GPPB Resolution No. 06-2020
GPPB Resolution No. 06-2020
GPPB Resolution No. 06-2020
06-2020
WHEREAS, Republic Act (RA) No. 9184, otherwise known as the “Government
Procurement Reform Act,” took effect on 26 January 2003, while its 2016 revised
Implementing Rules and Regulations (IRR) took effect on 28 October 2016;
WHEREAS, Section 63 of RA No. 9184 and its 2016 revised IRR authorizes the
Government Procurement Policy Board (GPPB) to formulate public procurement policies,
rules and regulations, and amend its IRR, whenever necessary;
WHEREAS, on 8 March 2020, the President signed Proclamation No. 922 declaring a
State of Public Health Emergency throughout the Philippines upon the recommendation of
the Department of Health (DOH) following the confirmed local transmission of the
Coronavirus Disease 2019 (COVID-19);
WHEREAS, under the State of Public Health Emergency, the relevant government
entities shall be capacitated to facilitate the sufficient and immediate access to funding,
particularly for all concerned government agencies and local government units, intensify
government response and measures such as easing procurement process, mandatory
reporting, and enforcing quarantine and disease control prevention measures;
WHEREAS, on 9 March 2020, the GPPB issued Resolution No. 03-2020 on the
Adoption of Efficient, Effective, and Expedient Procurement Procedures during a State of
Public Health Emergency, simplifying the rules in Negotiated Procurement under Emergency
Cases modality embodied in Section 53(b) of RA No. 9184 and Section 53.2 of its 2016
revised IRR;
WHEREAS, on 16 March 2020, due to the rapid increase of cases of infection in the
country, the President signed Proclamation No. 929 declaring a State of Calamity throughout
the Philippines for a period of six (6) months, unless lifted or extended as circumstances
may warrant, and further providing for the imposition of "Enhanced Community Quarantine
(ECQ)" over the entire Luzon;
WHEREAS, on 20 March 2020, the GPPB issued Resolution No. 05-2020 approving
the amendment of Item F of the General Guidelines of the Consolidated Guidelines for the
Alternative Methods of Procurement or Annex H of the 2016 IRR of RA No. 9184 to allow
acceptance of an expired Mayor`s Permit with official receipt for the renewal application and
unnotarized Omnibus Sworn Statement as basis for award under the Negotiated
Procurement (Emergency Cases) modality;
WHEREAS, the GPPB, through its Technical Support Office (TSO), likewise issued
Non-Policy Matter Opinion No. 03-20201 for the guidance of all Procuring Entities (PEs) in
the conduct of their Procurement Projects under a State of Calamity due to the COVID-19
pandemic, including Frequently Asked Questions and Emergency Rules in Four Steps;
1
Dated 23 March 2020.
WHEREAS, on 26 March 2020, the GPPB and the Commission on Audit (COA) issued
Joint Memorandum Circular No. 12, which confirmed the authority given to PEs to use
Negotiated Procurement (Emergency Cases) under Section 53(b) of RA No. 9184, Section
53.2 of its 2016 IRR and associated issuances, in order for them to properly and timely
respond to this Public Health Emergency;
WHEREAS, pursuant to RA No. 11469, the Office of the Executive Secretary issued
Memorandum dated 28 March 2020, authorizing, among others, the Honorable Secretary of
the Department of Budget and Management (DBM), who is likewise the Chairperson of the
GPPB, to craft guidelines for procurement activities that are entirely exempt from RA No.
9184, with clear and simple rules on liquidation, a liberal procedure in determining the price
most advantageous to the government considering the urgency of the present situation, and
measures to reasonably prevent abuses and corruption but not too restrictive as to delay the
process, in consultation with the COA;
WHEREAS, upon consultation with various PEs, advance payment is one of the most
pressing concerns in the procurement of medical supplies and personal protective
equipment (PPE) during the ECQ as suppliers tend to prioritize buyers who are willing to
make partial or full payment upon placing their orders;
WHEREAS, the GPPB acknowledges that the COVID-19 situation has been causing
widespread supply chain disruption and PEs must be able to respond to supplier or
contractor claims of “force majeure” or payment delays. Likewise, the enhanced community
quarantine or lockdowns imposed in various countries that limited business activities and
movement of goods and supplies cause suppliers and manufacturers of medical equipment
and PPEs to request for a higher amount of advance payment as mobilization fund;
NOW, THEREFORE, for and in consideration of the foregoing, WE, the Members of the
GOVERNMENT PROCUREMENT POLICY BOARD, by virtue of the powers vested on US, by law
and other executive issuances, hereby RESOLVE, to confirm, adopt, and approve, as WE
hereby confirm, adopt, and approve the following:
2
Issued on 26 March 2020 and published on 28 March 2020 in the Philippine Daily Inquirer.
