Dam Design PDF
Dam Design PDF
Sileshie Mesfin
Operation Type
When we find the slope The following graph has been developed that shows the relation of capacity and
depth.
M=1/0.363 =2.76
The reservoir m is 2.76 and thus it is classified as flood plane, foothill reservoir type (lower end of type II
reservoir). The reservoir is expected to have a considerable drawdown- that is at the beginning of rainy
season the reservoir is nearly empty – in this case According to USBR it is classified as type III and
weighted reservoir type is taken as type III
1. Weighted density
=1135.15
=K is 0 for type three dams so the density of the sediment will not change with time.
So WT is equal to W =1135.15
Trap efficiency
Inflow is 190 Mm3
Capacity inflow method (Brune) is used to calculate the trap efficiency for calculation.
E = 100*0.97**0.19**log (C/I)
Average Net
Annual River reservoir
Sediment inflow Trap Sediment capacity
Discharge, Capacity Discharge, Efficiency, Sediment Cumulative for N
Year Vt (Mm3) , C(Mm3) I (Mm3) C/I 0.19^(Log(C/I)) E Dep. deposition years
0 0 181.094 190 0.953126 1.035232 0.96896 0
5 2.149985 178.944 190 0.941811 1.044188 0.968695 2.08268
10 4.29997 176.794 190 0.930495 1.053331 0.968426 4.164201
15 6.449954 174.644 190 0.919179 1.062668 0.96815 6.244525
20 8.599939 172.4941 190 0.907863 1.072204 0.967869 8.323615
25 10.74992 170.3441 190 0.896548 1.081948 0.967582 10.40143 10.40143 170.6926
30 12.89991 168.1941 190 0.885232 1.091905 0.967288 12.47793
35 15.04989 166.0441 190 0.873916 1.102084 0.966989 14.55308
40 17.19988 163.8941 190 0.862601 1.112492 0.966682 16.62681
45 19.34986 161.7441 190 0.851285 1.123138 0.966369 18.6991
50 21.49985 159.5942 190 0.839969 1.134031 0.966048 20.76989 20.76989 160.3241
55 23.64983 157.4442 190 0.828654 1.145179 0.96572 22.83912
60 25.79982 155.2942 190 0.817338 1.156592 0.965384 24.90674
65 27.9498 153.1442 190 0.806022 1.16828 0.965041 26.9727
70 30.09979 150.9942 190 0.794706 1.180254 0.964689 29.03693
75 32.24977 148.8442 190 0.783391 1.192526 0.964328 31.09937 31.09937 149.9946
80 34.39976 146.6942 190 0.772075 1.205106 0.963959 33.15995
85 36.54974 144.5443 190 0.760759 1.218008 0.96358 35.21861
90 38.69973 142.3943 190 0.749444 1.231244 0.963192 37.27526
95 40.84971 140.2443 190 0.738128 1.244829 0.962793 39.32983
100 42.9997 138.0943 190 0.726812 1.258777 0.962384 41.38224 41.38224 139.7118
Sediment volume after 25 years =10.40143 Mm3
Modified accumulated sediment is prepared by taking the above values by summing the sediment
volume in each year obtained above in trap efficiency and the sediment volume in each elevation.
See the excel for detail. Finally the reservoir area and capacity for different elevation will be as follows.
a. Reservoir Area
b. Reservoir capacity curve is calculated as follows in the following table and graph
reservoir
Water Reservoir capacity
surface Original Original Relative Sediment Accumulated Modified area after after 25
No elevation area capacity Depth depth Ap type III area Sediment volume sediment accumulated 25 years years
[No
] [m] [ha] [Mm3] [m] [m] [Max dept] [ha] [Mm3] [Mm3] [Mm3] [ha] [Mm3]
[1] [2] [3] [4] [5] [6] [7] [8] [9] [10] [11] [3]-[8] [4]-[11]
1 1955 1016.543 253.629
2 1954 988.146 243.606
3 1953 960.177 233.864
4 1952 932.636 224.400
5 1951 905.522 215.209
6 1950 878.837 206.288
7 1949 852.579 197.631
8 1948 826.748 189.234 10.4014314
9 1947 801.346 181.094 71 1 0 0 6.2551E-05 10.2298 10.4013689 801.346 170.692
10 1946 776.371 173.205 70 0.985915 0.000846 0.0125102 0.000369762 10.22974 10.4009991 776.359 162.804
11 1945 751.824 165.564 69 0.971831 0.004157 0.06144229 0.001081099 10.22937 10.399918 751.763 155.164
12 1944 727.705 158.166 68 0.957746 0.010472 0.15477753 0.002256872 10.22829 10.3976611 727.551 147.769
13 1943 704.014 151.008 67 0.943662 0.020068 0.29659686 0.003928989 10.22603 10.3937321 703.717 140.614
14 1942 680.750 144.084 66 0.929577 0.0331 0.48920093 0.006114877 10.2221 10.3876173 680.261 133.696
15 1941 657.914 137.391 65 0.915493 0.049648 0.73377448 0.008822414 10.21599 10.3787948 657.181 127.012
16 1940 635.506 130.923 64 0.901408 0.069739 1.03070828 0.012052472 10.20717 10.3667424 634.476 120.557
17 1939 613.526 124.678 63 0.887324 0.093357 1.37978603 0.015800455 10.19511 10.3509419 612.146 114.327
18 1938 591.974 118.651 62 0.873239 0.120457 1.78030498 0.020057323 10.17931 10.3308846 590.193 108.320
19 1937 570.849 112.837 61 0.859155 0.150962 2.23115967 0.024810314 10.15926 10.3060743 568.618 102.531
20 1936 550.152 107.232 60 0.84507 0.184775 2.73090322 0.030043486 10.13445 10.2760308 547.421 96.956
21 1935 529.882 101.832 59 0.830986 0.221778 3.27779392 0.03573813 10.1044 10.2402927 526.605 91.591
22 1934 510.041 96.632 58 0.816901 0.261836 3.869832 0.041873106 10.06866 10.1984196 506.171 86.433
23 1933 490.627 91.629 57 0.802817 0.304798 4.50478915 0.048425111 10.02679 10.1499944 486.122 81.479
24 1932 471.641 86.817 56 0.788732 0.350499 5.18023299 0.055368903 9.978367 10.0946255 466.461 76.723
25 1931 453.083 82.194 55 0.774648 0.398762 5.89354758 0.062677493 9.922998 10.031948 447.190 72.162
26 1930 434.953 77.753 54 0.760563 0.4494 6.64195093 0.070322306 9.86032 9.96162574 428.311 67.792
27 1929 417.250 73.492 53 0.746479 0.502213 7.4225102 0.078273326 9.789998 9.88335242 409.827 63.609
28 1928 399.975 69.406 52 0.732394 0.556994 8.23215503 0.086499222 9.711725 9.7968532 391.743 59.609
29 1927 383.128 65.491 51 0.71831 0.613527 9.06768936 0.094967457 9.625225 9.70188574 374.060 55.789
30 1926 366.709 61.742 50 0.704225 0.671588 9.92580205 0.103644393 9.530258 9.59824135 356.783 52.143
31 1925 350.717 58.154 49 0.690141 0.730945 10.8030765 0.112495381 9.426614 9.48574596 339.914 48.669
32 1924 335.153 54.725 48 0.676056 0.791361 11.6959996 0.121484845 9.314118 9.36426112 323.457 45.361
