TF 0050 Well Control and Barrier Definitions
TF 0050 Well Control and Barrier Definitions
This well control barrier philosophy aims to meet the recommendations from the International
Association of Oil and Gas Producers (IOGP) in report number 476 issued in August 2016.
IWCF will incorporate the barrier principles of ISO, NORSOK and API as applied during different
phases of the well life cycle.
IWCF will use the relevant barrier terms and definitions included in the following standards:
• ISO 16530-1
• NORSOK D-010.
Local legislation, company standards and policy may differ. These differences must be addressed
for each operation.
IWCF will not create new terms or definitions. While the reference sources outlined above have
slightly different wording in their definitions, they are similar in principle.
The terminology that is reflected in the syllabi and in the assessments is outlined below:
A "well barrier element" is a physical element that, when combined with other well barrier elements
will prevent flow.
• A primary barrier is the first well barrier that prevents flow from a source.
• A secondary barrier is the second well barrier that prevents flow from a source.
A "well barrier envelope" is made up of well barrier elements that together prevent flow.
Minimum Requirements
There must always be two independent and tested well barriers (primary and secondary) to
prevent flow. Both must be risk assessed, verified, approved and monitored during any operation
on the well.
Well barriers must be tested in line with the well owner’s performance standards and where
applicable legislative requirements.
Any deviation must follow a Management of Change (MOC) process, be specified and documented
including:
• Mitigation actions and responsibilities must be in place and understood by all personnel.
• A note of approval from senior person of the well owner management team who is
accountable for the integrity of the well.
Verification
To verify a well barrier element, it must be installed where it is it intended to be used and must be
function and integrity tested when installed.
A mechanically activated well barrier element must be able to contain well bore fluids by their own
control system regardless of power failure.
Integrity testing a mechanical well barrier element is done by applying pressure against the barrier
in the direction of flow. Where this is not possible, integrity can be confirmed by decreasing
pressure on the downstream side of the barrier (inflow testing/negative testing).
If this cannot be achieved, other methods can be used if there is a formally endorsed risk
assessment. For example:
- pressure testing, not in the direction of flow from the well
- verification of location (for example, tagging of cement)
For a shear/seal device to qualify as a mechanical well barrier element, it must be able to first
shear tubulars and then seal the well bore.
To qualify a hydrostatic well barrier, the fluid level and properties must be monitored and
maintained.
Operating Principles
At all times, personnel working on the well should understand: