1.0 Introduction
This document has been prepared by Eastern Precast Concrete to describe the methods and
procedures to be followed for the application of grout on concrete wall panel and other precast
concrete elements. This document shall be read together with the Method Statement for
Erection of various precast elements.
All grouting works application shall be conducted by EPC Erection Team according to the
procedures here to describe prior for project hand over.
2.0 Scope
This method statement details the various procedures and working phases required for the application
of grout on the wall panel and other precast connection using an approved grouting material.
Precast wall panel connection for grouting:
Dowel and Bolt connection
4.0 Materials
All materials shall be supplied in a ready to use form requiring only mixing
Note: All materials shall be mixed and placed in accordance with the manufacturer’s
instructions
- The grout shall be placed / pour into the pipe or bolt grout hole inlet
provided and a grout head shall be maintained at all times to avoid air
entrapment
2 MATERIALS APPROVAL
10.0 Checklist
Project:
Location:
QR 7.5.2/5
Inspection
Checklist Remarks
Date Result Inspector Signature
INSTALLATION
FINAL INSPECTION
Inspection
Checklist Remarks
Date Result Inspector Signature
Pre-Grouting Works
Materials Approval
Grouting Procedure Approval
(by grouting materials manufacturer)
Test Cube Sampling
Grouting Works
Mixing
Casting
Test Results
Curing and Drying
Anchor Bolts and any Connection Fixing
Final Inspection
Personal Protective Equipment shall be considered only as “last resort of defense” against
potential risk and hazards. All workers shall be provided with job specific Personal
Protective Equipment.
EPC shall ensure that adequate stock of Personal Protective Equipment is readily either
available on site or issued to personnel. PPE shall be considered as consumable items.
All PPE utilized shall be manufactured to a recognized international acceptablestandard.
EPC is required to comply all requirements stated EPC Construction Safety Manual.
Safety officer or safety coordinator shall be present full time on site during the
17
Execution of works and shall implement the safety rules and regulation at working area all
the time.
Favoring strategies and methods to reduce/minimize excessive dust emission and
occupational noise levels.
c. Contractual Requirements
The works described in this Method Statement must be executed in compliance with the Health & Safety
Requirements. In addition, the works described in this method statement must be executed in full
compliance with company and client Occupational Health and Safety and other Health & Safety
Requirement.
Read labels and the material safety data sheet (MSDS) before using any material to make
sure you understand hazards and precautions.
Always use required PPE; replace worn out or damaged PPE as it won’t provide adequate
protection.
Make sure that all materials are properly labeled and contained.
Store all materials properly, separate incompatibles, and store in ventilated, dry, cool
areas.
Materials Safety Data Sheet (MSDS) shall be available and display at storage area