TWENTY-FIFTH REPORT
NEW DELHI
CPU.. ____
TWENTY- FIFTH REPORT
(2018-2019)
INTRODUCTION (v)
CHAPTER I Report 1
APPENDICIES
MEMBERS
Lok Sabha
1. Shri L.K. Advani
2. Shri Ramesh Bais
3. Shri B. Vinod Kumar
4. Shri G. Hari
5. Dr. Hari Babu Kambhampati
6. Shri Ajay Nishad
7. Shri Prahlad Singh Patel
8. Shri Shanta Kumar
9. Shri Nagendra Kumar
10. Prof. Saugata Roy
11. Adv. Narendra Keshav Sawaikar
12. Shri Ravneet Singh
13. Shri Sushil Kumar Singh
14. Shri Rameswar Teli
15. Vacant
Rajya Sabha
SECRETARIAT
3. The Committee considered and adopted the draft Report at their sitting held on
03 December, 2018.
CHAPTER I
This Report of the Committee deals with the action taken by the Government on
the observations/recommendations contained in the Nineteenth Report (Sixteenth Lok
Sabha) of the Committee on Public Undertakings (2017-18) on “National Highways
Authority of India (NHAI)" which was presented to Lok Sabha on the 2nd August, 2018.
It contained twenty-seven observations/recommendations.
2. Action taken notes have been received from the Government in respect of all the
twenty-seven observations / recommendations contained in the Report. These have
been categorized as follows:
" The Committee observe that to accelerate the construction process, the
Ministry of Road Transport and Highways had set an ambitious target of
awarding 25,000 km of National Highways for the year 2016-17 while the
construction target was set at 15,000 km. out of the total length of Highways
targeted for awarded, 10,000 km was the target of NHAI and its target for
construction was fixed at 8000 km. However, the Committee are disappointed to
note that during the year 2016-17 (as on March 2017), 4336 km of roads were
awarded and 2628 km were constructed by NHAI against the targets of 10000
km and 8000 km respectively. In view of the above, the Committee feel that
despite remedial steps taken by NHAI and the Ministry to accelerate the
construction process of highways, current progress of construction of highways
has, perhaps, not gained the requisite momentum even during 2016-17. Hence
the Committee opine that there is a need to further analyse factors hindering the
progress of construction of highways during this period too. Further, taking note
of the responsibility assigned to NHAI to construct new roads of 6000 km in
border areas under the ambitious Bharat Mala project, the Committee desire that
the procedures should be completed in time. They desire further to be apprised
of the progress made in this project at the action taken stage."
Further, to expedite the project appraisal and approval, the Board of NHAI
(Authority) has been delegated the power for appraisal and approval of projects
with certain limits. The Board of NHAI (Authority) has also been authorized to
delegate its power for approval within NHAI. Accordingly, a Committee has also
been constituted namely Project Appraisal and Technical Scrutiny Committee
(PATSC) for appraisal and technical scrutiny of projects.
Of the total length identified for Border and International Connectivity Roads,
2,000 km have been approved to be implemented in Bharatmala Pariyojana
Phase-I. Under Border Roads category, projects with aggregate length of 970 km
have been awarded by June, 2018. Feasibility Study / DPR works for a total
length of about 1790 km is under process. Under International Connectivity
Roads category, an aggregate length of about 50 km have been awarded by
June, 2018. Feasibility Study/ DPR works for approximately 1310 km is under
process."
7. In the subsequent Recommendation No. 5, the Committee had recommended as
follows :-
"PPP Model: From BOT to Hybrid Annuity Model – From the deposition of NHAI,
the Committee note that poor performance of concessionaries on account of
economic slowdown is a major factor responsible for delay in Build Operate and
transfer (BOT) projects under the PPP model. Most of the delayed projects
under the BOT mode of execution could not takeoff in the wake of economic
slowdown as developers were not able to finance the projects due to their over
leveraged balance sheets. Further, due to reduced growth of traffic and lesser
revenue realization consequently, the concessionaires could not meet their debt
service obligations and defaulted in their debt accounts. As a result of the
aforesaid factors, financial viability of BOT mode of projects got heavily
jeopardized.
While taking note of the reasons for sluggish performance of BOT mode of
projects, the Committee observe that apart from economic slow-down, sluggish
performance of BOT projects can also be attributed to deficiency in the planning
and execution capacity of the Government as well as delay in acquisition of land
and arrangement of requisite regulatory approvals for the projects under BOT
mode. The Committee feel that the Government introduced PPP model without
due planning and even without creating an enabling policy environment for
successful implementation of such a model. In this connection, the Committee
recall the recommendations made by the Kelkar Committee constituted by the
Ministry of Finance which has inter-alia recommended that PPP model should
not be used at the first delivery mechanism without checking the suitability for a
particular project. Kelkar Committee has also recommended for constitution of a
infrastructure PPP Projects Review Committee to examine the performance of
PPP projects and legacy issues associated with these projects. While taking
note of recommendation of Kelkar Committee this Committee desire that the
Government should examine the reasons for failure of BOT mode under PPP
model and take suitable measures to revive the languishing projects. In this
direction the Committee take note of some of the initiatives taken by NHAI to
revive the languishing BOT projects. These include permitting 100 percent
equity divestment after two years of construction completion for all BOT
projects, equity infusion in BOT projects and rationalization of compensation to
concessionaire in case of delays not attributable to them. The Committee are of
the view that in view of the huge cost of infrastructure development projects,
there is a need to mobilize resources from sources other than Government
funding and therefore, it is imperative that the project execution model under
public-private partnership remains reasonably attractive for the private investors.
The Committee, accordingly, support the initiatives taken by the Government to
revive the languishing BOT projects by making them more conducive to the
demands of private investors, and desire to be apprised of the impact of these
measures on ground.
The Committee also feel that it is equally important to ensure that private
investors do not manipulate the contract provisions of concession agreement to
generate profuse returns at the cost of public interest. The Committee hence are
of the view that it is the responsibility of NHAI to protect the interest of highway
users as well as the Government in all public-private partnership contracts.
In view of the fact that most of the projects awarded under the BOT modes of
PPP model could not be completed on time, the Committee find that the
Government introduced a new ‘Hybrid Annuity Model (HAM)’ of project
execution combining the main features of two prevailing models i.e. Build
Operate Transfer (BOT)-Annuity & Engineering, Procurement and Construction
(EPC).
In this regard, they were informed that unlike the BOT models, HAM assures
better risk allocation amongst private concessionaires and NHAI/Government as
40% of bid project cost shall be payable to the concessionaire by NHAI in five
equal installments linked to project completion milestones and concessionaries
shall have to bear the balance 60% of bid project cost through combination of
equity and debt. With assured annuity payments to concessionaries it is
expected that the operations & maintenance risks during construction and
operation period will be mitigated and it will also allay the apprehensions arising
out of the uncertainty in traffic volume. Further, HAM projects are expected to be
completed on schedule as payments to concessionaire have been linked to the
project completion milestone which are based on both physical and financial
progress unlike the BOT mode wherein the project completion milestone were
based on financial progress only. During 2016-17, out of the total awarded
projects of 4336 km by NHAI, projects of 2434 km have been awarded under
HAM. The Committee are glad to learn that with HAM projects getting
momentum, total length of road construction by NHAI has also increased to
2628 km during the year 2016-17 from 1987 km during the year 2015-16.
Taking note of the successful beginning of HAM projects and interest shown by
investors for these projects, the Committee appreciate the efforts of the
Government to revive the PPP projects in road and highways sector with
introduction of HAM. They hope that with its better risk allocation structure,
interest of private concessionaire in infrastructure sector could be revived. The
Committee also feel that if HAM projects are implemented with due caution,
many delayed projects may be expedited and stalled projects may be revived.
However, in view of the experience gained from the implementation of PPP
model so far, the Committee desire that for development of highways
infrastructure projects, PPP model, be it BOT mode or HAM, should be
preceded by proper planning and due assessment of the feasibility of the
projects.
While the Committee expect good progress of projects under the PPP model, as
is evident with the HAM mode, it is still a reality that the private sector does not
prefer projects which have low profitability for them. In such projects, the
Ministry has to come forward for public good. Hence the committee
recommended that the Ministry must adopt a proactive approach towards
highway construction throughout the length and breadth of the Country. They
have to also convince the private sector for enhanced participation in the same
as better road linkage translates into better industrial performance resulting into
better profits for all stakeholders."
(ii) Lack of availability of debt products aligned with revenue stream profile of
highway projects.
Ministry, after having duly considered the recommendations of Kelkar Committee, had
taken the following measures for revival of languishing projects:
(i) MoRTH has been taking proactive steps to identify bottlenecks involved in
awarded but languishing NH projects and address them through appropriate
policy initiatives in course of the last two and half years.
(ii) 73 NH projects with aggregate length of around 8,310 km were languishing
around three years back. These projects involved estimated capital investment of
around Rs. 1,00,000 crores that remained blocked. As a result of MoRTH
interventions, most of the languishing projects have been effectively put back on
track.
(i) Exit Policy – the policy enables private developers to take out their entire equity
and exit operational BOT projects two years from start of operations (COD)
irrespective of date of award thereby enabling reinvestment of such unlocked
equity.
(iv) One-time fund infusion – the policy enables revival and physical completion of
languishing BOT projects that have achieved at least 50% physical progress,
through one-time fund infusion by NHAI, subject to adequate due diligence on a
case to case basis.
(v) Introduction of Hybrid Annuity Mode - In the model, 40% Project Cost is provided
by the Government as ‘Construction Support’ and balance 60% as annuity
payments during operations period with interest (Bank Rate +3.00%). Separate
provision for O&M payments to concessionaire. The private party does not have
to bear the traffic and inflation risks. The model has been widely accepted by the
market.
(vi) Introduction of TOT model (Toll Operate Transfer) - In the Model, collection rights
for Toll Fees for operational public funded NH projects is assigned for a 30 year
concession period to concessionaires against upfront payment of a lump-sum
amount. O&M obligations is with the concessionaire during the concession
period. First round of bid completed at NHAI for TOT projects - bundle of 9
project stretches (length 680 km) bid out. H1 bidder quoted concession fee of Rs
9681.5 cr (against NHAI estimated Rs 6258 Cr).
(ix) The Ministry with the help of National Informatics Centre has developed a Web
Portal – BhoomiRashi, to digitize the entire process of land acquisition. LA
process has been expedited significantly through this initiative. BhoomiRashi has
also been integrated with the Public Financial Management System (PFMS)
platform of the Ministry of Finance, for deposition of compensation in the account
of affected/interested person, on real-time basis.
(x) Further, the Ministry issued comprehensive guidelines on Land Acquisition for
NHs vide letter No. NH-11011/30/2015-LA dated 28.12.2017 to simplify the
complex issues of Land Acquisition viz. applicability of certain provisions of
RFCTLARR Act 2013 on NH Act 1956, date of determination of market value of
land, issue of multiplication factor, bulk acquisition through consent of land
owners etc.