33 1923 320.017 51.449 47 0.661972 0.852592 12.6009694 0.130576365 9.192633 9.23368475 307.416 42.216
34 1922 305.309 48.323 46 0.647887 0.914389 13.5143035 0.139732744 9.062057 9.09395201 291.794 39.229
35 1921 291.028 45.341 45 0.633803 0.976498 14.4322452 0.148916081 8.922324 8.94503593 276.596 36.396
36 1920 277.175 42.500 44 0.619718 1.038659 15.350971 0.158087838 8.773408 8.78694809 261.824 33.713
37 1919 263.750 39.795 43 0.605634 1.100611 16.2665966 0.1672089 8.61532 8.61973919 247.484 31.176
38 1918 250.753 37.223 42 0.591549 1.162087 17.1751833 0.176239634 8.448111 8.44349956 233.578 28.779
39 1917 238.183 34.778 41 0.577465 1.222817 18.0727436 0.185139956 8.271872 8.2583596 220.111 26.520
40 1916 226.042 32.457 40 0.56338 1.282528 18.9552476 0.193869379 8.086732 8.06449022 207.086 24.392
41 1915 214.328 30.255 39 0.549296 1.340945 19.8186281 0.202387076 7.892862 7.86210315 194.509 22.393
42 1914 203.042 28.168 38 0.535211 1.39779 20.658787 0.210651936 7.690475 7.65145121 182.383 20.517
43 1913 192.183 26.192 37 0.521127 1.452786 21.4716002 0.21862262 7.479823 7.43282859 170.711 18.759
44 1912 181.752 24.322 36 0.507042 1.505651 22.2529238 0.226257617 7.261201 7.20657097 159.499 17.116
45 1911 171.749 22.555 35 0.492958 1.556104 22.9985997 0.233515306 7.034943 6.97305567 148.751 15.582
46 1910 162.174 20.885 34 0.478873 1.603863 23.7044616 0.240354013 6.801428 6.73270166 138.470 14.153
47 1909 153.027 19.309 33 0.464789 1.648647 24.3663409 0.24673207 6.561074 6.48596959 128.661 12.823
48 1908 144.307 17.823 32 0.450704 1.690172 24.9800731 0.252607886 6.314342 6.2333617 119.327 11.589
49 1907 136.015 16.421 31 0.43662 1.728159 25.5415041 0.257940008 6.061734 5.97542169 110.474 10.446
50 1906 128.151 15.100 30 0.422535 1.762327 26.0464975 0.262687195 5.803794 5.7127345 102.105 9.387
51 1905 120.715 13.856 29 0.408451 1.792399 26.4909414 0.26680849 5.541107 5.44592601 94.224 8.410
52 1904 113.706 12.684 28 0.394366 1.818097 26.8707565 0.270263304 5.274298 5.1756627 86.836 7.508
53 1903 107.125 11.580 27 0.380282 1.83915 27.1819043 0.273011502 5.004035 4.9026512 79.944 6.677
54 1902 100.972 10.539 26 0.366197 1.855286 27.4203961 0.275013494 4.731023 4.62763771 73.552 5.911
55 1901 95.247 9.558 25 0.352113 1.866241 27.5823027 0.276230343 4.45601 4.35140736 67.665 5.207
56 1900 89.950 8.632 24 0.338028 1.871753 27.6637658 0.276623876 4.17978 4.07478349 62.286 4.557
57 1899 85.080 7.757 23 0.323944 1.871567 27.6610093 0.276156813 3.903156 3.79862668 57.419 3.958
58 1898 80.638 6.928 22 0.309859 1.865433 27.5703532 0.274792908 3.626999 3.52383377 53.068 3.404
59 1897 76.624 6.142 21 0.295775 1.85311 27.3882284 0.272497112 3.352206 3.25133666 49.235 2.891
60 1896 73.037 5.394 20 0.28169 1.834366 27.111194 0.269235757 3.079709 2.9821009 45.926 2.412
61 1895 69.878 4.679 19 0.267606 1.808977 26.7359573 0.264976769 2.810473 2.71712413 43.142 1.962
62 1894 60.287 4.028 18 0.253521 1.776732 26.2593964 0.259689917 2.545496 2.45743421 34.027 1.571
63 1893 55.641 3.449 17 0.239437 1.737434 25.6785871 0.253347109 2.285806 2.2040871 29.963 1.245
64 1892 50.950 2.916 16 0.225352 1.6909 24.9908346 0.245922735 2.032459 1.95816437 25.959 0.958
65 1891 46.212 2.430 15 0.211268 1.636966 24.1937123 0.237394099 1.786537 1.72077027 22.018 0.709
66 1890 41.428 1.992 14 0.197183 1.575489 23.2851075 0.227741936 1.549143 1.49302833 18.143 0.499
67 1889 36.599 1.602 13 0.183099 1.506352 22.2632796 0.21695106 1.321401 1.27607727 14.336 0.325
68 1888 31.723 1.260 12 0.169014 1.429466 21.1269323 0.205011193 1.10445 1.07106608 10.596 0.189
69 1887 26.801 0.967 11 0.15493 1.344779 19.8753063 0.191918037 0.899438 0.87914804 6.926 0.088
70 1886 21.834 0.724 10 0.140845 1.252287 18.5083012 0.176641628 0.70752 0.70250642 3.325 0.022
71 1885 16.820 0.531 9 0.126761 1.152036 16.8200243 0.151320682 0.530879 0.53087868 0.000 0.000
72 1884 13.444 0.380 8 0.112676 1.044148 13.4441121 0.119447754 0.379558 0.379558 0.000 0.000
73 1883 10.445 0.260 7 0.098592 0.928836 10.4454388 0.091343861 0.26011 0.26011024 0.000 0.000
74 1882 7.823 0.169 6 0.084507 0.806439 7.82333352 0.067005649 0.168766 0.16876638 0.000 0.000
75 1881 5.578 0.102 5 0.070423 0.677479 5.57779635 0.046433118 0.101761 0.10176073 0.000 0.000
76 1880 3.709 0.055 4 0.056338 0.542752 3.70882725 0.029626267 0.055328 0.05532762 0.000 0.000
77 1879 2.216 0.026 3 0.042254 0.403505 2.21642624 0.016585098 0.025701 0.02570135 0.000 0.000
78 1878 1.101 0.009 2 0.028169 0.26185 1.1005933 0.007309609 0.009116 0.00911625 0.000 0.000
79 1877 0.361 0.002 1 0.014085 0.122002 0.36132845 0.001806642 0.001807 0.00180664 0.000 0.000
80 1876 0.000 0.000 0 0 0 0 0 0 0 0.000 0.000
River Bed Level 1876
Dam Height, H 79
Reservoir New Zero Level, K = Ao/ap 20.832916
Modified
Realtive Sediment Accumulated Modified Sediment Modified
Area, Ao Volume, V Volume, V Depth, D Relative Sediment area, As Sediment Volume, increament, Vs = sediment, Vs accululation Area, Asm Capacity,
Elevation (mamsl) (ha) (MMC) (ha-m) (m) Depth, P Area, ap =K*ap 1/2(El1-El2)*(As1+As2)/100 (ha-m) (ha-m) (ha-m) (ha) (ha-m) Remark
ha 1861.2964
1955 1016.543 253.629 25362.9 79 1.00 0.00 0.00 4.29 1643.16 1857.01 1016.54 23505.89
1954 988.146 243.606 24360.6 78 0.99 0.41 8.58 9.94 1638.87 1847.07 979.57 22513.53
1953 960.177 233.864 23386.4 77 0.97 0.54 11.31 12.28 1628.93 1834.78 948.87 21551.62
1952 932.636 224.4 22440 76 0.96 0.64 13.26 14.03 1616.64 1820.75 919.38 20619.25
1951 905.522 215.209 21520.9 75 0.95 0.71 14.80 15.45 1602.61 1805.30 890.72 19715.60
1950 878.837 206.288 20628.8 74 0.94 0.77 16.10 16.66 1587.16 1788.64 862.74 18840.16
1949 852.579 197.631 19763.1 73 0.92 0.83 17.21 17.70 1570.50 1770.94 835.36 17992.16
1948 826.748 189.234 18923.4 72 0.91 0.87 18.19 18.63 1552.80 1752.31 808.55 17171.09
1947 801.346 181.094 18109.4 71 0.90 0.92 19.06 19.46 1534.17 1732.86 782.28 16376.54
