0% found this document useful (0 votes)
276 views2 pages

L Excavation & Earth Works: Bill of Quantities

The document is a bill of quantities for the construction of a proposed cafeteria at Uva Wellassa University in Baddulla. It includes items for excavation and earth works, concrete works, formwork, reinforcement, and miscellaneous works. The earth works section includes excavating, filling, and totals to LKR 55,750. The concrete works include mass concrete, reinforced concrete, formwork and totals to LKR 974,043. The miscellaneous works include waterproofing, perforated pipes, metal packing, geotextile wrapping and totals to LKR 301,675.

Uploaded by

dimuthu lasintha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
276 views2 pages

L Excavation & Earth Works: Bill of Quantities

The document is a bill of quantities for the construction of a proposed cafeteria at Uva Wellassa University in Baddulla. It includes items for excavation and earth works, concrete works, formwork, reinforcement, and miscellaneous works. The earth works section includes excavating, filling, and totals to LKR 55,750. The concrete works include mass concrete, reinforced concrete, formwork and totals to LKR 974,043. The miscellaneous works include waterproofing, perforated pipes, metal packing, geotextile wrapping and totals to LKR 301,675.

Uploaded by

dimuthu lasintha
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

BILL OF QUANTITIES

CONSTRUCTION PROPOSED CAFETERIA OF UVA WELLASSA


UNIVERSITY-BADDULLA

Rate Amount
Item Description Unit Qty
LKR LKR

L EXCAVATION & EARTH WORKS

Excavation

L1
Excavating in any material, except rock
requiring blasting, commencing from formation
level, including upholding sides of excavation, m3 25 700.00 17,500.00
leveling, grading or ramming where necessary
as specified in Retainning wall foundation.

Filling

L2 Filling to make up levels with excavated


materials or other approved type fill material in
m3 34 1,125.00 38,250.00
Retainning wall foundation, well rammed and
consolidated in layers.

Total for Earthwork


L/ LKR 55,750.00
Carried to Bill No 02 Summary

M CONCRETE WORKS

Concrete

30 mm thick grade 25 (maximum aggregate


size 20mm) Mass Concrete poured into
ground in follows;

M1 Screed under Retainning wall base m2 75 699.00 52,425.00

Concrete grade 30 (maximum aggregate size


20mm) in following:

M2 Retainning wall and base m3 18 27,763.00 499,734.00

Formwork

M3 Formwork for Retaining wall m2 106 1,729.00 183,274.00

Reinforcement

Supplying,Fabricating & laying high yield steel


M4 kg 1115.00 214.00 238,610.00
reinforcement bars

Total for Concrete


M/ LKR 974,043.00
Carried to Bill No 02 Summary

28
BILL OF QUANTITIES
CONSTRUCTION PROPOSED CAFETERIA OF UVA WELLASSA
UNIVERSITY-BADDULLA

Rate Amount
Item Description Unit Qty
LKR LKR

N MISCELLANEOUS WORKS

N1 Water proofing for Retaining wall m2 95 1,600.00 152,000.00

Supplying & Laying 160mm dia.(type 600)


N2 PVC pipes as Perforated Pipe m 25 3,666.00 91,650.00

Supplying of 3/4 " metal packing along the


N3
perforated pipe m3 10 4,665.00 46,650.00

Supplying & Wraping 160mm dia.(type 1000)


N4 PVC pipe using Geotextile m2 35 325.00 11,375.00

Total for MicellaneousWork


N/ LKR 301,675.00
Carried to Bill No 02 Summary