Punchlist Clearance Rev.01 AFC
Punchlist Clearance Rev.01 AFC
Punchlist Clearance Rev.01 AFC
A) DESB’S INHOUSE
B) SUBMISSION TO JX
INDEX / CHECKLIST
1.2 Objectives
5.0 Procedures
8.0 Drawings
1.2 Objectives
The purpose of this workpack is to provide specific instructions and safe guides to
the personnel engage in BU-1 ST1 Rectification and HL-10 & HL-11 work on Helang
Integrated Platform.
DESB have identified the numerous activities based on work priority due to short
shutdown window and to utilize ALQ bedding to accommodate construction’s crew.
Offshore Work
o BU-1 Rectification: Replace Seal Ring
Erect Scaffolding (Pre SD scope)
Break Flange – 6 joints (SD scope)
Replace Seal Ring and reinstate Piping (SD scope)
Bolt Torquing (SD scope)
Dismantle Scaffolding (Post SD scope)
The works will be commencing in February 2019 for duration of 2 days shutdown
period. Work execution will be carried out during platform Shut Down, where
concurrent activities are going on such as daily operation and maintenance. The
manpower requirements will be accommodated at ALQ
The project materials will be delivered to DESB warehouse for storage purposes
prior shipment to offshore location via Asian Supply Base (ASB). Materials will be
inspected and verified DESB Matco and QA/QC against delivery order (DO),
purchase order (PO) and materials take-off (MTO) where the inspection will be
witnessed by JX Nippon Representative. This will be transpired and logged into
DESB materials verification record form (MVR) and filed for reference.
Preservation and safe keeping to be carried out accordingly to avoid any damage
to sensitive and rusting of metal materials.
The platform main pedestal crane will be utilized to lift-up all construction
materials, equipment and tools from supply vessel and then place it at the
identified storage area in the upper deck.
DAYANG ENTERPRISE SDN. BHD.
(Company No. 61505-V)
During construction or maintenance activities, DESB crew will hand carry small
items and large items such as compressors, tool boxes, consumable close
container, scaffolding materials etc will be transferred to nearest work location
via platform main pedestal crane.
1.8.1 There are few major constraints that have impact on the project
schedule need to be taken into considerations but not limited to are as
below;
1.8.1.1 Materials availability
1.8.1.2 Limited time of Shut Down window
1.8.1.3 Adverse weather
1.8.1.4 HIP Operation requirements
In general, the work will not start until Permit To Work (PTW) has been approved
and issued out by HIP issuing authorities. Upon receiving the approved PTW,
DAYANG ENTERPRISE SDN. BHD.
(Company No. 61505-V)
supervisors should conduct tool box meeting with the crew that is to explain on
the workscope, HSE issue and etc which is related to the work.
2.1.1 Structural
NIL
2.1.3 Instrument
NIL
2.1.4 Electrical
NIL