Sec-8
TF/1:30-3:00
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the
total time for all tasks is 18 minutes. The line will operate for 450 minutes per day.
OT = 450 minutes
Range of output:
450
@ 2.4 min.: = 187.5 units
2.4
450
@ 18 min.: = 25 units
18
Dx Σ t 187.5(18)
N= = = 7.5, which rounds to 8
OT 450
d. What cycle time will provide an output rate of 125 units per day?
OT 450
Output = solving for CT, CT = = 3.6 minutes per cycle
CT 125
e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15minutes?
OT 450
1. CT = 9 min.: = = 50 units
CT 9
OT 450
2. CT = 15 min.: = = 30 units
CT 15