1946 776.371 173.205 17320.5 70 0.89 0.95 19.85 20.20 1514.72 1712.65 756.52 15607.85
1945 751.824 165.564 16556.4 69 0.87 0.99 20.55 20.87 1494.51 1691.78 731.27 14864.62
1944 727.705 158.166 15816.6 68 0.86 1.02 21.20 21.49 1473.64 1670.29 706.51 14146.31
1943 704.014 151.008 15100.8 67 0.85 1.05 21.78 22.05 1452.15 1648.24 682.23 13452.56
1942 680.75 144.084 14408.4 66 0.84 1.07 22.32 22.56 1430.10 1625.68 658.43 12782.72
1941 657.914 137.391 13739.1 65 0.82 1.09 22.80 23.03 1407.54 1602.65 635.11 12136.45
1940 635.506 130.923 13092.3 64 0.81 1.12 23.25 23.46 1384.51 1579.20 612.25 11513.10
1939 613.526 124.678 12467.8 63 0.80 1.14 23.66 23.85 1361.06 1555.35 589.86 10912.45
1938 591.974 118.651 11865.1 62 0.78 1.15 24.04 24.21 1337.21 1531.14 567.94 10333.96
1937 570.849 112.837 11283.7 61 0.77 1.17 24.38 24.54 1313.00 1506.60 546.47 9777.10
1936 550.152 107.232 10723.2 60 0.76 1.19 24.69 24.84 1288.46 1481.76 525.46 9241.44
1935 529.882 101.832 10183.2 59 0.75 1.20 24.98 25.11 1263.62 1456.66 504.90 8726.54
1934 510.041 96.632 9663.2 58 0.73 1.21 25.24 25.35 1238.52 1431.30 484.81 8231.90
1933 490.627 91.629 9162.9 57 0.72 1.22 25.47 25.57 1213.16 1405.73 465.16 7757.17
1932 471.641 86.817 8681.7 56 0.71 1.23 25.68 25.77 1187.59 1379.96 445.97 7301.74
1931 453.083 82.194 8219.4 55 0.70 1.24 25.86 25.94 1161.82 1354.02 427.22 6865.38
1930 434.953 77.753 7775.3 54 0.68 1.25 26.02 26.09 1135.88 1327.93 408.93 6447.37
1929 417.25 73.492 7349.2 53 0.67 1.26 26.17 26.23 1109.79 1301.70 391.08 6047.50
1928 399.975 69.406 6940.6 52 0.66 1.26 26.29 26.34 1083.56 1275.36 373.69 5665.24
1927 383.128 65.491 6549.1 51 0.65 1.27 26.39 26.43 1057.22 1248.94 356.74 5300.16
1926 366.709 61.742 6174.2 50 0.63 1.27 26.47 26.50 1030.80 1222.43 340.24 4951.77
1925 350.717 58.154 5815.4 49 0.62 1.27 26.53 26.56 1004.29 1195.88 324.18 4619.52
1924 335.153 54.725 5472.5 48 0.61 1.28 26.58 26.59 977.74 1169.29 308.58 4303.21
1923 320.017 51.449 5144.9 47 0.59 1.28 26.60 26.61 951.15 1142.68 293.41 4002.22
1922 305.309 48.323 4832.3 46 0.58 1.28 26.61 26.61 924.54 1116.07 278.69 3716.23
1921 291.028 45.341 4534.1 45 0.57 1.28 26.61 26.59 897.93 1089.47 264.42 3444.63
1920 277.175 42.5 4250 44 0.56 1.28 26.58 26.56 871.33 1062.91 250.59 3187.09
1919 263.75 39.795 3979.5 43 0.54 1.27 26.54 26.51 844.77 1036.40 237.21 2943.10
1918 250.753 37.223 3722.3 42 0.53 1.27 26.48 26.45 818.26 1009.95 224.27 2712.35
1917 238.183 34.778 3477.8 41 0.52 1.27 26.41 26.36 791.81 983.59 211.77 2494.21
1916 226.042 32.457 3245.7 40 0.51 1.26 26.32 26.27 765.45 957.33 199.72 2288.37
1915 214.328 30.255 3025.5 39 0.49 1.26 26.21 26.15 739.19 931.17 188.12 2094.33
1914 203.042 28.168 2816.8 38 0.48 1.25 26.09 26.02 713.03 905.15 176.95 1911.65
1913 192.397 26.245 2624.5 37 0.47 1.25 25.95 25.87 687.01 879.28 166.45 1745.22
1912 181.752 24.322 2432.2 36 0.46 1.24 25.80 25.71 661.14 853.57 155.96 1578.63
1911 171.749 22.555 2255.5 35 0.44 1.23 25.63 25.53 635.43 828.04 146.12 1427.46
1910 162.174 20.89 2088.5 34.00 0.43 1.22 25.44 25.34 609.90 802.70 136.73 1285.80
1909 153.027 19.309 1930.9 33 0.42 1.21 25.24 25.13 584.56 777.57 127.79 1153.33
1908 144.307 17.823 1782.3 32 0.41 1.20 25.02 24.90 559.43 752.67 119.29 1029.63
1907 136.015 16.421 1642.1 31 0.39 1.19 24.78 24.66 534.53 728.01 111.23 914.09
1906 128.151 15.1 1510 30 0.38 1.18 24.53 24.39 509.87 703.62 103.62 806.38
1905 120.715 13.856 1385.6 29 0.37 1.16 24.26 24.12 485.48 679.50 96.45 706.10
1904 113.706 12.684 1268.4 28 0.35 1.15 23.97 23.82 461.36 655.68 89.73 612.72
1903 107.125 11.58 1158 27 0.34 1.14 23.67 23.51 437.54 632.17 83.46 525.83
1902 100.972 10.539 1053.9 26 0.33 1.12 23.35 23.18 414.03 609.00 77.62 444.90
1901 95.247 9.558 955.8 25 0.32 1.10 23.01 22.83 390.86 586.17 72.24 369.63
1900 89.95 8.632 863.2 24 0.30 1.09 22.65 22.46 368.03 563.71 67.30 299.49
1899 85.08 7.757 775.7 23 0.29 1.07 22.27 22.07 345.57 541.64 62.81 234.06
1898 80.638 6.93 692.8 22.00 0.28 1.05 21.87 21.66 323.50 519.98 58.77 172.82
1897 76.624 6.142 614.2 21 0.27 1.03 21.45 21.23 301.84 498.75 55.17 115.45
1896 73.037 5.394 539.4 20 0.25 1.01 21.01 20.78 280.61 477.98 52.03 61.42
1895 69.878 4.679 467.9 19 0.24 0.99 20.54 20.30 259.84 457.68 49.33 10.22 100yr
1894 60.287 4.028 402.8 18.00 0.23 0.96 20.06 19.80 239.54 437.88 40.23 -35.08
1893 55.641 3.449 344.9 17 0.22 0.94 19.54 19.27 219.74 418.60 36.10 -73.70
1892 50.95 2.916 291.6 16 0.20 0.91 19.00 18.72 200.46 399.88 31.95 -108.28
1891 46.212 2.43 243 15 0.19 0.88 18.44 18.14 181.74 381.75 27.78 -138.75
1890 41.428 1.992 199.2 14 0.18 0.86 17.84 17.52 163.61 364.23 23.59 -165.03
1889 36.599 1.602 160.2 13 0.16 0.83 17.21 16.87 146.09 347.35 19.39 -187.15
1888 31.723 1.26 126 12.00 0.15 0.79 16.54 16.19 129.21 331.16 15.18 -205.16 50 yr
1887 26.801 0.967 96.7 11 0.14 0.76 15.84 15.46 113.02 315.70 10.96 -219.00
1886 21.834 0.724 72.4 10 0.13 0.72 15.09 14.69 97.56 301.01 6.74 -228.61
1885 16.82 0.53 53.1 9.00 0.11 0.69 14.29 13.87 82.87 287.14 2.53 -234.04
1884 13.444 0.38 38 8 0.10 0.65 13.44 12.99 69.00 274.15 0.00 -236.15
1883 10.445 0.26 26 7 0.09 0.60 12.53 12.04 56.01 262.11 -2.09 -236.11
1882 7.823 0.169 16.9 6 0.08 0.55 11.54 11.00 43.97 251.11 -3.72 -234.21 25 yr
1881 5.578 0.102 10.2 5 0.06 0.50 10.46 9.86 32.97 241.25 -4.88 -231.05
1880 3.709 0.055 5.5 4 0.05 0.44 9.26 8.58 23.11 232.67 -5.55 -227.17
1879 2.216 0.026 2.6 3 0.04 0.38 7.90 7.11 14.53 225.56 -5.69 -222.96
1878 1.101 0.009 0.9 2 0.03 0.30 6.31 5.29 7.42 220.28 -5.21 -219.38
1877 0.361 0.002 0.2 1 0.01 0.21 4.27 2.14 2.14 218.14 -3.91 -217.94
1876 0 0 0 0 0.00 0.00 0.00 0.00 0.00 218.14 0.00 -218.14
1. INTRODUCION
Godebe micro earth dam study is carried out at small scale irrigation level for the purpose of self-food
sufficiency and to increase per house hold income of the local farmers.
The dam can impound around 86.48ha.m of water to irrigate a total command area of 68ha at
reservoir full supply level (3198.00masl). The impound water can inundate around 13.37ha of land.
The project has a number of hydraulic structures to be constructed for its feasibility.
The headwork site is found at about 5Km north east of Mehal Meda town (woreda capital city).
Hydrology
Catchment Features
The catchment has a shape of fern leaf type with a total size of about 4.91km2. The whole catchment
area geology is made up of volcanic rocks. The dominant soil types of the catchment are silty loam and
clay loam.
The main stream has a total length of 5.9km and an overage slope of 2.37%. The estimated runoff
coefficients of the catchment area are 0.37 and 0.52 with and without catchment treatment
respectively
There is no recorded stream discharge of the project area. As the study team information, there is no
river flow. The nearby station for the proposed project site is Mehale Meda meteorological station,
which has an air distance of about 27km. From this station 20 years of monthly rain fall, 10 years of
heaviest rainfall and certain years’ of temperature, relative humidity, wind speed and sunshine hours.
Year Jan Feb March April May Jun July Aug Sept Oct Nov Dec MAX
1992 15.0 4.0 5.8 51.2 9.0 5.7 33.8 34.6 14.0 27.0 5.0 5.0 51.2
1994 0.0 0.0 20.8 14.1 3.9 5.7 28.9 50.1 25.5 3.0 4.1 0.0 50.1
1995 0.0 10.6 12.7 10.3 20.0 9.0 46.4 28.1 16.0 6.5 0.0 9.3 46.4
1996 12.7 0.0 25.0 3.2 15.8 19.5 40.3 42.5 8.7 1.7 7.8 0.0 42.5
1997 15.7 0.0 6.2 9.8 5.0 17.3 43.0 20.5 16.1 10.9 10.2 0.0 43.0
1998 8.6 5.2 21.1 39.5 23.8 5.2 52.8 54.8 13.2 8.3 0.0 0.0 54.8
1999 11.6 0.0 13.6 15.3 9.7 14.6 62.3 24.4 17.3 22.5 0.0 1.2 62.3
2000 0.0 0.0 3.9 28.9 13.2 18.7 47.0 39.2 23.9 5.7 6.3 6.8 47.0
2001 0.0 9.2 19.0 14.0 23.4 9.2 68.5 47.3 12.3 1.8 0.0 1.9 68.5
2002 14.6 13.7 30.4 14.6 3.9 4.9 53.2 35.1 5.4 3.4 0.0 9.8 53.2
Lower outlier
YlY Kn*Sy
kn -Depends on the number of data, form Applied Hydrology, the value is 2.036 for 10 data.
Sy- Is the standard deviation and is given by the equation below:
n 1 n1
=0.067
Then, Yl1.712.036
*0.0671.57
Minimum rainfall X 10Yl
101.57 34.153mm
The lower limit for the series is 34.153mm, but there is no data in our record less than this value.
Hence there is no lower outlier in our record.
Higher Outlier
YmY Kn*Sy
=1.71+2.036*0.067=1.846
X 10Ym
=101.846 = 70.212mm,
All the data in the series is less than the higher value and hence, there is no outlier data.
The main water potential for this project is the surface runoff during the rainy season. To calculate the
Catchment yield, the following equation is used:
Catchment yield, Y R*A*C
Where R= Dependable rainfall (mm), for this project 80% dependable is assumed
A= Catchment area= 4.91Km2
C= Runoff coefficient= 0.56 (as calculated by the Catchment expert, with out the treatment)
As experience shows that, the run off coefficient will be reduced by 50% after catchment treatment,
i.e., it becomes 0.28 when the catchment is treated as planned.
The catchment yield is then calculated using the treated condition as follows:
Y= (755.7/1000)*4.91*1000*1000*0.28
= 1,038,936.36m3
= 103.89ha.m
Design Rainfall
The table above shows the daily heaviest rainfall at Mehale Meda Metrological station.
Using this data, the design point rainfall is calculated based on Gamble’s extreme value method.
Rf Rn1 *k
Where: R- average of all values of annual heaviest rainfall, 51.9mm
K- is a constant depends on the data number,
n1- Standard deviation, 8.296
K YtYn
Sn
For 10 data size, Yn=0.4952, and Sn= 0.9496 (from gamble’s extreme distribution table)
Yt ln(ln(
T /(t 1))
T- The return period, 100years
Yt = 4.6
Using the above values, the value of k is 4.323
There fore the design point rainfall for 100 years return period is calculated as:
Rf = 51.9+8.296*4.323 = 87.76mm
Height Time of
Elevation Difference Length concentration
Sr.No. (m) (m) (m) (hr) Remark
1 3380 0 0 Remote point
2 3360 20 827.371 0.240356
3 3300 60 907.000 0.175088
4 3260 40 630.237 0.134413
5 3240 20 918.822 0.271296
6 3200 40 863.157 0.193285
7 3180 20 902.283 0.265664
8 3170 10 305.890 0.099457 Outlet point
Sum 1.379561
The time of concentration is around 1.4hr. Therefore, the time increment is half hour (0.5hr) and the
arrangements are shown below.
Q I 0.2 * S2
I 0.8*S
I 0.2*28.22 I 5.644
2 2
I 0.8*28.22 I 22.576
Using the above discharge values, the expected maximum flood is computed and tabulated on the
table below.
Table 0-9: Synthesis of Complex Hydrograph
Time H1 H2 H3 H4 H5 H6 HTotal
(hr)
0.000 0.000 0.000
0.500 0.000 0.000 0.000
1.000 0.000 0.012 0.000 0.012
1.100 0.000 0.014 0.163 0.177
1.500 0.000 0.024 0.813 0.000 0.837
1.600 0.000 0.027 0.975 1.759 2.761
2.000 0.000 0.021 1.626 8.794 0.000 10.440
2.100 0.000 0.019 1.788 10.552 0.650 13.009
2.500 0.000 0.013 1.386 17.587 3.249 0.000 22.235
2.600 0.000 0.012 1.286 19.346 3.898 0.244 24.786
2.880 0.000 0.007 1.005 16.303 5.718 0.927 23.960
3.000 0.006 0.884 14.998 6.497 1.220 23.605
3.100 0.004 0.784 13.912 7.147 1.464 23.310
3.380 0.000 0.502 10.868 6.023 2.147 19.541
3.500 0.382 9.564 5.541 2.440 17.927
3.600 0.281 8.477 5.140 2.684 16.582
3.880 0.000 5.434 4.015 2.262 11.711
4.000 4.130 3.533 1.330 8.993
4.380 0.000 2.008 0.963 2.971
4.880 0.000 0.482 0.482
5.000 0.366 0.366
5.380 0.000 0.000
Different methods can be utilized to obtain water level – storage capacity and water level –surface
water area curves from the contour map prepared at the reservoir site. The end –area method is used
to calculate as below.
V= h/2 (Ao + 2 (A1 +A2 +A3 +.... An-1) +An)
Partial Cumm.
Cumulative Partial Partial Cum Area Volume Volume
Sr. No. Contour Area (m2) Area (m2) Area (ha.) (ha) (ha.m) (ha.m)
1 3179 0.00 0.00 0.00 0.00 0.00 0.00
2 3180 500.02 500.02 0.05 0.05 0.03 0.01
3 3181 2788.36 2288.34 0.23 0.28 0.28 0.16
4 3182 5246.02 2457.66 0.25 0.52 0.40 0.57
5 3183 9346.17 4100.15 0.41 0.93 0.73 1.30
6 3184 13210.54 3864.37 0.39 1.32 1.13 2.42
7 3185 18051.48 4840.94 0.48 1.81 1.56 3.99
8 3186 23561.57 5510.09 0.55 2.36 2.08 6.07
9 3187 29801.46 6239.89 0.62 2.98 2.67 8.74
10 3188 35661.43 5859.97 0.59 3.57 3.27 12.01
11 3189 42440.20 6778.77 0.68 4.24 3.91 15.91
12 3190 49848.12 7407.92 0.74 4.98 4.61 20.53
13 3191 58096.01 8247.89 0.82 5.81 5.40 25.93
14 3192 66167.86 8071.85 0.81 6.62 6.21 32.14
15 3193 73887.32 7719.46 0.77 7.39 7.00 39.14
16 3194 82169.87 8282.55 0.83 8.22 7.80 46.94
17 3195 90205.74 8035.87 0.80 9.02 8.62 55.56
18 3196 98554.75 8349.01 0.83 9.86 9.44 65.00
19 3197 107430.00 8875.25 0.89 10.74 10.30 75.30
20 3198 116260.09 8830.09 0.88 11.63 11.18 86.48
21 3199 124931.74 8671.65 0.87 12.49 12.06 98.54
22 3200 133703.42 8771.68 0.88 13.37 12.93 111.48
The maximum capacity of the dam is 111.48ha.m and the catchment yield after treating the
catchment is 105.45ha.m. There fore, it is better to fix the dam height with the catchment yield, i.e.
by 105.45ha.m. It can be possible to take the dam volume of 86.48ha.m at elevation of 3198m.a.s.l
(i.e. 2m is left for free board; and elevation of FRL will be fixed at 3198m.a.s.l.).
Sedimentation
The incoming sediment is not totally deposited in the reservoir; therefore to allocate the dead storage
volume from the total volume of the reservoir, estimation of the trapped sediment by the reservoir is
necessary.
The quantity of sediment, which would be trapped in the reservoir, has been computed using the well-
known Brune’s curves and the reduced capacities due to sediment accumulation in the years of
operation are shown in the table below.
According to Borland and Miller (1958), reservoirs are classified according to their shape and
configuration as Lake, Floodplain-foothill, Hill and Gorge.
Where M: is the ratio of (abscissa of the graph is the relative depth which is the ratio of the height
above the stream bed level at which sediment deposition is desired to the total height of the dam at
full supply level and the ordinate represents the sediment area at the desired relative depth p above
the stream bed by a newly introduced dimensionless relative area Ap).
The reservoir is Floodplain -foothill type (I.e. type II) as shown on the above analysis.
The empirical Area reduction method for the distribution of the deposited sediment is expressed as:
Ap cpm(1P)n
P=h/H= relative depth of the reservoir,
h= the calculated depth of reservoir measured from the bottom,
H= the maximum reservoir depth at the dam wall, and
c, m, n= dimensionless coefficients for the four standard reservoir types and given on Table 2-
13 below, and is 2.324,0.5 and 0.4 respectively.
Using Brune (1953) method the average trap efficiency is determined as shown on the Table 2-14
below. The trap efficiency empirically given by:
0.19log(C/ I )
E100*0.97
Table 0-13: Trap efficiency of the reservoir and cumulative sediment deposition.
From the above table analysis, the volume of sediment accumulated at the end of 20 years is
21.80ha.m. This volume of sediment rises to 49.79ha.m for 50 years of dam service. Hence, to
increase the life of the dam, the catchment should be treated to minimize the incoming sediments.
Fixation of the new zero levels are made using empirical area reduction method of the sediment
distribution pattern for the sediment trapped in 20 and 50 years.
The empirical Area reduction method is expressed as
Ap CPm(1P)n
Where: AP= Dimensionless relative sediment area
P= Dimensionless relative depth
c, m, n,= Dimensionless constant determined by the type of the reservoir
So as to use the reservoir water efficiently as discussed earlier initially the dead storage is allocated for
the sediment trapped in 20 years and raises to the volume of the sediment trapped in 50 years by
providing submerged front entrance intake tower.
In this case the last three factors are considered to fix the useful life of the dam, since those factors
are the critical factors to determine the life of the dam.
As discussed earlier, the 1st MDDL and the 2nd MDDL is filled by the sediment after 20 and 50 years
respectively, if the catchment is untreated. But if the catchment is treated, the expected filling time of
MDDL.’S by the sediment may be longer.
Hence, considering quality of workmanship during catchment treatment and risk due to the incoming
sediment useful life of the project which is taken here as 30 years for the finical analysis of the project.
The design yield (i.e. 80% probability of exceedence) from the catchment for reservoir planning is
determined using rainfall data of Mehale Meda meteorological station by rainfall-runoff relation ship.
QC* A*PMD
Where Q = 80% dependable yield (monthly)
C= Runoff coefficient = 0.28
A= Catchment area = 4.91km2
PMD = monthly 80% dependable Rainfall
PMD Pm *PDA
PA
Pm= Monthly Rain fall pattern of each particular year T
PA= Annual Rain fall of year T
PDA= 80% Annual dependable rainfall= 755.7mm.
Q = 0.28*4.91*106 m2 *(Pm*755.7*10 -3m)/PA
=1,038,936.36m3
=103.89 Pm/PA ha.m
Using this equation the yield is calculated for each month for 20 years and shown in the reservoir
operation table.
1. Evaporation loss
The evaporation loss from the reservoir water is estimated using U.S. Geological survey method as
shown below:
E (4.57*T 43.3) /1200
Where: E= monthly evaporation loss in m;
T= mean annual temperature (0c) (Mehale Meda station)
The irrigation demand using penman month method is calculated for 12-hour irrigation and the result is
shown in the table below
Table 0-15: Irrigation demand
Month Dec. Jan Feb Mar Apr May Jun Jul Aug Sept Oct Nov
Demand
(l/s.ha) 0.70 0.75 0.80 0.80 0.41 0.38 0.00 0.35 0.58 0.60 0.46 0.55
NIR Demand
0.00
2169.11
1272.00
1915.33
1709.56
1202.67
499.33
502.67
1414.89
1197.56
998.89
1170.67
(m3/ha/mont
h)
To interpolate the area during reservoir operation, the following equation is developed.
The reservoir operation is carried out with the assumption that the operation begins when the reservoir
is full. The reservoir simulation shows that, this micro-earth dam at 3198masl FRL and 3179 masl
Riverbed can command 68ha of land for 200% cropping intensity with 80% success.
Hence, this project is planned for 68ha Command, if the dead storage level is at
3184.0masl and for 44ha command area if the dead storage level is 3190.5masl.
The volume of water that flows over the spillway depends on the type of the control device. For this
project, a simple broad crested weir is adapted. The over flow of water at 0.20m head interval is given
in Table 2-17.
The general equation of the discharge over the broad crested weir is
QC*L*H3/ 2
Where Q = Discharge over the Spillway
C= Coeff. Of discharge = 1.70
L- Crest length
4. Elevation Vs
2S Q data
t
S is the storage volume of the reservoir and Δt is the time interval between inflows (I1 and I2) or
outflows (Q1 and Q2), which is fixed by accounting the maximum inflow flood not to miss. Therefore Δt
is taken 0.20times the rise of the inflow time,
As shown in the above table, the routed peak flood is 10.543m3/s after 3.9hr the start of the flood and
the maximum head corresponding to this flood is 0.842m.
As shown in the above table, the routed peak flood is 7.575m3/s after 3.9hr the start of the flood and
the maximum head corresponding to this flood is 0.92m.
Considering safety on one hand and economical construction of the spillway on the other side (i.e. the
spillway is aligned on widely jointed vesicular basalt and it is very low workability by manpower) adapt
spillway crest length of 6.0m.
Table Abrajit M.E.D Irrigation Project Reservoir operation at 2420.00 m a.s.l Maximum draw down level (MDDL)
year -1990
Year- 1991
Year - 1993
Year – 1995
Year – 1996
Initial Rain 85% Evap. Final
Month storage fall Dependable Reser.area Evap.rate Rate Irr.Demand Irr.Demand Live stock Deficit Available stor. Surplus
(ha.m) (mm) Inflow (ha.m) (ha) (m) (ha.m) (m^3/ha) (ha.m) Demand(ha.m) (ha.m) volume(ha.m) (ha.m) (ha.m)
Dec. 93.27050829 6.72 0.889114162 23.436546 0.092 2.156162 988.6 9.58942 0.062 0 82.35204018 82.35204 0
Jan. 82.35204018 0.22 0.029107904 21.903336 0.094 2.058914 1955.6 18.96932 0.062 0 61.29091446 61.29091 0
Feb. 61.29091446 1.53 0.202432242 18.794507 0.101 1.898245 2721.1 26.39467 0.062 0 33.13843151 33.13843 0
Mar. 33.13843151 48.47 6.41300051 14.216022 0.106 1.506898 2590.4 25.12688 0.062 0 12.85565369 12.85565 0
Apr. 12.85565369 44.82 5.930073919 10.442769 0.107 1.117376 1292.8 12.54016 0.062 0 5.066191379 5.066191 0
May 5.066191379 148.7 19.67429701 8.8203512 0.106 0.934957 173 1.6781 0.062 0 22.06543115 22.06543 0
Jun. 22.06543115 80.74 10.68260081 12.222587 0.102 1.246704 407.4 3.95178 0.062 0 27.48754808 27.48755 0
Jul. 27.48754808 226.72 29.99701827 13.216019 0.095 1.255522 0 0 0.062 0 56.16704455 56.16704 0
Aug. 56.16704455 266.96 35.32111855 18.002447 0.095 1.710232 532.5 5.16525 0.062 0 84.55068063 84.55068 0
Sept. 84.55068063 119.72 15.83999218 22.215966 0.095 2.110517 16.3 0.15811 0.062 0 98.06004608 98.06005 0
Oct. 98.06004608 42.63 5.640317965 24.094631 0.095 2.28899 545.5 5.29135 0.062 0 96.0580241 96.05802 0
Nov. 96.0580241 51.47 6.809926475 23.820571 0.093 2.215313 487.9 4.73263 0.062 0 95.85800748 95.85801 0
Total 1038.7 137.429
Year – 1997
Year – 1999
Year – 2001
Year- 1991
Year - 1993
Year - 1995
Year - 1997
Year - 1999
Year - 2001
Stream flow is an important factor in the irrigation project in two aspects, one to determine the design
flow through the peak flow analysis and secondly to determine dependable flow that required to compute
the amount of available water to deliver to the irrigated field and help to fix the size of the irrigation.
The directorate of Hydrology in the ministry of Water, Irrigation and Electricity is responsible for
collecting, processing, quality assurance and dissemination of stream flow data in Ethiopia. Currently,
there about 570 operational stream flow gauging stations. However, they are not evenly distributed and
also not cover most of the streams in the country. In addition, expanding the stream flow gauging stations
are to expense and technical complexity associated with stream flow gauging compared to rainfall
measurement, therefore, computation of the stream flow using rainfall-runoff methods are preferred.
Design Flood
Design flood is the flood magnitude, which is expected to occur with a certain return period during the
design period of a structure. The selection of the return period is genearly based on saftey, econmy, size
and category of the scheme, and it should be grater than the design period of the structures. With the
national and international expriance, the design flood criteria and the methods of flood estimation are
recommended in this guideline.
Using gauged stream flow
Although they are not evenly distributed over the spatial variability of the country, there are about 570
stream flow gauging stations that have flow data since 1960’s. Therefore, one can use these gauged flow
data for the computation of design flow if the target location fitted with the point of the gauging stations
or if it is possibly to transfer with homogenous region. The stream flow data has to test for its trend and
stationary also. In general before we use the observed stream flow data to compute design flood, it has to
test for trend and define its homogenous region.
A steady increase or decrease of the time series characteristics is known as trend. Natural and man-made
changes like deforestation, urbanization, large scale landslide, large changes in watershed conditions are
the possible causes for the introduction of trend in stream flow time series data. Test for the presence of
trend can be done with Turning point test and Kendal’s Rank-Correlation test.
If a value, named as Xi either greater than both preceding and succeeding values or less than both, turning
point occurred. The procedure is outlined as
III. Expected number of turning points is E(P) 2(N 2) , where N is the total number of data
3
IV. Variance of P is Var (P) (16N 29)
90
V. Expressing P in standard normal form Z
{P E(P)}
{Var(P)}1/ 2
VI. Test it at 5% level of significance, and if Z is less than ±1.96, there is no any trend on the data set.
Homogeneous region
There is significance research gap in order to delineate the hydrological homogenous regions in Ethiopia.
Most of the researches limited with flow regimes defining and catchment similarity characterizations,
which not fully support data transferring from gauging stations to ungauged catchments. Therefore in high
limited conditions, even if we can’t get sufficient rainfall data to use rainfall-runoff relations, it is
suggested to use generalized data transfer equation of Admasu Gebeyehu (1986) for Ethiopian basins.
Qu Qg Au / Ag 0.7
Where: Qu = mean annual daily maximum flow at ungauged site (m3/s), Au= ungauged catchment area
(km2) Qg = mean annual daily maximum flow at gauged site (m3/s), Ag = gauged catchment area (km2),
Once the daily stream flow data access for the gauge station and transfers to the target ungauged
catchment, the procedures of frequency analysis based on annual maximum series followed as stated in
rainfall analysis section.
Information required for design or evaluation and where that information is needed. For
example, if the project requires designing a culvert, the rational method, which computes peak
flow only, may be adequate. However, if the project is affected by or will affect behavior of a
detention or retention pond, a runoff hydrograph will be required for the evaluation.
