Annexure III Scope of Work and Special Conditions
Annexure III Scope of Work and Special Conditions
Annexure III Scope of Work and Special Conditions
Scope of work
Objective:
Ensure Asset integrity of all pipings and static equipment is maintained to ensure
fitness for service over the remnant life.
Ensure that current inspection strategy, frequency and practices are in line with the
recommended RBI inspection recommendations, identify gaps if any.
There are 11 process complexes for which Risk based Inspection study was
carried out besides unmanned platforms. Risk based inspection was done based on
the inspection plan provided by consulting agencies like DNV, BV and ABS. NDT
reports for any vessel will be like UT conventional / advanced NDT, DP test, external
inspection, hardness test etc. to account for different damage mechanisms. It is
proposed to treat one pipe (based on tag in P & ID) / vessel as a unit for
interpretation of advanced NDT or conventional UT reports for that vessel/ pipeline.
Asset-wise certification of process complexes / Un-manned platforms for NH and MH
Assets are as follows:
1 MH 3 4 78 Nil
2 NH Nil 2 Nil 33
3 B&S 1 1 12 Nil
1.0 Analysis of defects found in Non-Destructive Testing carried out as a part of Risk
Based Inspection program for static equipment and piping will be done as per Rule
30 of petroleum and Natural Gas (Safety in Offshore) and broad guidelines provided
by OISD 128, OISD 130, API 510, API 570 and API-579
2.0 Area of Operation: This job covers Fit for service analysis for all the defects found in
NDT carried out mainly as a part of Risk Based Inspection program for ONGC
offshore installations of Mumbai High Asset, B & S Asset and Neelam Heera Asset.
3.0 Asset-wise tentative quantum of work is as follows
3 NH 92 746 DNV
3 L-III 36 210
Quantum of work is tentative for the quantity as well as locations. ONGC may
offer NDT reports of other vessels/pipelines for FFS analysis due to operational reasons.
However total value of work will not exceed total value of the contract reported in
aforesaid tables. Quantities for L2 level assessment are 65% of the quantities for L1
level assessment. Quantities for L3 level assessment are 10% of quantities for L2 level
assessment.
4.0 General facilities and details. Soft and Hard copies will be provided for interpretation
purpose.
5.1 “Fitness for Service” analysis based on reports provided defects noted during
Non-Destructive Testing for static equipment and piping.
5.4 Bidder shall finalize the defect category from all the anomalies noted in
reports.
5.5 All the defects shall be analysed by Bidder based on Fitness for service
standard API-579, API 510 and API 570.
5.6 In order to get the best out of Fitness-For-Service (FFS) assessment and help
the final decision process, bidder shall effectively use the results in the Risk
Based Inspection (RBI) study for the affected equipment or piping.
5.7 Bidder shall provide analysis based on plant operational loads and process
conditions (e.g., normal operation, fault scenarios, start-up/shutdown,
chemical cleaning, etc.)
5.9 Bidder shall gather all relevant data and shall complete the assessment, by
analyzing the results.
5.10 Bidder shall carry out Fitness for service considering following to
demonstrate integrity of equipment and piping
Tolerable thinning (e.g. corrosion, erosion) damage sizes and damage rates
Tolerable crack sizes and crack growth rates
Tolerable pressure vs. temperature operating envelope
Tolerable material toughness and/or other mechanical properties
Remaining life
Fatigue Life
Creep life
Integrity Operating Limits / Windows
Critical Maintenance Activities
Other risk mitigating measures (e.g. design improvements, material upgrade,
changes to current operating conditions, etc)
Suitable intrusive and/or non-intrusive NDT inspection (If required further to
analyze)
5.13 In addition to 5.12, assessment report shall clearly mention following items as
Outcome and final decision making
6.0 Bidder will involve experienced personnel for interpretation of NDT reports. He will
submit the list of API-510 and API 570 certified personnel along with their resume,
who will be signing final FFS reports, before taking up the job. He will also submit
resume of experienced personnel carrying out FFS certification before initiation of
the job, in mobilization period.
7.0 L1,L2 and L3 level assessments are the assessment levels for deciding the
fitness level of vessels and pipes. They are as specified in API 579. Assessment
complexity increases with ascending order of degree of assessment, i.e. L3 is the most
complex, L1 is the least complex type of assessment. All NDT reports of pipes and
vessels will undergo L1 level assessment. Out of those reports some may require
further probing. They will qualify for L2 level assessment. Few reports of L2 level
assessment may require L3 level assessment.
Flow chart for the Interpretation process is tabulated below:
Sr. No. Activity Duration
1 Handing over of NDT reports by ONGC to As and when available
bidder in soft or hard form on a particular date to ONGC
2 Carry out L1 level assessment for the reports 6 months from handing
handed over over of reports by
3 Submit FFS report if no further assessment is ONGC
required. If further assessment is required
then, submit interim report stating the need for
further assessment
4 L2 Level assessment will be presumed to be 3 months from the
started as soon as ‘Go ahead’ is received from date of receipt of ‘Go
ONGC for further analysis interim report is ahead’.
received
5 Submit FFS report if no further assessment is
required after L2 level assessment. If further
assessment is required then submit interim
report stating the need for further assessment
6 L3 Level assessment will be presumed to be 3 months from the
started as soon as ‘Go ahead’ is received from date of submission of
ONGC for further analysis interim report is interim report or
received submission of data
requested by
contractor for study. In
case ONGC is not able
to provide the data in
six months after the
receipt of the request
of the contractor then
payment for that
report will be released
for assessed levels.
API 570 – Piping Inspection Code: In-service Inspection, Rating, Repair, and
Alteration of Piping Systems
1. Mobilization L.D will be 0.5% of the total contract value, for relevant asset, per
week. L.D. will be applicable on annual contract value excluding taxes.
2. FFS reports which get delayed beyond stipulated period i.e. 6 months after the
handing over of NDT reports by ONGC will attract L.D. of 0.5% per week per
tag of vessel/pipe, depending on applicable rate for that FFS report excluding
tax. L.D will not exceed 10% of the applicable rate for a delayed FFS report.
3. Total L.D. (L.D. on account of mobilization and delay in submission of reports)
will not exceed 10% of the total contract value excluding taxes.