Construction Rating

Site Audit Protocol


 

Pearl Rating System for Estidama


Construction Rating
Site Audit Protocol

Version 1.0

March 2012

 
 
 

Contents 
1.0  Introduction .......................................................................................................................................................... 1 
Estidama ‐ General ................................................................................................................................................................ 1 
The Pearl Rating System for Estidama .................................................................................................................................. 1 
The Pearl Rating Stages ......................................................................................................................................................... 2 
Key Team Members .............................................................................................................................................................. 2 
The Pearl Rating Process ....................................................................................................................................................... 3 

2.0  Construction Audit Process Applicability .................................................................................................. 4 
Project Applicability .............................................................................................................................................................. 4 
Municipality Contact Details ................................................................................................................................................. 4 

3.0  Design and Development Teams Responsibility ..................................................................................... 5 
General ................................................................................................................................................................................. 5 
Pearl Qualified Professional (PQP) ........................................................................................................................................ 5 
Independent Commissioning Agent ...................................................................................................................................... 5 
Construction Rating Submittals............................................................................................................................................. 5 

4.0  Audit Stages ........................................................................................................................................................... 6 
Timing and Responsibilities ................................................................................................................................................... 6 

5.0  Audit Procedure .................................................................................................................................................. 8 
6.0  Audits Timeline ................................................................................................................................................... 9 
7.0  Communication Protocol ............................................................................................................................... 10 
Construction Rating Questionnaire & Site Audits ............................................................................................................... 10 
Credit Clarification Requests – Construction Elements ....................................................................................................... 10 

8.0  Corrective Action Procedure ........................................................................................................................ 11 
9.0  Certification ........................................................................................................................................................ 12 
Municipality Certificate of Completion ............................................................................................................................... 12 
Estidama Pearl Construction Rating Certificate .................................................................................................................. 12 


 
 

1.0 Introduction 

ESTIDAMA - GENERAL
Estidama, which means ‘sustainability’ in Arabic, is the initiative of the Urban Planning Council (UPC)
aimed at creating more sustainable communities, buildings and villas and to balance the four pillars of
sustainable development: environmental, economic, cultural and social.
Figure 1: The Four Pillars of Estidama

The aspirations of Estidama are incorporated into Plan 2030 and other UPC policies such as the Public
Realm Design Manual (PRDM). Estidama began two years ago and is the first program of its kind that is
tailored to the Middle East region. In the immediate term, Estidama is focused on the rapidly changing built
environment, where UPC is making significant strides to influence projects under design, development or
construction within the Emirate of Abu Dhabi.

THE PEARL RATING SYSTEM FOR ESTIDAMA


One of Estidama’s key initiatives is the Pearl Rating System, which aims to address the sustainability of a
given development throughout its lifecycle from design through construction to operation. The Pearl Rating
System provides design guidance and detailed requirements for rating a project’s potential performance in
relation to the four pillars of Estidama.
The Pearl Rating System is organized into seven categories that are fundamental to more sustainable
development. These form the heart of the Pearl Rating System:
ƒ Integrated Development Process: Encouraging cross-disciplinary teamwork to deliver environmental
and quality management throughout the life of the project.
ƒ Natural Systems: Conserving, preserving and restoring the region’s critical natural environments and
habitats.
ƒ Livable Buildings: Improving the quality and connectivity of outdoor and indoor spaces.
ƒ Precious Water: Reducing water demand and encouraging efficient distribution and alternative water
sources.
ƒ Resourceful Energy: Targeting energy conservation through passive design measures, reduced
demand, energy efficiency and renewable sources.
ƒ Stewarding Materials: Ensuring consideration of the ‘whole-of-life’ cycle when selecting and
specifying materials.
ƒ Innovating Practice: Encouraging innovation in building design and construction to facilitate market
and industry transformation.
 


 
 
THE PEARL RATING STAGES
The Pearl Rating System recognizes the reality of ownership and responsibility transitions as a project
evolves from a design team to a construction team to a facility management team. Accordingly, three rating
stages have been established: Design, Construction and Operational.
Pearl Design Rating - The Design Rating rewards measures adopted during the design development of
the project that meet the intent and requirements of each credit. A Pearl Design Rating is valid only until
construction is complete, and requires that all collateral, branding and communication materials identify the
project as a Pearl Design Rated project.
Pearl Construction Rating - The Construction Rating ensures that the commitments made for the Design
Rating have been achieved. The Construction Rating requires that all collateral, branding and
communication materials identify the project as a Pearl Construction Rated project.
Pearl Operational Rating – The Operational Rating assesses the built-in features and operational
performance of a Pearl Construction Rated project and ensures the building is operating sustainably. The
Operational Rating can only be achieved a minimum of two years after construction completion and when
the building has reached a minimum occupancy of 80%.

