Proposed Four-Storey Residential Building

This document outlines the process for developing a proposed four-storey residential building project from pre-set-up through project turn-over. It involves feasibility studies, design, permitting, and construction of the building in sequential phases from site preparation through finishing activities for each floor and roof. The project implementation section provides extensive detail on forming, rebar installation, concrete pouring and stripping for the structural elements at each level.

Uploaded by

Chrispin Barnigo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
1K views4 pages

Proposed Four-Storey Residential Building

This document outlines the process for developing a proposed four-storey residential building project from pre-set-up through project turn-over. It involves feasibility studies, design, permitting, and construction of the building in sequential phases from site preparation through finishing activities for each floor and roof. The project implementation section provides extensive detail on forming, rebar installation, concrete pouring and stripping for the structural elements at each level.

Uploaded by

Chrispin Barnigo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

PROPOSED FOUR-STOREY RESIDENTIAL BUILDING

 Project Pre-Set-Up
 Set Objectives / Scope
 Identify Team
 Assign Roles
 Feasibility Study
 Identify Project Requirements
 Analyze Legal Approvals
 Conduct Land Survey
 Identify Competitors
 Gather Community Opinion
 Investigate Environment Impact
 List All Development Risks
 Produce Feasibility Report
 Project Design
 Identify Two Options
 Choose the Best Solution
 Create 2D and 3D Building Plans
 Project Initiation
 Get Design Approval, Design Approval from Client
 Apply for Permits
 Prepare Project Specification for Contracting
 Appoint the Contractors
 Select the Most Suitable Contractor
 Project Implementation
 Site Preparation
 Measure and Set Boundaries of the Land
 Secure the Site
 Earthworks
 Excavation
 Water and Sewer
 Insert Utility Pipes
 Laying the Foundation
 Backfill
 Structure
 Ground Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Second Floor Slab)
 Stripping of Formworks
 Second Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Third Floor Slab)
 Stripping of Formworks
 Third Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Fourth Floor Slab)
 Stripping of Formworks
 Fourth Floor
 Rebar Laying of Columns
 Rebar Laying of Beams
 Rebar Laying of Exterior and Interior Walls
 Laying of Electrical Wirings and Plumbing
 Formworks Installation of Columns
 Formworks Installation of Beams
 Exterior and Interior CHB Walls Installation
 Formworks Installation of Slabs
 Formworks Installation of Stairs
 Rebar Laying of Slabs
 Rebar Laying of Stairs
 Column Concreting
 Beam Concreting
 Slab and Stairs Concreting (Simultaneous with Roof Deck Floor Slab)
 Stripping of Formworks
 Roof Deck
 Rebar Laying of Exterior and Interior Walls
 Exterior CHB Wall Installation
 Formworks Installation of Slabs
 Rebar Laying of Slabs
 Slab Concreting
 Stripping of Formworks
 Roofing
 Truss Installation
 Laying of Electrical Wirings
 Galvanized Iron Sheet Installation
 Gutter Installation
 Down Sprout Installation

 Utilities
 Waterproofing
 Electrical and Plumbing Utilities Installation
 Ceiling Installation
 Handrail Installation (Bolted)
 Finishing
 Fixtures Installation
 Plastering
 Doors and Windows Installation
 Tiles Installation
 Painting
 Project Turn-Over
 Assures the Completion of the Project
 Identify Any Unfinished Activities
 Inspect the Site for Final Review Before the Turning Over Day
 Prepare the Site for Turning Over to the Client
 Sign the Ending Contract with the Client