D:/IRPWM With cs/ACS To IRPWM/ACS 122
D:/IRPWM With cs/ACS To IRPWM/ACS 122
D:/IRPWM With cs/ACS To IRPWM/ACS 122
doc
-2-
DTK(MC), DTK(M), DTK(P), Dir(Works)I & II, Dir. Works(Plg.), Dir(L&A), DCE(B&S), DVE-I &
DVE-II, JD(B&S),IPWE(I), OSD(ME),
------
(I) A new para 238(2)(g)(iii) and 238(2)(g)(iv) may be added to Indian Railways Permanent
Way Manual as under:-
Para 238(2)(g)(iii) - Deep Screening with BCM (Ballast Cleaning Machine) and followed by
Tamping and Stabilisation of Track with TTM (Tie Temping Machine) and DTS (Dynamic Track
Stabliser) respectively for BG - The work is to be carried out in stages on various days after the start
of the screening operations and the speed restriction recommended to be imposed are indicated in the
schematic representation in table – III below. According to the schedule, normal sectional speed can
be resumed on the 8th day.
Table – III
Schedule of speed restriction for deep screening by BCM followed by Tamping and
Stabilisation by TTM and DTS machines for BG
The period of the schedule shown above can be suitably increased to suit local conditions of
the track consolidation.
Para 238(2)(g)(iv) - Precautions to be taken during deep screening of track by BCM followed by
TTM and DTS machines;
(i) All precautions laid down in LWR manual (specially those in para no.6.3.2) shall be strictly
followed.
(II) The existing sub paras 257(4), (6) & (7) and para 917 of Indian Railways Permanent Way
Manual shall be replaced by the following:-
Para 257 (4) - Reports of Rail failures – In addition to the records maintained in the section register,
as detailed above, a report has to be prepared as per Annexure 2/10 in all cases of rail failures
occurring in track with the exception of the cases noted below -
(a) Rail failures occurring in non-running lines.
(b) Non-standard and obsolete rails.
(c) Rails removed due to casual renewals on account of accidental damages to the rails such as
wheel burns and scabbings, buckling, kinks, derailments, abnormal slipping of loco wheels,
excessive wear, loss of section by corrosion, battering, elongation of holes etc.
(d) Machined rails such as mitred joints, switch expansion joints, switches and crossings.
For this purpose, the Permanent Way Inspector will prepare a ‘Rail failure’ Report in
quadruplicate as per proforma at Annexure 2/10 and shall forward 3 copies to the Assistant Engineer,
who will transmit all the copies with his remarks to the Divisional Engineer, for onward transmission
of one copy each to the Chief Engineer and Executive Director (M&C)/RDSO/Lucknow. In case of
D:\IRPWM with cs\ACS to IRPWM\ACS 122.doc
failures requiring metallurgical investigation, the report should be prepared in quaintuplicate, the
extra copy being sent to the Chemist and Metallurgist of the Zonal Railway along with the samples as
detailed in the sub-para (7) below. Efforts should be made by Divisional Engineer so that the report
reaches the Executive Director (M&C)/RDSO within a fortnight of the rail failure. Sketches
illustrating the fractures will be prepared and submitted with the failure reports on each case, care
being taken that the running face of the rail is indicated thereon. It is particularly essential to record
the type of failure in the failure reports against item No. 5.3 as per R.D.S.O. monograph “Rail
Failures - Description, Classification and Reporting”. The Executive Director (M&C) will arrange
to carry out analysis of rail failures from the reports received from the Permanent Way Inspectors and
the Chemist and Metallurgist and publish reports with suggestions for reducing failures. In most
cases, it is possible to determine the cause of the failure by visual examination/ultrasonic detection
without the need for metallurgical investigation. However, in cases mentioned in sub-para (5) below,
it is obligatory to take up full metallurgical examination by the Chemist and Metallurgist of the
Railway concerned with a view to ascertaining the exact cause of failure. In such cases the rail failure
report should be made out in the prescribed proforma inserting the most probable code of failure
against item No. 5.3 and indicating whether the sample has been sent to the Chemist and Metallurgist
for metallurgical investigation.