KEY TEAM MEMBERS


The assessment process requires the following key team members:

Pearl Assessor
Figure 2: Key Team Members
The Pearl Assessor is an Estidama representative
who assesses the Pearl Rating submission
documents.
Pearl Qualified Professional
The Pearl Qualified Professional (PQP) is a member
of the Design and Development Team who
facilitates the Pearl Rating System for both Design
and Construction stages. To become a PQP, the
individual must pass an exam which will test their
administrative and technical knowledge of the Pearl
Rating Systems.
The PQP’s role is as follows:
ƒ Understand the requirements of the Pearl
Building and Community Rating Systems and
associated Guides;
ƒ Facilitate the rating process; and
ƒ Provide quality assurance to documents prior to
submission to Estidama.
Communication with Estidama and the Pearl
Assessor will generally be via email, with frequently
asked questions available on the Estidama website.
The website will also provide information to help
guide Design and Development Teams through the
Pearl Rating Systems and will contain schedules of
training sessions, seminars and events.

2
 
THE PEARL RATING PROCESS
The Pearl Rating System is designed to facilitate an effective way to assess the sustainability performance
of a specific development.
Once planning approval has been obtained (if required), the project will continue toward design stage
completion and it is at this point that a Pearl Design Rating will be submitted, either to the relevant
Municipality or to the UPC’s Estidama team. A full Design Rating submission is linked to obtaining a
building permit from the Municipality and can only be made at Detailed Design stage when the project is
ready for tendering. Similarly a full Construction Rating application is linked to obtaining a certificate of
completion from the Municipality and can only be made upon the completion of construction. Up to date
information on how to submit your project and how it will be reviewed can be obtained from the Estidama
website (‘Submit Project’ page of www.estidama.org).
The general steps required as part of this process are summarised as follows:

Pearl Rating Steps


Stage

All Step 1: Check the Estidama website for details on the submission process.
Step 2: Appoint a PQP to facilitate the rating process and co-ordinate the submission.

Design Step 3: Prepare final design credit submissions and issue to the reviewing authority
upon completion of construction documentation.
Step 4: The submission will be reviewed by a Pearl Assessor, who may request
clarifications or additional information from the PQP as necessary.
Step 5: The Pearl Assessor will award a Pearl Design Rating based on the credits
achieved by the project.  

Construction Step 6: PQP will prepare the Construction Rating Questionnaire in order to initiate the
Construction Rating process and associated Site Audits
Step 7: Site Audits during each construction stage (Stages 1 – 4b). PQP to liaise with
UPC / Municipality to conduct Stage 1 – 4b site audits before building handover
Step 8: Prepare final construction credit submissions and issue to the reviewing authority
upon completion of construction.
Step 9: The submission will be reviewed by a Pearl Assessor, who may request
clarifications or additional information from the PQP. Estidama reserves the right
to undertake on-site verification if deemed necessary.
Step 10: The Pearl Assessor will award a Pearl Construction Rating based on the credits
achieved by the project.

Operational Two years following construction completion submissions can be made for the Pearl
Operational Rating (currently under development).

3
 

2.0 Construction Audit Process Applicability 

PROJECT APPLICABILITY
This Site Audit Protocol is only applicable to community, building and villa projects that received Design
Rating Award from the Abu Dhabi Urban Planning Council Estidama Team.
The audits and Construction Site Audit Checklist related to this Protocol are only related to the Pearl Rating
System for Estidama and its associated compliance. All other Municipality and Civil Defence approvals
must be sought as per the normal construction practice within the Emirate.
All questions relating to the Construction Rating process and any site audits should be addressed to the
UPC Assessor in the first instance in accordance with the Communication Protocol section later within this
document.
For projects that have been awarded their Design Rating through the local Municipality, a separate local
protocol will be advised, for details please contact the relevant Municipality:

MUNICIPALITY CONTACT DETAILS


Abu Dhabi Municipality - Estidama Team

Email: [email protected]   