Data available to develop the required hydrologic information. For example, the designer
must determine if flow records are available from a stream gauge at or near the location of
interest. If not, frequency analysis to find the design flow is not possible, nor is proper calibration
of a conceptual model that will compute a hydrograph.
Conditions in the watershed that may limit applicability of alternative models. If ponds,
lakes, and depressions in the watershed will affect runoff by storing water, the rational equation
will not be appropriate, as it does not simulate behavior of these features.
The following methods can be used in determining peak flood magnitudes for design of irrigation head
works and infrastructures in Ethiopia. The omission of other flow estimation methods from this manual
does not necessarily disqualify their use. The methods to be used and the circumstances for their use are
listed below in Table 5.1
Rational Catchment area, flow length, average slope, Excel and GIS
0.5 Urban
Method catchment characteristics, rainfall intensity combination
QP 0.00278
CIA (5.1)
The run off coefficient (C) in the rational equation can be expressed in two ways, one as scientific
parameter that expressing the abstractions (infiltration, interception, detention storage, etc) and
diffusion, the tendency for a hydrograph to spread in time and attenuate in peak as it moves
downstream. In other way, it expressed as empirical parameter that best quantified by the art of
watershed observation. In both perspectives runoff coefficient can be determined from the catchment
characteristics that consider the land use/cover, slope and soil cover of the catchment area that evaluated
in a number of hydrological researches for the long year use of rational methods. Therefore, the runoff
coefficient for different land use/cover, slope ranges, and soil cover recommend as presented below in the
table.
< 3.5% Flat 0.05 Well drained soil e.g. sand and 0.05 Dense forest/thick bush 0.05
gravel
3.5% - 10% Soft to 0.1 Fair drained soil e.g. sand and 0.1 Sparse forest/dense 0.1
moderate gravel with fines grass
10% - 25% Rolling 0.15 Poorly drained soil e.g. silt 0.15 Grassland/scrub 0.15
25% - 45% Hilly 0.2 Impervious soil e.g. clay, organic 0.25 Cultivation 0.2
silts and clay
C= Cs+Cp+Cv
Residential (0.5 hectare lots or more) 0.30-0.45 Apartment dwelling areas 0.50-0.70
Source: Chow, 1964, p. 21-38; HEC No. 19, 1984, ASCE, 1996, p. 590,
In addition to the catchment characteristics the runoff coefficient is affected by the return period. The
return period less than 25 year hasn’t significant change on the runoff coefficient, but return period 25
year and above has effect on the runoff coefficient that can be expressed with the multiplier presented in
the table.
There is a chance runoff coefficient (C) can be more than 1.00 if it multiply by the multiplier. But it has not
been more than 1.00. Therefore a modification equation proposed by Chow (1964) and Singh (1988)
applied to adjust the value of runoff coefficient.
C C100 Tr
x
(5.2)
100
Where Tr is return period in years, C100 is C for the 100 year event and x is equal 0.075
Many watersheds are not of a single land treatment therefore an area-weighted composite C has to
compute for a watershed spatially distributed by subareas.
C A
n
i i
Ccomp i1
(5.3)
Ai
n
i1
Where the watershed has n subareas, Ci and Ai are runoff coefficient and area of subarea.
As discus in chapter 4, the rainfall intensity of a catchment computed based on the time of concentration
of a catchment. It can be computed based on the maximum rainfall for the different return periods. Here
the major assignment is computing the time of concentration for the given catchment.
Time of concentration (tc) is the time required for an entire watershed to contribute to runoff at the
point of interest for hydraulic design; this time is calculated as the time for runoff to flow from the
most hydraulically remote point of the drainage area to the point under investigation. Travel time and
tc are functions of length and velocity for a particular watercourse. A long but steep flow path with a
high velocity may actually have a shorter travel time than a short but relatively flat flow path. There
may be multiple paths to consider in determining the longest travel time. The designer must identify
the flow path along which the longest travel time is likely to occur.
Roussel et al. 2005 conclude that, in the Kerby-Kirpich approach, for estimating watershed time of
concentration is preferable. The Kerby-Kirpich approach requires comparatively few input
parameters, is straightforward to apply, and produces readily interpretable results. The Kerby-Kirpich
approach produces time of concentration by adding the overland flow time (Kerby) and the channel
flow time (Kirpich):
For small watersheds where overland flow is an important component of overall travel time, the
Kerby method can be used. The Kerby equation is
Tov KLN0.467S0.235 (5.5)
Where: Tov = overland flow time of concentration, in minutes; L = the overland-flow length, in meters;
K = units conversion coefficient, K = 1.44 for SI units; N = a dimensionless retardance coefficient;
S = the slope of terrain conveying the overland flow
Poor grass, cultivated row crops, 0.20 Dense grass, coniferous forest, 0.80
Where: Tch = Chanel flow time of concentration, in minutes L = the overland-flow length, in meters;
If it is determined that a low slope condition or a transitional slope condition exists, the user should
consider using an adjusted slope in calculating the time of concentration. See Time of Concentration.
Example
This example is taken from one of the small scale irrigation project at Bench Maji Zone SNNPR.
The Analysis for peak discharge cross drainage point (Shewu_DC_L1) on the main canal
The drainage area = 21ha
The main flow length = 641.39m
Upstream Elevation = 1419m asl Computation of Time of Concentration
Downstream Elevation = 1368m asl
Soil Hydrological Group = B Slope = (upstream elevation – Downstream
Land use condition = more 60% cultivated elevation)/flow length = (1419-1368)/641.39 = 0.08
Area
For over land flow use the Kerby Method with N= 0, 2
for cultivated land and K= 1.44 for SI unit
Runoff coefficient
For catchment slope 8% CT = 0.1; For ‘B’ hydrological
soil group Cs = 0.1; for cultivated Cv =0.2
C= CT +CS+CV = 0.1+0.1+0.2 = 0.4
Rainfall Intensity
Peak discharge
Qp = 0.00278CIA = 0.00278*0.4*(153.05mm/hr)*(21ha)
= 3.574 m3/sec
S 2541001
SCS-CN Method
(5.
The SCS method is widely used for estimating CN
floods on small to medium-sized ungaged
drainage basins around the world. The method The land use/cover and the soil in the catchment has
was developed based on 24-hr rainfall runoff major role in selecting the curve number values of the
data in USA. In its derivation it is assumed that no watershed or the sub watershed area. Land use/cover
runoff occurs until rainfall equals an initial of the catchment area refers all the cover types,
abstraction (that is losses before runoff begins) Ia, including agricultural and nonagricultural uses,
and also satisfies cumulative infiltration F (the vegetation’s, water surfaces, roads, roofs, etc. Similarly,
actual retention before runoff begins) or water soil properties influence the relationship between
retained in the drainage basin, excluding Ia. The rainfall and runoff by affecting the rate of infiltration.
potential retention before runoff begins (S) is the The SCS has divided soils into four hydrologic soil
value that (F + Ia) would reach in a very long groups based on infiltration rates (Groups A, B, C, and
storm. The SCS runoff equation is therefore a D) (Table 5.6). The experiment for the determination of
method of estimating direct runoff from 24-hour runoff curve number is also considering the effects of
or daily storm rainfall. The equation is: land-treatment measure in cultivated land use. It
2
Q PIa includes mechanical practices such as contouring or
PIa S (5.7)
terracing and management practices such as rotation of
crops. Therefore, the runoff factor of SCS method,
called Curve Number (CN) has to determine with the
Where: Q = accumulated direct runoff, mm P combination all aspects as describe here. The values
= accumulated rainfall (potential also presented in successive tables below (Table 5.7,
maximum runoff), mm; Ia = initial 5.8, 5.9, and 5.10).
abstraction including surface storage,
interception, and infiltration prior to
runoff, mm; S = potential maximum
The curve number values give in the tables are based on
retention, mm.
an average antecedent moisture condition, i.e., soils
that are neither very wet nor very dry when the design
storm begins. Curve numbers shall be selected only
The relationship between Ia and S was developed after a field inspection of the catchment area and a
from experimental catchment area data. It review of cover type and soil maps. Table 5.11 gives the
removes the necessity for estimating Ia in the SCS antecedent conditions for the three classifications and
runoff equation as Ia = 0.2S, and if we substituting the relations below will help to convert the normal
it in the above equation, the SCS rainfall-runoff curve number to wet and dry curve numbers.
equation become.