(xi) Electronic Toll Collection (ETC) is being encouraged to minimize toll collection
time and reduce pilferage in toll collection on NHs. Enabling facilities for ETC
being put proactively in all toll plazas. Out of the total 429 Toll Plazas, 275 Toll
Plazas are on PPP Concession Roads and 154 are on Public funded road
assets. Of these, all lanes have been equipped with the requisite Infrastructure in
case of 165 PPP Toll Plazas and 77 Public Funded Toll Plazas. Further, 108
PPP Toll Plazas and 24 Public Funded Toll Plazas have been equipped with two-
lane dedicated ETC Infrastructure. 32,86,918 lakh FASTags have been sold so
far (as on 25.10.2018) and average daily toll collection through ETC has reached
22.5 % of total toll revenue.
In view of the above, the Committee are of the opinion that while it may not be practical
to completely rule out the practice of sub-contracting, NHAI should explore the
possibility of imposing certain restrictions with respect to sub-letting of contracts, in
order to ensure quality of work and timely completion of projects. This could also be
done by levying of penalty on the main contractor if the sub-contractor leaves the
project incomplete. Registration of sub-contracts and blacklisting of contractors may
also be made mandatory to ensure that practice of sub-contracting does not affect the
projects adversely. The Committee would like to be apprised about the preventive
action taken in the matter."
11. The Ministry, in their action taken reply, have stated as follows :-
"To strengthen the resources available with the Contractor for execution of the project,
practice of sub-contracting is resorted to. This is admissible under contract. Adequate
provisions are there in the contract agreements to ensure that the main contractor, who
is fully responsible to the employer for the work, complies with the various terms of the
agreement irrespective of employment of sub-contractor for the work. Following
provision exist in various contract document in this regard:
(a) Clause 2.1.18 of the RFP for BOT (Toll) projects stipulates as under:
(i) The Bidder, in case it does not have the O&M experience specified
in Clause 2.2.3 of the RFQ, by submitting its Bid, shall be deemed to
acknowledge and agree that for a period of at least 5 (five) years from the
date of commercial operation of the Project, it shall enter into an
operation& maintenance (O&M) agreement with an entity having the
specified experience, failing which the Concession Agreement shall be
liable to termination.
(ii) The Bidder would provide an undertaking to NHAI that EPC works
of the project would be executed only by such EPC contractor who have
completed at least a single package of more than 20% of the TPC or
Rs.500 Cr, whichever is less. An undertaking to this effect shall be
provided by the Bidder.
3. EPC Projects:
12. The Committee in their original report while noting that due to the sub-
contracting by the main contractors, quality of work has significantly suffered in
many projects, had recommended for making provision for levying of penalty on
the main contractor, if the sub-contractor leaves the project incomplete as well as
mandatory registration and blacklisting of such contractors. The Ministry in the
action taken note have drawn the attention of the Committee to the provisions
made in various contract documents under BOT, HAM and EPC Model whereby
the whole responsibility for the work seems to rest with the main contractor.
While appreciating for having such provisions in the contract, the Committee
note that in the absence of some sort of regulatory provisions for sub-
contractors, poor performing sub-contractors continue to be given work by the
contractors thereby affecting the quality of projects. The Committee in this regard
had recommended for making provision for registration of sub-contracts and
blacklisting of contractors to which the Ministry has chosen not to respond. The
Committee would, therefore, like to reiterate their earlier recommendation and
would like the Government to act upon their recommendation and apprise them at
the final action taken stage.
Recommendation (Sl.No. 9)
13. The Committee in their Nineteenth Report, had recommended as follows :-
"Audit Issues - The Committee observe that the C&AG, in course of their examination of
the accounts of NHAI during the year 2013-14 and 2014-15, had noticed several
discrepancies in the accounts and other records of NHAI. As per Audit observations, the
balance sheet and profit-loss accounts of NHAI were not drawn up in accordance with
the format approved by the Government of India under NHAI Act, 1988. They further
observe to their dismay that since the issues raised by Audit were not resolved, Audit
had to issue a disclaimer certificates stating their inability to form a firm opinion about
whether the financial statement of NHAI was true and fair. The Committee note that
NHAI, as a follow up, had appointed M/s KPMG to submit a report on the issues raised
by C&AG and their report is currently being analyzed by an expert Committee of C&AG.
The Committee regret to note that despite being a Statutory body, the account books of
NHAI were found as not being maintained in accordance with desirable GOI standards
by the C&AG for the year 2013-14 & 2014-15. Deviation from the standard accounting
principles is not justified and NHAI should maintain its accounts as per the format
prescribed by the C&AG so as to enable the Audit to have a meaningful assessment of
the financial performance of NHAI. The Committee desire to be apprised about the
comments of the expert Committee appointed by the C&AG on the same. The
Committee also urge the Ministry of Road Transport and Highways to take note of the
recommendations of the said expert Committee and ensure their implementation by the
NHAI so that the accounting standard of NHAI does not attract any adverse comments
from the C&AG in future."
14. The Ministry, in their action taken reply, have stated as follows :-
"The format of accounts was prescribed by C&AG in the year 1992. The present format
is 25 years old. Since the time C&AG prescribed this format several changes have
taken place in the working and reporting requirement of NHAI. Accordingly, year after
year based on the reporting requirements some minor changes were made in the
existing format of accounts. These were mostly data/information which was neither
required nor considered at the time of prescription of format by C&AG in the year 1992.
Since the inception of NHAI, C&AG is auditing NHAI accounts on yearly basis.
However, the issue of change in format of accounts has been raised by C&AG in the
last few years’ audit report.
The issue of changes in the format of accounts was discussed with C&AG officials and
it was decided to appoint a financial consultant for expert opinion on the matter and also
to suggest a new format of accounts. Accordingly, M/s KPMG was appointed as
financial consultant in this regard. M/s KPMG have submitted their report along with
revised format of accounts and the same is to be approved by the Ministry in
consultation with C&AG. Ministry has held a meeting with C&AG and NHAI. The new
format is being finalized by NHAI whose report is awaited.
In view of the above, the disclaimer issued by C&AG in the annual accounts 2014-15 &
2015-16 have been withdrawn in the annual accounts 2016-17."
15. The Committee find that M/s KPMG, the financial consultant appointed with
regard to the issue of changes in the format of accounts pursuant to several
discrepancies noticed by C&AG during the year 2013-14 and 2014-15 in the
accounts and other records of NHAI, has now submitted their report along with
revised format of accounts and the same is to be approved by the Ministry in
consultation with C&AG. While noting that the format of accounts of NHAI are 25
years old which unduly invites audit objections, the Committee would stress for
expeditious finalization of new format of accounts.
Management of Toll-plazas
"Management of Toll plazas – The Committee observe that location of toll plazas inside
the cities or densely populated areas results into chaotic traffic conditions causing
pollution, traffic hazard and inconvenience to highway users and the local population.
The Committee, therefore, recommend that NHAI should examine the feasibility of
setting up toll plazas away from the cities/ densely populated areas in order to avoid
inconvenience to public. Further, it has also been observed that in some toll plazas,
most of the toll counters are kept non-operational in order to reduce the cost. In some
toll plazas, users have also been inconvenienced by unscrupulous elements deployed
by toll operators for collection of toll charges, who many a times misbehave with users
or demand undue charges. In view of this, the committee feel that NHAI should develop
an inspection mechanism to monitor the management of toll plazas in order to ensure
that users are not troubled by the toll operators/collection staff. A well trained staff
needs to be deployed at toll counters and all complaints regarding the mismanagement
at toll plazas should be promptly enquired and suitable action taken."
17. The Ministry, in their action taken reply, have stated as follows :-
"Efforts are being made to locate / establish the toll plaza beyond 10 kms of the
municipal limit of a town/city. However, sometimes due to site constraints and
engineering consideration, the toll plazas are also established within the distance of 10
kms of the municipal limit as per the provision of National Highway Fee Rules 2008,
especially when the project is developed for the benefit of local users.
In order to not to give scope for complaints about misbehaviour by toll plaza staff,
display of concessions and information, NHAI also issued a policy circular dated
02.02.2016 for standardization of uniform of toll collection staff, user fee receipts, user
fee display boards at toll booths at both NHAI and concessionaire toll plazas. Further
following measures have also been taken:
(i) Efforts are being made to not give scope for complaints about misbehavior by toll
plaza staff. Toll plazas employees are being advised for courteous behavior with
road users for smooth implementation of user fee collection.
(ii) NHAI have established various HOU (Highway Operation Unit) in RO and PIUs
to avoid any mismanagement at toll plazas. These HOUs make regular visits to
ensure that the complaints have been resolved in time.
(iii) NHAI also proposed to conduct behavioural training to toll plaza employee
through IITTM (Indian Institute of Tourism and Travel Management) as per NHAI
circular no. NHAI/GM(T)HO/Misc./2018/79 dated 12.03.2018 to reduce toll
issues like ill treatment by toll plaza employees/ ETC or FASTag not working,
excess deduction of toll fee at toll plazas and other misc. type of complaints of
the toll plazas.
18. The Committee in their earlier recommendation had raised various issues
relating to management of toll-plazas NHAI in the action taken reply has
mentioned about the various steps taken in this regard which inter-alia include
issuance of circular for standardization of uniform of toll collection staff, user fee
receipts, user fee display boards, conducting behavioral training to toll-plaza
employees and adopting electronic tolling mechanism to avoid human interface
etc. The Committee observe that besides issuing circulars it is utmost necessary
to have monitoring mechanisms to ensure that the directions given through
various circulars are complied with thereby avoiding inconvenience to public.
The Committee in their recommendation had also raised the issue of all toll
counters not being kept operational at most of the toll-plazas in order to reduce
the cost by the toll operator thereby adding to the public inconvenience. The
Ministry / NHAI has not responded to the issue. The Committee would like a
categorical response in this regard.
Dedicated Highway Security Force
"The Committee have also been apprised that although law and order issues exclusively
come in the domain of State Governments, NHAI is planning to evolve a system to
ensure increased patrolling on National Highways every eight hours so as to deal with
issues of traffic congestions and other inconveniences to commuters. Taking note of the
growing security concern on Highways, the Committee recommend to consider creation
of a dedicated Highways Security Force similar to the General Railway Police Force
(GRP), for safeguarding the movement on National Highways. The aid of advance
technologies such as geo-tagging. Global Positioning System (GPS), positioning of
CCTV cameras in this direction on sensitive areas across the Highways are other steps
which can enhance the efficacy of the monitoring system. The Committee would like
NHAI to take action as suggested above and furnish the details about the specific action
taken in this regard."
20. The Ministry, in their action taken reply, have stated as follows :-
"NHAI have informed that they are in the process of conceptualization to set up a
National Highways Security Services in consultation with the DS&BPRD. However, no
formal proposal has been received in Ministry. Ministry would take a decision on it after
receiving and examining the proposal in this regard.