Website: http://www.adm.gov.ae/en/menu/index.aspx?MenuID=115&mnu=Pri  

Al Ain Municipality - Building Permit Team

Email: [email protected]

Website: http://am.abudhabi.ae

Western Region Municipality - Building Permit Team

Online Contact Form: http://www.wrm.ae/default.aspx?uid=cqdj12cq

Website: http://www.wrm.ae/

4
 

3.0 Design and Development Teams Responsibility 

GENERAL
As a fundamental requirement of the Pearl Rating System, it remains the Design and Development Team’s
responsibility to prove compliance with all Required and Optional Credits.
This Site Audit Protocol has been developed to assist projects in achieving Credit Compliance, and on this
basis does not remove any form of liability from the Design and Development Team.
The Design and Development Team must ensure when required that any audits are carried out in a
timeframe to suit the requirements of the project; neither the UPC nor the Municipality will accept any
responsibility for program delay in relation to non-compliance with a Credit Requirements and the
associated responsibilities.
The Design and Development Team must ensure all areas can be inspected when the visit takes place
relevant to the particular stage of the project and appropriate attendance for each stage as outlined in this
Protocol.

PEARL QUALIFIED PROFESSIONAL (PQP)


The PQP manages the Pearl Rating System certification process and helps integrate the input of the
Design and Development Team throughout the project life-cycle, in particular during construction. The PQP
is also the single point of contact with the UPC Estidama Assessor and is responsible for managing queries
related to compliance and the certification process. Specifically, the PQP is responsible for:
ƒ Construction Credit Clarification Requests;
ƒ Planning of the Site Audits including ensuring the required attendance (UPC, Municipality,
Commissioning Agent, Contractor, etc.) and any appropriate logistics; and
ƒ Construction Submittal Documentation.
Whilst the UPC and the Municipalities can provide assistance in process questions, it remains that all
Estidama project specific queries must be addressed internally through the project PQP. Only
correspondence received from the Appointed PQP will be addressed by the Pearl Assessor.

INDEPENDENT COMMISSIONING AGENT


The Independent Commissioning Agent (ICA) has a fundamental role in relation to project sign-off and
ensuring that design intent was met during construction and later during operation as detailed under IDP
credits "Basic Commissioning" and "Re-Commissioning".
The ICA must be in attendance during the two last stages of the audit to present the commission plan,
activities and results.

CONSTRUCTION RATING SUBMITTALS


At the completion of the development the Design and Development Team must submit full and final
documentation to prove compliance with all Required and Optional Credits.
The submittal template must be completed and issued to the UPC Assessor by the assigned PQP within 3
to 4 weeks from the date of the issuance of the Completion Certification. Up to date information on how to
submit your project and how it will be reviewed can be obtained from the Estidama website (‘Submit
Project’ page of www.estidama.org).

5
 

4.0 Audit Stages 

TIMING AND RESPONSIBILITIES


Prior to any site commencement, the PQP is required to submit a completed Construction Rating
Questionnaire to the Pearl Assessor. The questionnaire will communicate the construction start date and
an outline program to completion, in particular the proposed dates for each of the four following Site Audit
Stages. The Construction Rating Questionnaire will have been issued to the project Design Stage PQP
following the Design Rating Award.
It is within the Design and Development Teams control to propose or change dates within a suitable
timeframe to suit the project’s program of works and where possible these dates can coincide with other
relevant Municipality inspections.

Figure 3: Audit Stages

Stage 4a & 4b Stage 1


Commissioning & Site Set-Up &
Handover Docs Sub-Structure

Stage 3 Stage 2
Internal Fit-Out Superstructure
& MEP Works & Envelope

The following notes provide an overview of the expected discussion points during each Site Audit Stage.

6
 

Audit Stages Attendees Discussion Topics

Stage 1 – ƒ PQP ƒ Design and Development Team Estidama Awareness: This is to identify and
Site set-up and ensure that an appropriate handover process has been implemented from design
ƒ Contractor to construction and that the Construction Rating requirements are fully understood
sub-structure Senior including any handover meetings, Estidama training, sub-contractor training and
Representative documentation and evidence reporting process.
ƒ Design ƒ General procurement requirements: An appropriate procurement strategy and
Consultant approval process should be in place to ensure that materials, appliances etc have
ƒ Any other been reviewed against the requirements of the Pearl Rating System and evidence
relevant party obtained for the Construction Rating submission.
as considered ƒ Natural Systems Credits: Any valuable assets identified as part of the Natural
appropriate Systems Assessment, where applicable need to be appropriately protected.
ƒ Construction Waste Management: This is to demonstrate the implementation of
the Construction and Demolition Waste Management Plan (CDWMP) and
appropriate documentation and recording of construction and demolition waste.

