Equipment Calibrated
Make Sr. No.
4. Details of Used on Date
Instrument Used: CRM KIT CRM KIT
IR TESTER IR TESTER
MEASURED IR VALUE IN GΩ
PHASE UPPER TERMINAL AND EARTH LA OF THE WAVE TRAP
(5000 V) (500 V)
R–Ø
Y–Ø