Heat Exchanger Network Retrofit For Energy Savings
Heat Exchanger Network Retrofit For Energy Savings
Heat Exchanger Network Retrofit For Energy Savings
energy savings
Identifying cost effective energy savings by optimising plant heat integration in
the crude preheat section
I
ndustrial energy use accounts for preheat train was applied to find crude oil in the market and changes
approximately one-third of the the optimal and most profitable in the quality of crude from tradi-
world’s energy demand. In heat exchanger network design that tional sources motivate the heat
particular, the 1970s oil crises saw yields the highest net present value exchanger network retrofit to be
how the efficient use of energy (NPV). operated in multiple periods for
becomes a priority for policy Energy conservation has become greater flexibility. The application
makers in many industrialised more important as public aware- of energy cost and capital cost
countries. Rising concerns about ness and concerns regarding global trade-off from the retrofit technique
climate change have sharpened the warming and energy shortage of the pinch design method
importance of energy efficiency. continue to grow. Naturally, energy proposed by Tjoe and Linnhoff5,
Energy-related emissions accounted management programmes have integrated with thermodynamic
for 9.9 gigatonnes of carbon dioxide been applied to refineries as they properties, provides the energy
in 2004, which represented an are the most energy intensive oper- saving plots and optimum target.
increase of about 65% from 1971 ations in the manufacturing In the present scenario, the retro-
levels.1 With the current best avail- industry. There are many ways to fit of the heat exchanger network is
able technologies and given the increase energy efficiency, and an important way of improving
huge amount of wasted heat, design and process heat integration energy efficiency in process indus-
energy efficiency is practically tries. An industrial plant of 40
regarded as the most cost effective
tool to reduce CO2 emissions and
The retrofit of the years-plus lifetime may need to be
retrofitted several times to improve
climate change.2 At the company heat exchanger energy efficiency and/or to meet
level, energy efficiency also reduces increased production. There are
the key performance indicators of network is an several approaches to achieve
energy intensity and increases energy savings in a retrofit study:
companies’ competitiveness.1 important way of for example, reducing utility use,
According to the US Energy modifying the network topology,
Information Administration, the improving energy upgrading heat transfer units,
industrial sector consumed 31.4 installing additional heat transfer
quads of energy in 2008, which was
efficiency in process area, repiping streams, and reas-
approximately one-third of all the
energy used in the US that year.3
industries signing heat recovery matches. The
retrofit’s objective is to identify a
Further, more states are deploying cost effective heat exchanger
regulations that will limit the emis- are widely used methods. Heat network, subject to design and
sions of greenhouse gases. transfer from hot products and operating constraints, that will not
Combined, these circumstances pumparound streams to the crude hinder any future retrofits.
present a convincing opportunity feed by the application of heat Implementing such retrofit strate-
for industrial manufacturers to exchanger networks reduces the gies in practice may be difficult due
implement energy saving projects energy demands of both coolers to constraints related to topology,
and processes to lower their energy and furnaces. This reduction in safety and maintenance, which
consumption and reduce their energy demand diminishes operat- often exist in a complex network.6
carbon footprint. ing costs while increasing the As well, the capital cost is usually
Crude distillation units (CDUs) capital cost of the exchanger area high because of the considerable
are major consumers of energy in installation; therefore, a retrofit piping and civil works required for
oil refineries because of the high design is preferable to a grassroots the retrofit and potential produc-
energy consumed in the crude design for oil refineries. In a real tion losses during process
furnace.4 Retrofit of the crude situation, the uncertain quality of modification. Since the late 1970s,
Naphtha
Preheat Crude
exchangers furnaces
5 SC Fuel oil
Desalter
6 SC
HCK
Preheat 6 7 SC
J80
exchangers 8 SC
Reduced
crude
Crude from Vacuum residuum Visbreaker
tankage Crude J85
furnaces
Paving
Cutback
Asphalt
Air
blower
a certain minimum value. The two constraints, there are usually Pinch analysis is used to identify
composite streams are moved hori- enough opportunities for inter-unit energy cost and heat exchanger
zontally toward each other until integration to make the overall network capital cost targets for a
this minimum temperature differ- target calculations valid. A major process, and for recognising the
ence is reached at one point. This advantage of using pinch technol- pinch point. The procedure first
point is known as ‘the pinch’. ogy for target setting is that a predicts, ahead of design, the mini-
As Figure 1 shows, composite structured approach can be used to mum requirements of external
temperature enthalpy graphs can survey a large chemical plant or energy, network area, and the
be used to set targets for process- refinery. The approach ensures that number of units for a given process
to-process heat recovery, furnace attractive possibilities for inter-unit at the pinch point. Next a heat
duty, and cooling loads. Process-to- integration are identified and eval- exchanger network design that
process heat recovery is possible uated first. Once this is satisfies these targets is synthesised.