ƒ Outstanding information and/or clarifications (Design Assessment).

Stage 2 – As above ƒ Design and Development Team Estidama Awareness (Up-Date).


Superstructure ƒ General procurement requirements (Up-Date).
& Envelope
ƒ Construction Waste Management (Up-Date).
ƒ Envelope verification and inspection: This is to ensure that the relevant
certificates / tests for cladding systems and water infiltration and air tightness tests
have been carried out and the envelope elements have been installed
appropriately.
ƒ Outstanding information and/or clarifications (Stage 1).

Stage 3 – As above plus: ƒ Construction Waste Management (Up-Date).


MEP & Fit-out ƒ Independent ƒ Envelope verification and inspection (Up-Date).
Commissioning
Agent ƒ Commissioning Plan and Activities: This is to ensure that pre-commissioning
checks and commissioning as per manufacturers guidelines and design
requirements have been carried out. Outstanding information and/or clarifications
(Stage 2).

Stage 4a – As above ƒ Commissioning Activities & Results – Preliminary: This is to provide an


Commissioning update from Stage 3 with initial results presented to the UPC Assessor.
Documentation ƒ Construction Rating Submittal Documentation: The Design and Development
Team are required to provide at least 70-80% of the completed draft Construction
Rating submittal documentation to UPC for initial review. This will provide initial
feedback from the UPC to the team to minimise delays in the final review period
and to ensure the appropriate documentation has been gathered to identify any
issues.
ƒ Draft Operational & Maintenance Manuals
ƒ Outstanding information and/or clarifications (Stage 3)

Stage 4b – As above ƒ Final Site Walk-around & Envelope Inspection


Commissioning ƒ Commissioning Activities & Results (Up-Date)
Verification
ƒ Construction Waste Management (Up-Date)
ƒ Outstanding information and/or clarifications (Stage 4a)
The final site audit will consist of final checks to ensure all mandatory credits have
been implemented appropriately, commissioning checks have been conducted and
final envelope inspection and other outstanding issues identified in earlier audit
stages.

7
 

5.0 Audit Procedure 
The audit will take the form of two levels, these being:
ƒ Audit meeting; and
ƒ Site walk-around.
Generally the audit process will take no more than two hours, but can be extended to accommodate larger
or more complex developments. Time allocation is to be determined by the Design and Development Team
as applicable to their project.
General Procedure

Item Task Owner

1 Initial meeting at the pre-allocated venue (PPE and site regulations to be Contractor
supplied by the Contractor) to discuss relevant Estidama elements to the
particular audit stage

2 General site walk-around focusing on key inspection areas for the applicable PQP/
PRS for Estidama audit stage Contractor

3 Minutes of the walk-around and audit meeting will be taken PQP

4 The Construction Site Audit Checklist for the relevant audit stage will be PQP
completed live in the audit meeting

6 A provisional date will be agreed for the next audit All

7 The Audit Report include minutes of meeting and the Construction Site Audit PQP
Checklist will be issued to all relevant Design and Development Team
members and the UPC team by email within five working days of the audit

Where items of concern were noted during the audit and were agreed with all parties, an intermediate audit
can be carried out to align concerns and ensure credit compliance is achieved as outlined in the Corrective
Action Procedure section below.

8
 

6.0 Audits Timeline 
As intimated previously the Design and Development Team should request a formal time for audits to suit
their actual construction activities. Where possible, audits shall be booked at least ten working days in
advance with the UPC Estidama Team.
However, within Stage 4 of the Audit Process the following timeline must be adhered to by the Design and
Development Team.

Figure 4: Submission Timeline

Building
Joint Audit Joint Audit Municipality Issue Handover
Documentation Site Walk Round Completion
Stage 4a Stage 4b Certificate

‐7 ‐6 ‐5 ‐4 ‐3 ‐2 ‐1 0

Timeline (weeks)

Assessment
Correspondence

UPC Assessment Construction Submission


+7 +6 +5 +4 +3 +2 +1

As mentioned previously, Stage 4 audits will accommodate two forms of audits, the first being PRS for
Estidama documentation and the second being a site walk-around.
The Stage 4a audit will be at the offices of UPC.
On completion of the building and formal Municipality approval being issued, the Design and Development
Team will formally submit the Construction Rating application within 3 to 4 weeks as shown above. The
UPC will then undertake the assessment and provide a response within 3 to 4 weeks.

