Basic Building Measurement
Basic Building Measurement
Basic Building Measurement
BUILDING
MEASUREMENT
Paul K. Marsden
A UNSW Press book
Pi1 hirshrd bv
Universic ofNew South Wales Press Ltd
University of New South Wales
UNSW Sydney NSW-2052
AUSTRALIA
\ w w .unswpress.corn.au
C PK Marsden
First published I992
Reprinted 1994
Second edition I998
Reprinted 1999
Reprinted 2002
Reprinted 2003
Reprinted 2005
This book is coplnght. Apart horn any fair dealing for the purpose of private study. research.
criticism or review, as permitted under the Cop>Tight Act, no part may be reproduced by any
process without written permission. Inquiries should be addressed to the publisher.
Includes index.
ISBN 0 86840 576 0
692 50994
AchowIedgment IS made to The Australian Inshtute of Quanhh SurveLors and The Master
Builders' Construction and Houstng Associahon Australia. Inc for pemssion to tnclude excerpts
from the Australian Standard Method of Measurement of Buillng Worhs, (5' edn) 1990
CONTENTS
CHAPTER 1 INTRODUCTION 1
CHAPTER 6 FINISHES 27
CHAPTER 7 MASONRY 39
CHAPTER 8 WOODWORK 48
CHAPTER 9 ROOFING 63
CHAPTER 10 CONCRETE 76
CHAPTER 11 GROUNDWORKS 98
INDEX 170
CHAPTER 1
INTRODUCTION
This book is a basic introductory text for students studying the measurement of
building works and is designed to be used in'conjunction with the Australian Standard
Method of Measurement of Building Works, 5th Edition, 1990 (SMM).
The sequence of this book is different from most other quantity surveying text books
in that the material is not presented in trade order, but follows an approach of starting
with simple tasks and then proceeding to the more difficult areas. This aligns with the
traditional method of training staff adopted by most quantity surveying practices.
1-01. TERMINOLOGY
There are a number of terms and phrases used by the quantity surveying profession
when measuring quantities and it is essential that these are fully understood by the
student before measurement begins. Many of the terms and phrases are unique to the
construction industry and have a different meaning from that which is listed in the
dictionary. The following terminology is used in this book and as such students
should become familiar with these terms.
Bill of Quantities: A trade order list of materials, labour and services
necessary to construct a particular project.
Billing: The quantity surveying process of writing or drafting Bill of
Quantities descriptions and presenting the quantity for each description.
Billing Units: The unit of measurement used when billing. For example:
Bill, measure and extend rb.m.e.1: The total quantity surveying process of
writing a description, measuring the quantity from the drawings, carrying out
all the necessary calculations and, finally, billing the answer. This total
process is explained in Chapters 3 and 4.
Ditto [do.]: A term meaning "all as above described", that is, in the preceding
description. This is illustrated in the following example:
a Internal flush hollow core doors each 2040
x 820 x 35 thick, veneered for paint
finish and hung on a pair of lOOmm steel
butt hinges to timber frames. no 10
b Ditto, each 2340 x 820 x 35 thick, and
hung on three lOOmm steel butt hinges. no 6
The "Ditto" used in the second description means Infernal flush hollow core
doors, each 2340 x 820 x 35 thick, veneered for paintfinish and hung on three
l O O m m steel butt hinges fo timber frames.
Ditto is used very frequently in a Bill of Quantities and saves the quantity
surveyor a lot of time when writing Bill of Quantities descriptions.
Item: A term used in the Bill of Quantities to signify a description involving a
cost to the builder but where no quantity is required to be given. For example:
a Allow for the preparation of shop
drawings. Item
Note: A term used in the Bill of Quantities to signify a description involving
no direct cost to the builder but which will influence the pricing of subsequent
descriptions. For example:
a Refer to the Specification for
particulars of woodwork. Note
1.02. ABBREVIATIONS
Quantity surveyors often use standard abbreviations when billing and it is essential
that the student has a knowledge of these abbreviations. The following abbreviations
have been used in this text and students are advised to familarise themselves with
these terms.
a.b.d. as before described
a.b.s. as before specified
b.me. bill, measure and extend
c.p. chromium plated
CtS centres
ddt deduction
Chapter 1 Introduction 3
diarn diameter
d.p.c. damp proof course
figs footings
galvd galvanised
G.F.A. gross floor area
t.C. terracotta
LENGTH metre m
millimetre m l O O O m = lm
2
AREA square metre m
l h a = 10,000m2
hectare ha
3
VOLUME cubic metre m
3
litre L lOOOL = l m
MASS tonne t
kilogram kg lOOOkg = It
Except for the hectare, the construction industry is resmcted to using only the
following metric prefixes:
mega M lo6
kilo k 103
milli m 1o - ~
micro P lo4
CHAPTER 2
A Bill of Quantities is a trade order list of materials, labour and services necessary to
complete a given project.
For large building projects the client may employ a professional quantity surveyor to
prepare a Bill of Quantities. However, on small building works it is normal for the
builder to prepare his own Bill of Quantities.
When a professional quantity surveyor is employed by the client to prepare the Bill of
Quantities, each tenderer is issued with several copies of the Bill of Quantities. The
Bill of Quantities is then used to assist the builder in arriving at his tender figure by
pricing each item in the Bill of Quantities.
The traditional Bill of Quantities is arranged in trade order. The order of trades is
normally in the same order as the Specification.
Apart from being arranged in trade order, each trade has the facility for each
description to be priced and totalled to give the total cost of each trade. The total trade
cost is then transferred to a General Summary to obtain the total project cost.
In order to be able to refer to any section in the Bill of Quantities, each description is
given a separate and distinct reference. It is also normal practice for each page to be
numbered and labelled with the project name and trade.
A Bill of Quantities prepared by a professional quantity surveyor is prepared in
accordance with the rules set out in the Australian Standard Method of Measurement
of Building Works (SMM) and is measured NET, and as such is not an order list.
Other Bill of Quantity formats include:
Specification and Bill of Quantities: As the name implies, this document
contains both the Specification and the Bill of Quantities rather than having
two separate documents.
Specified Bill of Quantities: This document is similar to the Specification
and Bill of Quantities except that the Specification is incorporated with the Bill
of Quantities ~ I I the form of preamble notes and the Bill of Quantity
descriptions. The quantities do not normally form part of the contract but the
preambles and descriptions are part of the contract.
Elemental Bill of Quantities: A Bill of Quantities prepared in elemental
format rather than the traditional trade order sequence.
6 Basic Building Measurement
Following are typical pages from a traditional trade order sequence Bill of Quantities.
Page 7 is a typical trade section page. Note that each description has an alphabetical
prefix, measurement details are not shown, specific locations are not given in the
descriptions, and the unit rate column and monetary column are left blank. The
builder would estimate the cost of each item, total all the items on the page and
transfer the total to the Trade Collection.
Page 8 is a typical Trade Collection where the builder collects all the page totals for
the particular trade to arrive at the total cost of the trade section.
This total trade cost is then transferred to a General Summary (refer page 9) where all
the trade sections are totalled to arrive at the total amount of tender.
Bills of Quantities prepared using computer software packages are presented in the
same format as noted above. However, they are more convenient for the builder to
price during the tender stage since the builder is only required to enter the unit rates
for each description. The multiplication of the unit rate by the quantity, monetary
additions, trade totals and the General Summary total are automatically carried out and
are a function of the software. This saves the builder time when preparing a tender.
Chapter 2 BiHs of Quantities and the SMM 7
Doors
C Internal doors type A, each 2040 x 820
x 40 thick hollow core doors h e d on both
faces with Coachwood veneer for clear
finish; include for hanging to timber
kames with two l O O m m steel butt hinges. no 8
Skirtings
d 75 x 25 dressed select Coachwood splayed
skirting fixed to timber framed walls. rn 120
Architraves
e 50 x 25 dressed select Coachwood splayed
architraves fixed to door kames. rn 84
Shelving
f 300 wide, 300 high gallows brackets
to support shelving, framed up having
50 x 25 wrot Oregon members, plugged
and screwed to brick walls. no 18
-
SAMPLE BILL
WOODWORK 140
ll
8 Basic Building M m e m e n t
WOODWORK COLLECTION:
Page 138
Page 139
Page 140
Page 141
SAMPLE BILL
WOODWORK 142
2.03.03. SAMPLE GENERAL SUMMARY PAGE
GENERAL SUMMARY
PRELIMINARIES 11
DEMOLITION 16
GROUNDWORKS 22
CONCRETE 26
MASONRY 55
STRUCTURAL STEEL 75
METALWORK 101
WOODWORK 142
GLAZING 144
HARDWARE 150
ROOFING 160
WINDOWS 170
DOORS 180
FINISHES 185
PAINTING 205
FURNITURE 215
HYDRAULICS 224
DRAINAGE 236
ELECTRICAL INSTALLATIONS 242
The SMM states that the '@purposeof the Standard Method of Measurement is to
provide a uniform basis for the measurement of building works". It is a book of
measurement rules and like most other rule books does not instruct you how to
measure quantities but rather lists the principles and conventions that apply when
measuring quantities. After perusing the SMM you will notice that it is broken into a
number of sections commencing with Section 1, Introduction, General Rules and
Recommendations, which is followed by a number of trade sections. These trade
sections generally align with the NATSPEC Specification sections.
After reading Section 1 you should have noted the following major points:
1. Unless otherwise stated, all work is measured net as fixed in position.
2. Minimum deduction requirements.
3. Unless otherwise stated, descriptions in Bills of Quantities are deemed
2000
200
16342
1114
38
999 I
772
12 Basic Building Measurement
I I 2 3 4 5 1 6
I
I
The paper also has facility for the project name, trade and page number to be listed on
the top right hand comer. This is important as it acts as a control to avoid missing or
misplaced pages and confusion with other projects. It is essential that this information
is filled in on every sheet when measuring the quantities.
PROJECT
TRADE:
PAGE:
Chapta 3 The Measurement Rocess 13
PROECT:
TRADE:
PAGE:
14 Basic Building Measurement
Following are examples of linear, area, volume and number take-off. Note the
following points:
1. Except for number take-off, all take-off figures are expressed in metres
to two decimal places, and NO metric symbol is used after each take-
off figure. In the case of number take-off, integer numbers are used.
2. Take-off figures are written down the page and not across the page.
4. All extensions, except for number take-off, are calculated to the closest
second decimal place.
5. All take-off figures are referenced back to the drawings in the location
subcolumn. This allows work to be identified and checked at a later
date.
7. The fifth column is used to calculate a take-off figure where the take-
off figure cannot be taken directly from the drawings. Such
calculations are termed sidecasrs. This column is also used to list
supplementary information and location keys.
I i i
2 I 2 I w1,2 i i
1 3 I 3 w3-7 1 1
i I 5 1
I 1 I
16 ' Basic Building Measurement
ROOM A
b
PLAN
2 17.50 Rm A
2 / 5.50 ,I
26.00
Deductions:
0.90 0.90 RmA/Dl
25.10m
Chapter 3 The Measurement Process 17
5990 1
1
4810 1
1
2630
1
1
-D’
7550 L 5880
1
13430
-
5.88 a
1.44 b
4.92 C
1.44 d
2.52 e
5.88 f
5.88 g
-
1.20 h
7.44 i
7.08 j
43.68m
18 Basic Building Measurement
Area take-off is a simple procedure, requiring the measurer to determine length and
width take-off figures. Consider the plan shape shown below. There are two methods
of determining the area. Firstly, to measure overall and deduct the comer rectangle.
Secondly, to divide the room into two separate rectangles. The overall method is the
preferred option; however, the other method is acceptable. Both methods are shown
below.
PLAN
Most volume take-off uses previously calculated centre line lengths or total areas
when determining volume quantities, e.g. concrete strip footings, concrete floor slabs,
etc. In these cases the lengths can be repeated and multiplied by the cross-sectional
areas or the total area repeated and multiplied by the thickness.
3.08.01. EXERCISE 1 Measure and extend the perimeter, area and volume of a
concrete floor slab 7070- x 5630mm x 150mm thick.