CNI CNII
Q P0.2S (5.8)2.30.013
2
CNII
P0.8S
CNIII CNII
S relate with soil and corves through the
empirical value called CN, the values of CN ranges
0.430.057CNII
0 -100 and its relation with S can be expressed as
Off course the selection of CN value always subjective
on engineer’s experience and understanding of the
catchment. Selection of overly conservative CN’s Runoff
Group Description
will result in the estimation of excessively high Potential
runoff and consequently excessively costly
These soils have a very slow
structures. Selection of conservatively low values
rate of water transmission.
will result loss of safety in the construction of
structures. Therefore, the major care has to take
when selecting the CN value. This subjectivity of
the CN is also the major limitation the method. Table 0-7: Runoff Curve Numbers- Urban Areas*
Curve numbers for hydrologic
Cover description
soil groups
Desert urban 63 77 85 88
areas: Natural
desert cover
Urban districts:
Commercial and 89 92 94 95
85
business
81 88 91 93
72
Industrial
Residential
districts by
average lot size: 77 85 90 92
65 61 75 83 87
0.05 hectare or
less 38 57 72 81 86
0.1 hectare 30 54 70 80 85
0.135 hectare 25 51 68 79 84
0.2 hectare 20 46 65 77 82
0.4 hectare 12
0.8 hectare
Developing urban
areas
77 86 91 94
Newly graded
areas (pervious
areas only, no
vegetation)
Hydrologic soil
group
Rotation Good 5 6 7 8
5 9 8 3
Meadow Poor 6 7 8 8
C&T 3 3 0 3
Good
5 6 7 8
1 7 6 0
4
6 7 8
8 Table 0-10: Arid and Semi-arid Rangelands*
7 7 3
Poor
Brush-weed-grass 3 Cover description Curve numbers for
5 7 7 hydrologic soil
mixture with brush the Fair 5
3 6 0 7 group
major element
Good 3
4 6 7Cover type Hydrologic
0
4 8 5 3
condition A B C D
5 7 8 8
Mixture of grass, Poor 80 87 93
7 3 2 6
Poor weeds, and low-
Woods-grass 4 6 7 8growing brush, Fair 71 81 89
Fair
2with brush the
5
combination 3 5 6
minor element Good 62 74 85
Good
3 5 7 7
2 8 2 9 Poor 66 74 79
Mountain brush
4 mixture of small Fair 48 57 63
6 7 8trees and brush
5
6 7 3 Good 30 41 48
Poor
3
6 6 7 7 Poor 75 85 89
Woods Fair 6
0 3 9Small trees with
Fair 58 73 80
Good 3 grass understory
5 7 7
0 Good 41 61 71
4 5 0 7
An optimum
Condition of
catchment
area soils,
Dry where soils
are dry but
Less than Less than
not to the
36 mm 13 mm
wilting point,
and when
satisfactory
plowing or
cultivation
takes place
The average
case for 36 to 53 13 to 28
Average Figure 0-1: SCS triangular hydrograph
annual mm mm
floods
3
Where: qp = peak discharge (m /s) ; Q = the
excess rainfall depth (mm) or the runoff
depth computed with SCS-CN equation; A
2
= watershed area (km ) ; Tc = time of
concentration (hr); D = duration of excess
rainfall (hr), which can approximated with
help of Tc
D Tc , if T 3hrs
6
D1hr if T 3hrs
Example
For 60% cultivated catchment with ‘B’ hydrological soil group and poor condition CN = 81
For 40% woodland catchment with ‘B’ hydrological soil group and poor condition CN = 66
The project area is at R5-B3 rainfall regime; based on the rainfall frequency analysis on the station
identified in the project area, the peak daily rainfall of the catchment of the drainage point with 25 year
return period 197.54 mm
qd = 0.208*(A in km2)*(Q in mm)/(0.5*D +0.6TC in hr) ; D= Tc/3 since Tc < 3; 0.5D = 0.167Tc
Table 0-12: Procedures with Example for Synthetic Unit Hydrograph Method
Example
NO Procedure Remark
(Arjo Catchment)
2
1 Catchment area (A), km 5488.77
Compute the lag time (Tl) of the basin, which is the time
from the midpoint of rainfall excess (Dhr) to the peak of the
unit direct runoff hydrograph.
5 10.901
10 m3/sec/mm as qp 0.208
A 3
95.15m /sec/mm
Tp Where A is
2
drainage area in(km ), Tp is peak time in hr
Plot the UH with a smooth line with the three know values, Tp, Tb, and qp
13 Using an iterative process in excel to adjust the ordinate of the UH with a checking point the volume of the
2
hydrograph should be 1mm X catchment area (km )
Time 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30
Quh 0 9 18 34 52 76 95.15 86 64 48 38 33 29 26 23 20
Time 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60
Quh 18 14 13 11 10 9 8 7 6 5 4 3 2 1.18 0
Once develop the UH, consider the daily rainfall distribution to get the rainfall excess. If the distribution of the
15 rainfall excess duration is different from the duration of the UH, the UH has to converted to the duration of
excess rainfall using S-UH.
The 24hr peak rainfall has to take from the regional IDF of 175.2 In this example we take
16
the site or it compute based on the frequency analysis. 100 year return period
18 19 20 21 22
The time for the rainfall distribution take based on the rainfall duration computed in synthetic UH and it has
18
to be extend up to the time of lag of the synthetic UH
The intensity of the rainfall computed based on the 24hr peak rainfall and 0.5hr MRF computed in step 16 and
17 and the following intensity exponential equation.
19
The infiltration rate of the catchment computed based on the Horton equation, which parameters given the
following table with soil hydrological group
With the current example the catchment identified with soil hydrological group of B as dominate group and
-0.18t
the Horton equation of the catchment formulated as fp = 15.24 + 89.76e . Then the infiltration rate at
each time computed as presented above in the column. If the hydrological soil group varied proportionality
the weighted values the parameters computed based on the area proportion of the soil hydrological
distribution in the catchment.
The rate of excess rainfall simple computed by subtracting the infiltration rate from rainfall intensity. (i.e.,
21
column 19 – column 20)
To get the excess rainfall depth, multiply the excess rate with the changing time of the time distribution. (2hr
22
in the current example )
Time distribution based on the rainfall excess duration up to the base time of the unit Hydrograph (i.e., 60hr ,
23
ref. row 9)
Bring the excess rainfall computed in column 22 and multiply the excess rainfall for each UH ordinate. If there
25
is two or more excess rainfall multiply with keeping the lag time.
Compute the direct runoff by sum all the ordinate in the same row; for the current example we have only one
26
time excess rainfall so the sum also the same.
27 Compute the base flow based on the relationship fixed for the river basin
23 24 25 26 27 28
Compute the total discharge by add the direct runoff and the base flow. It give the stream flow with peak
28 rainfall for the given catchment using the synthetic unit hydrograph for the catchment. Finally select the peak
3
discharge for the design of required hydraulics structure for the site. For the current example 953.41m /sec