9
 

7.0 Communication Protocol 
It is the Appointed PQP’s responsibility to act as the main point of contact between the Design and
Development Team and the UPC. Only correspondence received from the Appointed PQP will be
addressed by the Pearl Assessor.

CONSTRUCTION RATING QUESTIONNAIRE & SITE AUDITS


Following the Design Rating Award, the UPC Estidama Team will have issued a Construction Rating
Questionnaire to the PQP/Owner requesting project information and outline program to completion. Prior
to any commencement of works onsite, the PQP/Owner is required to notify the UPC in writing of the
proposed start date, outline program and Design and Development Team contact details by completing a
revised Construction Rating Questionnaire which is included as Appendix A of this Protocol. This
Construction Rating Questionnaire should be submitted to the UPC by email.
Following the submission of the Construction Rating Questionnaire, a Pearl Assessor will be assigned and
provisional dates for site audits agreed with the Design and Development Team. It is within the Design and
Development Teams control to propose date changes for site audits within a suitable timeframe to suit the
project’s program of works and where possible these dates can coincide with other relevant Municipality
inspections. Where feasible, the Pearl Assessor for Construction Rating will remain the same as Design
Rating. Any following correspondence can be via email from the Appointed PQP to the Pearl Assessor.

CREDIT CLARIFICATION REQUESTS – CONSTRUCTION ELEMENTS


Any clarification on credits should be submitted through the credit clarification procedure. The Credit
Clarification Request (CCR) system is essentially a question and answer mechanism between Design and
Development Teams and the UPC Estidama Team. It is intended to enable confirmation that the Pearl
Rating System requirements are correctly understood and can therefore be effectively delivered in the
context of the project.
Where Design related CCRs have been previously issued, Construction related CCRs must be added to
the same register for continuity. All CCRs to be submitted via email to the UPC Pearl Assessor. Where no
pervious CCR has been issued to the UPC a new form can be downloaded for each relevant typology at:
www.estidama.org/credit-clarification-requests-.aspx?lang=en-US
During the site audits, the PQP will complete the Construction Site Audit Checklist live and minute the
meeting. The PQP is responsible for issuing Audit Report and soft copy of the Construction Site Audit
Checklist and associated risk register within five days of the site audit. An Audit Report template is included
in Appendix A and will be sent electronically to each project PQP.
If corrective action is required following a site audit as outlined in the Corrective Action Procedure, the PQP
is responsible for rescheduling any re-audit and submitting the appropriate resolution plan via email to the
Pearl Assessor within the agreed timeframe.

10
 

8.0 Corrective Action Procedure  
Following any site audit stage, if the Construction Site Audit Checklist identifies areas of high risk or where
the mandatory requirements are not being implemented appropriately, the UPC may request corrective
action. This can be in two forms as illustrated below.
If a re-audit is deemed required, the PQP is responsible for scheduling a re-audit and submitting a
Resolution Plan to the UPC Assessor in accordance with the Communication Protocol. The re-audit will
ensure the measures in the Resolution Plan have been implemented appropriately.
Where a re-audit is deemed not necessary, but corrective measures are still required, the PQP will submit
a Resolution Plan to the UPC Assessor in accordance with the Communication Protocol.

Figure 5: Corrective Action Procedure

Establish Resolution
PQP to schedule a
Corrective Action Rule
Yes re-audit and
Required (Is a re-audit
resolution plan
required)
No

UPC Assessor
PQP to issue a confirms Acceptance
resolution plan or provides
comments

11
 

9.0 Certification 

MUNICIPALITY CERTIFICATE OF COMPLETION


The Municipality will issue the Certificate of Completion for the project following Stage 4a and Stage 4b Site
Audits. It is the responsibility of the Design and Development Team to coordinate with the Municipality and
UPC to arrange the site audits which should be in line with the construction program.

ESTIDAMA PEARL CONSTRUCTION RATING CERTIFICATE


Following the Certificate of Completion the Design and Development Team will have 3 to 4 weeks to issue
the Construction Rating submission through the PQP to the Pearl Assessor. The UPC will review the
submission over 3 to 4 weeks, communicating with the PQP to clarify any issues / request for further
information or documentation. The UPC will then issue the Estidama Pearl Construction Rating certificate.

