HEADINGS: Level Books & Arithmetic Checks
HEADINGS: Level Books & Arithmetic Checks
HEADINGS: Level Books & Arithmetic Checks
The entry of observations has to be very clearly written in the right line and column in the field
book. When there is an elevation error found in a project, the original filed becomes very
important player in sorting the problem.
Two systems are used for recording and reducing these observations;
This method is very useful in setting out levels on excavation sights and similar where the level
instrument is set on a convenient spot to sight to the BM and take observations to all points of interest
and giving them instance RLs.
The RL of the BM + the BS is = H I of Coll. reading normally is stored in the calculator and recalled when
needed to given RL of ground surface.
The table below is the booking of HI of Coll; where there are no rise and fall columns.
BS IS FS HI RL Remarks
While set up at 1 the backsight to BM1 is 6.482. This indicates that the horizontal line of sight
defined by the level is 6.482 above BM1. Therefore the height of the horizontal line of sight at
the set up is 40.000 + 6.482 = 46.482m (RL of Ht. of instrument).
The foresight to CP1 shows that CP1 is 2.159m below instrument height and therefore has RL of
46.482 – 2.159 = 44.323m.
On shifting to station 2 a backsight of 5.844 is read to CP1. The height of instrument at station is
44.323 + 5.844 = 50.167m.
While setup at 2, consecutive readings (Intermediate) were observed to C,D,E and CP2 as 3.141,
2.956, 5.600 and 7.318m below the instrument height.
By repeated application of the above computations, all observations are reduced until
an RL for the final point (BM2) is deduced.
A typical set out for Rise and Fall method of recording and reducing leveling observations is
shown below.
In this method the height of instrument is not computed. The difference in RL’s between two
consecutive points is computed directly as the difference in staff readings to those points from
the same instrument station.
3
If the convention is adopted that difference in elevation = backsight – foresight, then a positive
answer indicates a Rise, while a negative answer indicates a Fall, e.g. the difference in
elevation between BM1 and CP1 is 6.482 – 2.159 = + 4.323 = a rise.
Usually the Rise and Fall method is used when a you want to transfer a level value from BM some
distance afar to a an established TBM near a project site. It is good as you can check your work
especially when you use the same change point on your reverse run.
It will be noticed in both methods negative staff readings or inverted staff readings are treated
exactly the same as other readings except that their algebraic sign is taken into account.
∑BS - ∑FS = RL final point – RL initial point (where RL’s are those reduced in the level books.)
For the Rise and Fall method the arithmetic checks to be made are that;
If these checks prove correct, then no arithmetic errors exist in the reduction of the levelling
observations. In order that the level work be self checking, level runs are always made;
The Rise and Fall method of reduction of level run observations is preferred because it allows a good
check on all readings as all intermediate points are used twice.
However the Height of Instrument is very appropriate for setting out specific levels on a construction
site.
2.950 BM1
2.148 1.168 1.782 CP1
1.994 0.973 1.175 CP2
2.014 0.925 1.069 CP3
0.650 0.778 1.236 TBM
0.812 1.885 1.235 CP3
0.750 1.880 1.068 CP2
0.805 1.825 1.075 CP1
2.589 1.784 BM
This indicates an error since work started and finished on the same BM.
Since the same points were used each way, each bay was levelled twice, i.e. the height difference BM –
CP1, CP1 – CP2, etc. has been measured twice.
Checking the reductions shows that the whole error lies in the bay CP1 – CP2. The rise is 1.175 and on
the back run a fall of 1.075 so the difference is 0.10 the error.
Hence, this bay only need be checked in the field. If temporary change points had been used
throughout, the error could not have been isolated in this way.