China Shandong Ruyi Sahiwal of Pakistan 2×660MW Coal-Fired Power Station Project 1 Boiler, Set To Start The Debugger Steps
China Shandong Ruyi Sahiwal of Pakistan 2×660MW Coal-Fired Power Station Project 1 Boiler, Set To Start The Debugger Steps
China Shandong Ruyi Sahiwal of Pakistan
2×660MW
Coal-fired power station project 1 boiler,
set to start the debugger steps
XI ' an thermal power
Research Institute company
limited
The year November 2016
Series Write: Bull Pei
RECORDING
1 The purpose
Unit is set to start the debugger sets a major process of trial operation,
started trial operation of whole units, such as safety, quality, is a
comprehensive inspection of the performance of the unit, but also on the early
commissioning of the unit a comprehensive inspection, test. Try to guide the
boiler set to start the debugger work, ensure the safe and normal operation of
the unit, this measure is enacted.
Measures according to the situation on site commissioning phase of startup
programs, requirements, test conditions, methods and considerations, and
approved before implementation.
2 Prepared based on
2.1 Thermal power construction project started trial operation and acceptance
of the Statute of the Office ( DL/T 5437-2009 )
2.2 The construction technical specification of boiler articles ( DL/T5190.2-
2012 )
2.3 Commissioning the construction of coal-fired power generation engineering
quality acceptance and assessment Regulation ( DL/T 5295-2013 )
2.4 The steam pipe blowing scheme of thermal power construction project unit
guidelines ( DL/T 1269-2013 )
2.5 The steam boiler safety technology supervisory regulations ( TSG G0001-2012
)
2.6 Of the thermal power plant construction project commissioning specification
( DL/T 5294-2013 )
2.7 The boiler starts debugging guidelines ( DL/T 852-2004 )
2.8 Of the people's Republic of China engineering construction compulsory
article (electric power engineering) ( 2011 Year Edition)
2.9 Specification for safety operation of electric power construction (part of
thermal power plant) ( DL 5009.1-2014 )
2.10 Design drawings, specifications and equipment description
2.11 25 key requirements for the prevention of accidents of electric power
production (National Energy Board 2014 Year Edition)
2.12 The Shandong Huaneng Sahiwal of Pakistan 2 × 660MW Coal-fired power
station project 1 Outline of unit commissioning
3 Debugging quality objectives
In accordance with the commissioning of thermal power construction
engineering quality acceptance and assessment Regulation ( DL/T5295-2013 )
Unit complete with load in the commissioning phase of the quality standard,
and all tests pass rate 100% To meet unit package are required.
4 System introduction
China Shandong Ruyi Pakistan 2 × 660MW Coal-fired power plant boiler
design of Harbin boiler company limited 660MW Parameters of supercritical
once-through boilers, boiler models HG-2118/25.4-HM16 , П-type arrangement,
furnace, balanced ventilation, solid slag, steel frame, suspension structure,
boiler open layout, MPM Burners with separate burning wind ( SOFA ) The
combination of low NOX Air combustion system, corner tangential firing mode.
Boiler start-up system using built-in boot system without a Recirculation
pump, equipped with 6 -speed Coal mill consisting of Taichung direct firing
pulverizing system, when the burning coals 5 run, maximum continuous rating of
the boiler operating mode (B-MCR) for the design parameters. Synchronization
of the project construction of flue gas desulphurization facilities, reserved
and denitrification facilities (chimneys and steel frame construction). Spiral
of middle and lower part of furnace water wall tubes of boiler, the upper
vertical tube water wall once rose, with excessive header between the two
connections. Overheating steam thermostat way to coal water than regulation
mainly, while set two level four points spray water reduction temperature;
again hot steam thermostat main used shaft separated smoke road thermostat
bezel thermostat, while burning device of swing on again hot steam temperature
also has must regulation role, and in low temperature again hot device and
high temperature again hot device connection pipeline Shang also set has
accident spray water reduction temperature device.
Boiler mill uses heavy machinery plant in Shanghai HP1063/Dyn Mills,
positive pressure direct blowing pulverizing system uses medium speed mill
system, each furnace 6 Mills, B-MCR Work conditions 5 Running, 1 The reserve.
Each grinding for a total of 4 burners, burning a total of 24 groups, arranged
for furnace water wall 4 corners, forming a small circle cutters, burning, the
use of corner tangential firing large bellows structure, main burner using low
horizontal bias NO X Pulverized coal burner. Fineness of coal powder mill
exports R90=22%. Boiler is equipped with 2 capacity for 50% a fan, blower,
induced draft fan, merged with the buf in desulfurization of induced draft fan
settings. Blower in boiler primary air fan by the Shanghai factory production
of moving blade adjusted axial-flow fan and blower model PAF18.5-13.3-2. By
Shanghai boiler fan blower works limited production of moving blade adjusted
axial-flow fan and blower model FAF25.5-15-1. By Shanghai boiler induced draft
fan blower works limited production of moving blade adjusted axial-flow fan
and blower model SAF35-22.4-2. Configure two of the boiler air preheater for
three-ljunstoem structure of Rotary air preheater. For this project, using
micro-oil ignition of the boiler system, configured with three layers 12
mechanical atomizing type oil guns, guns the total heat input of light oil
boiler 15%B-MCR design, only design output for 1700kg/h. Coal and ash
characteristics are shown in table 1, ignition help fuel characteristics are
shown in table 2.
Table 1 And ash composition of coal quality characteristic analysis
1. technical analysis
4. elemental analysis
6. ash analysis