"Road Fatalities - The Committee note with concern that incidence of road deaths in
India is comparatively higher as compared to other countries. A Report prepared by the
Ministry of Road Transport and Highways on Road Accidents in India in 2015 states that
the total number of road accidents increased by 2.5 percent from 4,89,400 in 2014 to
5,01,423 in 2015. The total number of persons killed in road accidents increased by 4.6
percent from 1,39,671 in 2014 to 1,46,133 in 2015. Out of the total road accidents, 28.4
percent accidents took place on National highways. They note that Ministry of Road
Transport and Highways has set a target of reducing the number of road accident
fatalities to 50 percent by 2020 in line with the target of United Nations Decade for
Action on Road Safety. The committee appreciate that the Government has launched a
major initiative namely Pradhanmantri Sadak Suraksha Yojna (PMSSY) to improve the
safety on different categories of roads viz. National Highways, State Highways, major
district roads etc through engineering improvement measures. The Committee would
like to be apprised about the budgetary allocations and status of the implementation
with respect to PMSSY at the action taken stage."
23. "Pradhan Mantri Sadak Suraksha Yojna (PMSSY) has not been launched by the
Ministry of Road Transport and Highways. This Scheme is administered and
implemented through the Ministry of Rural Development. Therefore the details of this
scheme are not available."
24. The Committee take exception to the way the Ministry / NHAI has
responded to the recommendation seeking specific information about the
budgetary allocations and status of implementation of Pradhan Mantri Sadak
Suraksha Yojana (PMSSY). Even though the programme is being implemented
through the Ministry of Rural Development, avoiding the response to the issue
particularly when the Yojna has been launched to improve the safety on different
categories of roads which includes National Highways is not appreciated by the
Committee. In Committee’s view, NHAI should have followed the implementation
of the programme and if the specific data was not available, they could have
obtained from the concerned Ministry and placed before the Committee. The
Committee would like to be apprised of the details as desired in the earlier
recommendation.
"Construction of Common Underground Utility Ducts – The Committee find that roads
are frequently dug up for various purposes such as laying of gas pipelines, power lines,
phone lines and optical fiber cables for INTERNET availability etc. Frequent digging of
roads leads to inconvenience for public use causing traffic jams and water-logging, if
roads remain under digging for a long period without adequate repairing. Further,
repeated digging of roads and consequent destruction of road surface significantly raise
the maintenance cost of the roads. In view of the above, the Committee urge the NHAI
to conduct a study on the financial and technical viability of the idea of laying
underground utility ducts to facilitate the installing of gas pipelines, power and phone
lines and optical fiber cables etc. to reduce frequent digging of the roads. If found
feasible, NHAI may plan for making the laying of common underground utility ducts
mandatory for their road construction projects."
26. The Ministry, in their action taken reply, have stated as follows :-
"The Indian Road Congress have provided the guidelines for laying the Utility Ducts in
urban roads vide IRC-98:2011 and are being followed for urban areas. However, the
cost estimates for construction of common underground utility ducts all along the roads
are estimated to be about Rs.2.0 crore per km length. The service providers generally
lay their utilities depending upon their convenience and there are no provisions to force
them to utilize the ducts so constructed.
"Construction of concrete-Cement highways for better road quality - The Committee are
happy to note that owing to the multiple advantages of cement concrete pavement over
the traditional road paving surfaces, particularly bituminous roads, and construction of
cement concrete pavement is now being preferred by NHAI. The long term durability,
longer service life, lesser fuel consumption, and resistance to extreme weather
conditions etc. are various features that make Cement-Concrete an ideal material for
highways and roads which endure very large volume of vehicular traffic. The Committee
have been apprised that during the current Financial Year, out of the 26 projects
awarded for a length of 1502km, 17 projects covering the length of 967 km will be
constructed on cement concrete pavement. In this connection, the Committee recall the
recommendations made by the Department related Parliamentary Standing Committee
on Commerce (2011) which in their 95th Report on “Performance of Cement Industry”
had strongly advocated the construction of roads including expressways using cement
concrete pavement. In the said report, the Committee while noting that about 40% of the
roads in developed Countries such as USA, West Germany etc. are made of cement
concrete whereas it is only 2% in India, had recommended for construction of cement
roads and highways to bring at par with international norms and standards. A cost-
benefit analysis of bitumen and concrete road over 25-30 year life cycle cost in
Rajasthan and Gujarat, which was undertaken by MoRTH, has suggested that the
variation of the price of cement vis a viz bitumen is required to be mapped out and
unless there is price comparison within an acceptable limits to 20%, the use of flexible
(bitumen) pavement may perhaps required to be continued. The Committee also agree
that with expansion of concrete-cement roads, it is important to undertake requisite cost
research, yet feel that once the quality of concrete and cement used in construction is
ensured so as to guarantee the long term durability of the roads, the savings on the
maintenance would offset the initial rise in cost of construction. Considering the lesser
fuel consumption, resistance to extreme weather conditions and long term durability of
concrete-cement roads, the Committee recommend that in future concrete-cement may
be used in construction of highways in place of bitumen as in being done in many
developed counties. In places where highways cannot be constructed using concrete-
cement, the reasons for these may be satisfied."
29. The Ministry, in their action taken reply, have stated as follows :-
"The initial cost of construction of Highways with cement concrete is more than Flexible
pavement. The initial cost of flexible pavement is less than that of rigid pavement but
having long-term maintenance requirement.
Based on the requirement of site conditions, maintenance requirements, life cycle cost
analysis of pavement longer service life, and resistance to extreme weather conditions,
saving of natural material etc. and as per directions issued vide Ministry of Road
Transport & Highways Circular No. RW/NH-33044/31/2014/S&R(R)/Part dated
04.08.2014, type of pavement is decided on case to case basis.
It can, therefore, be concluded that single type of pavement may not be suitable under
all conditions."
30. The Committee express unhappiness over the casual way the Ministry /
NHAI has responded to such an important issue concerning the construction of
highways. Instead of taking concrete action for analyzing various cost factors for
constructing concrete, cement highways, considering the lesser fuel
consumption, resistance to extreme weather conditions and long term durability
of these roads, it has casually been stated that type of pavement is decided on
case to case basis. The Committee while reiterating their recommendation would
like the Ministry/NHAI to take concrete action on their recommendation and and
apprised them at the final action taken stage.
National Green Highways Projects
Recommendation (Sl. No. 23 & 24)
31. The Committee in their Nineteenth Report, had recommended as follows :-
"National Green Highways Projects - The Committee note that the Ministry of Road
Transport and Highways have launched the National Green Highways Project to
develop green corridors along National Highways for sustainable environment and
inclusive growth which envisions development of eco friendly highways with
participation of various stakeholders. The Committee also note that National Green
Highways Mission (NGHM), established by Ministry of Road Transport and Highways
(MoRTH) under National Highways Authority of India (NHAI), has been entrusted with
the task of planning, implementation and monitoring roadside plantations and
building fences along one lakh kilometre network of National Highways. The
Committee, while acknowledging the fact that roadside plantation have immense
potential to enhance the green cover of the nation and also generate employment
opportunities for rural economy, feel that this initiative is a novel step towards
improving the aesthetics of highways while contributing in a big way towards
environment protection which is a global concern. However, the Committee regret to
note that during the year 2016-17 against the allocation of Rs.500 Cr. In Green
Highways Fund, no amount was actually received by NHAI, which implies that the fund
is yet to be operationalised and no work has been initiated under the National Green
Highways Mission. Further, no amount has been allocated for the said fund for the
year 2016-17. The Committee may be apprised of the reasons for not releasing money
for the Green Highways Funds."
32. The Ministry, in their action taken reply, have stated as follows :-
"The Committee also desire that the Government should allocate the release the
required funds under the Head ‘Green Highways fund’ and ensure its optimum
utilization for development of green corridors along National Highways. Further, the
Committee insist that in course of development of Green Highways Project,
appropriate exit gates for crossing the fenced highways for the public is provided at
appropriate distances and places so that movement of people living in habitations on
either side of highways are not inconvenienced. The Committee thus recommend the
Government to vigorously follow up the project of greening of highways at all levels."
34. The Ministry, in their action taken reply, have stated as follows :-
"Funding for greening of highways is not a constraint as plantations on the ROW are
part of all Highway Development Projects and the expenditure on plantations is made
out of the funds available with NHAI as done for land acquisition and utility shifting.
Fencing for the roadside plantations are raised depending on the requirement on the
site. Fencing of various types ranging from tree guards for individual saplings to multi
stranded barbed wire fences are recommended. However, there is no conflict on the
issue of providing passage to public wherever deemed necessary. On a high-speed
highway, access to public is not recommended all along the stretch. However, breaks
are provided in the plantation fences at appropriate places to provide access to the
public across the plantations. The recommendation of the Committee to vigorously
follow up the project of greening of highways at all levels is duly noted."
35. The Committee had in their earlier recommendation noted that National
Green Highways Mission (NGHM), established by Ministry of Road Transport and
Highways (MoRTH) under National Highways Authority of India (NHAI), has been
entrusted with the task of planning, implementation and monitoring roadside
plantations and building fences along one lakh kilometer network of National
Highways. The Committee, while acknowledging the fact that roadside plantation
have immense potential to enhance the green cover of the nation and also
generate employment opportunities for rural economy, and that this initiative is a
novel step towards environment protection which is a global concern, had
regretted that during the year 2016-17 against the allocation of Rs. 500 crore in
Green Highways Fund, no amount was actually received by NHAI. The Ministry of
Road Transport and Highways in their reply has stated that the Ministry of
Finance had objected to the creation of a separate Green Highways Fund and
advised the Ministry to obtain approval of the Cabinet / Cabinet Committee, if the
Ministry still feels that a separate Fund/SPV would yet be required to take their
proposal (of creating a Green Highways Fund) forward in the public interest.
The Committee observed that the Ministry of Road Transport and Highways
have further stated that funding for greening of highways is however, not a
constraint as plantation on the ROW are part and parcel of all Highways
Development Projects and the expenditure on plantations is made out of the
funds available with NHAI as done for land acquisition and utility shifting. The
Committee while taking note of the reply furnished by the Ministry, express their
unhappiness as to why the proposal for creation of a dedicated 'Green Highways
Fund' was then moved by the NHAI when admittedly funding for greening of
highways had not been a constraint. Further, NHAI in their replies have also not
made it clear as to whether the projected budgetory requirement Rs. 500 crore for
greening of Highways during 2016-17 had been met from their regular budgetory
allocations when the money had not been received by them from the Ministry of
Finance. The Committee would therefore like to be apprised about the factual
position on all these issues and also about the year-wise allocations made and
expenditure incurred in greening of highways during the financial years 2016-17,
2017-18 and 2018-19. The Committee being highly concerned about the depleting
green cover resulting in environmental degradation, strongly reiterate that the
project of greening of Highways should be earnestly taken up and pursued
vigorously at all levels for timely and sustainable plantations on roadsides as
admittedly being part of the Highway Development Project, no financial constraint
is there. The Committee would further suggest that provision of breaks in
plantation fences should also be made at appropriate places for public
movement.
