Documents, Specification, Schedules and Drawings as well 
as relevant Standards and Codes of Practice for further information as no claim or variation 
shall be considered on account of the Contractor's failure to do so. 
 
Clause 1.3 The Contractor is cautioned to familiarize himself with the full content of other 
Contract Documents including the Tender Form, General Conditions, Particular Conditions, 
Tender  Drawings,  Specification  and  Schedules  or  any  other  information  that  can  be 
reasonably inferred from any of them and all obligations contained in the documents shall 
be included in the item rates and sums. 
 
Clause 1.4 Drawings, Specification, Schedules and Schedule of Prices and all other Contract 
Documents  are  complementary  and  if  any  item  is  included  in  any  of  them,  it  shall  be 
deemed included in all. 
 
Clause  1.6  The  Contractor  shall  not  use  this  Schedule  of  Prices  as  the  basis  for  a 
construction  programme  or  for  the  purposes  of  ordering  Materials  or  arranging  sub‐
contracts  or  assessing  the  required  quantities,  types  or  descriptions  of  Materials.  The 
references  for  these  matters  shall  be  the  Specification  and  drawings  and  any  instructions 
issued by the Engineer. 
 
Clause 3.2 The prices shall be comprehensive and shall include for complying in all respects 
with the Conditions of Contract, Specification and Drawings and for all matters and things 
necessary  for  the  proper  construction,  completion,  and  maintenance  of  the  whole  of  the 
Plant.  No  claims  for  additional  payment  shall  be  allowed  for  any  error  or 
misunderstanding by the Contractor of the work involved. 
 
Clause  3.3  The  prices  inserted  in  the  Schedule  of  Prices  are  deemed  to  include  for  the 
following: 
 Without  limitation  any  and  all  other  activities  which  are  not  included  above  and 
required for completion of the works. 
 

Page 3 of 4 
 
F. Clauses in Schedule of Prices. 
 
Please refer to item No. A2.2 & A3.25 and B1.25 
 

 
 
  
Conclusion: 

According to the above contract clauses, it can be concluded as below: 

‐ Particular Specification describes the minimum requirements. The contractor scope of work 
shall be extracted from the whole of the tender documents. 
‐ The  Contractor’s  process  design  and  equipment  selections  should  provide  all  the 
operational  flexibility,  functionality,  and  redundancies  as  shown  in  the  P&IDs  that  are 
included with the Contract Drawings. 
‐ Items not specifically mentioned but required to make the system complete shall be treated 
as included, supplied, and installed under contractor scope of work. 
‐ Contractor  scope  is  derived  from  any  obligation  mentioned  in  all  particular  specifications, 
drawings,  or  any  further  requirement  arisen  in  detailed  engineering  to  fulfil  complete 
process demands in plant expansion.  
‐ The  Contract  price  shall  include  any  missing  items  and  not  mentioned  in  BOQ  but  are 
required  according  to  the  Conditions  of  Contract  and  other  Documents,  Specification, 
Schedules  and  Drawings  as  well  as  relevant  Standards  and  Codes  of  Practice    No  claim  or 
variation shall be considered on account of the Contractor's failure to do so. 
 
Hence,  according  to  the  above,  the  two  valves  MV  039  and  MV  040  shall  be  provided  by 
EPPM. 
 
 
 
 
 
 
 
 
 
 

Page 4 of 4 
 

You might also like