Service Experience 2011
Service Experience 2011
Service Experience 2011
Two-stroke Engines
Contents
Introduction.................................................................................................. 5
Quality of ME Electronics (Hardware and Software)........................................ 5
Time Between Overhaul (TBO) for ME-Engines.............................................. 8
Optimised Low-load Operation for ME Engines............................................ 10
Operation on Low-sulphur Fuels.................................................................. 12
Second Order Moment Compensator Bracket Crack Case........................... 13
Cylinder Condition Update – Small Bore Engines......................................... 16
Cylinder Condition Update – Large Bore S-type Engines.............................. 19
Case Story: Jumping Fuel Injectors on S50ME-C with
300-bar Hydraulic System........................................................................... 22
Case Story: Breakage of High-pressure Fuel Pipes on 6S80ME-C Mk 9....... 23
Design – Production – In-service Cycle for MAN B&W Two-stroke Engines... 25
Conclusion.................................................................................................. 27
Service Experience – Two-stroke Engines
30.0%
We have now released new ESC soft- L1
25.0%
ware with much improved trouble-
20,0%
shooting possibilities available on the L2
15.0%
Main Operating Panel (MOP). The im- L3
10.0%
provements can be summarised as fol-
lows: 5.0%
0.0
2008 2009 2010 2011
original overhaul regime (black) com- shipyard. These filters will be disman-
pared with the latest “step-by-step” tled before vessel delivery. In this way,
approach (red). we will be able to obtain 32,000 hours
between exchange of the pilot valve.
Another central part of the ME sys- The pilot valve can be exchanged on
tem is the fuel injection valve actuation board by the ship’s crew. Fig. 7 shows
(FIVA). For the FIVA valve, we also state the FIVA valve with a sandwich filter
32,000 hours between overhauls. In or- installed. The main valve is green, the
der to reach this interval, we need to sandwich filter is red and the pilot valve
protect the pilot valve from dirt in the is dark grey.
hydraulic oil during commissioning. We
are presently testing so-called sand-
wich filters installed during commis-
sioning at the engine builder and at the
Fig. 10: Carbon deposits on the swing gate valve on the turbine side
For engines in service, the flexible tur- from 25% and down to 10%. Service
bocharger cut-out system with control experience on this issue is dealt with
of the so-called swing gate valves has in our latest service letter on low load
become a retrofit solution often applied operation from June 2011. We have
on engines with two, three or four tur-
bochargers. Fig. 8 illustrates this de-
injection corresponding
Breakpoint at 15 rpm/
Reduction factor
to ~35% engine load
ont
0.9 al c
10% load
n
rtio ro
l
po nt
0.8 pro co
For the swing gate valve on the turbine rpm al
l
on
tro
0.7 rti
on
pr
na
0.6 ad
tio
0.5
pr
0.4
M
120
100
80
AL + Si (nig/kg)
60
40
20
00
0.80 1.00 1.20 1.40 1.60 1.80 2.00 2.20 2.40 2.60 2.80 3.00 3.20 3.40 3.60 3.80 4.00
Sulphur %
Fig. 13: Loss of propulsion incidents – California Ports. In 2009, a cap on fuel sulphur content was intro- In parallel with the design review, we is-
duced in California waters
sued a Circular Letter to owners with
the critical design in service. The aim of
It should be mentioned that not one this Circular Letter was:
single incident of fuel switching LOP
has been recorded with our ME engines 1. To ensure that engines with cracks
whereas other types of electronically were identified so that the planning
controlled engines are represented. for rectification could be initiated
in cooperation with the operators.
Many of the vessels affected are
tankers and postponement until
scheduled docking is preferable.
Design detail S60MC-C FWD and AFT S70MC-C FWD and AFT
S70MC-C FWD
Original design
Upgraded design
At the beginning of 2012, we discov- weak action code, and at most engine in order to determine the final and prop-
ered cracks in the second order mo- builders it had not taken effect in the er countermeasure in each case.
ment compensator bracket on an production at the beginning of 2012.
S50MC-C engine type. Fig. 17 shows
an example of these. The designs of Therefore, a new design update note
the S50MC-C and S46MC-C engines (DUN) with a harder action code has
had already been updated in June been released, specifying modification
2011 based on experience gained in instructions for all S46/50MC-C/ME-C
the meantime with 60 and 70-cm bore under production. At the time of writing,
engines. However, this was done on a vessels in service are being inspected
2nd ring: Left cut The introduction of the POP ring pack is
Base material: Grey cast CF5
based on the service experience gained
Run-in coating: 0.3 mm alu-coat
on the 6S40ME-B prototype engine. At
3rd ring: Right cut first glance, the cylinder condition looks
Base material: Grey cast CF5 very satisfactory after 10,000 hours of
Run-in coating: 0.3 mm alu-coat operation, see Fig. 20. Also, the cylin-
. der liner wear is very satisfactory, see
4th ring: Left cut
Fig. 21. All liners inspected have wear
Base material: Grey cast CF5
rates below 0.05 mm per 1,000 hours.