*********
CHAPTER II
1.1 As on 31st March 2017, work for construction of 9,204 km of roads out of
remaining 19,956 km road length under 7 phases of NHDP were yet to be awarded. In
this regard, 3674KM of projects have been awarded under NHDP post 31st March 2017
up to 30th September 2018, thus expediting the completion of projects remaining under
NHDP.
1.2 Further, till 30th September 2018, out of the 438 number of projects completed, 75
were completed on or before time. Thus, the overall speed of execution of projects has
also improved.
1.3 The Ministry has, from time to time, also taken various measures for speedy
approval &timely completion of projects. Some of the important initiatives are as follows:
(i) The Ministry has made it compulsory for projects under the Engineering,
Procurement and Construction (EPC) mode to be awarded only after completion
of 90% of the total land acquisition required for project. This has ensured lesser
delays between award of projects and the start of construction of roads.
(iii) Bidder Information Management System (BIMS): It has been observed that
technical evaluation of bids during procurement of civil works contracts, takes
almost 2 months to be completed. To reduce the time and effort taken in the
evaluation, the Ministry of Road Transport and Highways (MoRTH) has
developed the Bidder Information Management System (BIMS) for pre-
qualification and technical evaluation during procurement of civil works contracts
for all the project implementation agencies. MoRTH, through its implementing
agencies, will be using the online Bidder Information Management System
(BIMS) for the management of bidder information and technical evaluation to
ensure an efficient and transparent bidding process. The use of BIMS will create
a comprehensive database comprising of bidder wise information such as basic
details, civil works experience, cash accruals, net worth, annual turnover, etc.
such that the evaluation can be carried out in a faster manner using this
information.
(iv) Project Monitoring Information System (PMIS): For ensuring timely delivery of
projects, a state-of-the-art single unified tool Project Monitoring Information
System (PMIS), has been developed in-house. PMIS has a comprehensive
database with over 180 data fields being tracked for each project and a further
500 fields specifically for complex PPP Projects, covering all key progress
metrics such as designed progress, contracting progress, construction progress,
land acquisition, compensation disbursement, toll and traffic information and
concession/contract information. A series of Executive Dashboards have been
designed to provide updated progress on all these data fields at various levels,
such as National level, Regional office (RO) level, Project Implementation Unit
(PIU) level & Project level. Apart from dashboards views of data, the PMIS is also
enabled with Geographical Information System (GIS), which provides a
geographical visualization of all NHAI projects on an Indian map.
1.4 Regarding dispute resolution, NHAI is faced with a large number of pending
claims, Arbitration and Court proceedings for disputes in their old contracts for many
years. The present dispute settlement mechanism of Dispute Resolution Expert (DRE),
Dispute Resolution Board (DRB) and Arbitration Awards with contradictory decisions
and varying approaches have not been able to effectively resolve the disputes with the
result that a large number of them have finally reached the Courts. It is felt that delay in
decisions and settlements may eventually result into large liabilities on NHAI including
substantial interest component in Awards. Various settlement procedures have been
examined across the PSUs, Authorities, Financial Institutions, Nationalized Banks etc.
and it is felt desirable to adopt a settlement approach on similar lines with the one-time
settlement (OTS) system in vogue in Nationalized Banks framed on the basis of RBI
guidelines.
The Cabinet Committee on Economic Affairs (CCEA) took a decision on 31.08.2016 for
the revival of the construction sector, as conveyed vide OM dated 05.09.2016 of NITI
Aayog, for establishing a system of conciliation of disputes through Conciliation
Committee of Independent Experts (CClEs) to ensure speedy disposal of pending or
new cases. Accordingly, NHAI Board in its meeting held on 19.05.2017 approved a
revised procedure and a proposal to set up CCIEs. Accordingly, the Policy Guidelines
have been issued on 02.06.2017 and placed on the website of NHAI. Two Conciliation
Committees of Independent Experts were constituted in which 02 eminent persons from
the industry had also been nominated. The conciliation/amicable settlement of disputes
can be explored through this new mechanism, before referring the disputes to arbitration
or to settle the disputes pending before the Arbitral Tribunals/ Courts. Till date around 10
cases have been referred to CCIEs out of which 01 case has been settled, 03 cases
could not be settled and the remaining 06 cases are under process.
The Committee observe that to accelerate the construction process, the Ministry
of Road Transport and Highways had set an ambitious target of awarding 25,000 km of
National Highways for the year 2016-17 while the construction target was set at 15,000
km. out of the total length of Highways targeted for awarded, 10,000 km was the target
of NHAI and its target for construction was fixed at 8000 km. However, the Committee
are disappointed to note that during the year 2016-17 (as on March 2017), 4336 km of
roads were awarded and 2628 km were constructed by NHAI against the targets of
10000 km and 8000 km respectively. In view of the above, the Committee feel that
despite remedial steps taken by NHAI and the Ministry to accelerate the construction
process of highways, current progress of construction of highways has, perhaps, not
gained the requisite momentum even during 2016-17. Hence the Committee opine that
there is a need to further analyse factors hindering the progress of construction of
highways during this period too. Further, taking note of the responsibility assigned to
NHAI to construct new roads of 6000 km in border areas under the ambitious Bharat
Mala project, the Committee desire that the procedures should be completed in time.
They desire further to be apprised of the progress made in this project at the action
taken stage.
Targets for award of civil works by National Highways Authority of India (NHAI)
fixed for year 2016-17 and 2017-18 were 15,000 kms and 10,000 kms respectively and
NHAI awarded civil works of length 4336 kms and 7397 kms in the year 2016-17 and
2017-18 respectively. Regarding construction, NHAI constructed 2628 kms and 3037
kms roads in the year 2016-17 & 2017-18 against the target of 4600 kms & 6000 kms
respectively. On analysing, it was observed that NHAI could not achieve these targets
specially in BOT (Toll) projects due to the following factors:
Further, to expedite the project appraisal and approval, the Board of NHAI (Authority)
has been delegated the power for appraisal and approval of projects with certain limits.
The Board of NHAI (Authority) has also been authorized to delegate its power for
approval within NHAI. Accordingly, a Committee has also been constituted namely
Project Appraisal and Technical Scrutiny Committee (PATSC) for appraisal and
technical scrutiny of projects.
Of the total length identified for Border and International Connectivity Roads, 2,000 km
have been approved to be implemented in Bharatmala Pariyojana Phase-I. Under
Border Roads category, projects with aggregate length of 970 km have been awarded
by June, 2018. Feasibility Study / DPR works for a total length of about 1790 km is
under process. Under International Connectivity Roads category, an aggregate length of
about 50 km have been awarded by June, 2018. Feasibility Study/ DPR works for
approximately 1310 km is under process.
Timely redressal of issues related to land acquisition – The Committee note that
with effect from 1st January, 2015, compensation for land acquired under NHAI Act
1956 is to be determined in accordance with provisions specified in Sections 26 to 29 of
the new Land Acquisition Act namely the Right to Fair Compensation and Transparency
in Land Acquisition Rehabilitation and Resettlement Act, 2013 (RFCTLARR Act, 2013)
and its First Schedule. NHAI, during the course of examination, have further added that
higher amount of compensation under the New Land Acquisition Act has antagonized
those farmers who are entitled for lesser compensation as their land had been acquired
before 1st January, 2015 under the old Land Acquisition Act. As a result, aggrieved
farmers are approaching courts for reasonable compensation and litigations with
respect to compensation issues have increased manifold which has further delayed the
land acquisition process. Further, in some cases resentment of farmers may have
serious implications for law and order situation and cause untoward incidents. While the
Committee welcome the provisions relating to enhanced compensation as per
RFCTLARR Act, 2013 in respect of the land acquired by NHAI under the NHAI Act, the
Committee are of the view that the issues related to the timely payment of
compensation need to be settled amicably with due consultation with the stakeholders.
As stated by the CMD, NHAI, during the evidence before the Committee, the cost of
compensation in lieu of land acquisition has increased around 2.5 times after
amendments in the Land Acquisition Act. From the figures provided to them, the
Committee note that the expenditure on account of land acquisition which was Rs. 9097
cr. during 2014-15, rose to Rs. 21933 cr. during the year 2015-16 due to the higher
amount of compensation proposed under the new Land Acquisition Act. In view of the
rising cost of land and time taken in the land acquisition process, the Committee are of
the view that instead of planning the highways development programme on the basis of
present quantum of traffic, NHAI should envisage a future oriented highway
development programme keeping in view the long term requirements of the highways
infrastructure so that the growth in traffic demand in future could be addressed without
any difficulty.
The suggestion of the Committee that NHAI should envisage a future oriented
highway development programme keeping in view the long-term requirements of the
highways infrastructure so that the growth in traffic demand in future could be
addressed without any difficulty is fully appreciated.
In this regard, it is stated that the entire network of highways identified for development
under Bharatmala Pariyojana is based on an Origin-Destination Study on freight
movement across the country along with data from traffic surveys at more than 4500
locations on the National Highway network. It is a programme targeted to take care of
the future growth in traffic on National Highways. In order to reduce the cost of Land
Acquisition for National Highways, the Ministry is studying and examining the feasibility
of developing greenfield corridors connecting major cities.
Besides, the Ministry of Road Transport & Highways has developed Bhoomi Rashi
Portal through which the entire process of LA for National Highways including payment
of compensation has been digitised. While physical publication of LA notification used to
take 4-6 months, it has come down to less than 15 days with the help of the Portal. The
land is acquired for NH projects under the provisions of NH Act 1956 and the amount of
compensation is determined by CALA in accordance with the First schedule of
RFCTLA&RR Act 2013. After determination of the amount of compensation under
Section 3G of NH Act 1956, it can be disbursed to the landowner/ affected person or
beneficiaries using the BhoomiRashi Portal directly in their accounts without any delay.
In disputed, cases, CALA can deposit the disputed amount of compensation in the civil
court. The State Governments are being urged time-and-again to issue instructions to
CALAs to expedite and complete the disbursement of compensation amount.
The Committee note that for disbursement of compensation for the acquired
land, Competent Authorities for Land Acquisition (CALA) are appointed under National
Highways Act 1956 who follow a procedure specified in the said Act. The Committee
have been informed that in some States, for instance, Uttar Pradesh, despite the
finalization of acquisition process long back, compensation amounts remain to be
transferred into the account of actual beneficiaries. According to the NHAI, among
others, the reason behind the delay in compensation in some States is inability of the
district administration, which functions as CALA, to speed up the process. Though NHAI
pays around 10 percent of the cost of compensation to the district administration as
administrative fee for disbursement of compensation, expediting the compensation
disbursal process has remained a challenging task most of the time due to the apathetic
attitude of the concerned district administration. The Committee are of the opinion that
disbursal of compensation in time is essential to minimize the number of court cases.
