Inspection Test Plan For Storage Tank & Piping System (ITP) : (Arial 12)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 6

go>

Inspection Test Plan for Storage Tank & Piping System (ITP)

<DNO Document No.> (Arial 12)

DNO REVIEW STAMP

Proj. No.: 1079 P.O. No.: ________________

DOCUMENT REVIEW CODES:


R1 R2
Reviewed & Accepted. Reviewed & Accepted as
WORK may proceed. Marked. Revise & Re-Submit.
WORK may proceed.
R3 R4
Reviewed & Returned. Review NOT required. For
Revise and Re-Submit. information only. WORK may
WORK shall NOT proceed. proceed.

Acceptance of this document by DNO does not relieve the


CONTRACTOR or Supplier/Vendor of any responsibility for compliance
with the terms and conditions of the Contract/PO.

Name: Signature:

Date:

License TWK
Inspection Test Plan for Storage Tank & Piping
Cleaning & Relocating System (ITP)
Project Title
Storage Tank
Contractor Project No. Contractor Doc. No.
COMPANY Project No. KU-AAA-NNN COMPANY Doc. No.

Contract No. KU-AAA-NNN-A DNO Rev. A Page 1 of 6


Cleaning & Relocating Storage Tank
Inspection Test Plan for Storage Tank & Piping System (ITP)
System

REVISION RECORD
DNO Originated Checked
Date Description Approved by
Rev. by by
0 26.03.19 Issued for Review S.H.Fatemi A.soleyman A.Poursohrab
i
A 05.04.19 Issued for Review S.H.Fatemi A.soleyman A.Poursohrab
i

Proprietary Information
This document is the property of DNO. It must NOT be reproduced or transmitted to others
without authorization from the COMPANY.

<DNO Doc. No. + DNO Rev.> Page 2 of 6


Cleaning & Relocating Storage Tank
Inspection Test Plan for Storage Tank & Piping System (ITP)
System

TABLE OF CONTENTS
1 Scope 4……………………………………………………………………………………. 4
2 Definition …………………………………………………………………………………. 4
3 Definition of Contractor and Owner / TPI Involvement ……………………………… 4
5

<DNO Doc. No. + DNO Rev.> Page 3 of 6


Cleaning & Relocating Storage Tank
Inspection Test Plan for Storage Tank & Piping System (ITP)
System

1. Introduction of the Project:

1.Scope:

This document is an engineering document which defines for inspection storage tank and piping
system in IRAQ AS ,project No.:1079

2. Definition
Owner: DNO IRAQ AS

Contractor: Full Tech

3. Definition of CONTRACTOR and OWNER / TPI Involvement

The nature of CONTRACTOR and OWNER involvement is indicated against each activity of
fabrication and testing by means of the letters H, W, SW, R and RA with the following
definitions:

Hold Point (H)


A designated point during or following a specific activity at which inspection or examination
shall not proceed unless the designated parties have witnessed the inspection and/or test.

Witness Point (W)


A designated point during or following an important activity at which inspection or
examination is required in accordance with the relative procedure. Work may proceed through
the designated witness point if the inspector is not present for the previously established
activity.

<DNO Doc. No. + DNO Rev.> Page 4 of 6


Cleaning & Relocating Storage Tank
Inspection Test Plan for Storage Tank & Piping System (ITP)
System

Spot Witness (SW)


A designated point during or following an activity at which spot inspection or spot examination
is required in accordance with the relative procedure. Work may proceed through the
designated witness point if the inspector is not present for the previously established activity.

Review (R)
It is processed through reviewing any results of inspection or test as a method of ensuring that
the inspection or test is performed in accordance with any approved drawing, procedure,
specifications or acceptance criteria. (Certificates).

Review & Approval Point (RA)


It is processed through reviewing and approving any results of inspection, test or procedure as a
method of ensuring that the inspection, test or procedure is performed/will be performed in
accordance with any approved drawing, procedure, specifications or acceptance criteria.

4. Inspection Test Plan


The contractor inspection test Plan is according to below tables.

No. Activity Acceptance Verifying Involved Party


Criteria Doc.
C O
1 PIM Contract Mom H H
2 Raw Material Inspection DWG./ASTM Certificate H R
3 WPS,PQR API 650,ASME H A
Sec.IX
4 Fit up DWG./WPS Fit up Report H SW
5 Welding DWG./API 650 Welding H W
Report
6 NDT API 650 NDT Report H R
7 Test Package DWG/P&I D Test Package H W
8 Internal Cleaning Summary Cured Protocol H W

<DNO Doc. No. + DNO Rev.> Page 5 of 6


Cleaning & Relocating Storage Tank
Inspection Test Plan for Storage Tank & Piping System (ITP)
System

Oil Storage Tank


9 Hydro Static Test Hydro Test Hydro Test H W
Procedure Report
10 Surface Preparation & KUR-PR-INSP-14 Surface H W
Painting & Adhesion Preparation &
Test painting
Report
11 Final Book Final Book H RA
NDT Percentage is 10 % for all welding Joint.
1-RT is defined for Butt Weld Joints .
2-P.T is defined for fillet weld & other joints.

<DNO Doc. No. + DNO Rev.> Page 6 of 6