12
 

Appendix A
Audit Documentation Templates

 
 
 

Construction Rating Questionnaire

Project Name
PQP Name
PQP Email
PQP Number

Design Pearl Rating Achieved


Date
Rating
UPC Letter Reference
Pearl Assessor Name

Client Company
Client Main Contact
Client Email

Contractor Company
Contractor Main Contact
Contractor Email

Project Start Date


Project Completion Date

Alterations to Main Team Members from Design

Please note if the Design PQP and/or Commissioning Agent involved in the design stage will differ from
those at construction stage.

Construction Program
Construction Stage Enabling works Superstructure MEP & Fitout Commissioning
Start Date
Duration

Completion Date

Additional Notes

It is noted that the information provided is preliminary and construction dates may vary and must be
confirmed as the construction program progresses.

 
 
 

Pearl Rating System Audit Form

Project Summary
Project Name
Pearl Rating System
Building Use
Pearl Rating Stage Construction
PQP Name
PQP Number
Contractor Name
Contractor Company
Client Company
Date

Project Start Date


Current Construction Stage

Stage 1 Site Set-Up and Sub-Structure


Stage 2 Superstructure & Envelope
Stage 3 Internal Fit-Out & MEP
Stage 4a Commissioning & Documentation
Stage 4b Final Site Visit

Version 1.0 Last Updated March 2012


 

Estidama Stage 1 Checklist - Site Set-Up & Sub-Structure


Supporting documentation (e.g. training records, photographs, material datasheets, 
test certificates, purchase receipts, waste transfer notes, etc) must be available 
during the audit to demonstrate compliance.
Yes, No, 
Partly 
Design and Development Team Estidama Awareness   or N/A Comments
Does the contractor have an understanding of Estidama?  Have handover 
meetings been held between the contractor and design team / PQP?  

Has the contractor completed any Estidama training?  Have workers / sub‐
contractors been made aware of the Estidama and training provided?

Is the contractor aware of the Pearl Rating System and the construction 
submission requirements for Estidama e.g. photographic evidence 
confirming installation / purchase receipts/ delivery notes?

General Procurement Requirements
Is the design and development team aware of the specific procurement 
requirements for the project to meet the required credits? Particularly:
‐ U‐Values for glazing, walls, roof, floor
‐ Air Conditioning Units/Ventilation
‐ Energy Meters
‐ Water Fixtures & Exterior Water Meter
Has the design and development team been provided / made aware of 
the Estidama commitments for the project with regard to materials 
procurement? e.g. within specification documents, procurement 
strategy.  Have material specifications been included in bid packages / 
questionnaires to suppliers and sub‐contractors?  Is there a 
procurement approval process?

Is the contractor aware that No Asbestos Containing Materials can be 
used on‐site and that timber for external structures cannot be 
Chromated Copper Arsenate (CCA)‐ treated timber e.g. handrails?

Natural Systems  
Is the contractor aware of the requirements of Natural Systems?  If the 
project includes areas of ecological value, have appropriate protection 
measures been provided? e.g. fencing. 

Construction Waste Management
Is there a copy of the CDWMP on site?  Is it being implemented? Has a 
person responsible for the CDWMP been assigned?  

What is the current rate of salvaged / recycled construction and 
%
demolition waste?  Note Percentage

Optional Credits ‐ Site Audit

Have adequate facilities been provided for construction workers 
(recreational area, sanitation and hygiene facilities etc)?  Is a copy of the 
Guest Worker Accommodation Plan on‐site?

Is a copy of the CEMP on‐site? How is it being implemented/audited?  Has 
a person responsible for its implementation been assigned?

Have measures been made to remediate the site?

As per credits selected, have recycled, regional, certified timber, rapidly 
renewable materials been procured appropriately?
 

Estidama Stage 2 Checklist - Structure & Envelope


Supporting documentation (e.g. training records, photographs, material datasheets, 
test certificates, purchase receipts, waste transfer notes, etc) must be available 
during the audit to demonstrate compliance.
Yes, No, 
Partly or 
Estidama Awareness  & Procurement Update N/A Comments
Has Estidama training been provided for any new employees / sub‐
contractors? 