wherever the hot composite stream accomplished, attractive intra-unit Finally the network is optimised by
is vertically above the cold compos- heat recovery improvements are comparing energy costs and the
ite stream. As this procedure identified and evaluated further. capital cost of the network so that
involves only simple summations The structured approach not only the total annual cost is minimised.
over the streams, it can be applied ensures that no attractive improve- Thus, the prime objective of pinch
to a single process unit, a group of ments are missed, but also avoids analysis is to achieve financial
process units, or even an entire unnecessary effort in screening savings by better process heat
chemical plant or refinery. A intra-unit heat integration possibili- integration (maximising process-to-
number of commercial computer ties when inter-unit integration is process heat recovery and reducing
programs14, 15 are available to make either a better alternative or an the external utility loads).
this task relatively easy to perform. additional part of a revamp effort.
Although it is not possible to heat These features are major advan- Case study
integrate some units because of tages over previous approaches The primary focus of this study
operational, safety or piping cost based on multiple case studies. was to identify the most cost effec-
°F
°F
10
13
Train A 284.81°F Off gas
5.
3.
23
27
284.78°F
E-261 E-131 D-103
Atmospheric
°F
°F
°F
A/B/C
61
52
85
overhead
4.
6.
4.
Sour
17
10
28
SC-4 SC-2 ATCR
D-124 E-102 water
D101
°F
°F
°F
Desalter E-101 Off gas
66
95
70
3.
9.
0.
20
23
30
C-300
°F
Naphtha
25
E-142 E-121 E-116 TIC
8.
stabiliser
28
Train B A/B/C
D-301
Hot recycle 555.08°F Reflux
118.37°F
Secondary crude preheat trains E-305
E-301
°F
Train C
93
ATCR
9.
Stabilised
24
VR & BQ ABCR SC-8 & VBCR SC-4 ATCR
naphtha
°F
°F
°F
°F
°F
°F
°F
Pump
E-302
08
74
75
43
66
05
81
around
5.
4.
6.
0.
8.
0.
4.
55
58
52
42
38
35
28
369.13°F
SC-1
E-291 E-145 E-282 E-141 E-115 465.69°F
A/B/C A/B/C A/B/C A/B A/B/C Flue SC-2
gas
°F
502.78°F
00
°F
°F
°F
°F
°F
°F
49
81
ABCR
21
43
31
07
2.
4.
7.
9.
1.
1.
41
28
52
43
35
31
666.22°F
Pump
E-292 E-271 E-283 around
A/B/C/D/E/F A/B A/B SC-4
Train D 585.10°F
NC
555.08°F SC-5
Flash
Vacuum F-100 A/B zone 641.94°F
overhead Vacuum
174.57°F furnaces
Stripping steam 673.23°F Vacuum
overflash
C-100 Atmospheric
Atmospheric 647.69°F bottoms to
distillation vacuum furnaces
column F-200 A/B
VTCR P/A
SC-6
332.35°F
SC-7 NC
546.97°F SC-5
From C-100
Flue
gas
°F
35
7.
