Project Title: PROPOSED WAITING SHED

Location: BRGY. LUMBIA, CAGAYAB DE ORO CITY


Owner: LGU-BRGY. LUMBIA, CDOC

No. of Days to Finish


No. List of Task tems Predecessor ES EF
Task (days)
A Excavation 2 -- 0 2
B Fabrication of Rebar Works for Footing and Columns 2 A 2 4
C Installation of Rebar Works for Footing 1 B 4 5
D Concreting of Footing 1 C 5 6
E Fabrication of Rebar Works for Beams 2 B 4 6
F Installation of Rebar Works for Columns and Lower beams 1 D, E 6 7
G Installation of Formworks for Columns and Lower Beam 1 F 7 8
H Concreting of Columns and Lower beams 4 G 8 12
I Installation of Rebar Works for Upper Beams 1 F 8 9
J Removal of Formworks for Columns and Lower Beams 1 H 12 13
K Backfilling Works 1 J 12 14
L Masonry Works 1 K 14 15
M Concrete Works for Benches 1 M 15 16
O Installation of Formworks for Upper Beams 1 J,I 13 14
P Concreting of Upper Beams 2 O 14 16
Q Removal of Formworks for Upper Beams 2 P 18 20
R Fabrication of Trusses 2 M 16 18
S Installation of Trusses 1 R, Q 18 20
T Intstallation of Purlins 1 S 20 21
U Installation of Roofing and Accessories 2 T 21 22
V Instation of PVC Pipe Downspout 1 U 22 23
W Installation of Electrical Works 1 V 23 24
NETWORK DIAGRAM (PERT-CPM)

5 6 8 12
12 13 14 15
16 18
Critical Path
D H J K L M R Non-Critical Path

14

16
C 4 5 G 7 8

13
0 2 2 4

15
6 7
A B
START

F
2 2 20 21 21 22 23 24

T U V W

FINISH
4 6 8 9 22 23
14 16 16 18
E I O P Q S 18 20

13 14

Manpower Schedule
Days 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Laborer 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Skilled 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 2 1 1 1
Total 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 2 2 2

Prepared By:

Name of Stuudents