The Committee feel that LA Cells can play a great role in expediting the
disbursement of compensation by providing necessary inputs to the Central
Government with respect to the delay in the disbursal process so that effective and
timely resolution of the issues causing delay may be resolved in coordination with State
Governments. The Committee, therefore, urge the Ministry/NHAI to strengthen the
functioning of the LA cells by delegating more powers to the Cells attached with regional
offices of NHAI and urge them to act as a bridge between the public and the local
bodies, so as to facilitate greater coordination between the stakeholders, State
Government officials and regional officers of the Authority. This will improve the
execution capacity of the Authority at the ground level with respect to the land
acquisition process.
Guidelines for engaging services of retired Revenue Officers to assist ROs/ PIUs
to expedite Land Acquisition Process have already been issued. In order to ensure that
there is no delay in disbursement of compensation, full financial powers to release
compensation amount have been delegated to Regional Officers of NHAI/ MORTH.
Regular meetings with State Authorities are being held at the level of Minister of
Road Transport & Highways, Chief Ministers, Secretary RT&H, Chairman NHAI, Chief
Secretaries etc. apart from regular interaction at RO and PO level with respective State
Government Officials.
PPP Model: From BOT to Hybrid Annuity Model – From the deposition of NHAI, the
Committee note that poor performance of concessionaries on account of economic
slowdown is a major factor responsible for delay in Build Operate and transfer (BOT)
projects under the PPP model. Most of the delayed projects under the BOT mode of
execution could not takeoff in the wake of economic slowdown as developers were not
able to finance the projects due to their over leveraged balance sheets. Further, due to
reduced growth of traffic and lesser revenue realization consequently, the
concessionaires could not meet their debt service obligations and defaulted in their debt
accounts. As a result of the aforesaid factors, financial viability of BOT mode of projects
got heavily jeopardized.
While taking note of the reasons for sluggish performance of BOT mode of
projects, the Committee observe that apart from economic slow-down, sluggish
performance of BOT projects can also be attributed to deficiency in the planning and
execution capacity of the Government as well as delay in acquisition of land and
arrangement of requisite regulatory approvals for the projects under BOT mode. The
Committee feel that the Government introduced PPP model without due planning and
even without creating an enabling policy environment for successful implementation of
such a model. In this connection, the Committee recall the recommendations made by
the Kelkar Committee constituted by the Ministry of Finance which has inter-alia
recommended that PPP model should not be used at the first delivery mechanism
without checking the suitability for a particular project. Kelkar Committee has also
recommended for constitution of a infrastructure PPP Projects Review Committee to
examine the performance of PPP projects and legacy issues associated with these
projects. While taking note of recommendation of Kelkar Committee this Committee
desire that the Government should examine the reasons for failure of BOT mode under
PPP model and take suitable measures to revive the languishing projects. In this
direction the Committee take note of some of the initiatives taken by NHAI to revive the
languishing BOT projects. These include permitting 100 percent equity divestment after
two years of construction completion for all BOT projects, equity infusion in BOT
projects and rationalization of compensation to concessionaire in case of delays not
attributable to them. The Committee are of the view that in view of the huge cost of
infrastructure development projects, there is a need to mobilize resources from sources
other than Government funding and therefore, it is imperative that the project execution
model under public-private partnership remains reasonably attractive for the private
investors. The Committee, accordingly, support the initiatives taken by the Government
to revive the languishing BOT projects by making them more conducive to the demands
of private investors, and desire to be apprised of the impact of these measures on
ground.
The Committee also feel that it is equally important to ensure that private
investors do not manipulate the contract provisions of concession agreement to
generate profuse returns at the cost of public interest. The Committee hence are of the
view that it is the responsibility of NHAI to protect the interest of highway users as well
as the Government in all public-private partnership contracts.
In view of the fact that most of the projects awarded under the BOT modes of
PPP model could not be completed on time, the Committee find that the Government
introduced a new ‘Hybrid Annuity Model (HAM)’ of project execution combining the main
features of two prevailing models i.e. Build Operate Transfer (BOT)-Annuity &
Engineering, Procurement and Construction (EPC).
In this regard, they were informed that unlike the BOT models, HAM assures
better risk allocation amongst private concessionaires and NHAI/Government as 40% of
bid project cost shall be payable to the concessionaire by NHAI in five equal
installments linked to project completion milestones and concessionaries shall have to
bear the balance 60% of bid project cost through combination of equity and debt. With
assured annuity payments to concessionaries it is expected that the operations &
maintenance risks during construction and operation period will be mitigated and it will
also allay the apprehensions arising out of the uncertainty in traffic volume. Further,
HAM projects are expected to be completed on schedule as payments to
concessionaire have been linked to the project completion milestone which are based
on both physical and financial progress unlike the BOT mode wherein the project
completion milestone were based on financial progress only. During 2016-17, out of the
total awarded projects of 4336 km by NHAI, projects of 2434 km have been awarded
under HAM. The Committee are glad to learn that with HAM projects getting
momentum, total length of road construction by NHAI has also increased to 2628 km
during the year 2016-17 from 1987 km during the year 2015-16.
Taking note of the successful beginning of HAM projects and interest shown by
investors for these projects, the Committee appreciate the efforts of the Government to
revive the PPP projects in road and highways sector with introduction of HAM. They
hope that with its better risk allocation structure, interest of private concessionaire in
infrastructure sector could be revived. The Committee also feel that if HAM projects are
implemented with due caution, many delayed projects may be expedited and stalled
projects may be revived. However, in view of the experience gained from the
implementation of PPP model so far, the Committee desire that for development of
highways infrastructure projects, PPP model, be it BOT mode or HAM, should be
preceded by proper planning and due assessment of the feasibility of the projects.
While the Committee expect good progress of projects under the PPP model, as
is evident with the HAM mode, it is still a reality that the private sector does not prefer
projects which have low profitability for them. In such projects, the Ministry has to come
forward for public good. Hence the committee recommended that the Ministry must
adopt a proactive approach towards highway construction throughout the length and
breadth of the Country. They have to also convince the private sector for enhanced
participation in the same as better road linkage translates into better industrial
performance resulting into better profits for all stakeholders.
Ministry of Road Transport & Highways has analysed the causes/ factors likely to
attribute to poor performance of BOT projects, some of which are mentioned as under:
(viii) Lack of availability of debt products aligned with revenue stream profile of
highway projects.
(iii) MoRTH has been taking proactive steps to identify bottlenecks involved in
awarded but languishing NH projects and address them through appropriate
policy initiatives in course of the last two and half years.
(xii) Exit Policy – the policy enables private developers to take out their entire equity
and exit operational BOT projects two years from start of operations (COD)
irrespective of date of award thereby enabling reinvestment of such unlocked
equity.
(xv) One-time fund infusion – the policy enables revival and physical completion of
languishing BOT projects that have achieved at least 50% physical progress,
through one-time fund infusion by NHAI, subject to adequate due diligence on a
case to case basis.
(xvi) Introduction of Hybrid Annuity Mode - In the model, 40% Project Cost is provided
by the Government as ‘Construction Support’ and balance 60% as annuity
payments during operations period with interest (Bank Rate +3.00%). Separate
provision for O&M payments to concessionaire. The private party does not have
to bear the traffic and inflation risks. The model has been widely accepted by the
market.
(xvii) Introduction of TOT model (Toll Operate Transfer) - In the Model, collection rights
for Toll Fees for operational public funded NH projects is assigned for a 30 year
concession period to concessionaires against upfront payment of a lump-sum
amount. O&M obligations is with the concessionaire during the concession
period. First round of bid completed at NHAI for TOT projects - bundle of 9
project stretches (length 680 km) bid out. H1 bidder quoted concession fee of Rs
9681.5 cr (against NHAI estimated Rs 6258 Cr).
(xix) Proactive steps taken to accelerate Land Acquisition (LA) - Single CALA account
set up at NHAI to aggregate disbursed compensation funds and maximize
interest savings. NHAI ROs empowered to expeditiously approve land
compensation.
(xx) The Ministry with the help of National Informatics Centre has developed a Web
Portal – BhoomiRashi, to digitize the entire process of land acquisition. LA
process has been expedited significantly through this initiative. BhoomiRashi has
also been integrated with the Public Financial Management System (PFMS)
platform of the Ministry of Finance, for deposition of compensation in the account
of affected/interested person, on real-time basis.
(xxi) Further, the Ministry issued comprehensive guidelines on Land Acquisition for
NHs vide letter No. NH-11011/30/2015-LA dated 28.12.2017 to simplify the
complex issues of Land Acquisition viz. applicability of certain provisions of
RFCTLARR Act 2013 on NH Act 1956, date of determination of market value of
land, issue of multiplication factor, bulk acquisition through consent of land
owners etc.
(xxii) Electronic Toll Collection (ETC) is being encouraged to minimize toll collection
time and reduce pilferage in toll collection on NHs. Enabling facilities for ETC
being put proactively in all toll plazas. Out of the total 429 Toll Plazas, 275 Toll
Plazas are on PPP Concession Roads and 154 are on Public funded road
assets. Of these, all lanes have been equipped with the requisite Infrastructure in
case of 165 PPP Toll Plazas and 77 Public Funded Toll Plazas. Further, 108
PPP Toll Plazas and 24 Public Funded Toll Plazas have been equipped with two-
lane dedicated ETC Infrastructure. 32,86,918 lakh FASTags have been sold so
far (as on 25.10.2018) and average daily toll collection through ETC has reached
22.5 % of total toll revenue.
Financial Performance - The Committee have been informed that being a nonprofit
organization under the section 10(23)(C)(IV) of Income Tax Act 1961, NHAI is
exempted from income tax and is assessed as a ‘charitable trust’. Likewise, financial
statement of NHAI is prepared in the format of income-expenditure statement instead of
profit-loss statement. The Committee also note that it is the statutory obligation of NHAI
to ensure that investment made by the Government in infrastructure projects yields
desirable results and does not turn unprofitable. The Committee opine that if delayed
projects result into cost overrun and funds raised by NHAI in the form of tax free bonds,
which add to the liabilities of the Government, are not properly utilized, it is ultimately
the loss of scarce Government resources. Though NHAI has clarified that only EPC
mode of project implementation involves cost overrun on account of delay in project
completion and there is no cost overrun in case of BOT projects, the Committee still feel
that even in the modes of projects implementation which involves no cost overrun, the
cascading effect of delays may result into revenue loss to the Government on account
of delay in collection of toll charges. Further, delay in completion of projects has an
overall impact on the growth of economy and deprives the public of the convenience of
a developed infrastructure.
In view of the above, the Committee are of the view that losses on account of
delayed projects is a loss to the national economy. The Committee, therefore,
recommended that being an executive agency of the Government, NHAI should strive
hard to complete the project on time in order to minimize the downside risks to the huge
investment made by the Government in the infrastructure projects. The Committee also
recommend that accountability mechanism in NHAI should be strengthened so as to
ensure the optimal utilization of the Government’s funds invested in the infrastructure
projects.
(i) MoRTH & NHAI are already rolling out various initiatives to streamline project
execution, fast-track permissions through better inter-ministerial coordination,
and several steps have been taken to amend various agreements, contracts and
contracting methods through stakeholders consultation.