3.08.02. EXERCISE 2 Measure and extend the perimeter and area of the rooms
shown below.
4 1
w
F\&=>
8100
c=
23 ROOM
9580
g-z)
4 9560 1
1 6000 iS6004
3.08.03. EXERCISE 3 Measure and extend the volume of the footings shown below.
4900
PAD FTG. PI (92-6 SWIU)
4.01. BILLING
There is no set format for drafting Bill of Quantities descriptions and each office
adopts its own particular style. Basically, there are two different formats. The
traditional approach is to draft a full description incorporating all essential
information, whilst the second approach is typified by the use of subheadings together
with very short descriptions. Both methods are equally acceptable and the method
adopted is usually dictated by office policy. This text will mainly use the traditional
method. Following is an example of each style:
Traditional Method:
Reinforced concrete F c 20 MPa in strip
footings poured into trenches. m3 10
Alternative Method:
IN-SITUREINFORCED CONCRETE
F c 20 MPa Concrete
Smp footings poured into trenches. m3 10
Regardless of which method is adopted the same basic principles still apply. In
addition to giving the billing unit and total quantity, each Bill of Quantities description
should:
NAME
SIZE
DESCFUBE and
NAME: Name the subject, that is, what does the quantity represent? In the above
case, there is no doubt that "Internal cement render" is the subject and the total
quantity is 100 m2
SIZE: "12mm thick
Chapta 4 The Billing Process 21
4.03.01. EXERCISE 1 In accordance with the SMM, bill the following quantities:
190.01m
190.01t
190.01kg
CHAPTER 5
5.01. GENERALLY
After the basic knowledge contained in the previous chapters has been fully
understood, the next step is the billing and measurement of elementary work which
essentially involves abstracting simple information from the drawings and
specification. Typical examples would involve billing and measuring: doors, frames
and hardware; windows; and furniture.
QUESTION: B.me. the doors, frames, architraves and hardware as specified and
detailed in Drawing 5.1.
SPECIFICATION NOTES
DOOR
2
e Ex 50 x 25 splayed Pacific maple
architraves fixed to timber door frames
and mitred at corners. m 73
5 1 2 1 2 f U 42.40 D1-5
5 1 2 l U 9.40
2 1 2 1 2 f U 16.96 D6,7
2/21 0.89 3.56
72.32m
f C.p. mortice latch set complete with all
necessary lever furniture. no 7
-
7 -7 D 1-7
7
SPECIFICATION NOTES
DOORS, FRAMES AND HARDWARE
Provide and f i x doors, frames, trims and hardware of the types and sizes as
set out in the schedule below. Door frames to be plugged and f u e d to
brickwork All frames to be solid rebated Oregon. Provide and fu 25mm
Oregon quadrant mould to door frames at junction with render and 25mm
Oregon square section storm moulds extentally. All moulds to be mitred at
comers.
REF. DOOR FRAME FURNITURE HINGES
D5-6 2040 x 820 x 35mm 75 x 50 C.p. mortice lock set 2 x l00mm steel
thick flush hollow with lever furniture butt hinges.
door veneered for C.p. door closer
paint finish.
26 Basic Building Measurement
25 QUADRarJT MOULD
7 5 % 50 FRAM€
DRAWING 5.2
CHAPTER 6
FINISHES
6.01. GENERALLY
After mastery of the elementary work contained in the previous chapters, the next task
normally assigned to trainees is the measurement of the finishes trades. These trades
include paving, tiling, plastering, terrazzo work, resilient finishes and carpet. They are
relatively simple to measure since they mainly involve area and linear measurements
which can be taken directly from the drawings.
QUESTION: B.me. the floor finishes as specified and as shown in Drawings 6.1 and
6.2.
SPECIFICATION NOTES
FLOOR FINISHES
FINISHES AS LAID-CONCRETE Steel trowel finish slab surface
suitable to receive carpet.
CARPET Finish all internal rooms with Ajax 101 carpet laid on Ajax
commercial quality rubber underlay in accordance with AS 2455.
QUARRY TILE THRESHOLD Provide 200 x 200mm selected colour
Australian manufacture quarry tile threshold to Door 1. Bed tiles in cement
on a bed of cement mortar, point up joints and set tiles to weather.
TIMBER TRIM-SKIRTINGS Provide 100 x 25mm Pacifx maple splayed
skirtings at junctions of walls with floors. Fir to wall plugs in brickwork.
28 Basic Building Measurement
TYPICAL SECTION
5’
8990 9.
PLAN
DRAWING 6.1
Chapter6 Finishes 29
1 280 , I10 .
'
DRAWING 6.2
30 Basic Building Measurement
FLOOR FINISHES
Finishes as Laid-Concrete
a Steel trowel finish to concrete floor slab
suitable to receive carpet. m2 49
8.65
-
5.65 -
48.87 Store, Office
48.87m2
Carpet
b Ajax 101 carpet laid on Ajax commercial
quality rubber underlay in accordance with
AS 2455 to concrete floor slabs. m2 46
3.99
5.43 21.67 Store
4.57
5.43 24.82 Office
2 10.97
0.11 0.21 D1,2
46.70
Deductions:
0.24
2.84 0.68 Store(5430 2700 + 110)
0.24
2.70 0.65 Office
1.33m2(ddt)
45.37m2
0.97 0.97 D1
0.97m
Chapter6 Finishes 31
Timber Trim-Skirting
d 100 x 25mm Pacific maple splayed skirting
fixed to wall plugs in brickwork. m 37
2 / 3 3 7.98 Store
215.43 10.86
214.57 9.14 Office
21 5.43 10.86
u r n
Deductions:
0.85 0.85 D1 ( 9 7 0 - 6 0 - 6 0 ~ 8 5 0 )
21 0.97 1.94 D2
2.79m (ddt)
36.05m
Item d Skirting: Perimeter length of all rooms is measured then all doorways
are deducted. Note that Door D2 is deducted twice since skirting has been
previously measured to both sides of the opening.
QUESTION: B.me. the ceiling finishes as specified and as shown on Drawing 6.1.
SPECIFICATION NOTES
CEILING FINISHES
CEILING FINISHES
Plasterboard Ceiling Lining
a lOmm thick recessed edge gypsum plasterboard
ceiling lining, finished with flush joints
and fixed direct to timber ceiling framing. m2 46
3.99
5.43 21.67 Store
4.57
5.43 24.82 Office
46.49
Deductions:
0.24
2.84 0.68 Store (5430 - 2700 + 110)
0.24
2.70 0.65 Office
1.33m2(ddt)
45.16d
Plasterboard Cornice
b 90mm coved gypsum plasterboard cornice mitred
at angles and fxed in accordance with AS 2589. m 40
39.20m
WALL FINISHES
Internal Cement Render
a Preparation of brick wall surfaces to receive
cement render by removing all dust and loose
material and applying one coat of approved
bonding agent. m2 82
21 3.99
-
2.40 19.15 Store
21 5.43
2.40 26.06 Store
21 4.57
2.40 21.94 Office
21 5.43
2.40 26.06 Office
93.21m2 (gross area)
Deductions:
0.97
2.15 2.09 D1
21 0.97
-2.15 4.17 D2
0.85
0.95 nil W1
21 1.61
1.38 4.44 W2,3
21 0.24
2.40 1.15 Store, Office < 250mm wide
11.85d (ddt)
8 1.361112(net area)
34 Basic Building Measurement
0.97 0.97 D1
21 2.15 4.30
5.27m x 0.06m = 0.32m2
2 / m 1.70 W1
21- 1.90
2/2/M 6.44 W2,3
21 21 1.38 5.52
15.56mx 0.11m= 1.71mz
25.63m 3.18mZ
Items a and c: First calculate the gross area, ignoring openings, then deduct all
the openings and surfaces less than 250mm wide included in the gross area.
Note that Door D2 is deducted twice since both sides of the opening have been
included in the gross area.
SPECIFICATION NOTES
FLOOR FINISHES
CARPET Finish all internal rooms with Ajar 101 carpet laid on Ajax
commercial quality rubber underlay in accordance with AS 2455.
TIMBER TRIM-SKIRTINGS Provide 100 x 25mm Pacific maple splayed
skirtings afjunctions of walls with floors. Fix to wall plugs in brickwork.
SPECIFICATION NOTES
CEILING FINISHES
1 6560 1
.I
6 28 0
’ I
I
0
\
\
CoMMUhl ROOM @
\
@ \
- - - - - - - - - - - - -
17 1’1 1’
c 12840
1
PLAN
DRAWING 6.3
--
Chapter6 Finishes 37
w.PLASTER60Ad
CEiLlrJC LINING 1I
PLASTERBOARD
CORNICE
520
cl
69 d
d)
CEMENT REND€& d'
N
FL
SECTION
DRAWING 6.4
38 Basic Building Measurement
280 1
DRAWING 6.5
CHAPTER 7
MASONRY
7.01. METRIC STANDARD BRICKWORK
This chapter will be confined to the measurement of metric standard brickwork. The
following brick chart may be helpful when measuring metric standard brickwork.
. . -_
I-r
;- - -1'!
1
* !I
I L-
L -- - -.
. -.-- J*.i ,
,1.
PLAN
Length of face brick outer skin = 2[A+B]
Length of common brick inner skin = 2[C+D]
Length for cleaning down face brickwork = 2[E+F]
QUESTION: B.me. the brickwork as specified and as shown in Drawings 6.1. and
6.2.
SPECIFICATION NOTES
BRICKWORK
BRICKS All brickwork exposed externally shall be constructed with selected
calcium silicate face bricks. All other brickwork to be constructed with
calcium silicate common bricks.
MORTAR All brickwork shall be laid in 1 :5 cement mortar.
BOND All brickwork shall be constructed in stretcher bond.
JOINTS Joints in facework shall be raked. Leave all other surfaces rough.
CLEANING DOWN Clean down all face brickwork on completion with 5%
hydrochloric acid solution and wash offwith clean water.
CAVITY TIES Provide and build in 4mm d i m . galvd wire wall ties to all
cavity walls spaced 900 apart everyfourth course in height and staggered.
SILLS Sills to windows shall be snapped headerface brick on edge sills, set
to weather.
BRICKWORK
Ground Floor Brickwork in 1 :5 cement mortar
a 110 thick face brick skins of cavity
walls in stretcher bond comprising
selected calcium silicate face bricks 2
having joints raked on one face. m 62
21 8.88
-
2.32 41.20 a,c
21 5.88 C
-
2.32 27.28
2
b,d
68.48m (Gross Area)
Deductions:
0.97
2.15 2.09 D1
0.85
1.12 nil w1
21 1.61
1.55 4.99 W2,3
7.08m (ddt)
21 8.54
-
2.40 40.99 a,c
21 5.54
-
2.40 - b,d
26.59
67.58m2 (Gross Area)
Deductions:
0.97
2.15 2.09 D1
0.85
-
0.95 nil w1
21 1.61
-
1.38 4.44 W2,3
6.53m’ (ddt)
5.43
-
2.40 13.03 e
0.24
-
2.40 -
0.58 e
13.61311’ (Gross Area)
Deductions:
0.97
-2.15 -
2.09 D2
2.09m (ddt)
11.52m (Net Area)
Sills
d Snapped header face brick on edge sills
to windows, comprising selected calcium
silicate face bricks laid in 1 : 5 cement
mortar and set to weather. m 5
0.85 0.85 W1
21 1.61 3.22 W2,3
4.07m
Cavity Ties
e 4mm diam. galvd wire wall ties to cavity
walls spaced 900 apart every fourth 2
course in height and staggered. m 62
61.40m’ (Repeat area of item a)
Sundries
f Clean down face brickwork on completion
with 5% hydrochloric acid solution and 2
wash off with clean water. m 64
21 8.99
2.32 41.71 a,c
21 5.99
2.32 27.79 b,d
4.07
0.30-1.22 sills
70.72311’ (Gross Area)
Deductions:
2
7.08m (ddt) Repeat area of ddt from item a
63.64m’ (Net Area)
44 Basic Building Measurement
MEASUREMENT NOTES-BRICKWORK
Item a - Face brick skins: Use centre line measurements multiplied by wall
height to determine the gross wall area. Deduct openings to determine the net
area. W1 is not deducted since it is less than lm’. (Refer SMM, 3.4, page 4.)