72
C-200
Mid Vacuum F-200 A/B
reflux distillation Vacuum
VBCR P/A column furnaces
SC-8
643.52°F
749.78°F
647.69°F
Vac O/F
673.23°F
Vac
resid 675.21°F
Cold streams
Stream Heat exchanger Tin, °F Tout,°F Duty, MMBtu/hr
Total feed E-101 87.6 162 145
Feed1 to desalter E-261 162 251 94
E-131 251 285 37
Feed2 to desalter E-142 162 188 26.6
E-121 188 227 40.1
E-116 227 290 70
Feed1 to furnace E-283 284 305 22
E-271 305 346 42.5
E-292 346 429 91.8
E-281 429 534 126.2
Feed2 to furnace E-115 284 332 57.1
E-141 332 379 56.2
E-282 379 424 57.4
E-145 424 513 119.7
E-291 513 560 66.5
Furnace F-100 548 679 383
Reboiler for C-300 E-305 340 364 56.3
Feed to C-300 E-301 130 295 41.4
Hot streams
OVHD of C-100 E-101 264 168 145
E-102 162 130 27.3
VC top SC6 E-261 382 214 94
E-262 214 192 27.3
SC3 E-131 486 280 37.3
E-133 280 66 31.8
SC2 E-121 445 219 40.57
E-122 219 72 22
ATCR E-115 361 325 57
E-116 325 278 70
278 271 1.1
SC4 E-141 565 344 56.2
E-142 344 224 26.6
E-143 223 102 23.7
Bottom recycle E-145 581 501 119
E-305 475 435 56.3
E-146 435 423 16.1
Vacuum bottom E-291 676 603 66.5
E-292 603 489 91.8
Visbreaker feed E-293 489 355 51.2
SC7 E-271 499 324 42
E-272 324 317 1.7
SC8 E-281 628 518 126
E-282 518 465 54.2
SC8-1 E-283 465 392 22
Bottom C-300 E-301 350 170 56
Table 1
tive potential energy saving and The main driver for this study year. This is the earliest expected
enhancement initiatives through has been the expected rise in the time frame in which potential
optimising refinery ADU/VDU cost of energy over time and new design modifications would be
plant heat integration, waste heat initiatives aimed at improving the commissioned in the unit.
recovery and utilities consumption refinery margins and energy inten- According to company project
in the crude preheat section at sity index performance. At the time cost forecasting practices, the net
minimum capital/operating cost this study was conducted, the present value (NPV) will be based
requirements. This would enable a corporate price for fuel gas was on a minimum 20-year operational
considerable reduction in the $5.90/MMBtu. This price is period. In addition, an assumed
required furnace duties and corre- projected to rise significantly within discount rate of 6.5% is used for
sponding reduction in fuel gas the coming years according to economic analysis as an estimate
consumption. This study consid- corporate planning quarterly for a large national corporation oil
ered modifications to both unit reporting. In fact, this study consid- refinery.
design and operation to achieve the ers a starting price of $7.40/ The study is a complete and
ultimate goal of improved energy MMBtu, which is the projected definitive energy assessment along
efficiency for the ADU/VDU and price by the beginning of year 2017 with a preliminary design of the
an overall improvement of the as the established price utilised for new required heat exchangers and
refinery’s energy intensity index. all new projects starting up that crude preheat configuration.
352°F
VR product
424°F VR quench
33.5 Mlb/h to C-200
E-293 42.7 Mlb/h
40 424°F
641°F
308°F
SC-8
ADU/VDU overview residuum. Two vacuum gas oil until an appropriate level of confi-
A plant’s crude distillation unit streams feed the hydrocracker dence was obtained in the base case
(atmospheric and vacuum distilla- plant. As much as 20 000 b/d of the simulation of the plant.
tion) currently processes 325 000 vacuum residuum can be charged The model output material and
b/d of crude oil feed consisting of to the asphalt section with the heat balance were compared to real
65 LV% (211 000 b/d) Arabian balance of the residuum going to a plant data to ensure the percentage
Light Crude (AL) and 35 LV% visbreaker and later to fuel oil error is accepted within engineer-
(114 000 b/d) Arabian Heavy blending. ing limits.