Can the contractor demonstrate that delivery notes have been retained 
to demonstrate compliance with Estidama?

Is the contractor aware of the specific procurement requirements for the 
Fit‐Out and MEP stage of the project for Water Credits?
‐ Flow rates for water fixtures, 
‐ Water use reductions
‐ Exterior water monitoring

Is the contractor aware of the specific procurement requirements for the 
Fit‐Out and MEP stage of the project for Energy Credits? 
‐ COP for air conditioning units, 
‐ Energy efficiency of appliances

Is the contractor aware of the specific procurement requirements for the 
Fit‐Out and MEP stage of the project for Livable Building Credits? 
‐ Ventilation
‐ Shading SRI (29)
‐ Occupant Thermal Controls (optional)
‐ High frequency lighting and/or daylight sensors (optional)

Is the contractor aware that No Asbestos Containing Materials can be 
used on‐site?  Is the contractor aware that timber for external structures 
cannot be Chromated Copper Arsenate (CCA)‐ treated timber e.g. 
handrails?

Envelope Verification & Inspection
Has a review of standard pre‐testing certificates for pre‐tested cladding 
systems been carried out? If custom made cladding has been used, has 
off‐site testing of prototypes been carried out?
Y es

Has on‐site water infiltration and air tightness tests been carried out on 
the building envelope or included in construction program?

Have the appropriate purchase receipts and manufacturer data been 
filed for U‐Values of the building envelope?

For fenestration‐type envelopes, have purchase receipts/delivery notes 
and manufacturer data been filed for SHGC of fenestration?

Have all the envelope elements (e.g. window and door frames) been 
installed and sealed properly? 

Construction Waste Management (Update)

Is there a copy of the CDWMP on site? Is it being implemented? Has a 
person responsible for the CDWMP been assigned?  

What is the current rate of salvaged / recycled construction and 
%
demolition waste? Note Percentage
 

Yes, No, 
Partly or 
Optional Credits ‐ Site Audit N/A Comments
Have inspections and maintenance been carried out in guest worker 
accommodation?

Is a copy of the CEMP on‐site? Has a person responsible been assigned, 
and is there a monitoring / implementation process? 

Have measures been made to remediate the site?

Is there a copy of the Indoor Air Quality Management Plan and checklist 
on‐site? Has the checklist been completed?

Is the contractor / team aware of the material emissions requirements 
e.g. low VOC?

As per credits selected, have recycled, regional, certified timber, rapidly 
renewable materials been used?
 

Estidama Stage 3 Checklist - Fit Out & MEP


Supporting documentation (e.g. training records, photographs, material datasheets, 
test certificates, purchase receipts, waste transfer notes, etc) must be available 
during the audit to demonstrate compliance.
Yes, No, 
Partly or 
Envelope Verification & Inspection Update N/A Comments
Have there been meetings with the PQP / design and development team?

Has a Building Envelope Verification Report been completed and all the 
appropriate evidence gathered?

Verification of Installation
Have the appropriate photographic evidence and purchase receipts / 
delivery notes been recorded? e.g. A/C units, water fixtures, exterior 
water monitoring, efficient appliances, renewable energy, ventilation, 
shading devices, relevant materials, etc?

Independent Commissioning Agent Plan
Has pre‐commissioning checks and commissioning as per manufacturers 
guidelines  and design requirements been carried out and a Building Log 
Book developed for:
‐ Air Conditioning Systems
‐ Ventilation Equipment
‐ Water Systems
‐ Solar Thermal Equipment
‐ Lighting & Lighting Controls

Required Credits ‐ Site Audit
For residential units ONLY, is the contractor aware of the commitment to 
have weather stripping, impermeable deck to deck partitioning 
installation and sealing of penetrations to walls, roofs and ceiling?

Has a Legionella Management Process audit check list been carried out?

Has exterior water monitoring system or water meter(s) been installed 
for each of the following uses (where present)?
‐ Heat rejection
‐ Irrigation systems & external hose bibs
‐ Swimming pools & water features

Is the team aware of the landscaping requirements for communities in 
terms of irrigation?

Have energy meters been installed? 

What is the current rate of salvaged / recycled construction and 
%
demolition waste?  Note Percentage
Optional Credits ‐ Site Audit
Have inspections and maintenance been carried out in guest worker 
accommodation?

Is there a material tracking register to comply with material emissions 
requirements e.g. low VOC?