B. Maintain the maximum amount of fifty percent (50%) for advance payment
of the contract amount for contracts entered into by PEs for the services
where requirement of down payment is a standard industry practice such
as the lease of real property or venue for use to house health workers or
serve as quarantine centers, medical relief and aid distribution locations
or temporary medical facilities; and
C. Direct the PEs to promptly release the advance payment within three (3)
working days from the award of contract to support the supplier or
contractor during the delivery of the necessary items or services.
2. ISSUE a Circular providing the Guidelines for the Emergency Procurement under
RA No. 11469 or the Bayanihan to Heal as One Act, a copy of which is attached
as Annex “A”.
____________________________________ ____________________________________
NATIONAL ECONOMIC AND DEPARTMENT OF EDUCATION
DEVELOPMENT AUTHORITY
(SGD)
____________________________________ ____________________________________
DEPARTMENT OF ENERGY DEPARTMENT OF FINANCE
(SGD) (SGD)
____________________________________ ____________________________________
DEPARTMENT OF HEALTH DEPARTMENT OF THE INTERIOR AND
LOCAL GOVERNMENT
(SGD) (SGD)
____________________________________ ____________________________________
DEPARTMENT OF NATIONAL DEPARTMENT OF PUBLIC WORKS AND
DEFENSE HIGHWAYS
(SGD) (SGD)
____________________________________ ____________________________________
DEPARTMENT OF SCIENCE AND DEPARTMENT OF TRADE AND INDUSTRY
TECHNOLOGY
(SGD)
____________________________________ ____________________________________
DEPARTMENT OF TRANSPORTATION DEPARTMENT OF INFORMATION AND
COMMUNICATIONS TECHNOLOGY
(SGD)
____________________________________
PRIVATE SECTOR REPRESENTATIVE
CIRCULAR 01-2020
6 April 2020
SUBJECT : Guidelines for Emergency Procurement under Republic Act No. 11469
or the Bayanihan to Heal as One Act
1. OBJECTIVE
2.1 to all Procuring Entities (PEs) or to any branch, constitutional commission or office,
agency, department, bureau, office, or instrumentality of the Government of the
Philippines, National Government Agencies, including Government-Owned and/or
Controlled Corporations, Government Financing Institutions, State Universities and
Colleges, and Local Government Units procuring Goods,3 Infrastructure Projects4
and Consulting Services;5 and
2.2 for the procurement of the following, in order to mitigate, if not contain, the
transmission of Coronavirus Disease 2019 (COVID-19), immediately mobilize
assistance in the provision of basic necessities to families and individuals affected
by the imposition of Community Quarantine, especially indigents and their families,
undertake measures that will prevent the overburdening of the healthcare system,
immediately and amply provide healthcare, including medical tests and treatments
3
Refer to all items, supplies, materials and general support services, except consulting services and infrastructure projects,
which may be needed in the transaction of public businesses or in the pursuit of any government undertaking, project or
activity, whether in the nature of equipment, furniture, stationery, materials for construction, or personal property of any kind,
including non-personal or contractual services such as the repair and maintenance of equipment and furniture, as well as
trucking, hauling, janitorial, security, and related or analogous services, as well as procurement of materials and supplies
provided by the procuring entity for such services as defined in Section 5(h) of RA No. 9184.
4
Include the construction, improvement, rehabilitation, demolition, repair, restoration or maintenance of roads and bridges,
railways, airports, seaports, communication facilities, civil works components of information technology projects, irrigation, flood
control and drainage, water supply, sanitation, sewerage and solid waste management systems, shore protection,
energy/power and electrification facilities, national buildings, school buildings, hospital buildings and other related construction
projects of the government as defined in Section 5(k) of RA No. 9184.
5
Refer to services for Infrastructure Projects and other types of projects or activities of the Government requiring adequate
external technical and professional expertise that are beyond the capability and/or capacity of the government to undertake
such as, but not limited to: (i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv) construction
supervision; (v) management and related services; and (vi) other technical services or special studies as defined in Section 5(f)
of RA No. 9184.