Crude (AH). The plant also has A plant overview block diagram Lab data was used to assure the
asphalt producing facilities. The is shown in Figure 2. The plant simulation model output product
sustainable asphalt production overview process flow diagram is specification matches the real prod-
(paving and cutback) with 100% shown in Figure 3. uct specifications.
AL charged to the plant is 18 000
b/d, and 20 000 b/d when a mixed ADU/VDU hot and cold stream data Simulation model
crude of AL and 100 000 b/d of The cold streams to be heated and Once the base design model case
AM or AL and 30 000 b/d of AH hot streams to be cooled for the was established and the output
crude is processed. ADU/VDU plant used in this study figures matched real data, there
The products from the plant are: are shown in Table 1. commenced conversion of the
LPG, stabilised whole naphtha, model to a more comprehensive
kerosene, diesel (DGO), heavy Study approach rating model by using the heat
diesel, and vacuum residuum. The ADU/VDU plant process variables exchanger actual rating data. This
atmospheric column receives the (data collection) step involved extensive trouble-
crude charge and separates it into The plant information system was shooting in order to ensure
overhead product, kerosene, DGO, used to obtain relevant plant histor- non-modified parameters at the
and reduced crude. The naphtha ical process data such as flow rates, same values as the base case to
stabiliser receives the atmospheric temperatures, and pressures over maintain the benchmark for accu-
overhead stream and separates it different time intervals, and yearly rate comparisons.
into LPG and stabilised naphtha. average figures were used in build- At this stage the model was
The reduced crude is charged to ing the primary design simulation ready for engineers to propose
the vacuum tower where it is model. This step also involved improvements and alterations to
further separated into heavy diesel, comparing and consolidating actual the plant, thereby developing the
vacuum gas oils, and vacuum plant data to the simulated data, modification case.
Modifications to atmospheric E-146 (not in use) will be required. It should be noted that the
bottom pumparound (ABPA) proposed modifications maintain
The ABPA will be rerouted to Modifications to side cut 8 HVGO all column returned temperatures
exchange with crude in E-282 product streams and so the column temperature
downstream E-145, then to E-305 A total load of E-282 will be trans- profile, as well as the product
(unstabilised naphtha reboiler) to ferred to a new heat exchanger battery limit temperatures, will
exchange heat with unstabilised (NHX3) between the SC8 and have no impact on the current
naphtha from C-300 bottom to furnace feed. E-282 will be used to process operation. It is worth
reach 417°F, then back to the exchange heat between the bottom mentioning that a hydraulic study
atmospheric column. ABCR and crude feed as described was performed and validated the
This requires no new heat above. One new heat exchanger is capability of the entire hydraulic
exchangers. Modification to required – NHX3 system, especially the operation
Atmospheric furnace summary table Duties and fuel gas rates for F-100 A/B Potential savings from base case
Case Crude Tin, °F Duty, MMBtu/hr FG rate, MMSCFD Duty, MMBtu/hr FG rate, MMSCFD
Base Case F-100A/B 552.5 755.60 23.840 --- ---
Modified Case 572.1 698.80 22.040 56.80 1.800
Table 2
Steam requirement
Heat exchangers Steam type import/export Mass flow, lb/hr Duty, MMBtu/hr Tin, °F Tout, °F
E-293 (base case) LPS #60 - Generation 42 750.00 40.14 287 313
E-293 (modified) LPS #150 - Generation 33 510.00 32.07 287 352
E-146 (base case) MPS #150 - Generation 24 760.00 21.50 366 379
E-146 (modified) MPS #60 - Generation 19 100.00 16.55 366 371
Table 3
Table 6