Ahadzie2008 PDF
Ahadzie2008 PDF
Ahadzie2008 PDF
com
Received 18 May 2007; received in revised form 30 July 2007; accepted 4 September 2007
Abstract
Project success is a complex and often illusory construct. Nonetheless, it is crucially contingent towards enabling appropriate and
effective allocation of resources in project management practice. Mass house building projects (MHBPs) represent one of the largest
and most established project-based sectors of the construction industry in most developing economies. Above all, the management skills
required on these projects differ significantly from the one-off projects often encountered in the construction industry. While some success
criteria may be common across project types, there is no denying the fact that some determinants of success are likely to be unique to
projects of specific characteristics. This research sets out to address what constitutes the determinants of success in MHBPs. A question-
naire survey is used to establish property developers’ perception of critical success criteria in MHBPs in Ghana. Data analysis (involving
one-sample t-test) reveals some interesting findings in regard to how property developers perceive the importance of the project success
criteria. Factors analysis reveals four underlying clusters named in order of their significance as environmental-impact, customer satisfac-
tion, quality and cost and time. This systematic approach towards understanding the taxonomy of the success dimension in MHBPs is
important for re-enforcing effective project management practices in this significant sector of the construction industry.
Ó 2007 Elsevier Ltd and IPMA. All rights reserved.
Keywords: Mass house building projects (MHBPs); Ghana; Repetitive management techniques; Success criteria and factor analysis
knowledge and practices in the determinants of project suc- addition, MHBPs differ significantly (in terms of produc-
cess. Interestingly researchers have not attempted to sys- tion and management principles) from many of the one-
tematically address the issues of what constitutes project off projects often encountered in the wider construction
success in the implementation of these projects. This is industry [18,19]. Admittedly, while project success criteria
against the background that these projects differ signifi- may be common across some sectors, there is no denying
cantly from the ‘‘one-off’’ projects often encountered in the fact that there are likely to be unique criteria for
construction and requires unique management approaches MHBPs.
to, for example, engender the appropriate allocation of
resources. Identification of critical success criteria should 3. Definition and characteristics of mass house building
therefore be an important step towards enabling effective projects
project management in these projects.
As part of an ongoing study to develop a predictive The term mass house building projects (MHBPs) is used
model for project managers’ (PMs) performance measures in the construction industry to describe mass production
in MHBPs in Ghana [12–14], the results of a questionnaire techniques of housing development projects [18]. This def-
survey of property developers perceptions of success criteria inition, which has been used by many other researchers to
in the implementation of these projects is presented. The date, is derived from the manufacturing sector [19–21].
aim being to provide property developers and PMs operat- However the definition fails to explicitly highlight some
ing in developing countries such as Ghana, a much clearer of the characteristics found in construction such as the pro-
understanding of ‘‘successful outcomes’’ so that these can ject environment; site conditions including topography; the
be accurately monitored and anticipated. While the data is weather; bulky materials; design considerations [22]. In an
based on Ghana where the ‘‘paradigm’’ underlying housing attempt to provide a definition encapsulating the true char-
delivery may be different, the findings contribute towards acteristics of the industry and for the purpose of this study,
the systematic understanding of success criteria in MHBPs. MHBPs are defined as ‘‘the design and construction of
A review of some of the related studies on the determi- speculative standardised house-units usually in the same
nants of success criteria within the construction industry is location and executed within the same project scheme’’
first presented. This is followed by a working definition of [14]. Such house-units could include: terrace, multi-storey
MHBPs including a commentary on the unique character- or tower blocks, maisonettes, semi-detached, and/or
istics of these projects. Thereafter, a theoretical framework detached residences or a combination of them. Four main
is presented based on the current view of the determinants points are worth noting in regard to the definition of
of success criteria in mainstream project management prac- MHBPs as follows.
tice. Subsequently, a success framework for MHBPs is con-
ceptualised towards incorporating the appropriate They must be based on one or more standardized
variables. The next section then illuminates the research designs in the sense that the architectural design of all
methods adopted for the study followed by a discussion phases should largely be the same for all house-units.
of the findings. The final section provides an overview of This is necessary to ensure that the concept of repetition
the issues discussed in the paper and attempts to draw con- is met.
clusions from the study including recommendations for They should involve the construction of domestic resi-
further studies. dences (whatever their form).