(ii) Project based accounting enables tracking and reporting of financial performance
at the project level against the budget or financial plan. This can then be used to
optimize resource (or capital) allocation through prioritization of projects and/or to
identify problem areas and to take corrective action.
(iii) Financial planning and profit center are enabled by project level accounting of
revenue and expenditure. Accordingly, the 'Guidelines and Standard Operating
Procedure (SOP) for implementation of Bharatmala Pariyojana Program' issued
by Ministry of Road Transport & Highways has mandated the implementation of
'Project accounting' at NHAI.
2. In-line with the ‘SOP’, Project accounting shall capture all the major costs and
revenue and be apportioned to respective project. Major cost heads associated with the
projects include Grant, Land Acquisition, Utilities shifting, Civil Construction,
Maintenance, Debt servicing, Administrative charges and other Overheads. Major
revenue heads associated with a project include Toll Collection, Negative Grant,
Premium, Interest accruals and other default payments by contractors/concessionaire.
Figure 1: Standard Accounting vs. Project Based Accounting
(i) PMIS is the primary tool used for tracking project information across MoRTH and
its agencies. It captures all the key physical and financial metrics of the projects
including details such as land acquisition status and clearance status.
(ii) Parameters captured by PMIS vary depending on the current stage of the
project-Balance for Award (BFA), Under Implementation (UI) or O&M.
(iii) The data captured by PMIS is being currently entered by all the PDs and is being
updated on a monthly basis. There is a provision to upload IE/AE reports too and
a data certification (by the PD) mechanism has been created to minimize errors
in data updating.
(iv) PMIS is currently being used by the Monitoring Cell at MoRTH and Executive
Monitoring Cell at NHAI to disseminate project information to all relevant
stakeholders. All monthly MIS and review reports are being generated using
PMIS and customized reports have also been provided for the users to select
and view specific information. All senior officer level reviews, including the
reviews by Secretary and Chairman, NHAI are being conducted using the reports
generated by PMIS.
(v) Customized dashboards have also been designed to provide relevant information
to the users. Some of the key benefits of the PMIS system are summarized in the
figure below:
4.1 NHAI has deployed PFMS to capture expenditure. The system tracks
expenditure/transactions directly related to projects at individual project level.
4.4 There are 3 major types of transactions which are entered into PFMS through
PIUs currently. The payment process and entry in PFMS is as below:
Figure 3: Payment and Entry process
Budget Allocation - The Committee also note that apart from being dependent on the
Gross Budgetary Support from the Government, NHAI is also exploring the
opportunities to raise funds through ‘Internal and Extra Budgetary Resources’ (IEBR).
However, at the end of the financial year it could only raise Rs. 5518.92 Cr through
IEBR against the budgetary provisions of Rs. 59279 Cr. From the information furnished
by NHAI, the Committee note that in view of the growing non-performing assets (NPAs)
of banks and inability of banks to provide long term financing for infrastructure projects,
NHAI is planning to raise required funds through bond market as raising funds through
these routes is comparatively cheaper and provides long term financing option for
infrastructure development. Further, since institutions like EPFO and LIC are also keen
to invest in long term bonds in infrastructure sector, the NHAI is exploring the
opportunity of raising funds from these sources as per the broader budgetary
provisions.
Taking note of the initiatives taken by the NHAI to raise funds through market,
the Committee are constrained to note that as per financial statement of NHAI during
the last five years, huge amount of available funds were left unspent as ‘closing
balance’ at the end of respective financial year. The same unspent amount has been
shown as ‘opening balance’ at the beginning of subsequent financial year. This opening
balance was as high as Rs. 11002 Cr., Rs. 7730 Cr., Rs. 8869 Cr., Rs. 2672 Cr. and
Rs. 6740 Cr. for the years 2012-13, 2013-14, 2014-15, 2015-16, and 2016-17
respectively. Such large amount of unspent money is reflective of the NHAI’s inability to
optimally utilize the available funds for the development of National Highways. The
Committee, therefore, desire that NHAI should review its fund management strategy so
as to avoid huge amount left as unspent at the end of a Financial Year. Further, since
NHAI is trying to raise more funds through market borrowings, the Committee feel that
NHAI also needs to factor in its ‘opening balance position’ while devising its borrowing
strategy for a financial year as borrowings without taking into account the status of
unspent funds will ultimately add to the liabilities of NHAI and increase the burden of
interest payment.
At the beginning of financial year 2012-13, 2013-14, 2014-15, 2015-16 and 2016-
17 the opening balance in the books of NHAI was Rs. 11,002 crore, Rs. 7,730 crore,
Rs. 8,869 crore, Rs. 2,672 crore and Rs. 6,740 crore respectively. Reason for unspent
balances at the beginning of financial year is explained as under:
During the month of February and March 2013 Rs. 10,555.62 crore was received
through Tax free and 54 EC bonds and Rs. 1,616.42 crore was received from
MoRTH as toll plough back and NH (O) fund in March 2013.
During the last 2 months of the financial year Rs. 1,159.54 crore and Rs. 593.75
crore respectively were received as additional budgetary support and borrowings
(54 EC bonds) whereas Rs. 2,200 crore was unspent against Rs. 10,000 crore
received from Tax Free Bonds in the month of February 2014.
Borrowings during the last two months of financial year was Rs. 4,260.49 crore
whereas MoRTH provided Rs. 1,714.37 crore towards cess and Rs. 72.05 crore
towards maintenance of highways.
During the month of March 2016 MoRTH provided Rs. 772.14 crore towards
additional budgetary support and Rs. 647.87 crore was received through
borrowings.
Rs. 5,991.07 was received through issue of 54 EC bonds and Tax Free Bond
during Feb and March 2017 whereas Rs. 370.27 crore was provided by MoRTH
towards NH(O) Funds on 31.03.2017.
During corresponding financial years NHAI has spent Rs. 17,377.79 crore, Rs.
20,601.31 crore, Rs. 23,789.72 crore, Rs. 42,689.49 crore and Rs. 48,857.51
crore respectively on projects. Thus there is an expenditure growth of Rs. 181 %
during last five years.
It is also submitted that unspent amount are kept in fixed deposits after obtaining
competitive rates from the banks.
It has also been decided to install Hybrid-ETC lanes on all lanes of fee plazas
across NHs for seamless movement of vehicles across the fee plaza in addition to one
dedicated lane for FASTag users. This will further improve user acceptance of the ETC
infrastructure.
Further, letters have been written to all the State Governments to extend FASTag
on other State Highways also. Madhya Pradesh State Government has signed a MoU to
this effect for implementation on their State Highways. Maharashtra, AP, Telangana and
Gujarat State Government have expressed their desire to adopt it and the process is at
an advanced stage.
Toll collection without completion of projects – The Committee note from the
information furnished by NHAI that in certain cases concessionaires have started
collection of toll charges from users even without final completion of the roads. The
Committee, while urging MoRTH and NHAI to detect such instances through strict
monitoring, find it totally unjustified as the users are forced to pay user charges for
roads which are partially completed. It also leaves no incentive for the concessionaire to
complete the project on time, which results into delay in completion of projects. The
Committee, therefore, desire that NHAI should finalize specific guidelines fixing the
accountability of the toll operators with respect to collection of user charges. The
Committee also feel that specific provisions should be made in the “Contract
Agreements” itself to ensure that toll charges are made applicable only after completion
of the projects and for any violation, adequate penalties should be imposed on the toll
operators.
Management of Toll plazas – The Committee observe that location of toll plazas
inside the cities or densely populated areas results into chaotic traffic conditions causing
pollution, traffic hazard and inconvenience to highway users and the local population.
The Committee, therefore, recommend that NHAI should examine the feasibility of
setting up toll plazas away from the cities/ densely populated areas in order to avoid
inconvenience to public. Further, it has also been observed that in some toll plazas,
most of the toll counters are kept non-operational in order to reduce the cost. In some
toll plazas, users have also been inconvenienced by unscrupulous elements deployed
by toll operators for collection of toll charges, who many a times misbehave with users
or demand undue charges. In view of this, the committee feel that NHAI should develop
an inspection mechanism to monitor the management of toll plazas in order to ensure
that users are not troubled by the toll operators/collection staff. A well trained staff
needs to be deployed at toll counters and all complaints regarding the mismanagement
at toll plazas should be promptly enquired and suitable action taken.
Reply of the Government
Efforts are being made to locate / establish the toll plaza beyond 10 kms of the
municipal limit of a town/city. However, sometimes due to site constraints and
engineering consideration, the toll plazas are also established within the distance of 10
kms of the municipal limit as per the provision of National Highway Fee Rules 2008,
especially when the project is developed for the benefit of local users.
In order to not to give scope for complaints about misbehaviour by toll plaza staff,
display of concessions and information, NHAI also issued a policy circular dated
02.02.2016 for standardization of uniform of toll collection staff, user fee receipts, user
fee display boards at toll booths at both NHAI and concessionaire toll plazas. Further
following measures have also been taken:
(v) Efforts are being made to not give scope for complaints about misbehavior by toll
plaza staff. Toll plazas employees are being advised for courteous behavior with
road users for smooth implementation of user fee collection.
(vi) NHAI have established various HOU (Highway Operation Unit) in RO and PIUs
to avoid any mismanagement at toll plazas. These HOUs make regular visits to
ensure that the complaints have been resolved in time.
(vii) NHAI also proposed to conduct behavioural training to toll plaza employee
through IITTM (Indian Institute of Tourism and Travel Management) as per NHAI
circular no. NHAI/GM(T)HO/Misc./2018/79 dated 12.03.2018 to reduce toll
issues like ill treatment by toll plaza employees/ ETC or FASTag not working,
excess deduction of toll fee at toll plazas and other misc. type of complaints of
the toll plazas.
The Ministry of Road Transport and Highways introduced the Motor Vehicles
(Amendment) Bill, 2016 in the Parliament (Lok Sabha) on 9th August, 2016. The Bill
addresses issues such as road safety, passenger’s mobility, transport reform, citizen
facilitation and reduction of corruption in transport sector. The Bill was referred to the
Department related Parliamentary Standing Committee on Transport, Tourism and
Culture for examination and report. The Committee presented its report on 8.2.2017 to
the Rajya Sabha, which was examined in the Ministry. The Motor Vehicles
(Amendment) Bill, 2017 alongwith amendment was passed by Lok Sabha on 10th April,
2017. The Bill as passed by Lok Sabha was referred to a Select Committee of the
Rajya Sabha on 8.8.2017. The Select Committee has presented its report to the Rajya
Sabha on 22nd December, 2017. The Bill as passed by Lok Sabha and as reported by
the Select Committee of Rajya Sabha is presently in Rajya Sabha for consideration and
passing.
In this connection, the Committee also note that NHAI has a well-established
mechanism for monitoring the quality of construction work with respect to ongoing
national highways projects. NHAI has a dedicated Quality Division to conduct inspection
of various projects sites regularly to monitor the quality of work. NHAI also undertakes
Quality Audit of the projects by independent quality Auditors / consultants. However, the
Committee observe that NHAI does not have a similar mechanism to monitor the
maintenance of highways work after the construction is over. Since the maintenance of
the roads after construction is equally important in order to ensure the quality of roads in
long run, the Committee recommend that NHAI should evolve an effective system of
monitoring the maintenance of national highways for a specified period after completion
of the construction. The Ministry in consultation with NHAI may evolve the policy
regarding maintenance of roads after construction whereby there is a structural
mechanism for maintenance of roads.
