Moving Towards Clear Land Titles in India: Potential Benefits, A Road-Map and Remaining Challenges
Moving Towards Clear Land Titles in India: Potential Benefits, A Road-Map and Remaining Challenges
Moving Towards Clear Land Titles in India: Potential Benefits, A Road-Map and Remaining Challenges
By Rita Sinha
Secretary
Department of Land Resources
Ministry of Rural Development
Government of India
Introduction
2. Conclusive Titles
2.2 With regard to the four principles mentioned above, the status
in India today is that, most of the States have two or three agencies
handling property records. The Revenue Department usually
prepares and maintains the textual records; the Survey and
Settlement Department prepares and maintains the maps; the
Registration Department does verification of encumbrances and
registration of transfer, mortgage, etc. of property. A few States
have a Consolidation Department in lieu of a Survey and Settlement
Department. In some of the States, the local bodies have been
empowered to do undisputed mutations. The urban local bodies
update property records for purposes of taxation in urban areas.
Merging these departments into a single agency is, in many cases,
administratively and politically difficult.
Page 2 of 15
Moving towards Clear Land Titles in India
that the records do not always reflect the ground reality and, hence,
are not universally “real-time records”.
Page 3 of 15
Moving towards Clear Land Titles in India
3.5 The time taken for preparing and obtaining real-time records,
registration and mutation will be greatly reduced.
4.3 The district has been taken to be the unit for completing all the
activities enumerated above. The country has a little over 600
districts. Each State Government was requested to take up a few
districts per year in such a way that the entire State is covered in
the next eight years under the NLRMP. The States that are
undertaking cadastral surveys for the first time may take a little
longer to complete the NLRMP. The eight year Perspective Plans
include the numbers, names and details of districts chosen per
year, activities proposed to be undertaken, technologies proposed
to be used, milestones, time-frames and expenditure involved.
Sixteen State Governments have sent their Perspective Plans to
the Government of India. The latter has sanctioned Rs.2372.6
million during the current financial year through its Project
Sanctioning Committee, for implementing the NLRMP in 56
districts. It is anticipated that the activities in one district will be
completed within two to three years.
4.4 The total project cost of the NLRMP for eight years has been
estimated to be a little over Rs.56 billion of which the Central
Government will fund around Rs.31 billion and the State
Governments will be required to raise the remaining amount of Rs.
25 billion.
Page 6 of 15
Moving towards Clear Land Titles in India
4.5 It is obvious that even with the combined efforts of the Central
and State Governments, there may be gaps in fulfilling such an
ambitious programme within the targeted period. Public-private
partnerships for the NLRMP have, therefore, been made an integral
part of the scheme. The State Governments can identify areas
which can easily be contracted out to private parties, with
Government functionaries fulfilling only their legal obligations.
4.6 To roll out the NLRMP, the Government of India was expected
to prepare guidelines and technical manuals. The guidelines have
already been prepared and are in the process of being
implemented. The technical manuals are under preparation.
Page 7 of 15
Moving towards Clear Land Titles in India
4.8 It is, thus, clear that the NLRMP will enable India to achieve
three out of four principles which form the basis of Conclusive
Titling. Although it is envisaged that the NLRMP will be completed
in eight years, the country need not wait till then to introduce
Conclusive Titling. Appropriate legislation can enable the States to
implement Conclusive Titling in a modular way by introducing it in
those districts which complete all activities necessary for the same.
5.1.3 In the rural areas alone, more than 140 million land
owners have more than 430 million records. There are about 92
million ownership holdings each with four to six parcels of holdings.
Not only has the survey to be done for each plot of land, but a
Page 8 of 15
Moving towards Clear Land Titles in India
5.1.5 Considering the vast size of the country, i.e., 3.29 million
sq. kms., establishing the ground control point library (GCPL)
presents a major problem. The Survey of India (SoI) has developed
a national control frame and the first phase of GCPL of 300 points
at a spacing of about 200 to 300 kms. apart covering the whole
country has been provided. In the second phase, 2200 points at a
spacing of 30 to 40 kms. apart, and a third phase of GCPL with
control points at a distance of about 8 to 10 kms. apart have yet to
be established.
Page 10 of 15
Moving towards Clear Land Titles in India
Page 11 of 15
Moving towards Clear Land Titles in India
5.6 Technology
5.6.1 Selection of technology is a major challenge for the
country as a whole, as well as for each State Government. The
varied topography of the country requires a judicious combination of
technologies for proper survey. A single district may have a variety
of terrains such as plains, hills and valleys and forests. The
technology for valleys and forests and urban areas has yet to
stabilize.
Page 12 of 15
Moving towards Clear Land Titles in India
Page 13 of 15
Moving towards Clear Land Titles in India
Some States do not have a training institute and a way will have to
be found to establish one.
5.8 Pendency
******
Page 15 of 15