Is the Indoor Air Quality Management Plan being implemented and the 
IAQ checklist being applied on a regular basis?

Have thermal occupant controls been installed?

Have water metering facilities been installed for the following interior 
uses (where present)?
‐Bathroom/Toilet 
‐ Kitchen/Catering
‐ Indoor Swimming Pools
‐ Ablution  
 

Estidama Stage 4a Checklist - Documentation & Commissioning


Supporting documentation (e.g. training records, photographs, material datasheets, 
test certificates, purchase receipts, waste transfer notes, etc) must be available 
during the audit to demonstrate compliance.
Yes, No, 
Partly or 
Required Credits ‐ Supporting Documentation N/A Comments
Construction Rating Submission
Has a substantial proportion of the Construction Rating Submission been 
completed?

General Evidence ‐ Can the PQP demonstrate photographic evidence and 
purchase receipts / delivery notes for installed elements particularly the 
mandatory requirements

Natural Systems protected area calculations and management strategy

Updated Natural Systems Design and Management Strategy

Updated Building Log Book

Have the Operational & Maintenance Manuals been produced?

Evidence of draft Final Commissioning Report (and Envelope Verification 
Report for Villa projects)

Has the tenant fit out design & construction guide been produced? (Core 
& Shell Building Projects Only) or Sustainable Building Guidelines for 
Community Projects

Required Credits ‐ Supporting Documentation

Has the Legionella Management Checklist been carried out?

Building Envelope U‐value manufacturer data evidence, purchace 
receipts / delivery notes & photographic evidence

Interior water data sheets and photographic evidence of installation

Manufacturer information on all installed HVAC systems

Manufacturer information on installed appliances

Has the CDWMP been updated?

What is the current rate of salvaged / recycled construction and 
%
demolition waste? Note Percentage
 

Optional Credits ‐ Supporting Documentation
Yes, No, 
Partly or 
N/A Comments

Photographs, maintenance vistis and inspections of guest worker 
accomodation and formation of Worker's Representative Committee and 
development of Workers' social & welfare program

Signed off CEMP audit

Building Envelope Verification Report

Validation report of remediation

Tracking sheet, material safety data sheets and techincal data sheets for 
all interior adhesives and sealants, paints and coatings, carpet and hard 
flooring, ceiling systems and formaldehyde

Construction Indoor Air Quality completed checklists

Has noise field test report been prepared?

Photographs of installed irrigation systems, water recycling systems and 
mainline colour coded, cooling towers, district cooling plant, pool 
blankets where applicable

Have the storm water calculations been updated for the site?

Photographic of renewable energy installation

Manufacturer information confirming GWP for refrigerants, and fire 
suppression systems

Evidence of use of recycled, regional, certified timber, rapidly renewable 
materials
 

Estidama Stage 4b Checklist - Final Site Inspection


Supporting documentation (e.g. training records, photographs, material datasheets, 
test certificates, purchase receipts, waste transfer notes, etc) must be available 
during the audit to demonstrate compliance.
Yes, No, 
Partly or 
Required Credits N/A Comments

Confirm that external water meters have been installed

Confirm that energy meters have been installed

Confirm that bin storage has been provided

Have no smoking signage been installed? (this is not applicable for 
residential buildings / villas)

Optional Credits

Have the air‐conditioning systems been set according to building design 
and building flush out been carried out? Have the filters been changed / 
cleaned as appropriate?

Has bicycle parking been provided?

Has preferred car parking been provided?

Confirm that internal water meters have been installed

Confirm lighting meets lighting levels and controls requirements to 
satisfy light pollution reduction
Consttructio
on Aud
dit Re
eport
Subject:
Date:
Time:
T
Venue:
V
Attendees:
A
cc
c for non-
attendees:
a

Insert photo(s
s) of site reprresenting currrent constructtion stage
Description: Action by: Da
ate:

1. Introduc
ctions

2. Project Update

3. Stage X Site Audit

Update from previou


us Audits:

Stage X Audit:
Refer to
o audit form

4. Site Wa
alk-Around

5. Recomm
mendations / Summary

6. Next Sta
age
Insert relevan
nt pages of th
he Audit Form
m
Attach
A suppo
orting docume
entation
Abu Dhabi Urban Planning Council
62221 P.O.Box 62221
Abu Dhabi, United Arab Emirates
Tel: +971 2 409 6000
Fax: +971 2 443 9443
www.upc.gov.ae