Question 1 – Critical Path Method / 10 Marks
The activities of a project have the following durations (in weeks), dependencies and
resources.
Activity Duration Dependency
(Weeks)
A 2 -
B 4 A
C 6 B
D 3 A
E 7 B, D
F 5 C
G 2 F
H 1 C, E
J 4 E
K 6 H
L 3 J
M 2 K, L
N 4 G, K
O 2 N, M
P 2 O
Part 1: Draw a AoN Network Diagram (7 Marks)
Part 2: Determine the overall project duration (1 Marks)
Part 3: Determine the overall project critical path (1 marks)
Part 4: What is the project critical path if the Dependency on Activity G is changed
from F to F, H (1 Marks)