The height of all window openings includes an additional 172mm to allow for
the brick on edge sill course which is measured separately. (Refer SMM, M1
and 2, page 53.)
Item b - Common brick skins: Same technique as item a but centre line
measurements and wall heights are different.
Item d - Sills: Include all window openings, including those openings less
than lm’.
Item e - Cavity Ties: Purely for practical reasons the net area of the outer face
brick skin is repeated. This area (61.40m’) is slightly greater than the area of
the cavity and is used in order to avoid having to take off new quantities. Also,
the unit rate for this type of work is relatively low in cost.
Item f - Sundries: Exposed area measured excluding the area of reveals.
Pointing and cleaning down reveals is deemed to be included in the price.
(Refer SMM, P1, page 53. )
chapter7 Masow 45
7.04. EXERCISE-BRICKWORK
QUESTION: In accordance with Drawings 6.3, 6.4 and 6.5 and the following
specification notes, measure and extend the following Bill of Quantities, Brickwork
section.
SPECIFICATION NOTES
BRICKWORK
BRICKS All brickwork exposed externally shall be constructed with selected face
bricks P.C. $600.00 per thousand delivered to the site. All other brickwork to be
constructed with sound common bricks.
MORTAR All brickwork shall be constructed with I:1:6 composition mortar.
BOND All llOmm thick walls shall be constructed in stretcher bond. All 230mm
thick walls shall be constructed in English bond
JOINTS Joints in face brickwork shall be ironed.
CLEANING DOWN Clean down all face brickwork on completion with 5%
hydrochloric acid solution and wash off with clean water.
CAVITY TIES Provide and build in 4mm d i m . galvd wire wall ties to all cavity
walls spaced 900mm apart everyfourth course in height and staggered.
SILLS Sills to all windows shall be snapped header face brick on edge sills set to
weather.
AIR BRICKS Air bricks shall be 230 x 150 louvred pattern terracotta air bricks of
colour to match the face bricks. Build air bricks into outer skin of cavity walls
below floor level as required to ventilate the sub floor space and form opening in
inner skin behind air brick.
ANT CAPS Ant caps shall be 0.5mm thick galvd steel in accordance with ASI694.
Provide and build in ant caps at underside offloor frame as follows:
i. to all isolated piers
ii. to all engaged piers
iii. to allfoundation brick walls to provide a continuous barn-er
GALVANISED STRAPS Build in 1500mm long, 25mm wide, I.6mm thick galvd
steel straps to hold down wall plates. Straps to be spaced at 1800mm max cts and be
not less than 1200mm down cavity with ends turned 75mm into brickwork.
DAMP PROOF COURSES AND FLASHINGS Provide and build in 0.45mm thick
bitumen coated aluminium dpc and flashing in thefollowing locations:
i. all foundation walls and piers
ii sills to all windows
iii. heads of all windows and external doors extending 150mm at each
side of opening
CAVITY INFILLING Infill cavity to all cavity walls below ground level with F’c
ISMPa concrete and finish top with an outward splay.
Basic Building Measurement -
BRICKWORK
Sills
m Snapped header face brick on edge sills
to windows, comprising selected face bricks
P.C. $600.00 per thousand, bedded in 6: 1:1
composition mortar and set to weather. m
-
- chapter7 Masonry - 47
Cavity Ties
a 4mm diam. galvd wire wall ties to 280mm
thick cavity walls spaced 9 0 0 m apart
every fourth course in height and staggered. mz
Cavity Infilling
b F c 15 MPa concrete as infilling to 60mm
wide cavities below ground level2finished
on top with an outward splay. (m ) m3
Ant Caps
f 240 x 240 x 0.5mm thick galvd steel
ant caps to isolated piers. no
Sundries
WOODWORK
Refer to SMM, Section 11, Woodwork, pages 87-96 for the rules governing the
measurement of woodwork In particular the following basic requirements should be
noted:
1. Structural timbers and joinery timbers including frames, linings,
skirtings, trims,etc. are measured their NET length with no allowance
for joints and 0.3m order length requirements.
2. Structural timbers exceeding 3.60m long are given separately in
increments as noted. (Refer SMM, page 88.) However, in the
following examples, this rule has been interpreted to apply only to
structural timbers specified or shown to be in a single length.
For example, 100 x 75mm timber floor bearers are grouped together in
the same description, irrespective of their length, since there is no
specific requirement for them to be in single lengths. However, a
4.00m long timber beam spanning between two supports would be
given separately and described in increments of exceeding 3.60m not
exceeding 6.00m long.
In accordance with the SMM if this measurement procedure is adopted,
a note should be inserted at the commencement of the trade section in
the Bill of Quantities. (Refer SMM, 2.2, page 3.)
1. Calculate the spacing distance (ie. the distance between the centre of
the first member and the centre of the last member).
2. Divide the spacing distance by the specified centre spacing and convert
the answer to an integer number.
EXAMPLE 8.02.01. Calculate the number of studs for the wall frame as detailed in
Drawing 8.1 below.
1
1
7000
1
1
ELEVATION-WALL FRAME
DRAWING 8.1
No. of studs:
Step 1: Spacing distance = 7000 - 50 = 6950
Step 2: 6950 / 600 = 11.5833 = 12
Step 3: 12 + 1 = 13 studs.
0
CD
PLAN
DRAWING 8.2
Chapter8 Woodwork 51
WOODWORK
No. of bearers:
ROOITIS A,B = 3425 / 1800 = 2 + 1 =3
No. of joists:
RoomA=3950/450=9+1=10
Room B = 7050 / 450 = 16 + 1 = 17
Flooring
c 100 x 25 Cypress pine T & G flooring boards,
closely cramped, double nailed and punched. m2 39
4.00
-
3.50 14.00 Room A
7.10
3.50 24.85 RoomB
0.90
-
0.11 -0.10 doorway
38.95m2
QUESTION B.rne. the ground floor framing and flooring as specified and as shown
in Drawings 6.3, 6.4 and 6.5.
SPECIFICATION NOTES
WOODWORK
GROUND FLOOR FRAMING Floor framing to be F8 grade sawn
hardwood Bearers to be 100 x 75 spaced at 1800mm maximum centres.
Floorjoists to be 100 x 50 spaced at 450mm maximum centres.
FLOORING Flooring boards to be 100 x 25 T & G Cypress pine. Closely
cramp boards, double nail, punch and sand smooth on completion.
Chapter 8 Woodwork 53
QUESTION: B m e . the roof fiaming as specified and as shown in Drawings 8.3 and
8.4.
SPECIFICATION NOTES
WOODWORK
Eaves width = 5 0 0 m
Roof pitch = 20 degrees
PLAN
DRAWING 8.3
54 Basic Building Measurement
SECTION
DRAWING 8.4
WOODWORK
Roof Framing
a 125 x 50 seasoned F5 Oregon rafters. m 194
Number of Rafters:
Building length 13000
+ 2 x eaves width 1000
Overall roof length 14ooo
Divide cts spacing +-a
24
Add 1 +1
-
Rafters to one side 25
Both sides -
x2
Number of rafters = -
50
I I
Length of Common Rafter: 1
rl
H 1
Half building width 3000
+ eaves width 500
less half ridge - 12
Horizontal Distance [ H 3 3;188mm
Net rafter length [ R ] = H / cos 8
= 3488 / cos 20°
= 37 ~ ~ I T K I
Length of Ridge:
Roof length 14000
less roof width -7000
plus rafter thickness - 50
Ridge length = 7050mm
Length of Hip:
Net hip length =J-im
=&&z
= 5094m111
2113.00 26.00
26.00m
71 3.50 24.50
24.50m
e lOmm diam. galvd bolts securing collar ties to
rafters, 101-200 long. no 28
412 -
28 (4 per collar tie)
28
Item a-Rafters: The total quantity of timber in rafters in a hipped end pitched
roof is the same as a gable end pitched roof given the same plan dimensions
and pitch. Therefore, when measuring the rafters, in the first instance, ignore
the hipped ends and measure as a gable end pitched roof. First calculate the
number of rafters, then the length of a common rafter. Use simple
trigonometry to determine the net rafter length and add an allowance for the
plumb cuts at each end of the rafter. It is recommended that 150mm be added
for the plumb cut allowance (P.C.A.).
Item b-Ridge: For this simple rectangular plan the length of the ridge is equal
to the length of the roof less the width of the roof plus the thickness of one
rafter.
Item b-Hips: The net length of the hip is calculated by applying Pythagoras’s
theorem and using the horizontal distance (H) and net rafter length (R)
previously calculated for the rafters. It is recommended that 150mm be added
to the net hip length for the plumb cut allowance (P.C.A.).
QUESTION: B.rne. the roof framing as specified and as shown on Drawings 6.3 and
6.4, given that the roof pitch is 22.5 degrees and the eaves width is 520mm.
SPECIFICATION NOTES
WOODWORK
Rafters: Divide the roof into two rectangles starting with the greatest span.
Treat each rectangle as in Example 8.05.
I I
L I
Ridges: Use the same method as Example 8.05 to calculate the major ridge
length. The length of the minor ridge is determined using the knowledge that
the opposite sides of a parallelogram are equal.
Hips and Valley Rafters: Use the same method as the hips in Example 8.05.
58 Basic Building Measurement
QUESTION: In accordance with Drawing 8.5 and the following specification notes,
measure and extend the following Bill of Quantities extract for the roof trusses.
SPECIFICATION
WOODWORK
ROOF TRUSSES Frame up roof with Type A proprietary prefabricated
timber roof trusses spaced at 600mm maximum centres. Secure trusses to
wall plafes with Trip-L-Grip framing anchors. Provide two 75 x 50 Oregon
wind braces at each gable end truss and brace trusses with 75 x 25 Oregon
diagonal braces nailed fo underside of top chords.
SECTION
12000
,
ROOF PLAN
DRAWING 8.5
Chapter8 Woodwork 59
WOODWORK
Roof Trusses
a Type A proprietary prefabricated timber
roof trusses to suit concrete roof tiles,
spaced at 600mm maximum centres, nominal
6000mm span, 17 degrees pitch, 600mm
horizontal overhang each side, and
include for hoisting and fixing approx.
2.50m high above ground level. no
b Trip-L-Grip framing anchors securing
trusses to timber wall plates. no
c 75 x 50 Oregon wind bracing. m
d 75 x 25 ditto diagonal bracing. m
8.08. EXAMPLE-EAVES
Following is a worked example illustrating the measurement of fascias, barges, eaves
soffit linings and associated trims.
QUESTION: B.rne. the fascias, barges, eaves lining and trims as specified and as
shown in Drawing 8.6, given that the roof pitch is 22.5 degrees.
SPECIFICATION
WOODWORK
FASCIAS AND BARGE BOARDS to be ex. 200 x 38 dressed and grooved
bullnosed Oregon fixed in long lengths and mitred at external comers and
joints.
Provide matching infill panel at junction of fascia and barge board at gable
ends.
EAVES SOFFIT LINING Line eaves with 4Smm thick fibre cement
sheeting nailed direct to timber soffit framing and finished at joints with
extruded plastic H section moulding.
TRIMS Finish junction of eaves soffit lining and brickwork with 25mm
Pacific maple quadrant mould mitred at external corners and joints.
T
. 5H:wN?
