Random Rubble Masonry in Cement Mortar 1:5 in Superstructure
Random Rubble Masonry in Cement Mortar 1:5 in Superstructure
Random Rubble Masonry in Cement Mortar 1:5 in Superstructure
Ref
Labour Costs Unit No.of Days Rate (Rs) Amount (Rs)
No.
Skilled labor Labour Day 3 2,200.00 6,600.00
Unskilled labor Labour Day 4 1,600.00 6,400.00
Add for Small tools &
Scafolding 3% of 390.00
Labour
1 Sub-total for Labour 13,390.00
Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
6" - 9" Rubble Cu 1.3 8,250.00 10,725.00
Cement Bag 5 990.00 4,950.00
Sand Cu 0.3 19,000.00 5,700.00
Water Gal 100 1.00 100.00
Sub-total for Materials 21,475.00
1
Mixing & Placing of Grade C30 Concrete
Assumptions:
1 Considered additional 5% of materials for wastage during handling
Ref No. Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
Ref No. Equipment Cost No. of Units No.of Days Rate (Rs) Amount (Rs)
Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
2
Materials for Placing & Curing of concrete
Ref No. Material Costs Unit Qty Rate (Rs) Amount (Rs)
Water Gal 100 1.00 100.00
9 Sub-total for Materials 100.00
Unit Rate for Mixing & Placing of Grade C30 Concrete Rs/m3 27,763.00
3
225 mm thick Brick wall in cement sand 1:5 in Superstructure
Ref
Labour Costs No. of Units No.of Days Rate (Rs) Amount (Rs)
No.
Skilled labour 1 2.25 2,200.00 4,950.00
Unskilled labour 1 3.75 1,600.00 6,000.00
Add for Small tools & Scafolding
328.50
3% of Labour
1 Sub-total for Labour 11,278.50
Ref
Material Costs Unit Qty Rate (Rs) Amount (Rs)
No.
Bricks No 1090 10.00 10,900.00
Allow 5% of Wastage 545.00
Cement Bag 3 990.00 2,970.00
Sand Cu 0.2 19,000.00 3,800.00
Water Gal 115 1.00 115.00
3 Sub-total for Materials 18,330.00
4
Clearing site and grubbing up all small trees not exceeding 500mm girth and including
bushes, scrubs, undergrowth hedges etc
Ref
Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
No.
Unskilled labour 1 0.75 1,600.00 1,200.00
2.5% of Plant cost for
30.00
Tools
1 Sub-total for Labour 1,230.00
Unit Rate for Clearing site and grubbing up all small trees not
exceeding 500mm girth and including bushes, scrubs, Rs/m2 170.00
undergrowth hedges etc.
5
Removing top soil to a Depth not Exceeding 150 mm
Ref
Labour Costs No. of Men No.of Days Rate (Rs) Amount (Rs)
No.
Unskilled labour 1 10.00 1,600.00 16,000.00
2.5% of Plant cost for
400.00
Tools
1 Sub-total for Labour 16,400.00
Unit Rate for Removing top soil to a Depth not Exceeding 150 mm Rs/m2 226.00