Description Unit Qty Unit Cost Total Cost Rev. Cost Remarks
No.
1 Labour Charge
2 Axles
3 Rims
4 Spacers
5 Tyre
6 Landing Leg
7 King Pin
8 Brake System
9 Cylinder
10 Electrical System
11 Chassis
12 Channels
13 Steel Sheet
14 Chequered Plate
15 Tube
16 UPN
17 Pipe
18 Welding Material
19 Gas & Consumables
20 Tool Box
21 Water Tank
22 Bumper
23 Spare Wheel Carrier
24 Mudguard with Flap
25 Machining
26 Rolling
27 Bending
28
29
30
Optional
1
2
3
4
5
6
7
8
9
10
Revised Cost :