They must be speculative in the sense that the acquisi-
2. Project success tion of land, design of house-units and construction
are made without reference to any specific customer in
Generally, there is no consistent interpretation of the mind.
term project success [6]. There is also no standardised def- They should potentially be located in the same area and
inition of the term nor is there an accepted methodology be part of the same scheme and/or contract conditions.
for measuring it [6]. However, it is recognised that the cri-
teria for project success must be agreed at the commence- What is not clear in this definition is the quantity of
ment of the project to avoid differences amongst project house-units involved. Basic experience or learning curve
teams [2,6]. Accordingly, the last decade has witnessed theory suggests that each time the number of repetition
increasing research towards identifying success criteria doubles the cumulative production rate (man-hours per
within the construction industry in developing countries unit) declines by a consistent fixed percentage of the previ-
[5,10,15–17]. The key significance of these studies lies in ous cumulative production rate [23]. When this theory was
their systematic contribution towards developing an under- replicated in the construction industry using 45 identical
standing of the overall success model [10]. Nonetheless, house-units, it was confirmed that each time the house-
there lacks a systematic understanding of what constitute units doubled the cumulated production rate was 90%
success criteria in MHBPs. This is against the background [24]. This suggests that a minimum of two house-units is
that, arguably, MHBPs, constitutes one of the largest and sufficient to achieve a learning curve effect arising out of
established project-based sectors of the industry [11]. In the repetition involved in MHBPs. This not withstanding,
D.K. Ahadzie et al. / International Journal of Project Management 26 (2008) 675–687 677
the United Nations Economic Commission for Africa has frameworks. While these various frameworks conceptualise
suggested that for developing countries to meet their pres- the success criteria against the traditional measures, they
ent and future housing needs, they should aim at an annual also include criteria that represent the interests of other
production rate of 10 house-units per 1000 population [25]. stakeholders. Subsequently, new and emerging criteria such
Subsequently in this study the threshold for the minimum as health and safety, technology transfer, environmental
quantity of house-units is fixed at 10 house-units. friendliness, risk containment, client satisfaction and stake-
MHBPs differ in many ways from the traditional one-off holder’s satisfaction have become an accepted part of these
projects often encountered in the construction industry. emerging frameworks.
For instance, these projects by their nature must be based The framework developed by Pinto and Slevin [2] has
on standardised design; there is the need to identify the been the driver behind a number of studies aimed at iden-
stages in production at which control is to be exerted; tifying project success criteria [5,32,37]. This framework is
and there is the need for production time between stages based on the premise that the key factors in the implemen-
including delivery of house-units [26,27]. Furthermore tation of successful projects incorporate three criteria: tech-
because of their unique nature, the setting up of the pro- nical validity, organisational validity and organisational
duction system involves two associated problems; the mini- effectiveness. Technical validity is the first hurdle in identi-
mising of synchronising loss and the maximizing of fying success criteria and this is assessed in the context of
resource utilization [26]. Moreover, depending on the whether the project after completion performs as intended
quantity of house-units involved, these projects are often (i.e. an issue of functionality crops in here) [2]. With respect
relatively large-scale and can stretch over a considerable to organisational validity, an important consideration is
production area. This coupled with the numerous interre- that the project must be ‘‘right’’ or acceptable for the cli-
lated skills involved makes the management of these pro- ents for whom it is intended. Furthermore, an important
jects inherently more complex and difficult than many condition about organisational effectiveness is that the
one-off projects [18,19]. PM must be involved in making sure that the ‘‘right’’ pro-
Thus, the key to achieving project management success ject is delivered to the client and/or user [2]. Thus, organi-
on MHBPs is for PMs to have the requisite knowledge sational effectiveness is how well the accepted project
and skills that enhances management intuition in repetitive makes a positive impact on the user.
construction planning [18,19,28,29]. That is, the PM must A key implication of the three measures of implementa-
be able to take advantage of the repetitive tasks involved tion of success is that success criteria are equally important
so as to ensure continuity of work and in particular achieve both inside and outside the project organisation. Subse-
cost and time savings [18,19,28,29]. Subsequently, PMs are quently, Pinto and Slevin [2] developed a 12-factor model
faced with providing the appropriate management struc- based on the key constructs of time, cost, satisfaction,
ture consistent with available resources to support the usage, performance and effectiveness. In doing so the cen-
economies of large-volume work that help achieve tral theme was for the success criteria to focus on the needs
improved performance levels [30]. To this effect, a clear of the project and client (and/or user) [see [2]].
understanding of the determinants of project success in
these projects will assist property developers and PMs to 5. A project success framework for MHBPs
appropriately plan towards effective resource allocation.
Drawing on Pinto and Slevin’s [2] project success frame-
4. Theoretical framework work, Fig. 1 presents a proposed success framework for
MHBPs.
In mainstream project management practice, project Note that in this case the underlying themes have been
success is traditionally conceptualised and operationalised identified as: projects and customers. In addition to the
based on the iron triangle of time, cost and quality [2]. constructs in Pinto and Slevin’s model, other potential suc-
The conventional practice is that these output-based mea- cess criteria (such as health and safety, environmental
sures are only assessed at the end of a project (i.e. at com- friendliness and technology transfer) were incorporated to
pletion) [4]. The reason why these measures are so popular broaden the scope of the criteria [4,15]. It is contended that,
is that they are simple to apply and also largely objective, in MHBPs, the critical issue is for the PM to take advan-
particularly for time and cost [2,31]. However, in recent tage of the repetitive nature of the work involved so as to
times, there has been an acknowledgement that limiting ensure cost and time effectiveness through learning and
the success criteria to these traditional measures excludes experience [18,19,28,29]. Alternatively, it is expected that
the long-term satisfaction of the relevant stakeholders customers (as the potential users) will expect high quality
[32]. Thus, in recent times, the contemporary ideology is work that will make a positive impact on their well-being.
to view success criteria as both measures of the success of Thus, whereas issues relating to technical and organisa-
the production system in terms of time, cost and quality tional validity are critical in terms of the project and/or
and the benefit to stakeholders [32]. product, it is expected that organizational effectiveness will
In view of this, numerous project management research- be influenced largely by customer satisfaction, quality and
ers [2,32–36] have developed alternative project success other subjective measures. Indeed organisational effective-
678 D.K. Ahadzie et al. / International Journal of Project Management 26 (2008) 675–687
Fig. 1. Project success framework for MHBPs based on the idea of Pinto and Sleven [2].
ness is assessed subjectively based on a sense of smoother the information that will enable them to channel the
operations and employee and customer satisfaction [2]. appropriate behaviours towards implementing the rele-
To this end, 15 potential success criteria were identified vant management tools. This viewpoint is supported from
for MHBPs (see Fig. 1). Table 1 presents a definition of a psychological perspective that the behavioural actions of
the various variables identified. managers towards achieving project success is influenced
Granted that no systematic studies have been under- by the degree and expected level of results [39]. Subse-
taken to identify success criteria for MHBPs in developing quently, it is noted that, behaviours that might be associ-
countries, the definition of the 15 success criteria was ated with short term planning where ‘‘detail’’ is very
partly informed by generic definitions noted in the Asso- important may be different from undertaking strategic
ciation of Project Management (APM) body of knowl- planning where ‘‘creativity’’ is rather more important
edge (2000) [38] and, in the notion that, in MHBPs, [39]. Thus, the behaviours and skills underlying effective
PMs have to use their knowledge of repetitive techniques short term planning (e.g. attention to detail) can be
to achieve effective levels of performance [18]. This intui- expected to be different from those contributing to long
tion therefore led to the discrimination between meeting term planning (e.g. creativity). In a similar vain, it is
‘‘overall success criteria’’ (i.e. success in the larger project anticipated that if PMs were aware of the critical success
context) and ‘‘success criteria on individual house-units.’’ dimensions, appropriate resources could be allocated
The contention being that, this would provide PMs with towards fulfilling these.
Table 1
Definition of potential success criteria
Variable Variable name Definition
CSF1 Overall project cost Final out-turn cost for overall project including infrastructure such as road networks and street
lighting
CSF2 Cost of individual house-units Final out-turn cost for individual house-units.
CSF3 Overall project duration Time taken to complete entire project including provision of infrastructure such as road works and
street lighting
CSF4 Rate of delivery of individual Time taken to deliver individual house-units
house-units
CSF5 Overall project quality Quality of entire project including associated infrastructure as seen by customers and the public
CSF6 Quality of individual house-units Quality of individual house-units as seen by the customer or user
CSF7 Overall customer satisfaction Satisfaction of customers with overall project outcomes including infrastructure provision
CSF8 Customer satisfaction on Satisfaction of customers with individual house-units
individual house-units
CSF9 Overall risk containment The extent to which all kinds of risk were contained or minimised
CSF10 Risk containment on individual Ditto in relation to individual house-units
house-units
CSF11 Overall environmental impact Impact of construction waste, environmental degradation and pollution on the general public
CSF12 Environmental impact of Impact of living environment waste such rubbish, sewage, drainage
individual house-units
CSF13 Overall health and safety measures Number of accidents and the extent to which employees use appropriate safety gear and equipment
CSF14 Health safety measures with Health and safety in terms of health hazard posed by the living environment, poor materials poor
individual house-units construction practices
CSF15 Technology transfer The extent to which new technology significantly improves the design and construction of a living
space by decreasing installed cost, increasing installed performance and improving the construction
process is applied on the project
D.K. Ahadzie et al. / International Journal of Project Management 26 (2008) 675–687 679
Table 3
One-sample test
Test value = 3.5
T Df Sig. (2-tailed) Mean difference 95% confidence interval of the difference
Lower Upper
Technology transfer .535 56 .595 .0719 .1974 .3413
Health and safety on individual house-units 4.117 56 .000 .5351 .2747 .7955
Overall health and safety measures 4.367 56 .000 .5351 .2896 .7806
Environmental impact of individual house-units 2.765 56 .008 .3491 .0962 .6021
Overall environmental impact 4.033 56 .000 .5105 .2569 .7641
Risk containment on individual house-units 1.171 56 .247 .1386 .0986 .3757
Overall risk containment 2.273 56 .027 .2667 .0316 .5017
Customer/client satisfaction on individual house-units 8.485 56 .000 .8930 .6821 1.1038
Overall customer/client satisfaction 8.735 56 .000 .8930 .6882 1.0978
Quality of individual house-units 11.080 56 .000 1.0000 .8192 1.1808
Overall project quality 15.012 56 .000 1.1070 .9593 1.2547
Rate of delivery of individual house-units 5.262 56 .000 .5719 .3542 .7897
Overall project duration 6.374 56 .000 .6789 .4656 .8923
Cost of individual house-units 12.996 56 .000 1.0719 .9067 1.2372
Overall project costs 13.751 56 .000 1.2544 1.0716 1.4371
Table 7
Correlation matrix of factor analysis
Factor CSF1 CSF2 CSF3 CSF4 CSF5 CSF6 CSF7 CSF8 CSF9 CSF10 CSF11 CSF12 CSF13 CSF14 CSF15
CSF1 1.000
CSF2 .321 1.000
CSF3 .292 .082 1.000
CSF4 .095 .565. .518 1.000
CSF5 .071 ..401 .289 .475 1.000
CSF6 .029 .147 .137 .363 .651 1.000
CSF7 .435 .375 .082 .117 .282 .162 1.000
CSF8 .190 .235 .095 .209 .397 .304 .549 1.000
CSF9 .126 .409 .200 .312 ..481 .394 .320 .493 1.000
CSF10 .119 .451 .335 .374 .500 .371 .517 .420 .766 1.000
CSF11 .039 .450 .188 .343 .475 .179 .313 .375 .706 .706 1.000
CSF12 .100 .542 .184 .407 .434 .257 .320 .304 .755 .755 .858 1.000
CSF13 .174 .216 .198 .315 .422 .511 .396 .522 .686 .624 .424 .495 1.000
CSF14 .184 .189 .198 .299 .436 .448 .355 .412 .599 .685 .407 .536 .841 1.000
CSF15 .010 .214 .001 .129 .443 .474 .214 .453 .435 .356 .155 .173 .446 .381 1.000
Note: Kaiser–Meyer–Olkin measure of sampling adequacy = .758; Bartlett test of sphericity = 531.149; significance = 0.000.
