DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-17 Carpenter-2
Mason-5 Painter-21
Steelman-3 Plumber-2
Activity:
1. Applying of wood bleach at 2nd floor.
2. Painting in 2nd floor and 3rd floor.
3. Installation of ceiling cover in 2nd floor and 3rd floor.
4. Installation of tiles in 2nd floor and 3rd floor.
5. Applying of skim coat at 2nd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor : Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1
Laborer-6
Carpenter-3
Painter-1
Activities:
1. Installation of ceiling joist at 2nd floor.
2. Installation of tiles at ground floor.
3. Painting in ground floor and 2nd floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Electrical-2
Laborer-9 Skilled-11
Steelman-5 Fire Protection-3
Painter-4 Timekeeper-1
Activity:
1. Cutting of steel bars.
2. Preparation of reinforcement steel bars for slab and beam at 2 nd Floor. (10mm, 12mm,
25).
3. Painting in 2nd floor and 3rd floor Phase II.
4. Constructing of forms.
5. Installation of tire wires for reinforcement of slab at 2 nd floor Phase II.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Republic of the Philippines
PALAWAN STATE UNIVERSITY
Puerto Princesa City
DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-12 Carpenter-2
Mason-8 Painter-23
Steelman-1 Timekeeper-1
Activity:
1. Applying of skim coat in 2nd floor and 3rd floor.
2. Plastering of column at 2nd floor.
3. Applying of wood bleach for doors at 2nd floor.
4. Painting of doors at 2nd floor.
5. Plastering of stairs at 3rd floor.
6. Installation of ceiling cover at 3rd floor.
7. Applying of epoxy for ceiling cover at 3 rd floor.
8. Painting at 3rd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor : Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Mason-4
Laborer-4 Painter-7
Carpenter-2
Activity:
1. Leveling of angle wall at 2nd floor.
2. Installation of windows at 2nd floor.
3. Applying of skim coat at 2nd floor.
4. Installation of tiles at ground floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 SKilled-13
Laborer-15 Fire Protection-2
Steelman-5 Painter-4
Timekeeper-1
Activity:
1. Constructing of forms.
2. Removing of forms at ground floor Phase III.
3. Installation of tire wires for slab reinforcement at 2 nd floor Phase III.
4. Installation of electrical PVC at 2nd floor Phase II.
5. Cleaning of wall in 2nd floor and 3rd floor Phase II.
6. Installation of windows at 3rd floor Phase II.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Republic of the Philippines
PALAWAN STATE UNIVERSITY
Puerto Princesa City
DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-17 Carpenter-2
Mason-16 Painter-22
Steelman-1 Timekeeper-1
Activity:
1. Applying of skim coat in 2nd floor and 3rd floor.
2. Applying of wood bleach at 2nd floor.
3. Painting of doors at 2nd floor.
4. Installation of emergency lights at 2nd floor.
5. Installation of lavatory at 2nd floor.
6. Installation of tiles for stairs at 3rd floor.
7. Installation of ceiling cover at 3rd floor.
8. Installation of doors at 3rd floor.
9. Installation of scaffolding at 3rd floor.
10. Applying of epoxy for ceiling cover at 3 rd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor : Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1
Skilled-6
Labor-1
Activities:
1. Installation ceiling cover at 2nd floor.
2. Installation of windows at 2nd floor.
3. Applying of skim coat in stairs.
4. Cleaning of wall at ground floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Skilled-15
Laborer-15 Fire Protection-5
Steelman-5 Painter-5
Timekeeper-1
Activities:
1. Cleaning of wall at 2nd floor Phase II.
2. Installation of electrical PVC at 2nd floor Phase III.
3. Installation of reinforcement steel bars for column at 2 nd floor Phase II.
4. Installation of tile wires for reinforcement of slab and beam at 2 nd floor Phase II.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Republic of the Philippines
PALAWAN STATE UNIVERSITY
Puerto Princesa City
DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Cloudy – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-19 Carpenter-3
Mason-8 Painter-24
Steelman-2 Timekeeper-1
Activities:
1. Installation of doors at 2nd floor.
2. Applying of skim coat at 2nd floor.
3. Plastering of beam at 2nd floor.
4. Installation of ceiling cover at 3rd floor.
5. Applying of epoxy for ceiling cover at 3 rd floor.
6. Installation of doors at 3rd floor.
7. Plastering of stairs at 3rd floor.
8. Painting at 3rd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor : Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Cloudy – 1:00pm-5:00pm
Manpower:
Foreman-1
Skilled-5
Labor-5
Activities:
1. Installation of tiles in comfort room at ground floor.
2. Painting in ground floor and 2nd floor.
3. Applying of skim coat in stairs at 2nd floor.
4. Painting of ceiling at 2nd floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Cloudy – 1:00pm-5:00pm
Manpower:
Foreman-1 Skilled-14
Laborer-16 Fire Protection-2
Steelman-5 Painter-4
Timekeeper-1
Activities:
1. Preparation of aggregates.
2. Installation of reinforcement steel bars for slab and beam at 2 nd floor Phase II.
3. Installation of tile wires for reinforcement of slab at 2 nd floor Phase II.
4. Painting at 2nd floor Phase II.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Republic of the Philippines
PALAWAN STATE UNIVERSITY
Puerto Princesa City
DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-13 Carpenter-3
Mason-6 Painter-23
Steelman-2 Timekeeper-1
Activities:
1. Painting in 2nd floor and 3rd floor.
2. Installation of doors at 2nd floor.
3. Plaining of doors at 2nd floor.
4. Applying of skim coat in column at 2nd floor.
5. Applying of epoxy in ceiling cover at 3 rd floor.
6. Installation of tiles at 3rd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor: Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1
Skilled-5
Labor-5
Activities:
1. Installation of tiles at ground floor.
2. Installation of ceiling cover at 2nd floor.
3. Applying of skim coat at 2nd floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Cloudy – 1:00pm-5:00pm
Manpower:
Foreman-1 Skilled-12
Laborer-16 Fire Protection-1
Steelman-5 Painter-5
Timekeeper-1
Activities:
1. Fabrication of forms in cistern tank.
2. Installation of tire wires for reinforcement of slab at 2 nd floor phase II.
3. Painting at 2nd floor Phase II.
4. Chipping of canopy at 2nd floor Phase II.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Republic of the Philippines
PALAWAN STATE UNIVERSITY
Puerto Princesa City
DAILY MONITORING
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1 Welder-3
Laborer-17 Carpenter-3
Mason-6 Painter-22
Steelman-2 Timekeeper-1
Activities:
1. Installation of door knob in 2nd floor and 3rd floor.
2. Plaining of door.
3. Applying of epoxy for ceiling cover.
4. Installation of tiles at 2nd floor.
5. Applying of skim coat in column at 2nd floor.
6. Installation of ceiling joist at 2nd floor.
7. Applying of epoxy in ceiling cover at 3 rd floor.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction
Project: CONSTRUCTION OF THREE(3) STOREY STUDENT CENTER PHASE II
Address: PSU Main Campus, Tiniguiban P.P.C
Contractor : Kayano Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Sunny – 1:00pm-5:00pm
Manpower:
Foreman-1
Skilled-5
Labor-5
Activities:
1. Applying of skim coat in ground floor and 2 nd floor.
2. Installation of windows at 2nd floor.
3. Installation of ceiling cover at 2nd floor.
4. Installation of tiles at ground floor.
_______________________________
Engineer In-charge
Kayano Trading and Construction
Project: COMPLETION OF MEDICAL SCHOOL BUILDING
Address: Government Center, Sta. Monica P.P.C
Contractor: JB and Sons Trading and Construction
Weather Condition:
Sunny – 8:00am-12:00nn
Cloudy – 1:00pm-5:00pm
Manpower:
Foreman-1 Skilled-1
Laborer-1 Fire Protection-2
Steelman-5 Painter-4
Timekeeper-1
Activities:
1. Cleaning of tiles at 2nd floor Phase II.
2. Applying of skim coat at 2nd floor Phase II.
3. Installation of forms for beams at 2nd floor Phase III.
4. Installation of tile wires for reinforcement steel bars in slab at 2 nd floor Phase III.
_______________________________
Engineer In-charge
JB and Sons Trading and Construction