Sub-Contractor'S Accomplishment Form: Millennium Erectors Corporation
Sub-Contractor'S Accomplishment Form: Millennium Erectors Corporation
DATE : 30-Jul-12
NAME OF PROJECT : ORIENTAL GARDEN MAKATI-LILAC TOWER
Chino Roces Ave. corner Urban Ave., Makati City
SUB-CONTRACTOR : OHM-Struct Builders
CONTRACT AMOUNT : 60,215.30 Pesos
SCOPE OF WORK : MASONRY WORKS 12TH FLOOR
12th floor
FLOOR LEVEL QTY. UNIT TO DATE PREVIOUS PRESENT AMOUNT
sq. m COST AMOUNT % % % TO DATE PREVIOUS PRESENT
RC PLASTER 177.94 120.00 21,352.80 50.00 25.00 25.00 10,676.40 5,338.20 5,338.20
RUBBED CONCRETE 777.25 50.00 38,862.50 90.00 90.00 - 34,976.25 34,976.25 -
955.19 60,215.30 - 45,652.65 40,314.45 5,338.20
Fernando T. Gatchalian
Site Engineer Senior Project Manager
MILLENNIUM ERECTORS CORPORATION
SUB-CONTRACTOR'S ACCOMPLISHMENT FORM
DATE : 30-Jul-12
NAME OF PROJECT : ORIENTAL GARDEN MAKATI-LILAC TOWER
Chino Roces Ave. corner Urban Ave., Makati City
SUB-CONTRACTOR : OHM-Struct Builders
CONTRACT AMOUNT : 60,215.30 Pesos
SCOPE OF WORK : MASONRY WORKS 12TH FLOOR
ACCOMPLISHMENT
PARTICULARS
TO DATE PREVIOUS PRESENT
GROSS BILLING PHP 45,652.65 PHP 40,314.45 PHP 5,338.20
LESS
10% RETENTION PHP 4,565.27 PHP 4,031.45 PHP 533.82
LIQUIDATION
2% EWT PHP 913.05 PHP 806.29 PHP 106.76
OTHERS:
Janlou T. Barra
Cost Engineer JJC
Jose P. Maaliw
Q.C Engineer RGP
Fernando T. Gatchalian
Senior Project Manager MMC
Noted by:
CBD