Explanation to acronyms as in Table 1.
Table 9
Component transformation matrix
Component Initial eigenvalues Extraction sums of squared loadings Rotation sums of squared loadings
Total % of variance Cumulative % Total % of variance Cumulative % Total % of variance Cumulative %
1 6.558 43.721 43.721 6.558 43.721 43.721 3.737 24.910 24.910
2 1.680 11.197 54.918 1.680 11.197 54.918 3.149 20.990 45.900
3 1.438 9.586 64.505 1.438 9.586 64.505 2.166 14.438 60.338
4 1.246 8.308 72.813 1.246 8.308 72.813 1.871 12.474 72.813
5 .921 6.138 78.951
6 .624 4.157 83.108
7 .581 3.872 86.980
8 .458 3.056 90.036
9 .447 2.981 93.017
10 .308 2.051 95.067
11 .221 1.477 96.544
12 .190 1.267 97.811
13 .174 1.159 98.971
14 .086 .576 99.546
15 .068 .454 100.000
Extraction method: principal component analysis.
Scree Plot ticular, Torbica and Stroh [58] assert that for property
7 developers to compete in the long term, they must be sure
that current and prospective customers are satisfied.
6
Interestingly, Toole [59] has noted that homebuyers
5 approach the buying decision for a new home very differ-
ently from other purchases, often with very strong bonds
Eigenvalue
range of conditions associated with the production process, Given that one of the main objectives of repetitive con-
the end product of the task consists of many interacting struction methods is cost effectiveness, it seems plausible
parts and/or dynamic subsystems, the task requires high that quality of individual house-units and cost of individual
levels of tacit knowledge and skills and the task requires house-units are also seen to be measuring the same underly-
interaction with a large number of diverse entities. Hence ing criteria. The potential implication for PMs is that,
property developers have to been convinced that a new whilst striving to make cost savings on the delivery of
technology will provide significant advantages over existing MHBPs, this should not be done at the expense of the qual-
products before they will commit themselves. ity of individual house-units. This is against the background
What is also quite clear is that, the adoption of new that often ‘‘profit’’ made by property developers is at the
technology involves taking some risk. Hence the more expense of quality [63]. Property developers are therefore
uncertainties that exists the more reluctant property devel- reminded that while it is important to strive towards cost
opers would be to embrace technological innovations [59]. effectiveness in MHBPs this should be achieved by taking
Alternatively Yang et al. [60] have suggested that a plausi- advantage of improved productivity of resources arising
ble way forward for minimising the uncertainties is to out of the repetitive works involved and not by deliberately
clearly quantify the benefits to be derived from technology cutting down expenditure meant for quality improvement.
adaptation and application. They suggested that it might Furthermore, it is recommended that property developers
be appropriate to quantify these benefits in terms of cost, should create the necessary environment so that their
schedule and safety success as these are issues of major con- PMs can take advantage of the management tools available
cern to ‘‘project stakeholders.’’ to help strike the right balance in achieving cost savings
Given that customers’ satisfaction is arguably the most and maintaining quality standards.