3. PROCEDURE
PEs are guided by the following in the conduct of Emergency Procurement under the
Bayanihan Act:
3.1. PEs shall prepare the project requirements, with the following details:
a. Project Name;
b. Approved Budget for the Contract (ABC);
c. Technical Specifications, Scope of Work, or Terms of Reference;
d. Date of Delivery or Implementation;
e. Required quantity; and
f. Other relevant information that the PE may require.
3.2. Once the budget for the Procurement Project6 has been validated by the budget
officer or equivalent position, the Procurement Project shall be included in the
Annual
6
As defined under GPPB Circular No. 06-2019 dated 17 July 2019, a Procurement Project shall refer to a specific or identified
procurement covering goods, infrastructure project or consulting services. A Procurement Project shall be described, detailed,
and scheduled in the Project Procurement Management Plan prepared by the agency which shall be consolidated in the
However, in view of the urgent necessity of the procurement covered under the
Bayanihan Act, the PE may commence with the procurement even without an
approved APP, provided there is a document or certification from the budget officer
or equivalent position showing that there is a budget for the purpose. The APP
shall be approved thereafter and posted on the PE’s website and submitted to the
Government Procurement Policy Board (GPPB) or posted on the GPPB online
portal for Emergency Procurement under the Bayanihan Act, once operational, on
or before 30 September 2020.
3.3. PEs shall then directly negotiate or procure from a legally, technically, and
financially capable supplier, distributor, manufacturer, contractor, or consultant.
During negotiations, a formal written offer or bid may be submitted but is not
required. Verbal agreement on the price and compliance or commitment to comply
with the legal, technical and financial requirements of the Procurement Project shall
be sufficient basis to recommend award of contract to the supplier, distributor,
manufacturer, contractor, or consultant.
3.4. The BAC or End-user unit or any other appropriate bureau, committee, support or
procuring unit duly authorized by the HoPE, shall immediately recommend award of
contract to one that has the legal, technical, and financial capability to undertake
the procurement at hand, to wit:
For foreign suppliers, the equivalent document in their jurisdiction would suffice
consistent with Section 23.2 of the 2016 revised Implementing Rules and
Regulations of RA No. 9184.
3.5. The HoPE, upon recommendation of the BAC or duly authorized End-user unit or
any other appropriate bureau, committee, support or procuring unit, shall
immediately award the contract to a legally, technically, and financially capable
supplier, distributor, manufacturer, contractor, or consultant.
However, the HoPE reserves the right not to award the contract if the same will not
redound to the benefit of the government such as:
The HoPE is encouraged to delegate the authority to award the contract to any
official of the PE, except to those where there exists conflict of interest such as the
BAC Chairperson and members or the person authorized to negotiate the bidding.
Upon award, the supplier shall enter into contract with the PE. The HoPE or his
duly authorized representative shall immediately sign the contract or purchase
order, provided that all the documents required to be submitted prior to award of
contract are complied with and that the OSS has been submitted.
The contract shall include a warranty clause where the supplier, distributor,
manufacturer, or contractor warrants that, for the period stipulated covering the
procurement at hand, the Goods or Infrastructure Projects to be delivered or
implemented shall be free from defects and conform to quality standards and
technical specifications of the said contract. The contract awardee shall fulfill all the
obligations and undertakings under the contract and the OSS.
3.6. The BAC, through its Secretariat, shall post for information purposes the Notice of
Award (NOA), contract, or purchase order in (i) the website of the PE or if none,
any conspicuous place in the premises of the PE; and (ii) the GPPB online portal
for Emergency Procurement under the Bayanihan Act, once it becomes
operational.
3.7 PEs shall be accountable for: (i) monitoring performance and compliance by the
supplier, distributor, manufacturer, contractor, or consultant with all the obligations
and undertakings in the contract, and (ii) imposing sanctions for non-performance
by the supplier, distributor, manufacturer, contractor, or consultant which may
include adherence to an improvement plan or any other remedial measures.
4. DOCUMENTARY REQUIREMENTS
4.1. PEs already maintaining a bidder’s updated file of any of the following
requirements, whether through the Philippine Government Electronic Procurement
b. Income Tax Returns (Annual Income Tax Return of the preceding tax year)
OR Business Tax Returns (Value Added Tax or Percentage Tax Return
covering the previous six months);
c. OSS, which shall be an original copy;
4.3. The OSS shall be submitted at any time before award of contract. An unnotarized
OSS may be accepted by the PE subject to compliance therewith after award of
contract but before payment.