SECTION A SECTION 8
L A
9000
1
ROOF PLAN
DRAWING 8.6
Chapter8 Woodwork 61
WOODWORK
Fascias and Barge Boards
a Ex 200 x 38 dressed and grooved bullnosed
Oregon fascia, fixed in long lengths and
mitred at external comers and joints. m 27
219.74 19.48
6.98 6.98
a,c (250+9000+450+38)
d (38+450+6000+450+38)
JD-~I
C
26.46m
213.93 7.86 b
7.86m
-
2 -
2 gable ends
-2
Trims
f 25mm Pacific maple quadrant mould fixed at
the junction of eaves soffit lining and
brickwork, and mitred at external comers
and joints. m 33
2 / m 18.10 a,c
6.05 6.05 d
21 4.00* 8.00 b *approx. quantity
32.15m
MEASUREMENT NOTES-EAVES
Item a-Fascias: Fascias have been measured their extreme length.
Item b-Barge Boards: Calculate barge length using the same method used for
the calculation of the common rafter length previously.
Item d-Eaves Soffit Lining: Net area measured. Joint cover strips between the
sheets included in the description. (Refer SMM 11.12, page 90.)
Item e-Eaves Soffit Lining: Measure in metres. (Refer SMM 11.12, M18,
page 90.) Approximate quantity given since the cost of the moulding is
minimal and it does not just@ the time required to calculate the precise length
mathematically.
CHAPTER 9
ROOFING
SPECIFICATION NOTES
ROOFlNG
CONCRETE ROOF TILING Cover all roof slopes with selected colour
Roman pattern concrete roof tiles. Fix tiles to 38 x 25 Oregon battens
spaced to suit the tiles. Finish ridge and hips with matching cappings and
accessories bedded in cement mortar and point up with coloured mortar. On
completion sweep down all roof slopes and clean out all gutters.
ROOFING
Concrete Roof Tiling
a Selected colour Roman pattern concrete
roof tiles fixed to and include for
38 x 25 Oregon battens spaced to suit
the tiles. Roof pitch 20 degrees.
Single storey work. m2 108
Roof Area = 2LS
Roof Length (L):
Building length 13000
+ 2 x eaves width 1000
+ 2 x fascia thickness 50
+ 2 x 50mm oversail 100
Roof length (L) = 14150mm
64 Basic Building Measurement
Slope Height ( S ) :
Half building width 3000
+ eaves width 500
+ fascia thickness 25
+ 50mm oversail 50
Horizontal (H) = 3575mm
Slope height (S) = H 1 cos Roof Pitch
21 14.15
3.81 107.82
107.82m2
b Matching concrete ridge capping bedded
in cement mortar and pointed up in
coloured mortar. m 7
Length of Ridge:
Building length 13000
less building width -6000
Ridge length = 7000mm
7.00 7.00
7.00m
c Ditto hip capping. m 21
Length of Hip:
Hip length -m
-
= 3575’ + 3804’
= 5220mm
2 _.
2
2
Chapter 9 Roofing 65
Where roof tiles finish at an eaves gutter allow 50mm oversail into the gutter.
66 Basic Building Measurement
SPECIFICATION NOTES
ROOFING
TERRACOTTA ROOF TILING Cover all roof slopes with selected colour
glazed Modern French pattern terracotta roof tiles. Fix tiles to 38 x 25 pine
battens spaced to suit the tiles.
Finish ridge and hips with matching terracotta cappings and accessories
bedded in cement mortar and point up with coloured mortar.
Bed verge tiles in cement mortar on IOOmm wide fibre cement strip and
point up with coloured mortar as detailed.
On completion sweep down all roof slopes and clean out all gutters.
SARKING Prior to fming roof battens, sark the roof with double-sided
aluminium foil sarking, lapped and fmed in accordance with the
manufacturer’s instructions.
I / I
--@
e I
--< \
i
@ 1 1
SECTlON 0
DRAWING 9.1
Chapter9 Roofing 67
ROOFING
Terracotta Roof Tiling
a Selected colour glazed Modem French
pattern terracona roof tiles fixed to
and include for 38 x 25 pine battens
spaced to suit the tiles. Roof pitch
22.5 degrees. Single storey work. m2 211
Roof Area A = 2LASA
Roof Length (LA):
Building length 18280
+ eaves width 600
+ fascia thickness 25
+ 50mm oversail 50
+ gable 325
Roof length (LA)= 19280mm
Slope Height (SA):
Half building width 3960
+ eaves width 600
+ fascia thickness 25
+ 50mm oversail 50
Horizontal (HA)= 4635mm
Slope height (S,) = HAI cos Roof Pitch
0
= 4635 I cos 22.5
Slope height (S A)
Roof Area B = 2L,S,
Roof Length (L,):
Roof length (L,) = 3000mm
Slope Height (S,):
Half building width 2000
+ eaves width 600
+ fascia thickness 25
+ 50mm oversail 50
Horizontal (H,) = 2675mm
Slope height (S,) = % I cos Roof Pitch
= 2675 I cos 22.5'
Slope height (S,) = 2895mm
21 19.28
-5.02 193.57 RoofA
21 3.00
-2.90 - 17.40 RoofB
210.97m2
Length of Hip A:
Hip ALength =-
=&zzi7
= 6830mm
Length of Hip B:
=Jzzz
= 3942n~n
= 6830 - 3942
Chapter9 Roofing 69
3 3
-
3
f Verge treatment comprising bedding verge
tiles in cement mortar on l 0 O m wide fibre
cement strip and pointing up with coloured mortar
as detailed; include for all necessary cutting. m 11
Sarking
g Double-sided aluminium foil sarking,
lapped and fixed in accordance with
the manufacturer’s instructions. m2 211
LA 1
1
70 Basic Buildmg Measurement
SPECIFICATION NOTES
ROOFING
TERRACOTTA ROOF TILING Cover all roof slopes with selected colour
glazed Swiss pattern terracotta roof tiles. Fix tiles to 38 x 38 pine battens
spaced to suit the tiles.
Finish ridge and hips with matching terracotta cappings and accessories
bedded in cement mortar andpoint up with coloured mortar.
On completion sweep down aU roof slopes and clean out aU gutters.
SARKING Prior to fuing roof batfens, sark the roof with double-sided
aluminium foil sarking, lapped and f u e d in accordance with the
manufacturer's instructions.
SPECIFICATION NOTES
ROOFING
METAL ROOFING shall be Lysaght's Brownbuilt 305 manufactured from
0.75mm min. total thickness zincalume coated steel sheet. Fix roof sheeting
in single lengths and secure with snap-in clip fuings side fmed to roof
members. Roofing to be installed in accordance with AS 1562.
Cappings, flashings and other accessories shall be 0.75mm min. total
thickness zincalume coated steel sheet and shall be f u e d with monel blind
pop rivets.
GUTTERS Provide and fix 115mm wide, 0.60mm thick zincalume coated
steel quadrant section eaves gutters. Gutters to be supported on gutter
brackets spaced at 1200mm max. cts. Gutters to be lapped, riveted and
silicone sealed at joints. Provide aU necessary mitred angles, stop ends and
outlets.
DOWNPIPES Provide and f m 100 x 50 x 0.60mm thick zincalume coated
steel downpipes. Downpipes to be well entered, riveted and silicone sealed at
joints. Downpipes to be fmed to brickwork with matching astragals spaced
at 2700mm max. cts, minimum 3 per stuck. Provide aU necessary bends,
offsets, etc. and connect to P.V.C. drains.
Chapter9 Roofing 71
0A-f
CAPPING
3aw'
SECTION Y SECTION 2
18 280
,
PLAN
DRAWING 9.2
72 Basic Building Measurement
ROOFING
Metal Roofing
a Lysaght’s Brownbuilt 305 manufactured
fiom 0.75mm min total thickness zincalume
coated steel sheet, fixed in single lengths,
and secured with snap-in clip fixings side
fixed to roof members; all installed in
accordance with AS 1562. Roof pitch 22.5
degrees. Two-storey work. m’ 199
Roof Area A = 2LS
Roof Length (L):
Building Length 18280
+ eaves width 600
+ fascia thickness 38
+ 50mm oversail 50
+ gable 450
+ barge 38
Roof length (L) = 19456mm
Slope Height ( S ) :
Half building width 3960
+ eaves width 600
+ fascia thickness 38
+ 5Omm oversail 50
Horizontal (H) = 4648 mm
Net slope height = H I cos Roof Pihch
= 4648 1cos 22.5
= 5031
+ turn up
Slope height ( S )
21 19.46
-5.09 -198.10
198.1Om’
Length of Ridge:
-
14.81 -
14.81 Repeat ridge length, Item c
14.81m
Gutters
i 115mm wide 0.60mm thick zincalume
coated steel quadrant section eaves
gutter, lapped riveted and silicone
sealed at joints, and supported on and
include for gutter brackets spaced at
1200mm max. centres. m 49
a,b C a
2 f U 39.06 a,b
-9.43 -9.43 c
48.49m
Downpipes
m 100 x 50 x 0.60mm thick zincalume
coated steel downpipes, well entered,
riveted and silicone sealed at joints,
and fixed to brickwork with matching
astragals spaced at 2700mm maximum
centres, minimum 3 per stack. m 28
4 16.85 27.40 (200+700+5700+250)
27.40m
n Bends to downpipes. no 8
o Shoes ditto. no 4
CONCRETE
6 0.222
8 0.395
10 0.616
12 0.887
16 1.58
20 2.46
24 3.55
28 4.84
I
Chapter 10 Concrete 77
IlOOb
4
1 Allowance
,,
Dimension
/
t
Allowance
1
1
1 1
BRICKWORK FOUNDATION PLAN
CONCRETE
IN-SlTU CONCRETE
Footings
a F c 20 MPa reinforced concrete strip footings
poured in trenches. m3 6
Footing lengths:
ftg a,c: 11770 - 280 = 11490
ftg b,d: 4060 - 280 = 3780
ftg.e: 3500 - 270 = 3230
REINFORCEMENT
Footings
b Y12 to strip footings. t 0.19
Fitment length:
L = 2A + 2B + 2HE
where A = width of fitment
B = depth of fitment
and HE = fitment hook end allowance
550 x 300 ftgs:
L = 2 ~ 4 5 +0 2 x 200 + 2 x 100
= 1500mm
Number of fitments:
Ftgs a,c 11940 / 1200 = 10 + 1 = 11
Ftgs b,d,e 4330 - 1100 = 3230 / 1200 = 3 + 1 = 4
Multiply the centre line lengths by the cross-section size to obtain the concrete
volume.
All strip footings are included in the one description even though they may be
of different cross-sectional size.
Chapter 10 Concrete 81
Item c-Fitments: Calculate the length of the fitments for each different size
footing using the formula L = 2A + 2B + 2HE. A is equal to the width of the
footing less the concrete cover, similarly B is equal to the depth of the footing
less the concrete cover, and HE is 1OOmm. (Refer 10.02.02).
Unless the locations of the fitments are shown on the engineer’s drawings,
there is no set method for locating the fitments to strip footings. The method
adopted above is to space the fitments to the longitudinal footings overall, and
to space the fitments to the vertical footings in between as shown below.
4
LONGITUDINAL -SPACE OVERALL
.t
82 Basic Building Measurement
SPECIFICATION NOTES
CONCRETE
REINFORCED CONCRETE STRIP FOOTINGS Concrete to be F'c 20
MPa mix. Provide concrete strip footings to the extent as shown, reinforced
with bar reinforcement as detailed. Provide 40mm concrete cover to all
reinforcement.
CL
4-YE
.
RIO - 9 0 5
b
DRAWING 10.2
Chapter 10 Concrete a3
QUESTION: In accordance with the accompanying specification notes, b.me. the in-
situ concrete and formwork for the strip footings shown in Drawing 10.3 below.
SPECIFICATION NOTES
CONCRETE
REINFORCED CONCRETE STRIP FOOTINGS Concrete to be F’c 20
MPa mix. Provide concrete strip footings to the extent as shown.