Run-in coating: 0.3 mm alu-coat
0.05/1000
Max liner diameter (mm) hours (mm)
Liner wear engine type S40ME-B
400.60 Cyl. No. 2
Cyl. No. 3
400.20
400.10
400.00
399.90
0 2,000 4,000 6,000 8,000 10,000 12,000
Engine hours
p(scav) [bar]
2 0.60% -0.70%
1.8 0.50% -0.60%
1.6 0.40% -0.50%
1.4 0.30% -0.40%
1.2 0.20% -0.30%
1 0.10% -0.20%
0.8 0.00% -0.10%
0.6
0.4
0.2
0
1%
5%
9%
13%
17%
21%
25%
29%
33%
37%
41%
45%
49%
53%
57%
61%
65%
69%
73%
77%
81%
85%
89%
93%
97%
101%
105%
109%
113%
117%
Load [%]
Fig. 25: CoCoS-EDS data, scavenge air pressure in one period on S80ME-C9
p(scav) [bar]
2 1.90% -2.00%
1.80% -1.90%
1.75 1.70% -1.80%
1.5 1.60% -1.70%
1.50% -1.60%
1.25
1.40% -1.50%
1 1.30% -1.40%
1.20% -1.30%
0.75
1.10% -1.20%
0.5 1.00% -1.10%
0.90% -1.00%
0.25
0.80% -0.90%
0 0.70% -0.80%
1%
6%
0.60% -0.70%
11%
16%
21%
26%
31%
36%
41%
46%
51%
56%
61%
66%
71%
76%
81%
86%
91%
96%
101%
106%
111%
116%
600 3 Pressure in
Plastic deformation of seat between
atomiser (red)
fuel valve and cylinder cover → 500 2
Cylinder
400 1 pressure
(green)
Correct pre-tension of fuel valve 300 0
studs is lost → Atomiser pressure.
200 -1 cylinder pressure
OK
100 -2
Cylinder gas acts on the O-ring di-
0 -3
ameter of fuel valve →
-100 -4
Seizure Seizure
Parallel pipe
ends
Design Feedback
Production Feedback Service Feedback
09
group from 0 to 3 years. A strongly in- 5,000
5,000
5,000 MISC
MISC
MISC
20
creasing population can be seen dur- VLCC
VLCC
VLCC
4,000
4,000
4,000 CRUD
CRUD
ing the last years, and we can look for- CRUD
TANK
TANK
TANK
ward to a further increase in the years 3,000
3,000
3,000 LPGC
LPGC
LPGC
to come. This gives us an outstanding LNGC
LNGC
LNGC
2,000
2,000
2,000 GENC
GENC
possibility of receiving efficient feed- GENC
CONT
CONT
CONT
back and further optimise the MAN 1,000
1,000
1,000 BULK
BULK
BULK
B&W two-stroke concept.
000
2011**
2011**
2011**
2000
2000
2000 2002
2002
2002 2004
2004
2004 2006
2006
2006 2008
2008
2008 2010
2010
2010 2012
2012
2012
After the guarantee period, our serv-
ice organisation, PrimeServ, takes over
and continues feeding back information
throughout the lifetime of the vessel/ 6,000
6,000
6,000
engine.
5,000 MISC
MISC
MISC
5,000
5,000
10
VLCC
VLCC
VLCC
20
4,000
4,000 TANK
TANK
TANK
4,000
LPGC
LPGC
LPGC
3,000
3,000
3,000 LNGC
LNGC
LNGC
GENC
GENC
GENC
2,000
2,000
2,000 CONT
CONT
CONT
BULK
BULK
BULK
1,000
1,000
1,000
000
2000
2000
2000 2002
2002
2002 2004
2004
2004 2006
2006
2006 2008
2008
2008 2010
2010
2010 2012
2012
2012
7,000
7,000
7,000
Ships
Ships
Ships
6,000
6,000
6,000
5,000
5,000 MISC
MISC
MISC
5,000
VLCC
VLCC
VLCC
CRUD
CRUD
CRUD
4,000
4,000
4,000
TANK
TANK
TANK
LPGC
LPGC
LPGC
3,000
3,000
3,000 LNGC
LNGC
LNGC
GENC
GENC
GENC
2,000
2,000
2,000 CONT
CONT
CONT
BULK
BULK
BULK
1,000
1,000
1,000
000
2007 2008
2007
2007 2008 2009
2008 2009 2010
2009 2010 2011**
2010 2011** 2012
2011** 2012 2013
2012 2013 2014
2013 2014
2014
Fig. 38: Number of ships powered by MAN B&W two-stroke engines in the age group 0 to 3 years
[email protected]
www.mandieselturbo.com
Phone +45 33 85 11 00
Fax +45 33 85 10 30
MAN Diesel & Turbo
Teglholmsgade 41