critical factor here, there is also no doubt any uncertainty
reduction would have to take their interest into serious 9.4. Component 4: overall cost and time
consideration. Thus, ultimately, whilst it is important for
property developers to fully appreciate the potential risks Component 4 accounted for 8.3% of the variance and
associated with adopting technological innovation, their comprised overall project cost (loading factor 82.7%) and
knowledge about the factors that are related to home overall project duration (loading factor 76.5%) and was
buyers satisfaction or dissatisfaction would be an invalu- labelled cost and time. The issue of shortening construction
able tool in achieving a competitive edge (see for instance time, reducing cost and improving production performance
[59]). has engaged both practitioners and researchers for some
time, (see for instance [64–66]). The studies include motiva-
9.3. Component 3: quality tion and productivity investigations as well as analysis of
planning and scheduling techniques [67]. Prefabrication
Component 3 consists of quality of individual house-units and industrialisation have also been widely considered in
(81.3%), cost of individual house-units (77.2%) and overall housing projects in the name of improving overall time
project quality (59.5%), and was labelled quality of house- and cost associated with these projects. Other innovative
units accounting for 9.6% of the variance. Quality of indi- methods such as modular boxes, pre-stressed panels and
vidual house-units emerged the highest factor in this group- polystyrene have also been advocated [67].
ing and conforms to the empirical evidence that quality However, against the background of a huge demand for
significantly predicts overall homebuyer satisfaction and residential buildings in developing countries, delays and
ultimately project success [58]. Indeed just like satisfaction, cost overruns are still major militating factors influencing
the primary antecedents of quality are product and service the implementation of MHBP [47,66]. Indeed, in some
performance and customer expectation concerning the instances, the cost and time over-runs have been so severe
future performance of the product [61]. that serious questions about the human resource manage-
In effect, a focus on improving quality at all stages of ment practices have been raised [67]. Thus, at a time when
MHBPs is important to improving project success. The an estimated one billion people are living in inadequate
problem however is that no two identical houses are the housing in developing countries, the cost and time perfor-
same in quality because of variations in construction pro- mance remain crucial to project success.
cess and the weather, the skills and attitudes of the trades-
men and whether specified materials were correctly 10. Conclusion
delivered and installed. In short, it is difficult for property
developers to be completely confident that every portion The determinants of project success have been the sub-
of a new house that they build will stand up to the same ject of considerable debate in project management research
design installation, occupancy conditions over the years practice. Here, a success framework for MHBPs has been
[62]. The onus is therefore on property developers to make developed and presented. The results of a questionnaire
sure that the appropriate resources are channelled to enable survey of property developers has revealed no distinction
the understanding of effective quality management that in regards to how project success is perceived in terms of
meets the bespoke needs of potential customers. overall project and individual house-units.
D.K. Ahadzie et al. / International Journal of Project Management 26 (2008) 675–687 685
The determinants of success in MHBPs can be classified important criteria unique to MHBPs. It would therefore
into four main clusters, namely environmental impact, cus- be useful if this is considered as part of any further research
tomer’s satisfaction, quality and cost and time. These find- to advance the systematic understanding of the determi-
ings lend support to the prevailing evidence that the nants of success criteria in MHBPs. Furthermore, while
challenges facing property developers concern the need to the concept of repetition is an important consideration that
minimise cost and time over-runs and to keep current may influence the perception of success by property devel-
and potential customers satisfied [58,67]. It is therefore rec- opers ‘in MHBPs, its impact and/or degree of impact was
ommended that property developers and PMs pay particu- not specifically considered in this study. With the increas-
lar attention and resources towards ensuring these factors ing use of standardization in MHBPs this could also be a
are met in the delivery of MHBPs. potential source of future research towards fully under-
standing the taxonomy of the determinants of success in
11. Reflection on the findings these projects.
[14] Ahadzie DK, Proverbs DG, Olomolaiye P, Gameson R. A conceptual building projects. In: 22nd ARCOM conference, University of
predictive model for evaluating the performance of project managers Central England, September, 2006c, 4–7, p. 165–75.
in mass house building projects. In: Balwin A., et al., editors. [41] Ling YY. A conceptual model for the selection of architects by
Construction sustainability and innovation/CIB W 89, international project managers in Singapore. Int J Project Manag 2003;21:135–44.
conference on building education and research, Hong Kong. 10–13, [42] Field A. Discovering statistics, using SPSS for windows. London:
April, 2006a, p. 12 (ISBN: 962-367-511-9). Sage Publications; 2005.