--
A - 111; I
i
4
I x
n
X
-p
DRAWING 10.3
84 Basic Building Measurement
CONCRETE
IN-SJTU CONCRETE
Footings
a F c 20 MPa reinforced concrete strip footings
poured in trenches. m3 5
FORMWORK
Footings
b Formwork to vertical face of steps in
strip footings. m2 1
2 J 0.60 3c steps
0.26 0.31
0.60 4c steps
0.35 0.21
0.52m2
c Ditto, 0-250 high. m 2
SPECIFICATION NOTES
CONCRETE
REINFORCED CONCRETE SLAB ON GROUND Concrete to be F’c 20
MPa mix. Form for, reinforce and pour concrete jloor slab and attached
beams as detailed. Concrete cover to be 50mm, except f o r fabric
reinforcement to slab, which is to be located 25mm fro m the top of the slab.
Properly cure concrete and finish slab with a steel trowel.
I
A
6508 ,
SECTION AA
DRAWING 10.4
86 Basic Building Measurement
DETAfL Y D€TAlL Z
DRAWING 10.5
C0NCRETE
IN-SITU CONCRETE
Slabs
6.2 1
-
4.21 -
26.14 plan area
26. 14m2x 0.130m = 3.40 m3
Integral Finishes
2 1 U 13.02 a,c
2 1 4.5 1 9.02 b,d
22.04m
2 1 U 12.42 a,c
2 14.21 8.42 b,d
20.84m
REINFORCEMENT
Slabs
F72 to floor slab. m2 26
6.11
- -
4.11 25.11
25. I lm2
F8TM3 ditto. m 5
F8TM3 = 210mm wide
-
4.41 -
4.41 e (4502 - 100)
4.41m
88 Basic Building Measurement
L =2~210+2~325+2~100
= 1270mrn
2 / 8 / m 17.28 a,c
2 / 5 11.08 10.80 b,d
5 1 1.27 6.35 e
34.43m x 0.222kg/m = 7.64kg
Item d-Formwork: Free edge of slab is partially above ground level, therefore
formwork is measured full height to slab edge. (Refer SMM 6.2.1, M8, page
38.)
Items g and h-Trench Mesh: Trench mesh is billed in metres stating the
width. (Refer SMM 6.4.5, page 45.) Length of trench mesh includes for
design laps at comers and intersections.
Note: F8TM3 indicates trench mesh having three 8mrn diam. structural grade
round bar main reinforcement rods. The nominal width of F8TM3 trench
mesh is 2 1 0 m
Chapter 10 Concrete 89
SPECIFICATION NOTES
CONCRETE
PIER AND BEAM FOOTINGS Concrete to be F’c 20 MPa mix. Form for,
reinforce and pour concrete pier and beam footings as detailed
A11 piers are to be 600mm d i m .
Existing ground level is R.L. 10.000.
Top of footing beams is R.L. 9.900.
Schedule of Pier Depths:
Pier R.L. at bottom of Pier
PI 3.300
P2 3.150
P3 2.780
P4 4.100
P5 3.000
P6 2.340
r2YJ2 I
r’ k . R8 -300
qJ
I
w ‘ I
1
1 ..3000
c
. 3000
Chapm 10 Concrete 91
CONCRETE
IN-SITU CONCRETE
Footings
a F c 20 MPa unreinforced concrete in
piers poured in ground. m3 11
-
6.10 P1
6.25 P2
6.62 P3
-
5.30 P4
-
6.40 P5
7.06 P6
37.73m x 0.30 x 0.30 x x = 10.67m3
b F c 20 MPa reinforced concrete in
footing beams poured in ground. m3
2 1 6.00 , B1-2,B3-4
0.30
0.50 1.80
2 13.50 B5,7
0.30
0.50 1.05
3.20 B6
0.30
-
0.50 -
0.48
3.33m3
c Scabble top of 600mm diam concrete
piers prior to pouring beams. m2
6 1 1 0.30
0.30 1.70
1.70m2
FORMWORK
Footings
d Formwork to sides of footing beams
above piers. m2
6 1 1.00 P1-6
-0.50 3.00
3.00m2
REINFORCEMENT
Footings
e Y10 and Y12 to footing beams. t 0.12
92 Basic Building Measurement
y10:
2 / 2 / m B1,2; B3,4 T
41 4 1 D B1,2,3,4 B
74.36m x 0.616 kg/m = 45.81kg
y12:
2121- B1,2; B3,4 T
3121- B5,6,7 T
3141m B5,6,7 B
75.18m x 0.887 kg/m = 66.68kg
Total: 112.49kg
L = 2A + 2B + 2HE
500 x 300 beams (Bl-6):
L =2x170+2~385+2~100
= 1310mm
4 1 9/= B1-4
3/11/= B5-7
90.39m x 0.395kg/m = 35.70kg
SPECIFICATION NOTES
CONCRETE
I- F82 T.
Y 12 - 200 T.
w
Y16 -2OOT.
-
Y l d 200 0.
Y 12 - -2000.
SECTIOId D
DRAWING 10.7
94 Basic Building;Measurement
0
h
N
SECTION BB
S E C T I O N AA
DRAWING 10.8
Chapter 10 Concrete 95
DRAWING 10.9
-
96 Basic Building Measuren t
CONCRETE
a Refer to the SMM for details regarding
Measurement and Prices of Concrete. Note
IN-SITU CONCRETE
b Refer to the Concrete section of the
Specification for particulars of in-situ
concrete. Note
C Allow for providing samples of materials or
finishes. Item
d Allow for testing of materials, concrete
specimens and similar. Item
e Allow for protecting and curing concrete.
(m2 ) Item
Slabs and Stair
F c 25 MPa reinforced concrete in:
f Suspended floor slabs oured on formwork,
101-2OOmm thick. ( n-? ) m3
FORMWORK
i Refer to the Concrete section of the
Specification for particulars of formwork. Note
Slabs and Stair
Class 2 finish formwork to:
REINFORCEMENT
d Refer to the Concrete section of the
Specification for particulars of
reinforcement. Note
e Allow for the preparation of bending
schedules for t of bar reinforcement
and ~ m2 of fabric reinforcement. Item
g F92 to ditto. m2
h Y 12 trimmers to ditto. t
i Y 12 and Y 16 to suspended stair
flights and landing slab. t
CHAPTER 11
GROUNDWORKS
GROUNDWORKS
EXCAVATION
Trench Excavation
a The commencing level for excavation
is natural ground level. Note
b Trench excavation for strip footings,
in material O.T.R., not exceeding
1.OOm total depth, part backfilled
with the best of the excavated
material and surplus spoil spread
on site where directed. m3 8
30.54 repeat c/l length, Item a, page 79
0.55 ftg a,b,c,d.
0.40 6.72
3.23 repeat c/l length, Item a, page 79
0.38 ftg e
0.40 0.49
7.21m3
QUESTION: In accordance with Drawings 10.4 and 10.5 and the following
specification notes, measure and extend the following Bill of Quantities’
Groundworks section.
SPECIFICATION NOTES
GROUNDWORKS
EXCAVATION All excavation is to be allowed fo r in material other than
rock (O.T.R.).
Clear the area of the building of all rubbish and vegetable matter and cart
away spoil.
Excavate forfloor slab and attuchedfloor beams to the profiles as shown
and spread spoil on site where directed.
Trim and levellbatter ground and leave ready to receive hardcore filling and
concrete.
HARDCORE FILLING Provide lOOmm thick layer of hardcore filling
under Boor slab as detailed, thoroughly consolidate and blind over with
sand.
WATERPROOF MEMBRANE Cover the area under the floor slab and
attached floor beams with 0.2mm thick coloured polythene film sheet, lap
150mm at joints and seal with pressure sensitive tape. Turn membrane up
outside face of edge beams to base of rebate.
GROUNDWORKS
Preambles omitted
EXCAVATION
Clear the area of the building of all
vegetable matter and cart away spoiL
The commencing level for excavation
is natural ground level.
Surface excavation to reduce levels
in material O.T.R. and spread spoil
on site where directed. ( m2 )
HARDCORE FILLING
WATERPROOF MEMBRANE
SPECIFICATION NOTES
GROUNDWORKS
EXCAVATION All excavation is to be allowed for in material O.T.R. AD
surplus excavated material is to be spread on site where directed.
All piers to be 6OOmm d i m .
The site has been previously levelled and existing ground level is R.L.
10.000.
Top of footing beams is R.L. 9.900.
Schedule of Pier Depths:
Pier R.L. at bottom of Pier
PI 3.300
P2 3.150
P3 2.780
P4 4.100
P5 3.000
P6 2.340
GROUNDWORKS
EXCAVATION
a Refer to the Groundworks section of
the Specification for details of
excavation. Note
b Refer to the SMM for details
regarding measurement and prices
of excavation. Note
c Allow for establishing the pier
boring equipment on site. Item
Chapter 11 Groundworks 103
-6 -6 P1-6
-6
2 16.00 B1-2, B 3 4
0.30
0.60 2.16
2 1 3.50 B5,7
0.30
-0.60 1.26
3.20 B6
0.30
0.60 0.58
-4.00m3
Deductions:
6 10.55 P 1 4 (550mm taken as an average)
0.30
0.60 0.59
0.59m3 (ddt).
~m~
2 I 2 I 6.00 B1-2, 3 4
0.60 14.40
2 I 2 I 3.50 B5,6
0.60 8.40
2 13.20 B7
0.60 3.84
u r n 2
METALWORK
SPECIFICATION NOTES
DOORS
ALUMINIUM SLIDING DOOR UNIT Where indicated on Drawings,
supply and install Ajax Type X clear anodised aluminium sliding door unit
inclusive of factory glazing, flashings, fmings, furniture and other trims.
Extent: D l
WIND0WS
ALUMINIUM SLIDING WIND0WS Where indicated on Drawings, supply
and install Ajax Type X clear anodised aluminium sliding windows inclusive
of factory glazing,flashings, jixings, furniture and other trims.
Exlent: W l - 6 incl.
106 Basic Building Measurement
DOORS
Aluminium Sliding Door Unit
a Ajax Type X clear anodised aluminium
sliding door unit inclusive of factory
glazing, flashings, fixings, furniture
and other trims;to suit opening 3600
wide, 2175 high and include for building
into brick cavity wall. no 1
WINDOWS
Aluminium Sliding Windows
b Ajax Type X clear anodised aluminium
sliding windows inclusive of all factory
glazing, flashings, furniture and other
trims: to suit opening 3600 wide, 1800
high, and include for building into brick
cavity wall. no 1
-1 -1 w1
-1
-1 -1 w5
-1
-1 -1 w2
-1
-1 -1 W6
-I
f Ditto 600 wide, 1500 high. no 2
-
2 -2 w3,4
-2
Chapter12 Metalwork 107
SPECIFICATION NOTES
METALWORK
ARCH BARS AND ANGLES Support each llOmm thickness of brickwork
over all openings on galvd steel arch bars and angles of the sizes as specified
below:
Maximum Span Lintel Bearing at each end
mm mm mm
1050 75xlObar 150
1200 76 x 76 x 10 angle 150
2400 127 x 76 x 10 angle 230
3600 152 x 89 x 10 angle 230
METALWORK
Arch Bars and Angles
75 x 10 galvanised steel bar as lintel, built
into brickwork at ends. ( no 7 ) m 8
127 x 76 x 10 ditto. ( no 2 ) m 6
-
2.86 2.86 W2 (2400 + 460 = 2860)
2.86 2.86 W5
5.72m
108 Basic Building Measurement
d 1 5 2 x 89 x 10 ditto. ( n o 2 ) m 9
Item a-Arch Bars: Two 75 x 10 steel arch bars are required to D2 since the
opening occurs in a 230mm thick brick wall.
It has been assumed that all window and external door heads are at eaves soffit
level and there is only necessity to support the inner 1lOmm thick skin above
these openings. Each project has its own peculiarities and the elevations and
details should be studied carefully to avoid mistakes being made.
12.04. EXAMPLE-BALUSTRADES
SPECIFICATION NOTES
METALWORK
BALUSTRADES Provide and fir balustrades to Stair 1 as detailed.
Balustrades to be anodised aluminium balustrades as manufactured by
Ajax, Catalogue No. 101, consisting of Series X handrail, bottom rail, posts
and having evenly spaced balusters spaced at 120mm maximum centres.
Posts to be secured to concrete with countersunk head bolts and masonv
anchors as recommended by the manufacturer.