4.4. The PE is allowed to accept a copy of the recently expired Mayor’s or Business
Permit and the Official Receipt as proof of application and payment for the renewal
of the permit will suffice, subject to submission of the Mayor’s Permit after award of
contract.
4.5. The use of digital signature or similar means may be used in all procurement-
related documents.
5. PRICE NEGOTIATION
PEs shall negotiate for the most advantageous price to the government based on:
a. existing price data of the agency, the Department of Trade and Industry or other
relevant agencies; or
b. preliminary market scanning done by the agency showing prevailing market prices
and practice.
6.1. To ensure the availability of food for all affected sectors, PEs are encouraged to
directly purchase agricultural products from local farmers or farmers’ associations
or cooperatives. Procurement from farmers’ associations or cooperatives shall
follow the procedure and requirements above-stated.
a. a certification that the farmer is in the Registry System for Basic Sectors in
Agriculture (RSBSA);
b. RSBSA identification card; or
c. Barangay Certification that the supplier is a bonafide farmer.
6.3. PEs shall be guided by the following in the negotiation of prices for agricultural
products:
a. the average prevailing farmgate price for the province, if purchased directly
from the farmers;
b. the market price, if purchased from farmers’ association or cooperative; or
c. the recommended retail price by the local price coordinating council for
commodities sold by capable farmers, and farmers’ associations or
cooperatives in their respective provinces, municipalities and cities.
6.4 The farmer shall sign the disbursement voucher prepared by the PE to show
actual delivery and receipt of payment. This shall likewise serve as the delivery
invoice showing the quantity, description of the articles, unit and total value of the
items delivered.
7. ADVANCE PAYMENT
7.2 A single advance payment not to exceed fifty percent (50%) of the contract
amount shall be allowed for contracts entered into by a PE for services where
requirement of down payment is a standard industry practice such as in the lease
of real property or venue for use to house health workers or serve as quarantine
centers, medical relief and aid distribution locations or temporary medical
facilities pursuant to MO Order No. 172, s. 2005.
8.1 Considering the urgent necessity of the items to be procured under this Circular
as well as the difficulty in estimating the required quantity needed for such, and
the available funding at that time of the original purchase, a Special Repeat Order
may be availed by the PE provided all of the following conditions are present:
8.2 Upon determination of the need to re-order the goods earlier procured, the BAC
or End-user unit or any other appropriate bureau, committee, support or
procuring unit duly authorized by the HoPE shall directly negotiate for the
procurement of additional goods, after a careful study and confirmation of the
prevailing market price of the Goods to be reordered and comparing this with the
price of the Goods in the original contract.
8.3 When all the conditions are present, the HoPE, upon recommendation of the
BAC or duly authorized End-user unit or any other appropriate bureau,
committee, support or procuring unit, shall issue the NOA which shall include a
statement that the award is a Special Repeat Order. Thereafter, the supplier,
distributor or manufacturer shall enter into contract with the PE.
The PEs shall post in the GPPB online portal for information purposes the updated APP,
NOA, and other information relative to the Procurement Projects undertaken pursuant to
this Circular. This online portal shall be the source of data or information which shall be
used by the GPPB and its Technical Support Office to comply with the reportorial
requirements under the Bayanihan Act.
PEs are authorized to impose the following penalties for the corresponding violations:
7
Issued through GPPB Resolution No. 40-2017 dated 21 December 2017.
10.2 Delay in the completion or delivery of the Procurement Project through fault of the
supplier, distributor, manufacturer, contractor, or consultant shall result in the
imposition of liquidated damages, which is equivalent to at least one-tenth (1/10)
of one percent (1%) of the cost of the unperformed portion for every day of delay.
In case the total sum of liquidated damages reaches ten percent (10%) of the total
contract price, the PE may cancel the contract. Should the PE decide not to
cancel the contract, the same is without prejudice to the continued imposition of
liquidated damages; and
10.3 Refusal to prioritize and accept contracts for materials and services necessary to
promote the declared national policy under the Bayanihan Act shall be punishable
with imprisonment of two (2) months or a fine of not less than Ten Thousand
Pesos (PhP10,000.00) but not more than One Million Pesos (PhP1,000,000.00),
or both, such imprisonment and fine, at the discretion of the court.