[15] Odusami KT. Criteria for measuring project performance by [43] Bank of Ghana. Fiscal Report for Financial year 2006–2007, 2007.
construction professionals in the Nigeria construction industry. [44] Ayirebi-Dansoh K. Strategic planning practice of constriction firms in
J Financial Manag Property Construct 2003;8(1):10. Ghana. Construct Manag Economics 2005;23:148–63.
[16] Mbachu J, Nkado R. Factors constraining successful building project [45] Smallwood J. Practising the discipline of construction management:
implementation in South Africa. Construct Manag Economics knowledge and skills. In: 2nd international conference on construc-
2007;25:39–54. tion in developing countries: challenges facing the construction
[17] Shen Q, Liu G. Critical success factors for value management studies industry in developing countries, Gabarone, Botswana; 15–17
in construction. J Construct Eng Manag ASCE 2003;129(5):485–91. November, 2000, <http://www.odsf.co.za/cdproc/2nd_proceed-
[18] Ashley DB. Simulation of repetitive-unit construction. J Construct ings.html>, [accessed 31.03.04].
Div, Proc ASCE 1980;106(Co2):185–98. [46] Keivani R, Werna E. Modes of housing provision in developing
[19] Mahdi I. A new LSM approach for planning repetitive housing countries. Progress Planning 2001;55(2):65–118.
projects. Int J Project Manag 2004;22:339–46. [47] Hair F et al. Multivariate data analysis. New York: Prentice-Hall; 1998.
[20] Hyari K, EL-Rayes K. Optimal planning and scheduling for [48] Norusis MJ. SPSS 10.0 guide to data analysis. Englewood Cliffs, NJ:
repetitive construction projects. J Manag Eng 2005;22(1):11–9. Prentice Hall; 2000.
[21] El-Rayes K, Ramnathan R, Moselhi O. An object oriented model for [49] Ukoha OM, Beamish JO. Assessment of residents’ satisfaction with
planning and control of housing construction. Construct Manag public housing in Abuja, Nigeria. Habitat Int 1997;21(4):445–60.
Economics 2000;20:210–20. [50] Ngowi AB. Creating competitive advantage by using environment-
[22] Ahadzie DK, Proverbs DG, Olomolaiye P. Project managers’ friendly building processes. Build Environ 2001;36:291–8.
performance measures; a fresh perspective. In: 21st ARCOM confer- [51] Poon CS, Wan yu TA, Wong SW, Cheung E. Management of
ence, SOAS, London, 3–5 September, 3–10, 2005. construction waste in public housing projects in Hong Kong.
[23] Schwartzkopf W. Calculating lost productivity labour productivity in Construct Manag Economics 2004;22:675–89.
construction claims. New York: John Wiley and Sons Inc.; 1995. [52] Morrel JC, Mesbah A, Oggero M, Walker P. Building houses with
[24] United Nations. United Nations Committee and Housing, Building local materials: means to drastically reduce the environmental impact
and Planning, effect of repetition on building operations and of construction. Build Environ 2000;36:1119–26.
processes on site, New York, 1965. [53] Ofori G. Challenges of construction industry in developing countries:
[25] Edmonds GA, Miles DWJ. Foundations for change: aspects of the lessons from various countries. In: Proceedings of the 2nd interna-
construction industry in developing countries. London: Intermediate tional conference in developing countries: challenges facing the
Technology Publications; 1984. construction industry in developing countries. Gabarone, Botswana;
[26] Burgess RA, White G. Building production and construction 15–17, November, 2000 <http://www.odsf.co.za/cdcproc/1stproceed-
processes. London: The Construction Press; 1979. ings.html>, [accessed 31.03.04].