Chapter 12 Metalwork 109
I II II
c
1
STAIR 1 SECTION A
-
1.30 1.30 top landing
0.40 0.40 top landing return
0.25 0.25 mid landing
1.95m
-
1 -1 top landing
-1
d Ramps ditto. no 2
-
2 -2 flights
-
2
e Wreath ditto. no 1
-
1 -1 mid landing
-1
Chapter 12 Metalwork 111
12.05. EXERCISE-HANDRAILS
QUESTION: In accordance with Drawings 12.1 and 12.2 and the following
specification notes, measure and extend the handrails.
SPECIFICATION NOTES
METALWORK
HANDRAIL Provide and fu handrails to Stair 1 as detailed. Handrail to
be Series X anodised aluminium handrail as manufactured by Ajax,
Catalogue No. H1. Secure handrail brackets to brickwork with countersunk
head bolts and masonry anchors as recommended by the manufacturer.
I .:.-.-*.. .-:.-.
..': .a...:
I--/
ri/ '
-1 - /
r-/
STAIR 1 SECTION B
DRAWING 12.2
112 Basic Building Measurement
METALWORK
Handrails
a Horizontal Series X anodised aluminium
handrail to Stair 1, as manufactured
by Ajax, Catalogue No. H1; include for
stop ends and for fixing handrail brackets
to brickwork with countersunk head bolts
and masonry anchors as recommended by
the manufacturer. All to detail. m
d Ramps ditto. no
SPECIFICATION NOTES
DOORS
METAL DOOR FRAMES DOORS D l - 6 incl. shall be Ajax single rebated
prime coated steel door frames. Frames to be supplied complete with a pair
of lOOmm steel butt hinges, latch keep and striking plate. Build frames into
brick walls in accordance with the manufacturer’s instructions.
DOORS
Metal Door Frames
a Ajax single rebated prime coated steel
door frames, to suit 2040 x 820 x 35
thick single leaf doors, complete with
a pair of l O O m m steel butt hinges, latch
keep and striking plate; include for
building into brick walls in accordance
with the manufacturer’s instluctions. no 6
-
6 -6 D1-6
-6
CHAPTER 13
STRUCTURAL STEEL
3 23.6 12 94.2
4 31.4 16 126
5 39.3 20 157
6 47.1 25 196
8 62.8 28 220
10 78.5 32 252
114 Basic Building Measurement
13.02.06 EXAMPLE. In accordance with SMM, b.me. six 460uB74 roof beams
(RBl-6) each having an exact length of 5825mm.
Roof Beams
a 460UB74 beams. (6 15.90 ) t 2.65
QUESTION: B.me the sauctural steel as specified and as shown in Drawings 13.1
and 13.2.
SPECIFICATION NOTES
STRUCTURAL STEEL
Provide and erect all steelwork including galvanised steel purlins as
detailed.
All steelwork, excluding purlins, to be given a shop priming coat of R.O.Z.C.
(red oxide zinc chromate) primer.
Grout up under base plates with cement grout composed of 2 parts sand to I
part cement
5001
1q
I 4000
4
1 4000
1
1 4000
1 1
500
FRAMING PLAN
DRAWING 13.1
118 Basic Building Measurement
PLATE
DETAIL A DETAIL B
DRAWING 13.2
~
Chapter 13 Shuctural Steel 119
STRUCTURAL STEEL
Inspection of Welds
f Allow for inspection of welds including
the use of any special techniques. Item
Heaviest and Highest Lift
12mm plate:
4 / 2 / 0.30
0.30 0.72 CF1-4
0.72m2
x 94.2OkgIm2
67.82kg
120 Basic Building Measurement
12mm plate:
4 1 2 1 0.30
0.20 0.48 CFl4
0.48m2
x 94.20kg/m2
45.22kq
8mm plate:
4 1 5 1 0.10
-0.20 - 0.40 C F l 4 (average ht. = 200mm)
0.40m2
x 62.80kg/m2
25.12kq
4 1 2 1 4 3 Col./Beam
32
-
4 1 2 1 4 32 CFl4
32
-
81 0.30
--
0.30 0.72 CF14
0.72m2
Chapta 13 Structural Steel 121
Shop Priming
-
0.70t Roof Beams, Item k
0.03t At. connect., Item 1
0.73t
Proprietary Purlins
r 150C16 galvd steel roof purlins bolted
to covered way frames spaced at 4.00m
centres; include for bolts. m 65
13.04. EXERCISWTEELWORK
QUESTION: B m e . the structural steelwork as specified and as shown in Drawings
13.3, 13.4 and 13.5.
SPECIFICATION NOTES
STRUCTURAL STEEL
Provide and erect all steelwork as detailed.
All steelwork is to be given a shop priming coat of R.O.Z.C. (red oxide zinc
chromate) primer.
Grout up under base plates with 25mm thick cement grout composed of 2
parts sand to I part cement.
i
70
\
3
r9
lL
1 *
+0
3800
A
TB
3800
.
3800
4 # #C
FRAMING PLAN
COLUMNS 200UC46
FLOOR BEAMS [FBI 410UB53
ROOF BEAMS [RBI 3 10UB40
TIE BEAMS [TBl 200UJ325
DRAWING 13.3
Chapter 13 Structural Steel 123
SIDE ELEVATION
END ELEVATION
DRAWING 13.4
124 Basic Building Measurement
M16-8-8S.Bor
0L K
7 6 x 7 6 sI \
310UB40 ROOF BEAM
200U025
2 O O U C 46
SECTION A
DRAWING 13.5
CHAPTER 14
DRAINAGE
1. Pipework is measured net length along the centre lines of the pipes
over all bends, junctions and similar pipe fittings.
2. Pipework in trenches includes excavation with the trench depth stated
in 1.00m total depth increments.
3. Measurement and prices of drainage are deemed to include for
maintaining faces of drainpipe trenches and pits, backfilling, disposal
of surplus spoil, forming pockets beneath collars, and all jointing and
other incidental materials.
QUESTION: Given that the specified minimum drainage pipe gradient is 1:60 and
the minimum cover to drainage pipes is 30Omm, determine the invert level at points A
and B as shown in Drawing 14.1.
\ 0'y y
9'
1 85000 #
#
c
126 Basic Building Measurement
Invert level at A:
Existing Ground Level = 10.000
Less min. cover = -300
Less pipe diam = .090
Invert level at A = 9.610
Invert level at B:
Min. fall is 85.00m/ 60 = 1.417m
Using min. fall, invert level at B is 9.610-1.417 = 8.193
[Check cover at B: 9.000-8.1936-0.090 = 0.7 17m, i.e. satisfactory,
since greater than 300mm.1
Therefore, invert level at B is 8.193.
Determine the invert levels at A and B using the same information as Example 1,
except that the distance between A and B is 45.00m
QUESTION: Given that the specified minimum drainage pipe gradient is 1:60 and
the minimum cover to drainage pipes is 300mm, determine the point where the total
depth of the drainage trench exceeds 1.00m deep as shown in Drawing 14.2.
#
I18000 1
1
DRAINACf PLAN
DRAWING 14.2
SPECIFICATION NOTES
DRAINAGE
STORMWATER DRAINAGE All stonnwater drainage is to be cam'ed out
in 1OOmm diameter second qualify vitrified clay drainpipes andfittings with
rubber ring joints. All excavation is to be allowed for in material other than
rock. Backfill drainage trenches with the best of the excavated material and
spread surplus spoil on site where directed.
A 0
-EX I STIrJC CoNCLETE PAVEMENT 0
0
r 1' $ EXISTING K€EB 4 GUTTER 7 tr)
DRAlNAtE PLAN
DRAWING 14.3
128 Basic Building Measurement
DRAINAGE
Stormwater Drainage
a lOOmm diam. second quality V.C. drainpipes,
rubber ring jointed, laid in trenches
not exceeding 1.OOm total depth; include
for excavation in material other than rock,
backfilling with the best of the excavated
material and spreading surplus spoil on site
where directed. m 62
2/J& 2.84
18.00 18.00
19.00 19.00
1.42 1.42
16.00 16.00
-
4.25 -4.25
61.51m
-
3.00 -
3.00
3.00m
Item a-V.c. drainpipes: Examination of the given ground R.L.s and the
specified falls and minimum cover for drainage pipes indicates that no
drainage trenches will exceed 1.00m deep in this case. The net length of
pipework is measured along the centre lines of the pipes over all bends and
junctions.
Item &Vertical pipes: Vertical pipes are given separately. An average depth
of 5 0 0 m has been estimated as the requirement at each downpipe.
Item g-Stormwater drainage outside the site boundary: Work outside the
boundary of the property is given separately. (Refer SMM, M2, page 145.)
Describe work under public footpaths including making good. (Refer SMM,
M3, page 145.)
Item h-Drain connection: Refer SMM, clause 8, page 147.
130 Basic Building Measurement
QUESTION: In accordance with Drawing 14.4 and the following specification notes,
measure and extend the following Bill of Quantities, Drainage section.
SPECIFICATION NOTES
DRAINAGE
EXCAVATION: Excavate drainage trenches in material other than rock,
backf-ill with sand and spread spoil on site where directed.
SEWER DRAINAGE: All sewer drainage is to be cam'ed out in lOOmm
diameterfirst quality vitrifiid clay pipes andfittings to AS 1741 with rubber
ring joints.
Connect and extend drainage from existing lOOmm d i m . V.C. sewer main
branch to building as detailed with required bends, junctions, gully trap,
risers, etc. All pipes to have a minimum cover of 300mm with a minimum
fall of 1.~50. Provide lOOmm diam. vertical inspection shaft where shown
and fit airtight cast iron cover and frame at ground level and surround with
concrete. Fit cast iron grate to top of lOOmm diam. riser above gully trap
and surround with concrete.
STORMWATER DRAINAGE All stomwater drainage is to be cam'ed out
in 90mm diameter UPVC drainpipes andfittings complying with AS 1254.
Connect from downpipes to absorption trench as detailed with required
bends,junctions, risers, etc. All pipes to have a minimum cover of 300mm
and a minimum f d l of 1:lOO.
Absorption trench to be minimum 600mm wide and filled with a 600mm
minimum deep layer of coarse rubble covered with galvd steel sheeting and
a minimum 300mm deep layer of soiL
Chapter 14 Drainage 131
1
1
20000
d uPvc
1
1 *
-90 ~ .
\ D.P. \ D.P \at?
1
Venf
-
Stnk C.T.
D.r? /D.P /D. F!
90# U m .
- 0 -
0
0
F b o r p f i o n trench
I 8000 I
-I
OI
0
I .s.
9-La,
DRAINACf PLAN
I I
P" n
II I I00 r 7 5 QP.
(TY PI CA L)
FRONT ELEVATION
DRAWING 14.4
-
132 Basic Building Measureme
DRAINAGE
Sewer Drainage
f l o o m diam. first quality V.C. drainpipes,
rubber ring jointed, laid in trenches
not exceeding 1.00m total depth; include
for excavation in material other than rock,
backfilling with sand and spreading spoil
on site where directed. m
Stormwater Drainage
e 90mm diam. UPVC drainpipes, laid in
trenches not exceeding 1.00m total
depth; include for excavation in
material other than rock, backfilling
with sand and spreading spoil on site
where directed. m
HYDRAULICS
Refer to SMM, Section 23, Hydraulics, pages 139-143, for the rules governing the
measurement of hydraulic services. In particular the following basic requirements
should be noted:
2. Pipework is measured "the net length along the centre lines of pipes
over all bends, junctions, tees and similar fittings. Make no distinction
as to the use to which the piping is put or whether piping is in main
stacks or branches."
State the "nominal diameter of pipes, class or table of pipe and method
of jointing."
For pipework less than 32mm nominal diameter include in the
description of the pipework for "all expansion fittings, bends,
junctions, inspection openings, reducers, and similar fittings other than
glass fittings."
Describe and measure separately fittings to pipework equal to or
greater than 32mm nominal diameter.
