0% found this document useful (0 votes)
101 views3 pages

Test Report of Wave Trap: Client Sr. No. Location Testing Date Tested by Report No. Report Prepared by Report Reviewed by

This test report summarizes diagnostic testing performed on a wave trap located at Jaypee Bina Thermal Power Plant. The report provides background details on the purpose of the testing as part of preventive maintenance activities. It lists the scope of work to carry out testing and submit a detailed report. Test results are presented, including insulation resistance and contact resistance measurements for each phase of the wave trap. The document is intended for commercial and maintenance purposes by Jaypee Bina Thermal Power Plant.

Uploaded by

mayur dhande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
101 views3 pages

Test Report of Wave Trap: Client Sr. No. Location Testing Date Tested by Report No. Report Prepared by Report Reviewed by

This test report summarizes diagnostic testing performed on a wave trap located at Jaypee Bina Thermal Power Plant. The report provides background details on the purpose of the testing as part of preventive maintenance activities. It lists the scope of work to carry out testing and submit a detailed report. Test results are presented, including insulation resistance and contact resistance measurements for each phase of the wave trap. The document is intended for commercial and maintenance purposes by Jaypee Bina Thermal Power Plant.

Uploaded by

mayur dhande
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Client Sr. No.

Location Testing Date


Page | by
Tested 1 Report No.
Report prepared by Report Reviewed by

TEST REPORT OF WAVE TRAP

Nameplate Detail of Wave Trap:


Manufacturer
Voltage
Serial Number/Bay Number
Year of Manufacture

Purpose of Distribution:
This document is distributed to Jaypee Bina Thermal Power Plant for their own commercial and
maintenance purposes. Rights to copy or distribute this document are only granted for the stated
purpose. The document may not otherwise be used or distributed without the prior written
permission of Laxmi Associates.
Client Sr. No.
Location Testing Date
Page | by
Tested 2 Report No.
Report prepared by Report Reviewed by

Sr. No. Content Page No.


1 Background
2 Scope of work
3 Reference
4 Instrument used
5 Details of Test & Data Analysis

-As a part of preventive maintenance activities Jaypee Bina Thermal


Power Plant has decided to carry out testing on their Wave Trap.
1. Background:
-For the stated purpose Jaypee Bina Thermal Power Plant,
appointed Laxmi Associates as service provider & The detailed test
results and analysis are given in this document.
-Carry out diagnostic testing on Wave Trap and submit a detailed test
2. Scope of work:
report.
The condition of Wave Trap is evaluated in reference with the following
standards and publications.
3. Reference:
- IEC. 60353. Second edition, 1989-10. Line Trap for A.C Power
System.2. IS: 8792-1978. LINE TRAPS For AC Power Specification.

Equipment Calibrated
Make Sr. No.
4. Details of Used on Date
Instrument Used: CRM KIT CRM KIT
IR TESTER IR TESTER

5. Details of Test Results and Analysis:


Client Sr. No.
Location Testing Date
Page | by
Tested 3 Report No.
Report prepared by Report Reviewed by

5.1.1 INSULATION RESISTANCE MEASUREMENT TEST

MEASURED IR VALUE IN GΩ
PHASE UPPER TERMINAL AND EARTH LA OF THE WAVE TRAP
(5000 V) (500 V)
R–Ø
Y–Ø
B–Ø

5.1.2 CONTACT RESISTANCE MEASUREMENT TEST

CONTACT RESISTANCE (µΩ)


CURRENT
PHASE ACROSS TERMINAL ACROSS TERMINAL
INJECTED (A)
P1 P2
R–Ø 100
Y–Ø 100
B–Ø 100