100% found this document useful (1 vote)
6K views7 pages

Method Statement Box Culvert Construction Procedure PDF

The document discusses requirements and procedures for constructing concrete culverts. It outlines concrete class requirements, rebar specifications, preparation steps including required materials and equipment, construction procedures including excavation, forming, pouring and curing concrete, and quality control measures.

Uploaded by

TAMIL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
6K views7 pages

Method Statement Box Culvert Construction Procedure PDF

The document discusses requirements and procedures for constructing concrete culverts. It outlines concrete class requirements, rebar specifications, preparation steps including required materials and equipment, construction procedures including excavation, forming, pouring and curing concrete, and quality control measures.

Uploaded by

TAMIL
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 7

Concrete:

The batch plant concrete will be used for the cast-in-site culvert, and the requirement of the
concrete refers to the following list:

LIST OF REQUIREMENT FOR CONCRETE

Concrete Class Strength fc (MPa) Kind of structure in use

E 24 Box culvert., pipe culvert Retaining wall., wing wall, support


of pipe, drop inlet, catch
F 20 Apron, kerb
G 15 Lean concrete

Rebar:

No Description Related specification


Strength fy (MPa)
1 PLAIN ROUND BAR 250(Min) ASTM A615 or equivalent
2 High yield deformed bar 390(Min) ASTM A615 or equivalent

Specification:

LIST OF RELATED SPECIFICATION


NO.RELATED SPECIFICATION
1. AASHTO 98 _ LRFD BRIDGE DESIGN SPECIFICATION

AASHTO GUIDE SPECIFICATION FOR DESIGN AND CONSTRUCTION OF SEGMENT


2.
CONCRETE BRIDGES

3 VIETNAMESE HIGHWAY BRIDGE STANDARD 1979


2. Preparation for construction

2.1 Material

Rebar: the grade, Dimension should be accordance to the contract requirement, supply with
certification of quality, and keep the rebar surface from rust.

Cement: Use the qualified PC40 type.

Course aggregate: gravel>1X2cm, capacity of compress resistance > 500kg/cm2, impurity ratio<1%;

Sand: course sand or river sand, impurity ration<2%

Water: living water

Excavation under water level: Steel pile (L=12m), Shape steel for guide frame (400x400, 300x300),

Steel reinforcement cage with steel mesh (main steel bar d=25, L=1m, cage d=0.8m)

2.2 Equipment/machine

Excavation: vibration hammers, crawler crane, grab, bulldozer, loading vehicle, shovel, manual truck,
grade stick, etc.

Rebar work: rebar hook, wrench, ripping bar, curve machine, 22# iron thread, etc.

Formwork & support: 18mm thickness wood veneer formwork, 50X100mm timber, 3mm thickness
steel plate formwork, 4S><3 steel pipe and steel support!6^tension bar, axe, handsaw; power saw,
etc.

Equipment for pouring concrete: internal vibrator, shovel, hose, concrete tank car, concrete bucket,
concrete conduit pipe, wood float:

Equipment for drainage: Water pump. Temporary electric facilities, pipes

2.3 Pre-procedure

Complete the R.C pile works for the foundation, and get covering acceptance minute for the pile
works

Site clear and grub, arrange site plan, the material, formwork, timber will be stacked in sort.

Study the working drawing, confirm the location of embed rebar, the installation sequence of
formwork, and concrete casting sequence;

Before the next stage procedure, get the acceptance minute or temporary inspection for the current
procedure, make a record and report when the inspection is qualified.
3. Working procedure

3.1 Working sequence

The working sequence will be described as the following:

3.2 Procedure description

Foundation: the box culvert base and apron was usec><350 R.C pile. Until now the RC pile
foundation was almost completed in accordance with the Engmeequest on site

Excavation:

Due to current condition on site, the work level after excavation is under the water level for all box
culverts. And the countermeasure for excavating under the water is necessary. The more detail
information refers to following table:

Rebar work: Make survey line on the completed lean concrete surface., and also make line for the
rebar/ formwork arrangement., then prepare rebar work for bottom slab and side wall. Set steel
pipe to support the rebar cage when installation to prevent cage deviation. Then minimum cover to
main reinforcement shall be not less than 5cm: lap spliced will be not more than one bar than bar
12m for all.

Formwork: The concrete for culvert will be cast into two phases, the first phase is that cast the
bottom slab concrete, and the second phase is that cast the side wall and top slab concrete, the
construction joint will be set 50cm above the bottom slab. The formwork system will use wood
formwork with steel pipe support; the formwork will be pre-designed, fabricated in site. The
connection between the interior and exterior formwork of wall willFubS tension bar, the vertical &
horizontal distance will be 60cm:

Construction joint: Refer to the original design., there are two construction joints for each segment.,
the first joint will be set for the two segments connection location; the second joint will be set for
the connection between the culvert wall with the wing wall. For the first joint, the width of
connection concrete will be proposed to enlarge to 25cm, 2cm cork slab will be pre-embed in the
connection, sealed with waterproof strip outside. To ensure the vertical tolerance within the limited
requirement, it should be prepared two separately formwork (clamp the water stop). For the
seconctejoriatn <P20(vertical space 300mm) in the side wall of culvert, Fdsle rebar to connect
between the wing wall with the side wall. The connection joint detail refer to the following drawing:
@ Concrete pouring: The key point is the second phase for concrete casting, and the important point
for the concrete casting is side wall construction. The height of side wall will be 2.0m (1.5m, 3.8m
and 4.0m): casting with conduit pipe, remove the pipe per 1.5m. Keep the rebar out in the area of
conduit pipe to easily casting. Complete rebar installation when the side wall concrete is totally
Casting.

side wall concrete 50cm per layer. The concrete should be pumped into the formwork equality, the
specify worker will be equipped with each poker vibrator and located in specify area. Conform to the
working sequence: side wall to middle wall, then other side wall, for each layer and turn. While
complete the side wall concrete, begin the top slab concrete.

© Concrete curing: After the last treatment to surface of the top slab, cover the surface with sacks,
keep moisture for 7 days.

® The non-bearing formwork will be dismantled after 1 days, the bearing formwork will be
dismantled after 3 days.

4. Quality assurance

4.1 Rebar

The rebar type, quality, weld rod, weld flux, will be accordance with the contract requirement,

The rebar lap length, quantity, space, anchor distance will be checked and accordance the
requirement as described before.

The quantity of loose binding for rebar will be kept within 10% of all.

The rebar splice and lap length will be accordance with the requirement, and checked strictly.

4.2 Formwork

The formwork support should have enough bearing capacity and stability. The supports have enough
support area.

The gap between the formworks will be controlled within 1.5mm.

The interface between the formwork and the concrete should be cleaned and pre-treated with
insulate agent to prevent sticking. The total area of insulate agent will not more than 1,000 cm2.
4.3 Concrete

The cement, water, aggregate, adhesive agent will be accordance to the material requirement and
approved by the Engineer.

The mix design, material measurement, mixture method, curing and construction joint should be
pre-taught to the specify staff, and operate followed the standard procedure.

The sample cube will be tested as the AASHTO 98 requirement; the test result should achieve the
design requirement.

The concrete should be vibrated to the requirement strength, and prevent honey hole in the
concrete component.

Prevent the concrete surface from rebar out, crack, and other defection.

5. Safety precaution

Dress the safety helmet and prohibit dressing slipper into the site.

Dress safety belt when operation 2m above the surface., and prohibit throw anything from the high
level., and no jump from the support formwork.

The formwork will be selected from rotten, cracked ,wrecked ones, keep the bottom of formwork
level;

Specific switch shall be equipped to all kinds of electnc equipment. Those outside shall be equipped
with waterproof box with lock and operation area shall have insulation layer. Checking and
reparation of electric equipment shall cut off power first. If impossible, liable safe measure shall be
taken and monitored by specific person.

Prepare drainage system when the rainy season is coming, keep the drainage unblocked. And tide
the site after rainy.

6. Work schedule

The work schedule of box culverts will be attached in next independent documents.
Method Statement for Culvert Construction
1. Introduction and General Information
This method statement consists of construction of culverts, including material & machineries to be
used, casting & construction procedures, quality control tests & verifications, and also the safety
precautions to be implemented.
1.1. Location of Works
Locations will be as per the approved construction drawings.
2. Materials
The major materials used for construction of culverts work, but are not limited to the following.
 6” X 9” Rubble
 Concrete
 Small tools
3. Equipment
The major equipment used for construction of culverts, but are not limited to the following.
 Tractor
 JCB
 Concrete vibrators
 Vibrating rammers
 Leveling instrument
 Other minor tools
4. Safety Management and Control
Safety precaution will be taken complying with the Road Work Traffic Control Manual and as
described follows. Every precaution will be taken to avoid any accidents & damages to adjoining
properties, workers, and road users.
All workers will be advised to wear helmets, boots, and gloves while working. There will be a stand by
vehicle near site always if needed in a case of accident. 
The safety officer inspects several times to inspect safety matters.
5. Method and Procedures
Work procedures for construction of culvert described as below. 
5.1. Excavation for construction of half culvert will be done by arranging all traffic sign board as per
the road work traffic control manual. The Engineer will be requested to inspect & approve the 
excavation, and necessary soft ground treatments carry out after all.
5.2. The bed will be prepared maintaining required levels as per the original construction drawings
approved by the Engineer and requested from the Engineer to inspect and approve the surface. 
5.3. After getting approval for the bed, screed concrete will be placed, after that 6” x 9” rubble wall
(Abutments), deck concrete, Parapet wall and finishing work will be carried out respectively. 
5.4. Traffic will be diverted on the finished half of the culvert and after arranging all traffic sign boards
and other arrangements; the other side excavation will be started and continued as described above.
6. Quality Control
Certain inspections, verifications, and tests will be carried out, to ensure the quality and durability of
the product as described in the above procedures, as per the requirements given in the specification. 

You might also like