Faculty of Engineering and Computing Sciences: Annexure-I

This document provides instructions for a civil engineering assignment involving project planning and control. It includes 6 questions related to constructing network diagrams using the activity-on-arrow (A-O-A) method and calculating expected times, variances, and critical paths for activities. Students are asked to draw network diagrams, compute earliest and latest times, and determine critical paths for 10 and 8 activities. They must also calculate expected time, variance, and scheduled time for answering exam questions modeled as an activity.

Uploaded by

Akshay Mehta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
106 views2 pages

Faculty of Engineering and Computing Sciences: Annexure-I

This document provides instructions for a civil engineering assignment involving project planning and control. It includes 6 questions related to constructing network diagrams using the activity-on-arrow (A-O-A) method and calculating expected times, variances, and critical paths for activities. Students are asked to draw network diagrams, compute earliest and latest times, and determine critical paths for 10 and 8 activities. They must also calculate expected time, variance, and scheduled time for answering exam questions modeled as an activity.

Uploaded by

Akshay Mehta
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Annexure-I:

Faculty of Engineering and Computing Sciences


Assignment as consider for CT-II (Set-A)
Program: B.Tech Branch/Section: Civil Engineering
Course Name: Project Planning and Control Course Code: ECE811
Semester: 8th Faculty member: Dr. Shekhar Saxena
Total Marks: 30 Submission Date: 03 May, 2020

Unit-III
Q.1: Draw the network by A-O-A as detailed below: (4 Marks)
Activity A B C D E F G H I J
Immediate - A A A B C D D E, F, G H, I
Predecessors

Q.2: Draw a network diagram with the following data by A-O-A. (4 Marks)
Job a b c d e f g h
Immediate - - - a c a,b,c,d a,b,c,e a,b,c
Predecessors

Q.3: A building project consists of 10 activities, represented by the A-O-A network shown below.
Draw the A-O-N network for the same and compute the earliest and latest activity times and total float for
the each activity and determine the critical path. (7 Marks)

Unit-V
Q.4: A typical serious candidate for civil services examination take no less than 25 minutes to answer
a question and sometimes as much as 48 minutes, 35 minutes times are most frequent than any other time.
If this performance were an activity in a PERT project, estimates,
(i) would be expected time to answer a question
(ii) its variance
(iii) the time to be allocated for answering a question in scheduling the project. (4 Marks)
Q.5: With the help of data given below, draw the network diagram and find the project completion
time based on expected time. (4 Marks)
Preceding event Succeeding event to tm tp
node number node number
10 20 10 12 20
10 40 5 15 19
20 30 10 15 26
20 70 15 20 25
30 60 5 10 15
40 50 4 8 12
50 60 5 10 15
60 80 2 4 6
70 80 2 4 6

Q.6: Differentiate between CPM and PERT. The network for a certain project is shown in Figure.
Determine the expected time for each of the path or project duration. Which path is critical? (7 Marks)

+++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++++