15.02. EXERCISE-HYDRAULICS
QUESTION: In accordance with Drawings 15.1 and 15.2 and the following
specification notes, measure and extend the following Bill of Quantities' Hydraulics
section.
Chapter 15 Hydraulics 135
SPECIFICATION NOTES
HYDRAULICS
GENERALLY
Carry out all work in strict accordance with the rules and regulations of the
Supply Authority and other authorities having jurisdiction over the works.
Ascertain from the supply authority before tendering, the position type and
size of water main and allow f o r all charges and fees f o r connecting water
service to main.
Make application to authorities f o r permits to cany out the work and pay all
fees and charges in respect of work involved. On completion obtain
"Certificate of Compliance" indicafing satisfactory completion of services
and submit to the supervising architect.
MATERIALS
Copper tubes shall be solid drawn copper tubes to AS 1432 and of the
following types:
Water Service: Type B hard drawn copper tube.
Fittings to AS 1585: Approved capillary fittings manufactured from
drawn copper tube, tested and stamped by the Supply Authority.
UPVC for waste, soil and vent pipes and fittings to A S 1415, of manufacture
approved by Supply and Local Authorities.
Allow the P.C. sum of two thousand four hundred dollars ( $2,400.00 ) for
the supply and delivery only of four wall mounted model hot water heaters
complete with all necessary valves, thermostats, cut-outs, etc.
Install hot water heaters and hot water service in accordance with the
manufacturer's printed recommendations, the provisions of AS 1529 and as
specified hereunder. Provide hot water heater to each unit where indicated
Thermal insulate all copper tubing where embedded in concrete and
masonry walls with approved plastic coating.
Support each heater on approved wall brackets, 25mm thick fibre cement
base and tray. Connect 15mm copper drainpipe to combined
temperaturelpressure relief valve, conceal in wall and discharge into copper
tundish built into kerb. Extend 25mm copper drain line from tundish under
floor and connect to UPVCfloor waste.
Terminate hot and cold water services with Ajax high pressure tested c.p.
brass fittings complete with c.p. brass handles, covers and wall domes.
Provide taps, etc. asfollows all withfibre washers.
Laundry Tub. 15mm x 200mm long swivel outlet complete with
breeching piece and a pair of hot and cold recess taps.
Washing Machine. 15mm hot and cold washing machine taps
having threaded spouts to suit hose connection to washing machine.
Shower. 15mm hot and cold recess taps complete with breeching
piece, c.p. brass shower arm, cover plate, and 75mm c.p. brass ball
jointed shower rose.
Hand Basin. 15mm hot and cold pillar taps.
W.C. Suite. 15mm cistern stop.
Kitchen Sink. 15mm x 200mm swivel outlet complete with mixing
piece and a pair of hot and cold recess taps; all mounted on sink.
Water Heater. 15mm control tap and check valve.
Full Way Cocks. At entry point to each unit provide 20mm c.p.
recessed full way cock as detailed.
Standpipe. 20mm hose cock.
SANITARY FIXTURES
SANITARY PLUMBING
Provide and install approved UPVC pipes and fittings as required and as
detailed on the drawings. All work to be in accordance with the
requirements of the controlling authority.
All joints to be solvent welded.
All traps to have minimum 75mm deep water seal.
Floor wastes to be 80 x 50mm floor waste gully "S" trap complete with c.p.
screw-in grate.
Where vent pipe passes through roof, provide UPVC stock pattern apron
flashing set over upturned roof collar flashing (specifwd in Roofer) and
solvent weld to vent pipe. Solvent weld UPVC stock pattern vent cowl to top
of vent pipe.
138 Basic Building Measurement
DRAWING 15.1
ChaptK 15 Hydraulics 139
PLAN
LLEVATION I ELEVATION 2
ELEVATIOM 3
DRAWING 15.2
-
140 Basic Building Measurema -
HYDRAULICS
1 32 x 32 x 20mm tee. no
m 32 x 25 x 20- tee. no
Chapter 15 Hydraulics
h 20mm ditto. rn
i 15mm piping m
rn 15mm ditto. m
n 15mm c.p. piping. m
0 20mm ditto. rn
P 15mm piping. rn
Sanitary Fixtures
Sanitary Plumbing
UPVC pipes and fittings solvent
welded at ioints in:
a 50mm vent stacks secured to brickwork
inside duct. m
b 50mm stacks in roof space and above
roof and branches. m
C 50mm bends. ll0
h 32mm ditto. no
i Connect end of 50mm pipes to V.C.drain. no
j Ditto 3 2 m . no
SPECIFICATION NOTES
ELECTRICAL INSTALLATIONS
GENERALLY
Extent: Provide an electrical service installation, including consumer mains,
switchboard(s), consumer distribution board(s), wiring and equipment (accessories,
appliances, and luminaries) connecting the Supply Authority’s service to each point
of use including the connection of permanently connected equipment
Standards: To AS 3000 and to the requirements of the Supply and regulQtory
authorities.
InstaUation to AS 3000 and AS 3006.
Work-as-executed drawings: At practical completion submit work-as-executed
drawings.
UNDERGROUND SERVICES
General: To be in accordance with AS 3000 with PVC marker tape over all lengths
of underground conduit and provide 600mm minimum cover to underground
conduits.
Underground conduits to be 40mm HDUPVC conduit.
MATERIALS
TPI and TPS cables: To AS 3147 and AS 3008.1: 0.6111 kV range, 75°C
temperature rated cable delivered to site in the original packages.
Conductors: Provide str9nded copper conductors throughout a minimum of 1.5mm2
for lighting and 2.5mm for power sub-circuits. Take into account voltage drop
when determiningfinal size.
Conduit: Rigid or flexible non-metallic conduit to AS 3000:
Minimum size 20mm generally, 25mm in floor slabs
Conceal all conduits chased into masonry walls or cast into concrete.
Heavy duty type rigid non-metallic conduits and fittings to AS 2053.
Consumer mains conduit to be 30mm HDUPVC conduit
ELECTRICAL DISTRIBUTION
General: Supply electricity underground to each unit.
Point of Attachment: as required by the Supply Authority.
Switchboards and Metering: Provide a recessed, weatherproof, galvanised painted
steel meter cupboard enclosing all switchboard and metering equipment as required
by the Supply Authority.
Consumer Distribution Boards: Email LC86FD recessed moulded PVC enclosures
with window hinged cover mounted on walls in positions directed
Residual current device (safety switches): To AS 3190.
WIRING INSTALLATION
General : To AS 3000.
Cable routes: Routes shown on drawings are diagrammatic only. Determine the
final route of run to the approval of the Supply Authority.
ACCESSORIES
General: Install flush-mounted accessories, in wall boxes in masonry walls, located
as specified andlor as shown on the drawings.
Switches: Install 900mm abovefloor.
General Purpose Outlets: To AS 3112, install at 600mm above floor level
generally, 1500mm in laundrylbathroom, 1050mm in kitchen.
Chapter 16 Electrical installations 147
LIGHT FITTINGS
General: Provide in locations shown on the drawings complete with lamps, control
gear and d;ffusers.
Batten holders / lamp holders: Bayonet “electric white” heat-resistant type with
body which cannot be extracted withoutfirst removing the base securing screws.
External bollard lights: Pierlite Cat No. BOL 50 MV with 50 W mercury vapour
lamp.
External wall mounted lights: GEC Mediterranean R2 with 50 W MEFU lamp.
External post top mounted light: Associated Lighting SX2731 complete with post
standard and 80 W MBFU lamp.
Main Switchboard light: Philips FL.201 weatherproof vandal resistant fluorescent
light
Kitchen lights: 1 x 18W HPF enclosedfluorescent light with TLD 18W/33 lamp.
External wall lights to all units: Philips L1025 surface mounted weatherproof light
SMOKE DETECTORS
General: Provide one smoke detector to each unit as shown.
Installation: To AS 3000 and connect to any continuous 240V Ac 50 Hz electrical
circuit not protected by an RCD.
APPLIANCES
Fixtures and Fittings: Provide approved jbiures and fittings in the locations (IS
shown on the drawings and/or as specified below:
Appliances Extent
Cooking ranges 1 per kitchen
Water heaters Hvdraulic Services
/ POlUT OF ATTAUiMfF1T
7-
-t--1 MAIN -SWITCHBOALD
6 MnlN I
SWITCH
I
LANDLORD'S
SEKVlCf S
METELlrlG LINKS
1 TENANTS'
JERVI CL 5
LEPEAT FOR
I
~UCLUSIVE
DOMESTIC
TARIFF TA El FF
32A p' I
1
,,
i
u41hl AREA
SWITCH BoU I10 LIGHTS
MAIN
SWITCHBOARD
- - i
CUPBOARD CUPBOARD
LIGHT G.P.O.
DRAWING 16.1
Chapter 16 Electrical Installations 149
+
EXISTING SUPPLY
AUTHORIN mWfZ WLf
.. - . . -.. --
29.00 ..
c
I
I PARK1NC
I -CONSUMR MINS
LOCATED WUHIN
I ROOF SPACE.
i
0:
31
I
I
i
-I
I
-I
DRAWING 16.2
150 Basic Building Measurement
BEDROOM
DRAWING 16.3
Chaptes 16 Elecmcal Installations 151
1
I
Consumer mains
I
I& Q
I
unit (safety switch)
I Route of underground I
-.-.-.- conduits and clbling Photo electric daylight
between MSB and switch
distribution boards GEC 2320A
Supply author it y
kilowatt hour meter
I 1
Distribution Board Post top mounted light
w Supply Authority
Service fuses
Bollard light
Incandescent batten
holder
-single
Fluorescent light
Selector switch
Clipsal PS35COA m
Smoke detector Unit wall mounted light
DRAWING 16.4
-
152 Basic Building Measurement
ELECTRICAL INSTALLATIONS
Mains Connection
-
153
- Chapter 16 Elecmcal Installations
Main Switchboard
Sub-Circuits
Unit Sub-circuits
Switches
k Single ditto. no
Light Fittings
Lamps
C lOOW ditto. no
Water Heaters
Cooking Range
Smoke Detectors
-
CHAPTER 17
SPECIFICATION NOTES
GLAZING
MIRRORS to be 600 x 600 x 6mm thick clear float glass, of silvering
quality, backed with a reflective surface layer and protective coafing and
having clear anodised proprietary aluminium frame all around, mitred at
comers. Fix two mirrors to timber framed wall in bathroom in positions
indicated
GLAZING
Mirrors
a 600 x 600 mirrors, comprising 6mm thick
clear float glass of silvering quality,
backed with a reflective surface layer and
protective coating and having clear anodised
proprietary aluminium frame all around, mitred
at comers: include for fixing to timber framed
wall in position indicated. no 2
-
2 -2 Bathroom
158 ' Basic Building Measurement
Refer to SMM, Section 21, Painting, pages 133-136, for the rules governing the
measurement of painting. In particular the following basic requirements should be
noted:
The Painting section is usually the last trade section in the Bill of Quantities to be
completed. The recommended measurement technique is, firstly, to cany out the
billing process working from the Specification and lining off each clause after the
billing is completed. When all the descriptions have been completed, the next task is
to "paint" the project by working directly from the draft copy of each trade section.
Starting with the Preliminaries and systematically working through each description
in each section of the Bill of Quantities the measurement process can be completed.
Naturally, many of the quantities can be repeated and no further measurement is
required from the drawings.
This method ensures that all work included in the Bill of Quantities will be considered
for painting and does not solely rely on the accuracy of the Painting specification.
Often queries will arise concerning the painting and the Architect should be consulted
if there is any doubt concerning the nature and extent of the painting work. Painting
to some elements can often be overlooked by the Specification writer, such as paint
on fair face brickwork, off-form concrete, service pipework and ducting, temporary
works. etc.
Since many of the quantities are repeated from the previous measurements it is
important to carry out bulk checks to detect obvious mistakes and avoid compounding
errors. This is a good opportunity to exercise quality control and take a second look
at your previous work. Ask yourself if the quantity seems realistic and c m y out a
bulk check if in doubt.
