0% found this document useful (0 votes)
134 views1 page

Cost Estimate

The document provides a cost estimate for a proposed sanitary landfill project located in San Juan, Padilla, Antipolo City. It estimates earthworks will cost over 90 million, waterproofing over 32 million, and piping/venting nearly 1 million. General requirements are estimated at 3 million. The total estimated cost is over 127 million pesos.

Uploaded by

Cire Omalin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
134 views1 page

Cost Estimate

The document provides a cost estimate for a proposed sanitary landfill project located in San Juan, Padilla, Antipolo City. It estimates earthworks will cost over 90 million, waterproofing over 32 million, and piping/venting nearly 1 million. General requirements are estimated at 3 million. The total estimated cost is over 127 million pesos.

Uploaded by

Cire Omalin
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

COST ESTIMATE

Project name: Proposed Sanitary Landfill

Location: San Juan, Padilla, Antipolo City

Description Quantity Unit Labor cost total

eathworks        
excavation 623908 m3 93.33 58229333.64
backfill 617669 m3 50 30883450
disposal 620 m3 100 62000
clay layer capping 3940 m3 250 985000
gravel bedding 1578 m3 200 315600
sub-total       90475383.64

         

boring works        

boring of holes 2.5 mm diameter 500 m 1200 600000


clay layer bedding 1194 m3 350 417900
sub-total       1017900

         
water proffing works        
HDPE membrane 107403 m2 300 32220900
sub-total       32220900

         
piping/gas vent pipe        
6" dia. HDPE pipe with fitting 1980   500 990000
sub-total       990000

         
General requirements        
Mobilization/Demobilization 1 lot 500000 500000
field offices and sheds 1 lot 800000 800000
office facilities and equipments 1 lot 100000 100000
quality control 1 lot 1600000 1600000
sub-total       3000000
         

Grand total       127,704,183.64