[27] Muhlemann A, Oakland J, Lockyer K. Production and operations [54] Kirbert CJ, Coble RJ. Integrating safety and environmental regula-
management. London: Pitman Publishing; 1992. tions of construction industry. J Construct Eng Manag, ASCE
[28] Dhansekor M. Identification of optimal size resource for a repetitive 1995;121(1):95–9.
housing. Construct, Eng, Construct Architectural Manag [55] Xiao Hong. A comparative study of contractor performance based on
2000;7(4):347–61. Japanese, UK & US Construction practice, Unpublished PhD,
[29] Enhassi A. Site organization and supervision in housing projects in University of Wolverhampton, UK; 2002.
the Gaza strip. Int J Project Manag 1997;15(2):93–9. [56] Baker BN, Murphy DC, Fisher D. Factors affecting project success.
[30] Atkinson R. Project management: cost time and quality, two best In: Cleland, King editors. Project Management Handbook, New
guesses and a phenomenon, its time to accept other success criteria. York, Van Nostrand Reinhold, p. 669–85.
Int J Projects Manag 1999;17(6):337–42. [57] Torbica ZM, Stroh RC. Customer satisfaction in home building. J
[31] Latham GP, Fay C, Saari LM. The development of behavioural Construct Eng Manag, ASCE 2001;127:82–6.
observation scales for appraising the performance of foremen. [58] Toole M. Uncertainty and home builders adoption of technological
Personnel Psychol 1979;32:299–311. innovation. J Construct Eng Manag, ASCE 1998;124(4):323–32.
[32] de Wit A. Measurement of project management success. Int J Project [59] Yang LR, O’Connor JT, Wang CC. Technology utilization on
Manag 1988;6(3):164–70. different sizes of projects and associated impacts on composite project
[33] Morris PWG, Hough GH. The anatomy of projects. John Wiley; 1987. success. Int J Project Manag 2006;24:96–105.
[34] Wateridge J. How can IS/IT projects be measured for success. Int J [60] Anderson EWC, Lehman DR. Customer-satisfaction, market share
Project Manag 1998;16(1):59–63. and profitability, findings from sweden. J Marketing 1994;58:53–66.
[35] Turner JR. The handbook of project-based management. McGraw- [61] Ozsoy A, Atlas NE, OK V, Pulat G. Quality assessment model for
Hill; 1993. housing; a case study of Istanbul on outdoor spaces in Istanbul.
[36] Odusami KT, Iyagba RRO, Onirin MM. The relationship between Habitat Int 1996;20(2):163–73.
project leadership, team cooperation and construction project. Int J [62] Rukuro WR, Olima WHA. Developer profits undermine residents’
Project Manag 2003;21:519–27. satisfaction in Nairobi’s residential neighbourhood: implication for
[37] Morris PWG, Patel MB, Wearne SH. Research into revising the APM local government in Kenya. Habitat Int 2003;27:143–57.
body of knowledge. Int J Project Manag 2000;18:155–64. [63] Odenyinka HA, Yusif A. The causes of delay on completion of
[38] Tett RP, Guterman AB, Bleir A, Murphy PJ. Development and housing projects in Nigeria. J Financial Manag Property Construct
content validation of a hyperdimensional taxonomy of managerial 1997;2(3):31–44.
competences. Human Perform 2000;13(3):205–51. [64] Okuwoga AA. Cost-time performance of public sector housing
[39] Pickett L. Competencies and managerial effectiveness: putting com- projects in Nigeria. Habitat Int 1998;22(4):389–95.
petencies to work. Public Personnel Manag 1998;27(1):103–14. [65] Chan DWM, Kumaraswamy MM. Forecasting construction dura-
[40] Ahadzie DK, Proverbs DG, Olomolaiye P. Development of research tions for public housing projects: a Hong Kong perspective. Build
instrument for project managers performance measures in mass house Environ 1999;34:633–46.
D.K. Ahadzie et al. / International Journal of Project Management 26 (2008) 675–687 687
[66] Tam CM, Deng ZM, Zeng SX. Evaluation of construction methods [67] Kaming PF, Holt GD, Kometa ST, Olomolaiye PO. Severity
and performance for high rise public housing construction in Hong diagnosis of productivity problems-a reliability analysis. Int J Project
Kong. Build Environ 2002;37:983–91. Manag 1998;16(2):107–13.