SPECIFICATION NOTES
PAINTING
Paints shall be proprietary brand paints approved by the Commonwealth
Paint Committee and shall comply with the relevant Australian Standard
Codes.
STRUCTURAL. STEELWORK
Application: Touch up priming coat
One coat undercoat
Two coats gloss enamel
Extent: Covered way frames as detailed in Drawings 13.1
and 13.2. Galvd steel purlins to be left unpainted.
PLASTERBOARD
Application: One coat wallboard sealer
Two coats low gloss acrylic
Extent: Plasterboard ceiling lining and cornice as detailed
in Drawing 6.1
CEMENT RENDER
Application: One coat sealer
Two coats semi-gloss acrylic
Extent: Cement rendered walls including rendered reveals
as detailed in Drawing 6.1
WOODWORK
Application: One coat pink primer
Two coats gloss acrylic
Extent: Internal doors, frames and t r i m s as detailed in
Drawing 5.1
Skirtings as detailed in Drawing 6.1
PAINTING
Preambles omitted
EXTERNAL WORK
Structural Steelwork
a Thoroughly degrease, touch up priming coat,
one coat undercoat and two coats gloss
enamel on covered way frames. m2 50
Woodwork
b Properly prepare, one coat timber toned
acrylic on dressed timber fascias prior
to fixing. m2 14
- -
27.00 27.00 Fascias repeat length, Item a, page 61
27.00m (girth 125 + 38 + 10 = 173)
Chapter 17 Glazing and Painting 161
INTERNAL WORK
Plasterboard
f Properly prepare, one coat wallboard sealer,
and two coats low gloss acrylic on
plasterboard ceiling lining and cornice. m2 53
Cement Render
Woodwork
h Properly prepare, one coat pink primer, and
two coats gloss acrylic on timber doors. m2 25
5 / 5.10 D1-5
0.33 8.42
2 / 5.05 D6,7
-0.33 -3.33
11.75m2
- -
37.00 37.00 Repeat length, Item d, page 3 1
37.00m
MEASUREMENT NOTES-PATNTING
SPECIFICATION NOTES
PAINTING
Paints shall be proprietary brand paints approved by the Commonwealth
Paint Committee and shall comply with the relevant Australian Standard
codes.
PLASTERBOARD
Application: One coat wallboard sealer
Two coats low gloss acrylic
Extent: Plasterboard ceiling lining
Plasterboard cornice
Plasterboard wall lining
(Note: Wall, cornice and ceiling to be painted
with different colours.)
WOODWORK
Application: One coat pink primer
Two coats gloss acrylic
Extent: Timber doors, frames and trims; timber windows;
and timber skirtings.
I 12000 1
SECTION AA
DRAWING 17.1
- Chapter 17 Glazing and Paint YI 165
PAINTING
Preambles omitted
EXTERNAL WORK
Woodwork
a Properly prepare, one coat pink primer
and two coats gloss acrylic on timber doors. m2
b Ditto on timber door frames and trims,
0-25Omm girth. m
C Ditto on timber windows and trims. (Measured
flat overall, one side.) m2
d Properly prepare, one coat timber toned
acrylic on sawn finish timber fascias prior
to fixing. m2
e Ditto barges. m2
f Properly prepare, and two coats timber
toned acrylic on pre-painted sawn finish
timber fascias, 0-25Omm girth. m
INTERNAL WORK
Plasterboard
h Properly prepare, one coat wallboard sealer,
and two coats low gloss acrylic on
plasterboard ceiling lining. m2
i Ditto plasterboard wall lining. m2
Woodwork
k Properly prepare, one coat pink primer
and two coats gloss acrylic on timber doors. m2
1 Ditto on timber door frames and trims. m2
m Ditto, 0-25Omm girth. m
n Ditto on timber windows and trims. (Measured
flat overall, one side.) m2
PRELIMINARIES
Refer to SMM, Section 2, Preliminaries, pages 9-12, for the rules governing the
preparation of the Preliminaries section.
18.02. PRELIMINARIES
The Preliminaries section is the first section in the Bill of Quantities. Unlike the
following trade sections it contains very few measured quantities and mainly consists
of "Note" and "Item" descriptions. (Refer Chapter 1, 1.01 Terminology, page 2, for
the definition of "Note" and "Item".)
The SMM clearly sets out the order and information to be included in the
Preliminaries section of the Bill of Quantities. This is broadly divided into two
categories. The first of these two categories is what I refer to as "global information"
necessary for the estimator to understand the project. The information to be included
is as follows:
Names of the parties
Description of the site
Description of the works
Conditions of contract
Tender conditions
Bill of quantities
Contingencies
Tenderers are to allow for and include in their Tender Sum, the sum of Ten
Thousand Dollars ($10,000.00) for Contingencies.
The second category in the Bill of Quantities' Preliminaries section contains the
general particulars giving "Items" for the various contractual conditions and site
Chapter 18 Reliminaries / Quality Control Rocedures 167
conditions as listed in the SMM. (Refer SMM, Preliminaries, clause 8, pages 11 and
12, for full details.) Three typical Bill of Quantities descriptions giving general
particulars of site conditions are as follows:
Government Departments often insist that the Preliminaries section of the Bill of
Quantities is not priced by the tenderers. Any costs required to comply with the
conditions specified in the Preliminaries are to be allowed for in the various unit rates
in the subsequent trade sections of the Bill of Quantities. This action is taken to assist
contract administration. Following is a typical Bill of Quantities preamble clause for
the Preliminaries section taken from a Government project.
Generally
The following clauses are given for the guidance of the tenderers. Any costs
which the Tenderer may wish to allow for these clauses as well as any clauses
or conditions not especially mentioned hereafter, shall be included in the unit
rates and prices in the various Trade sections of the Bill of Quantities and shall
not be shown as individual amounts in this Preliminaries section of the Bill of
Quantities.
This clause is followed by the usual Preliminaries descriptions found in a typical Bill
of Quantities except that the descriptions are in specification format with no provision
for pricing.
The first step is to prepare a project programme before the work is commenced. This
programme, usually in the form of a simple bar chart, is prepared by the "Job
Captain" in consultation with the other team members responsible for the preparation
of the Bill of Quantities. The programme lists all the trade sections and indicates who
is responsible for each section of the work, the time allocated, the progress to date, the
stage that the Bill of Quantities manuscript has reached, and the documentation
(drawings and specification) that has been received from and returned to the design
consultants. The programme is constantly updated and monitored throughout the
duration of the work. At any given time during the progress of the work the team can
168 Basic Building Measurement
assess their progress and take any corrective action necessary to achieve the scheduled
completion date.
Each member of the team should exercise individual quality control during the
measurement of the various trade sections. This primarily involves:
1. Lining off each Specification clause and/or schedule after the billing
and measurement has been completed.
2. Colouring the drawings after each particular component or finish has
been measured.
3. On completion of each trade section, checking to ensure that all clauses
in the Specification section and/or schedule have been lined off and
that all trade work indicated on the drawings has been coloured in.
Never assume that the Specification and drawings are perfect. Simple
cross checking procedures as outlined in 1 and 2 above will often
reveal errors and discrepancies in the drawings and specification.
4. Looking for obvious errors, such as: unusually large quantities;
unusually low quantities: and major omissions.
5. Comparing with previous Bills of Quantities for similar type projects.
Historic Bills of Quantities act as useful guides and can often be
helpful when preparing the Bill of Quantities and assist in identifying
possible omissions.
6. Keeping and maintaining written query sheets. A query sheet is a
written record of questions and answers to problems that arise during
the preparation of the Bill of Quantities. Whenever a doubt as to the
nature and extent of the works arises during the measurement stage the
responsible design consultant (Architect, Engineer, etc.) should be
contacted and clarification sought. Answers to questions should be
recorded together with other relevant information, such as date, sketch
details, and the name of the consultant providing the information.
Quality control should also be exercised during the finalisation of each section and the
associated printing stage. It is normal practice to double check all mathematical
calculations and to proof read the typed draft where the Bill of Quantities is produced
using a traditional typed documentation process. If an integrated computer software
package is used to produce the Bill of Quantities, the checking of mathematical
calculations and proof reading is not critical, but it is still important that the surveyor
who measured the work checks the final computer printout.
After all the measurement has been completed by the team members, a total project
check should be carried out. This consists of all team members marking up a final set
of drawings and cross checking to ensure that all components have been measured. It
is good practice to return a corrected set of drawings and corrected draft specification
to the design consultants. This process improves the standard of documentation and
should result in less variations during the construction period. The drawings and
specification used to prepare the Bill of Quantities, work sheets, query sheets,
computer disks, etc. should be safely stored in case of future inquiries regarding the
accuracy of the Bill of Quantities during the construction period.
Chaptm 18 Preliminaries/Quality Control Rcedurs 169
Prior to issuing the Bill of Quantities it is essential to carry out bulk checks to avoid
possible major errors. This involves making comparative quantity checks, such as
comparing the total areas of floor and ceiling finishes; comparing total soffit
formwork area, total slab areas and the G.F.A. for the building; and checking that all
trades have been printed in full. If an elemental cost plan has been prepared for the
project the quantities in the bill should be compared with the quantities in the
elemental cost plan.
Finally, it is good practice to price the Bill of Quantities and compare the final cost
against previous estimates and elemental cost plans. The percentage cost of each
trade section can be compared with similar projects and can often be a handy guide
when trying to identify cost anomalies. After all of the above checks have been
carried out the team should be relatively confident that a high standard of work has
been achieved.
INDEX
Abbreviations 2
Area take-off 18
Australian Standard Method of Measurement 10
Ceiling finishes 31
Exercise 35
Plasterboard ceiling lining 32
Plasterboard cornice 32
Centre calculations 48
Centre line measurement 17
Concrete 76–97
Pier and beam footings 89–92
Rein. concrete slab on ground 85–8
Concrete (Cont.)
Rein. concrete strip footings 78–84
Rein. concrete strip footings exercise 82
Slabs and stairs exercise 93–7
Stepped strip footings 83–4
Drainage 125–133
Drainage exercise 130–3
Interpolation of drainage levels 125–6
Stormwater drainage 126–9
Doors, frames and hardware 23–6
Eaves 60–2
Fascias and barge boards 61
Eaves soffit lining 61
Trims 62
Electrical Installations 145–156
Exercise 145
Finishes 27–38
Floor finishes 27–31
Carpet 30
Exercise 35
Finished as laid concrete 30
Skirting 31
Quarry tile threshold 30
Glazing 157
Mirrors 157
Glazing and Painting 157–165
Ground floor framing and flooring 49–52
Exercise 52
Groundworks 98–104
Excavation for slab on ground
exercise 100–1
Pier and beam footings 102–4
Trench excavation 98–9
Trench excavation exercise 99
Hydraulics 134–144
Exercise 134–144
Taps and outlets 142
Cold water service 140
Hot water service 141
Sanitary fixtures 143
Sanitary plumbing 144
Introduction 1–4
Linear take-off 16
Masonry 39–47
This page has been reformatted by Knovel to provide easier navigation.
Index Terms Links
Measurement exercises 19
Measurement process 11–9
Measurement rules 11
Metalwork 105–112
Aluminium sliding windows and doors 105–6
Arch bars and angles 107–8
Balustrades 108–110
Handrails exercise 111–2
Metal door frames 112
Metric standard brickwork 39
Metric units 4
Painting 158–165
Example 158–162
Exercise 163–5
Measurement technique 158
Perimeter measurement 16
Pitched roof framing 53–6
Exercise 57
Preliminaries 166–7
Roofing 63–75
Concrete roof tiling 63–5
Terracotta roof tiling 66–9
Roof tiling exercise 70
Metal roofing, gutters and downpipes 70–5
Sample pages 6
Woodwork trade 7
Trade collection 8
General Summary 9
Set out of take-off figures 14
Standard ruled quantity surveying paper 12–3
Structural Steel 113–124
Covered way framing 117–121
Exercise 122–4
Mass details 113–6
Terminology 1
Volume take-off 19