0% found this document useful (0 votes)
737 views2 pages

Edited - Flange Joint Assembly Checklist

The document is a piping flange inspection checklist used during field inspections. It contains 14 inspection activities to check flanges, gaskets, studs, and bolt torque during flange assembly. Key items include checking flange faces are clean and undamaged, flanges are properly aligned, new gaskets are undamaged, studs are the correct size and material, and bolts are torqued to specified levels in multiple steps. Sign-off is required from the contractor engineer, contractor QC inspector, and client's representative upon completion and conformance.

Uploaded by

vivekkumarenzo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
737 views2 pages

Edited - Flange Joint Assembly Checklist

The document is a piping flange inspection checklist used during field inspections. It contains 14 inspection activities to check flanges, gaskets, studs, and bolt torque during flange assembly. Key items include checking flange faces are clean and undamaged, flanges are properly aligned, new gaskets are undamaged, studs are the correct size and material, and bolts are torqued to specified levels in multiple steps. Sign-off is required from the contractor engineer, contractor QC inspector, and client's representative upon completion and conformance.

Uploaded by

vivekkumarenzo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Flange/Joint Assembly Checklist

Piping Field Inspection Checklist


Company: ___________________________________________
Project: Document No. 201608-TUF-00001
2904-FIC-PIP-0003
FIC Title: WP No.
Location:
Drawing Number Revision Drawing Number Revision

Conforms Comments
No. Inspection Activities
ACCEPT N/A
1 FLANGES
Check both Flange Faces are Clean, Damage Free and that the Gramaphone
1.1
Finish is in Good Condition
Ensure that the Flange Surface comply to Allowable Gasket contact surface
1.2
flatness and defect depth
Are the Flanges Aligned within Tolerance. (Record the Maximum Angular Mis-
1.3
Alignment in the Comments Column)
Are the Flanges parallel within Tolerance. (Record the Maximum Parallel Mis-
1.4
Alignment in the Comments Column)
Confirm the Nut Seating Area on the Flanges is Clean, Smooth and Free of
1.5
Paint.
2 GASKETS AND STUDS
Is the New Gasket Free of Damage, check for defects in the
2.1
Spiral Windings or Scoring of the RTJ Surface
Check that the Studs are in Good Condition and are the Correct Size and
2.2
Material for the Pipe Class.
3 MAKING UP THE FLANGE

3.1 Equipment:

3.2 Model / Serial No:

3.3 Torque Range:

3.4 Calibration Expiry Date:

4 BOLT TORQUE
Confirm approved Anti-seize has been Applied to the Studs and the Nut
4.1
Seating Area.
4.2 Torque Studs at 25%: Nm

4.3 Torque Studs at 50%: Nm

4.4 Torque Studs at 75%: Nm

4.5 Torque Studs at 100%: Nm

4.6 Confirm all Studs 100% tight

Page 1 of 2
Tuffa Products accepts no responsibility for the use of this document. It is the users responsibility to ensure that it is suitable for the application.
Document No. 2904-FIC-PIP-0003 Rev No. 0 1 of 2
Flange/Joint AssemblyChecklist
Piping Field Inspection Checklist

Conforms
No. Inspection Activities Comments
ACCEPT N/A
4.7 Confirm flange tag has been installed and sign off

Contractor Engineer Contractor QC Inspector Clients Representative


Name: Name: Name:

Signature: Signature: Signature:

Date: Date: Date:

Page 2 of 2
Tuffa Products accepts no responsibility for the use of this document. It is the users responsibility to ensure that it is suitable for the application.
Document No. 2904-FIC-PIP-0003 Rev No. 0 2 of 2