Question #1:Choose the correct answer for each of the following questions (40 marks):
Questio 1 2 3 4 5 6 7 8 9 10
n
Answer B B G D B C B A C B
Questio 11 12 13 14 15 16 17 18 19 20
n
Answer C B B D B F F E B A
2. For the inverse time overcurrent relay, if Isetting= 2 A, CT ratio is 100/1, TMS =
0.1 sec and the operating time = 1.5 sec, the primary current in the CT is:
7. For the sensitive earth fault relay, if a 3% current setting is required then you
will set the plug bridge and the multiplier setting as:
a. 1% , 3
b. 2% , 1.5
c. 3% , 1
d. None
BB1 BB2 BB3
CT1 CT2 CT3
I f . max 2000 A
R1 R2 R3
Figure 1
Table 1
Case # CT Ratios Pick Up settings TMS settings
CT1 CT2 CT3 R1 R2 R3 R1 R2 R3
Case 1 500/1 500/1 500/1 1 1 1 0.5 0.6 0.8
Case 2 600/1 300/1 200/1 1.25 1.25 1.25 0.3 0.3 0.3
Case 3 400/1 400/1 400/1 1 0.8 0.60 0.4 0.4 0.4
Case 4 400/1 200/1 250/1 0.5 1 0.75 0.5 0.3 0.1
For the single line diagram shown in Figure 1 use Figure 1 and table 1 to answer
the next four questions:
12. Which statements is false about the inverse time overvoltage protection relay:
a. It time out to trip when a settable overvoltage threshold is reached and
maintained for the trip duration time.
b. It trips in the set time irrespective of the overvoltage magnitude.
c. It is used for the protection of synchronous machines, hydrogenation
plant and large inertia loads.
d. The tripping time is inversely proportional to the extent of the
overvoltage, dependent on settings.
e. None
f. All of the above
13 . For the inverse time over voltage protection relay MVTD12, if the voltage
setting Vsetting 120V , the selected time multiplier setting TMS = 0.4,
characteristic constant K=5 and the operation time of the relay is 12 seconds, then
the applied input voltage is:
The figure below illustrates the principle connection of the feeder protection
relay HO4, where the feeder located among a ring connection distribution
system:
a b c
CT Power Cable CT d
HO4 HO4
Biased Biased
Differential Differential
Relay #1 Relay #2
Pilot Wires
e
17. If open circuit occurs in the pilot wire at point (e), then:
a. Relay #1 will operate and Relay #2 will not operate.
b. Relay #2 will operate and Relay #1 will not operate
c. Both relays will operate but Relay #1 will operate before Relay #2.
d. Both relays will operate but Relay #2 will operate before Relay #1.
e. Both relays will not operate.
f. Both relays will operate at the same time.
18. If short circuit occurs between points (e) and (f), then:
a. Relay #1 will operate and Relay #2 will not operate.
b. Relay #2 will operate and Relay #1 will not operate
c. Both relays will operate but Relay #1 will operate before Relay #2.
d. Both relays will operate but Relay #2 will operate before Relay #1.
e. Both relays will not operate.
f. Both relays will operate at the same time.
For the inverse definite minimum time (IDMT) over current relay (IDMT
characteristic is attached in figure ( 1).
19. If CT ratio = 300/1, primary current (Ip) = 250 A, relay current setting (Is)= 1
A, TMS = 0.4, then the operation time is:
a. 4 sec. b. ∞ sec. c. 6 sec. d.7 e. None
20. If CT ratio = 250/1, primary current (Ip) = 1000 A, relay current setting (Is)=
2A, TMS = 0.8, then the operation time is:
a. 8 sec. b. 7 sec. c. 5 sec. d. ∞ e. None