Notwithstanding the above penalties, the PE may impose other fines or penalties under
other relevant laws, rules and regulations, or as agreed by the parties in the contract.
11. EFFECTIVITY
PEs which issued a NOA during the effectivity of this Circular may proceed with their
contract implementation even after said effectivity. After the lapse of the effectivity of
this Circular, no NOA shall be issued.
This Circular shall take effect immediately and shall be in full force and effect only for
three (3) months from 25 March 2020 or the effectivity of the Bayanihan Act.
(SGD)
WENDEL E. AVISADO
Chairperson
Government Procurement Policy Board
AF F I DA V I T
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of
Affiant], after having been duly sworn in accordance with law, do hereby depose and state that:
If owner of sole proprietorship: As the owner and sole proprietor of [Name of Bidder], I have full
power and authority to do, execute and perform any and all acts necessary to represent it in the
bidding for [Name of the Project] of the [Name of the Procuring Entity];
3. [Name of Bidder] is not “blacklisted” or barred from bidding by the Government of the
Philippines or any of its agencies, offices, corporations, or Local Government Units, foreign
government/foreign or international financing institution whose blacklisting rules have been
recognized by the Government Procurement Policy Board;
4. [Name of Bidder] commits to submit all the mandatory documentary requirements in Item
4.1 of the Guidelines for the Procurement Activities under RA No. 11469 or the Bayanihan to
Heal as One Act at anytime before award of contract or after award but prior to payment of
contract but before payment;
5. [Name of Bidder] confirms that the posting of a performance security has been dispensed with
due to the urgent need for the procurement covered by Republic Act (RA) No. 11469 or the
Bayanihan to Heal as One Act. In lieu thereof, [Name of Bidder] hereby commits to perform and
deliver all of the obligations and undertakings, including the warranty provisions under the
contract covering the procurement at hand. [Name of Bidder] further agrees and accepts that
failure to perform or deliver any of such obligations and undertakings shall result in Blacklisting
of [Name of Bidder] for two (2) years in all government procurement activities following the
procedure under the Guidelines for the Procurement Activities under RA No. 11469 or the
Bayanihan to Heal as One Act. Moreover, in case advance payment was made or given,
failure to perform or deliver any of said obligations and undertakings shall be sufficient grounds
to constitute criminal liability for Swindling (Estafa) or the commission of fraud with
unfaithfulness or abuse of confidence through misappropriating or converting any payment
received by a person or entity under an obligation involving the duty to deliver certain goods or
services, to the prejudice of the public and the government of the Philippines pursuant to Article
315 of Act No. 3815 s. 1930, as amended, or the Revised Penal Code;
7. Each of the documents submitted in satisfaction of the bidding requirements is an authentic copy
of the original, complete, and all statements and information provided therein are true and
correct;
8. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly authorized
representative(s) to verify all the documents submitted;
If a sole proprietorship: I am not related to the Head of the Procuring Entity, members of the
Bids and Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat,
the head of the Project Management Office or the end-user unit, and the project consultants by
consanguinity or affinity up to the third civil degree;
If a partnership or cooperative: None of the officers and members of [Name of Bidder] is related
to the Head of the Procuring Entity, members of the Bids and Awards Committee (BAC), the
Technical Working Group, and the BAC Secretariat, the head of the Project Management Office
or the end-user unit, and the project consultants by consanguinity or affinity up to the third civil
degree;
If a corporation or joint venture: None of the officers, directors, and controlling stockholders of
[Name of Bidder] is related to the Head of the Procuring Entity, members of the Bids and
Awards Committee (BAC), the Technical Working Group, and the BAC Secretariat, the head of
the Project Management Office or the end-user unit, and the project consultants by
consanguinity or affinity up to the third civil degree;
10. [Name of Bidder] complies with existing labor laws and standards;
11. [Name of Bidder] is aware of and has undertaken the following responsibilities as a
Bidder:
c) Made an estimate of the facilities available and needed for the contract to be bid, if any;
and
d) Inquire or secure Supplemental/Bid Bulletin(s) issued for the [Name of the Project]; and
12. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or any
form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
IN WITNESS WHEREOF, I have hereunto set my hand this ___day of __________, 2020 at
_________________, Philippines.
[JURAT]