In BOT (Toll) and HAM Projects, maintenance of the road after completion of
construction is undertaken by the concessionaire during the concession period, which is
normally 15- 20 years. The independent Engineer on the project is required to inspect
the Project Highway at regular intervals to ensure that maintenance requirement
specified in the concession agreement are complied with by the concessionaire.
For determining that the Project Highway conforms to the Maintenance Requirements,
the Independent Engineer shall require the Concessioner to carry out tests specified by
it in accordance with Good Industry Practice. The Concessionaire shall, with due
diligence, carry out all such tests in accordance with the instructions of the Independent
Engineer.
Further, the Committee also desire that the Government should allocate sufficient
funds for ensuring adequate safety norms in design and construction of Road Projects.
In this connection, Chairman, NHAI during the evidence before the Committee, had
highlighted the requirement of funds to the tune of Rs. 20,000 cr. in order to ensure
adequate safety norms in design and construction of Road Projects. The Committee are
constrained to note that out of estimated Rs 1128.48 cr. funds of maintenance, only Rs.
100 cr. were actually released during 2016-17 as per the data furnished to the
Committee. While deliberating the way maintenance issue is being ignored as is evident
from the data of utilization of funds status, the Committee strongly recommend for
focused attention as maintenance of roads. The Committee desire to be apprised of the
reasons for the reduction in the funds allocation to NHAI with respect to maintenance of
roads as well as the allocation made for the same in the current Financial Year.
(ii) Rectification of Accident Black Spots: The Ministry had identified 789 nos. of
Black Spots on National Highways including 136 nos. on State Roads.
(a) NHAI has rectified 209 nos. of Black Spots out of 506 Black Spots on NH
network with NHAI through long term measures such as construction of
flyovers, service roads, VUPs and PUPs etc. 162 nos. of Black Spots are
under rectification. Works pertaining to the rectification of 75 nos. of Black
Spots are at the bidding stage and 60 nos. of Black Spots are under
investigation. All Black Spots are targeted for rectification by March 2020.
(b) Out of the total 147 road accident Black Spots on NH stretches under
jurisdiction of State PWDs, 56 are already improved, 61 are being
improved in ongoing projects, 27 black spot rectification works are in
bidding stage and 1 is under survey investigation.
(c) 136 Black Spots are on State Roads which are not under the jurisdiction of
Ministry.
iv) For some of the developed NH stretches through public funding, maintenance
contracts have been taken up for a definite time period (4 to 9 years) on Operate,
Maintenance and Transfer (OMT) basis. The maintenance of the project highway
under OMT contracts is the responsibility of the Concessionaire.
NHAI has a shelf of 114 projects in 5890 km length of NHs for their monetization
on TOT mode.
The funds provided to NHAI under M&R during 2016-17 was Rs.100 crore
and during 2017-18 was Rs.575 crore.
Service Roads are generally provided in the built-up areas that are situated
within the municipal limits or the road sections in non-municipal areas where permanent
structures are built along the National Highways so as to segregate the local/slow
moving traffic from the through/fast moving traffic. The grade separated structures [i.e.
Vehicular Underpass (VUP), Vehicular Overpass (VOP) etc.] are provided at the
intersection of the Project Highway with all the National Highways and State Highways.
Such under/over passes are provided across other categories of roads as per site
requirement for crossing of traffic. The structure may be either an underpass or an
overpass depending upon the nature of terrain, vertical profile of road and availability of
adequate right of way, etc. Similarly, over bridges such as Road Over Bridge (ROB) are
provided at railway crossings. Moreover, structures such as Pedestrian Underpass
(PUP), Foot Over Bridge (FOB) are also provided to facilitate pedestrian crossing at
appropriate locations nearby schools/ hospitals/ factories/ industrial area.
In view of this, the Committee recommend that the NHAI and the Ministry of
Road Transport and Highways should ensure that provisions regarding construction of
additional structures such as under passes and over-bridges are included in concession
agreements and if not feasible, NHAI should undertake the responsibility of building
these structures using their own funds. The Committee note in this context that NHAI
has instructed and delegated necessary powers to all Regional Officers to provide
FOBs at pedestrian crossing locations on NH, wherever required. The Committee also
recommend that NHAI may formulate specific guidelines for the
developers/concessionaires to make construction of under passes and over-bridges
mandatory, if nearby areas of National Highways are densely populated. NHAI may fix a
rational criteria regarding minimum population for which providing of additional
structures would be mandatory for the concessionaire. The Committee also desire to be
apprised of the progress on the Indian Bridge Management System (initiated in 2015) to
collect condition survey data of all road bridges in the Country.
(i) Concern of the Committee has been noted for compliance. In this regard, it is
further mentioned that in order to provide adequate safety for the road users of
national highways, NHAI has made it mandatory for carrying out the safety audit
of the project highways through independent road safety auditors at all stages of
its development and O&M viz. design, construction and O&M stages. The safety
auditors during their audit of the project highways observe the pattern and
behavior of the traffic at all vulnerable locations and collects feedback from the
locals. Thereafter the safety auditor records the observations in the findings and
suggest the mitigation measures such as Vehicle Underpasses/ Pedestrian
Underpasses, Service road, footpath, grade separator, junction improvement and
other safety measures as necessary to be adopted to remove any safety
deficiency. The observations and suggestions of the safety auditor are
communicated to the concessionaire and the independent engineer which are
compiled by them at site and they submit compliance report to NHAI.
(ii) Besides the above, the Ministry has identified potential black spots on all NHs
based on the basis of accident and fatality data. NHAI has already taken up the
program for removal of these black spots on priority basis through the
concessionaire/ contractor based on the accident investigation, traffic analysis
and mitigation measures finalized by independent safety consultant/ independent
engineer. During the mitigation process, the requirement of underpasses,
flyovers and service/ access roads etc. are being provided in order to prevent
accident at the black spot locations. These measures are implemented through
the ongoing developmental works or change of scope or on standalone basis
depending upon the status of the project highway.
(iii) As already noted by the Committee, it is reiterated that NHAI has delegated
powers to the Regional Officers to provide FOBs at the vulnerable pedestrian
crossing locations on the National Highways, wherever required.
(iv) With regard to Bharatmala Project, it has been decided that the decision
regarding provision of underpass may be taken keeping in view the designed
traffic, civil cost of construction, vehicle operating cost, environment cost, travel
time, site condition, etc. on the basis of output obtained using lifecycle cost
analysis including vehicle operating cost keeping the design life of 30 years. If
the analysis results into savings, then cross roads be carried above the main
highway in form of VOP. In case of VUP/LVUP, the exposed structure base shall
be kept 6 inch (15 cm) above the ground level to minimize the height of
approaches and ensure that these VUPs don’t become water accumulation
points. However, the main highway shall be kept above the cross roads in form of
VUPs at interchange locations. As 70% of the cross roads are village roads (<5.5
m width), to ensure complete access –control and make cost-effective grade
separation, it was decided to introduce a third smaller dimension VUP-SVUP
(4m*7m) for all cross roads carriageway width lesser than 5.5m. Thus, the VUPs
would be of three grades i.e. VUP-5.5m X20; LVUP- 4mX12m; and SVUP:
4m*7m.
(v) IBMS: Ministry has established the Indian Bridge Management System
(IBMS) with the aim to carry out condition survey including Inventorisation of all
the bridges on National Highway System of India by using Mobile Bridge
Inspection Units. Till now, Inventorisation of more than 1.7 lakh bridge structures
including culverts has been completed. The software for this purpose is totally
indigenous. This IBMS has been acknowledged as Outstanding Digital
Monitoring Project. Identification of distressed bridges is an ongoing process.
IBMS has identified about 147 critically distressed bridges based on various
distress parameters, out of which 63 bridges are under consideration of NHAI.
For remaining bridges, the concerned executive agencies have been instructed
to undertake necessary remedial measures for the bridges requiring immediate
repair/ rehabilitation etc.
The Indian Road Congress have provided the guidelines for laying the Utility
Ducts in urban roads vide IRC-98:2011 and are being followed for urban areas.
However, the cost estimates for construction of common underground utility ducts all
along the roads are estimated to be about Rs.2.0 crore per km length. The service
providers generally lay their utilities depending upon their convenience and there are no
provisions to force them to utilize the ducts so constructed.
National Green Highways Projects - The Committee note that the Ministry of
Road Transport and Highways have launched the National Green Highways Project to
develop green corridors along National Highways for sustainable environment and
inclusive growth which envisions development of eco friendly highways with
participation of various stakeholders. The Committee also note that National Green
Highways Mission (NGHM), established by Ministry of Road Transport and Highways
(MoRTH) under National Highways Authority of India (NHAI), has been entrusted with
the task of planning, implementation and monitoring roadside plantations and building
fences along one lakh kilometre network of National Highways. The Committee, while
acknowledging the fact that roadside plantation have immense potential to enhance the
green cover of the nation and also generate employment opportunities for rural
economy, feel that this initiative is a novel step towards improving the aesthetics of
highways while contributing in a big way towards environment protection which is a
global concern. However, the Committee regret to note that during the year 2016-17
against the allocation of Rs.500 Cr. In Green Highways Fund, no amount was actually
received by NHAI, which implies that the fund is yet to be operationalised and no work
has been initiated under the National Green Highways Mission. Further, no amount has
been allocated for the said fund for the year 2016-17. The Committee may be apprised
of the reasons for not releasing money for the Green Highways Funds.
The Committee also desire that the Government should allocate the release the
required funds under the Head ‘Green Highways fund’ and ensure its optimum
utilization for development of green corridors along National Highways. Further, the
Committee insist that in course of development of Green Highways Project, appropriate
exit gates for crossing the fenced highways for the public is provided at appropriate
distances and places so that movement of people living in habitations on either side of
highways are not inconvenienced. The Committee thus recommend the Government to
vigorously follow up the project of greening of highways at all levels.
Training and Human Resource Development - Taking note of the BOT model and
newly introduced Hybrid Annuity mode of project implementation, the Committee feel
that successful implementation and effective administration of a highway project
requires induction of new set of skills in those employees of NHAI who deal with various
responsibilities and duties ranging from preparation of DPR to monitoring of
construction work, enforcement of contracts, liaisoning with State Government officers
etc. The Committee, therefore, recommends that NHAI should arrange specific training
programmes for its employees to upgrade their skills so as to enable them to resolve
the complex issues pertaining to implementation and management of highway projects.
