The document discusses assumptions for the foundations of a bridge project, including that bored piles will be used for the overall substructures. It lists the type of upper structure, length and diameter of piles, number of piles per pile cap, and an overall bored pile productivity rate. Counter circulation drilling machines, specifically the KP3000 model, will be used to boost progress of the pile drilling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
38 views1 page

Link 2

The document discusses assumptions for the foundations of a bridge project, including that bored piles will be used for the overall substructures. It lists the type of upper structure, length and diameter of piles, number of piles per pile cap, and an overall bored pile productivity rate. Counter circulation drilling machines, specifically the KP3000 model, will be used to boost progress of the pile drilling.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

1 GENERAL ASSUMPTIONS

1.1.Foundations

The overall substructures of the bridge will be using bored piles. The assumptions used for the
foundation are provided below:

No. Type of upper structure Length of Diameter No of piles Overall bored pile
pile of pile per pile cap productivity rate
1. Causeway
2. Approach bridge
3. Main bridge

The drilling will use counter circulation drilling machines to boost the progress. This project assumes
to use drilling machines of KP3000 model.