For the cases of rail failures detected visually, a short piece of rail approximately 1m
long(500mm+500mm) has to be sent to the Zonal Railway’s Chemist and Metallurgist by the
Permanent Way Inspector direct, along with a copy of the rail failure report, only for such cases
which come under the category listed in sub-para (5) below. In other cases, i.e., those detected by
ultrasonic flaw detectors, the rail pieces of 1m length (500mm + 500mm) containing the flaw shall
be sent for metallurgical test only from those rails which are removed from track based on the criteria
for removal of rails and falling in the category listed in sub-para (5) below. The test pieces for
metallurgical examination are to be sent only for rail failures which occur within test free period
subject to maximum of 10 years of rolling and for which detailed reports are to be prepared. In case
of repetitive failures of rails of same rolling mark, irrespective of the type of fracture/flaw, short
rail piece of approximately 1m long (500mm + 500mm) containing the fracture/flaw detected
visually or by ultrasonic flaw detector should be sent to the Chemist and Metallurgist together with
a rail failure report for metallurgical investigation. Chief Track Engineer of zonal railway shall
forward the cases of repetitive failure of rails of same rolling mark on account of chemical &
metallurgical reasons to Executive Director/M&C/RDSO along with investigation reports from
Chemist and Metallurgist. The rail pieces of approximately 1m long (500mm + 500mm) containing
the fracture should be sent to Executive Director (M&C)/RDSO together with a rail failure report
for metallurgical investigation where rail/ weld failure is prima facie cause of train accident. To
sum up, before sending the test pieces to the Chemist and Metallurgist or RDSO, it should be ensured
that –
(i) The rail failure is within test free period subject to maximum of 10 years of rolling of rail,
irrespective of the type of fracture/flaw.
(ii) The rails have been removed from track as a result of visual or ultrasonic detection and rail
failure falls in categories listed in sub para (5) below.
(iii) The rail where rail/ weld failure is prima facie cause of train accident should be sent to RDSO.
(iv) The rails with repetitive failure of same rolling mark irrespective of type of failure.
In cases of failures of imported rails occurring within guarantee period, stipulation of sub
para (6) shall be followed.
Para 257 (7) - Procedure for sending samples for metallurgical investigation - In case of fractured
rail, both the pieces of approximately 500 mm long each i.e. total 1m long containing fractured
faces/flaw should be sent to the Chemist and Metallurgist for investigation. To avoid damage in
transit, the fractured faces shall be protected with mineral jelly and suitably covered with hessian
cloth. Cracked rails may also be suitably protected at the crack location to avoid damage in transit.
Pieces having internal defects may be dispatched as such.
The Chemist and Metallurgist of the Railway will carry out metallurgical investigation, as
required, and forward one copy of the report each to the Chief Engineer of the Railway and the
Executive Director (M&C)/RDSO.
In case of failures of imported rails within the guarantee period, attributable to manufacturing
defects as revealed by metallurgical investigation, the Chief Engineer should immediately lodge a
provisional claim with the manufacturer pending Executive Director (M&C)’s confirmation of the
findings submitted by the Chemist and Metallurgist of the Railway. The Executive Director
(M&C)/RDSO will scrutinize the report submitted by the Chemist and Metallurgist and if he agrees
with the findings as submitted, inform the Chief Engineer accordingly. Where the Executive Director
(M&C)/RDSO feels the need for carrying out further investigation before giving his verdict, he will
call for the sample from the Chemist and Metallurgist of the Railway and carry out confirmatory
tests, as necessary and intimate the findings to the Chief Engineer. On the basis of Executive
Director (M&C)’s advice, the Chief Engineer will then finalise the claim with the manufacturer.
In case of failures of rails other than imported, the Executive Director (M&C)/RDSO will call
for samples from the Chemist and Metallurgist, for confirmatory test, where necessary. Based on the
trend indicated by the numerical analysis of the rail failures for the period under review, the
Executive Director (M&C) will bring to the notice of the indigenous manufacturers and Inspecting
Agency, any predominance of failures attributable to manufacturing defects, to enable corrective
action being taken.
*****