Further, in view of future growth potential of roads and highways section in India, the
Committee feel that a large number of civil engineers and technical experts will be
required to fulfill the demand of skilled personnel in the areas of design, construction
and maintenance of roads/Highways. The Committee, therefore, recommends that
NHAI and Ministry of Road Transport and Highways should collaborate with Ministry of
Human Resource Development, Ministry of Skill Development and Entrepreneurship
and premier research institutions in road construction sector such as the Central Road
Research Institute etc. for promoting quality education, skills, training and research work
in the field of road construction sector.
NHAI has been continuously making efforts to train its employees in various
fields by providing specific training program from premier training institutions viz. Indian
Association of Highway Engineers (IAHE), Indian School of Business (ISB), Indian
Institute of Management (IIM), Management Development Institute (MDI),
Administrative Staff College of India (ASCI). Recently, NHAI formulated its training
policy which mandates specific training to each employee for upgrading their skills.
Implementation of this training policy is in the process. Presently 300 Technical Officers
working in the Roads and Highway Sector have been nominated for “Contract
Management, Arbitration and Dispute Resolution” organized by Indian Academy of
Highway Engineers (IAHE) which is being held at IAHE Campus, Noida.
Further, the suggestions of the Committee for NHAI and Ministry of Road
Transport and Highways to collaborate with Ministry of Human Resource Development,
Ministry of Skill Development and Entrepreneurship, have been noted and shall be
included in upcoming training programs.
Given the high pace of growth in traffic across the Country and with so many
development projects of NHAI yet to be accomplished, it is essential that the manpower
requirement of NHAI be fulfilled by making the positions more lucrative so as to attract
the best talent from the industry. The Committee observe that although hiring of persons
on deputation/contract basis may have some advantages, but keeping in view the huge
mandate given to NHAI and the Government’s focus on development of infrastructure in
the country, it is essential for NHAI to have its own permanent Cadre which will ensure
dynamism, continuity in administration, management, inflow/ outflow of personnel and
retaining institutional memory. The Committee recommend the Government for creation
of a permanent cadre of NHAI and expediting the filling-up the vacancies in NHAI.
As for creation of a permanent cadre for the NHAI, it has found useful to keep a
mix of permanent staff and those taken on deputation. The CES officers recruited
through the UPSC are being increasingly deployed by the Ministry in the NHAI.
Similarly, it has been observed that the members of permanent cadre are reluctant to be
posted in difficult and far-flung areas e.g. North-eastern states, where taking
Engineering staff on deputation from the state PWDs works more efficient, especially
when the staff requirement is project linked. The Service Regulations of NHAI are under
a comprehensive review in this behalf. Further, NHAI is making its continuous efforts to
increase the strength of permanent cadre in NHAI. The snapshot of the manpower
position which depicts the gradual increase in the independent cadre (regular strength)
of NHAI is given below:-
*******
CHAPTER III
-- Nil --
*******
CHAPTER IV
In view of the above, the Committee are of the opinion that while it may not be
practical to completely rule out the practice of sub-contracting, NHAI should explore the
possibility of imposing certain restrictions with respect to sub-letting of contracts, in
order to ensure quality of work and timely completion of projects. This could also be
done by levying of penalty on the main contractor if the sub-contractor leaves the
project incomplete. Registration of sub-contracts and blacklisting of contractors may
also be made mandatory to ensure that practice of sub-contracting does not affect the
projects adversely. The Committee would like to be apprised about the preventive
action taken in the matter.
To strengthen the resources available with the Contractor for execution of the
project, practice of sub-contracting is resorted to. This is admissible under contract.
Adequate provisions are there in the contract agreements to ensure that the main
contractor, who is fully responsible to the employer for the work, complies with the
various terms of the agreement irrespective of employment of sub-contractor for the
work. Following provision exist in various contract document in this regard:
(d) Clause 2.1.18 of the RFP for BOT (Toll) projects stipulates as under:
(i) The Bidder, in case it does not have the O&M experience specified
in Clause 2.2.3 of the RFQ, by submitting its Bid, shall be deemed to
acknowledge and agree that for a period of at least 5 (five) years from the
date of commercial operation of the Project, it shall enter into an
operation& maintenance (O&M) agreement with an entity having the
specified experience, failing which the Concession Agreement shall be
liable to termination.
(ii) The Bidder would provide an undertaking to NHAI that EPC works
of the project would be executed only by such EPC contractor who have
completed at least a single package of more than 20% of the TPC or
Rs.500 Cr, whichever is less. An undertaking to this effect shall be
provided by the Bidder.
2. HAM Projects:
3. EPC Projects:
Road Fatalities - The Committee note with concern that incidence of road deaths in
India is comparatively higher as compared to other countries. A Report prepared by the
Ministry of Road Transport and Highways on Road Accidents in India in 2015 states that
the total number of road accidents increased by 2.5 percent from 4,89,400 in 2014 to
5,01,423 in 2015. The total number of persons killed in road accidents increased by 4.6
percent from 1,39,671 in 2014 to 1,46,133 in 2015. Out of the total road accidents, 28.4
percent accidents took place on National highways. They note that Ministry of Road
Transport and Highways has set a target of reducing the number of road accident
fatalities to 50 percent by 2020 in line with the target of United Nations Decade for
Action on Road Safety. The committee appreciate that the Government has launched a
major initiative namely Pradhanmantri Sadak Suraksha Yojna (PMSSY) to improve the
safety on different categories of roads viz. National Highways, State Highways, major
district roads etc through engineering improvement measures. The Committee would
like to be apprised about the budgetary allocations and status of the implementation
with respect to PMSSY at the action taken stage.
Reply of the Government
Pradhan Mantri Sadak Suraksha Yojna (PMSSY) has not been launched by the
Ministry of Road Transport and Highways. This Scheme is administered and
implemented through the Ministry of Rural Development. Therefore the details of this
scheme are not available.
The initial cost of construction of Highways with cement concrete is more than
Flexible pavement. The initial cost of flexible pavement is less than that of rigid
pavement but having long-term maintenance requirement.
It can, therefore, be concluded that single type of pavement may not be suitable
under all conditions.
*******
CHAPTER V
Audit Issues - The Committee observe that the C&AG, in course of their
examination of the accounts of NHAI during the year 2013-14 and 2014-15, had noticed
several discrepancies in the accounts and other records of NHAI. As per Audit
observations, the balance sheet and profit-loss accounts of NHAI were not drawn up in
accordance with the format approved by the Government of India under NHAI Act,
1988. They further observe to their dismay that since the issues raised by Audit were
not resolved, Audit had to issue a disclaimer certificates stating their inability to form a
firm opinion about whether the financial statement of NHAI was true and fair. The
Committee note that NHAI, as a follow up, had appointed M/s KPMG to submit a report
on the issues raised by C&AG and their report is currently being analyzed by an expert
Committee of C&AG.
The Committee regret to note that despite being a Statutory body, the account
books of NHAI were found as not being maintained in accordance with desirable GOI
standards by the C&AG for the year 2013-14 & 2014-15. Deviation from the standard
accounting principles is not justified and NHAI should maintain its accounts as per the
format prescribed by the C&AG so as to enable the Audit to have a meaningful
assessment of the financial performance of NHAI. The Committee desire to be apprised
about the comments of the expert Committee appointed by the C&AG on the same. The
Committee also urge the Ministry of Road Transport and Highways to take note of the
recommendations of the said expert Committee and ensure their implementation by the
NHAI so that the accounting standard of NHAI does not attract any adverse comments
from the C&AG in future.
The format of accounts was prescribed by C&AG in the year 1992. The present
format is 25 years old. Since the time C&AG prescribed this format several changes
have taken place in the working and reporting requirement of NHAI. Accordingly, year
after year based on the reporting requirements some minor changes were made in the
existing format of accounts. These were mostly data/information which was neither
required nor considered at the time of prescription of format by C&AG in the year 1992.
Since the inception of NHAI, C&AG is auditing NHAI accounts on yearly basis.
However, the issue of change in format of accounts has been raised by C&AG in the
last few years’ audit report.
The issue of changes in the format of accounts was discussed with C&AG officials and
it was decided to appoint a financial consultant for expert opinion on the matter and also
to suggest a new format of accounts. Accordingly, M/s KPMG was appointed as
financial consultant in this regard. M/s KPMG have submitted their report along with
revised format of accounts and the same is to be approved by the Ministry in
consultation with C&AG. Ministry has held a meeting with C&AG and NHAI. The new
format is being finalized by NHAI whose report is awaited.
In view of the above, the disclaimer issued by C&AG in the annual accounts 2014-15 &
2015-16 have been withdrawn in the annual accounts 2016-17.
Further, the Committee regret to note that incidents like the gang rape near a
Highway in Bulandshahar, Uttar Pradesh indicate that travelling on Highways is quite
risky for the users, which need to be dealt on priority. In view of growing criminal
activities on National Highways, the Committee urge that CCTV cameras with adequate
storage capacity should be invariably installed at all toll plazas and vulnerable places at
National Highways. The Committee are also of the view that NHAI should start helpline
numbers and develop mobile apps, utilize the social media to encourage public
involvement and enable the passengers to register their complaints with respect to poor
quality of maintenance of Highways, misbehavior by toll staff at toll plazas, incidents of
road rages and traffic violations and other inconveniences being faced by the
passengers on National Highways. NHAI should also take necessary steps to make the
public aware about such helpline numbers / mobile apps dedicated to the service of
highway passengers through display boards and other mechanism installed at
appropriate places. In this connection, a proposal for ‘access controlled’ highways is
also understood to have been under examination in Ministry of Road, Transport and
Highways wherein limited and designated entry and exit points on the highways would
be constructed for better safety. The Committee would like to be apprised of the
decision taken on the matter.
The Committee have also been apprised that although law and order issues
exclusively come in the domain of State Governments, NHAI is planning to evolve a
system to ensure increased patrolling on National Highways every eight hours so as to
deal with issues of traffic congestions and other inconveniences to commuters. Taking
note of the growing security concern on Highways, the Committee recommend to
consider creation of a dedicated Highways Security Force similar to the General
Railway Police Force (GRP), for safeguarding the movement on National Highways.
The aid of advance technologies such as geo-tagging. Global Positioning System
(GPS), positioning of CCTV cameras in this direction on sensitive areas across the
Highways are other steps which can enhance the efficacy of the monitoring system. The
Committee would like NHAI to take action as suggested above and furnish the details
about the specific action taken in this regard.
NHAI have informed that they are in the process of conceptualization to set up a
National Highways Security Services in consultation with the DS&BPRD. However, no
formal proposal has been received in Ministry. Ministry would take a decision on it after
receiving and examining the proposal in this regard.
The Committee sat on Monday, the 3rd December, 2018 from 1110 hours to 1200 hours
PRESENT
MEMBERS
Lok Sabha
Rajya Sabha
SECRETARIAT
2. At the outset, the Chairperson welcomed the members to the sitting of the
Committee and informed them about the two agenda items i.e. (i) Consideration and
adoption of the draft report on action taken by the Government on the Observations /
3. The Committee then first took up for consideration the draft action taken report
on the subject 'National Highways Authority of India Limited'. The Committee adopted
the draft report without any changes/modifications. The Committee then authorized the
------------
APPENDIX - II