Turbine Start Up
Turbine Start Up
ATTENTION: Water must be available to the exhaust hood spray control valve and lub
oil cooler when ever the turbine is rolling over 3 rpm.
Turbine and Bypass system Status at 600rpm
SYSTEM/VALVE STATUS
Throttle Valves Fully closed
Governor Valves Fully open(Single Valve Mode)
Interceptor Valves Half of the valves will be throttling in speed control
(demand to valve has a small bias)
Reheat Stop Valves Fully open
HP Turbine Exhaust Vent Valve Open to keep HP turbine under vacuum
HP Exhaust Check Valve Closed due to pressure difference between Cold
Reheat and HP exhaust.
VVV Inlet Loop Vent Valves Closed
HP Drain Valves Open
IP Drain Valves Open
LP Exhaust Hood Sprays Closed
HP Bypass Controlling Main Steam pressure at its setpoint
LP Bypass Controlling Hot Reheat pressure at its setpoint
The eccentricity recorder < 600 rpm ( less than 0.076 mm )
Monitor vibration at speeds above 600 rpm.
Turbine and Bypass system status (during the turbine speed ramp up to the IV to
TV/IV transfer speed)
SYSTEM/VALVE STATUS
Throttle Valves Begin opening to take control of speed
Governor Valves Fully open(Single Valve Mode)
Interceptor Valves Half of the valves will be throttling in speedcontrol
(demand to Valve has a small bias) until IV to IV/TV
transfer speed is reached. Once transfer is complete, IV
is will throttle alongwith TV is to hold speed.
Reheat Stop Valves Fully open
HP Turbine ExhaustVent Valve Open to keep HP turbine under vacuum
HP Exhaust Check Valve Closed due to pressure difference between Cold
Reheat and HP exhaust.
VVV Inlet LoopVent Valves Closed
HP Drain Valves Open
IP Drain Valves Open
LP Exhaust Hood Sprays Closed
HP Bypass Controlling Main Steam pressure at its setpoint
LP Bypass Controlling Hot Reheat pressure at its setpoint
Turbine and Bypass System Statues during Load Changing ( Constant Pressure )
SYSTEM/VALVE STATUS
Throttle Valves Pully opened
Governor Valves Controlling a constant low throttle pressure.
Interceptor Valves Fully opened at approximately the same load as by pass
valves are fully closed.
Reheat Stop Valves open
HP Turbine ExhaustVent Valve Close
HP Exhaust CheckValve Open
VVV Inlet LoopVent Valves Closed
HP Drain Valves Close at 10% load
IP Drain Valves Closed at 20% load
LP Exhaust Hood Sprays Off at 10% load
HP Bypass Closed ( in Standby mode )
LP Bypass Closed ( in Standby mode )
When the 5th stage extraction pressure falls to 0.147MPa, deaerator steam source will change
over from 4th stage extraction to auxiliary steam automatically.
Decrease load gradually to 330MW.
LIMITATION
LP defferential expantion for long rotor alarm 12.0768 and trip 12.32 input I & C mA
LP defferential expantion for short rotor alarm 6.8736 and trip 7.1168 input I & C mA
HP defferential expantion for long rotor alarm 18.016 and trip 18.624 input I & C mA
HP defferential expantion for short rotor alarm 6.752 and trip 7.36 input I & C mA
Bearing oil pressure alarm 0.075 -0.084 Mpa shut down 0.069 -0.075 Mpa
Cold start up,steam is admitted to the Turbine with a minimum of 56°C superheat at the throttle
valve inlet but not more the 427°C total temperature
Temperatue steam for start up >56 °C upper saturated steam maximum 111 °C
Bearing LO press interlock with Turning gear and lifting oil pump 0.31 kpag
Lifting oil system oil pres > 4.2 Mpag turning gear can put into work
Lifting oil system oil pres < 6.5 Mpag spare lifting oil pump into work
Eccentricity should not exceed 0.076 mm double amplitude ( Turning Gear to 600 rpm)
Drain from sources up stream of the Turbine reheat stop valves close 10 % load
Drain from sources up stream of the Turbine Interceptor valves close 20 % load
Gland steam operation temperature 121 °C - 177°C normal operation 142 °C minimum 14°C
Superheat .Diff temp rotor and steam must less than 110 °C
Pressure swing 105 % press and accidental swing pressure 120 % does not exceed 12 hour over any
12 months. The temperature differential between multiple Condenser (or Condenser zone ) should
not excess 17 °C and alarm at 11°C differential and trip the unit at 17 °C differential. The permissible
pressure differential between multiple Condenser ( or Condenser zones ) is 8.6 kpa (a) alarm at 6.9
kpa (a) differential and trip the unit at 8.6 kpa (a)
Relay setting
Bearing lubricating oil pressure 0.069 – 0.075 Mpa ( g) the emergency oil pump put into work
Bearing lubricating oil pressure 0.031 Mpa ( g) interlock with turning gear and lifting oil pumps
Lifting oil system oil pressure > 4.2 Mpa(g)turning gear can put into work
Lifting oil system oil pressure < 6.5 Mpa(g) spare lifting oil pumpput into work
The actual pressure setting values are specified on the “Turbine Control Setting”.All the pressure
switch in lubricating oil supply system must test at least once a year
For Cold start ,hold the speed out of blade resonant speed range and shaft critical speed for warning
period determined from the curve “Cold start rotor warning prosedure”
Power 37 Kw
Voltage 400 V
Jacking oil work 6.5 Mpa ,Turning Gear can’t worked 4.2 Mpa
Generator change fuction mechanical power of the steam Turbine into electricity.Turn the power of
the steam Turbine is coupled directly to the Generator with rotation 3000 rpm to generate
electricity with a voltage of 22 Kv at 50 Hz freq , and the number of turn of the rotor 1 pair of pole.
Generators installed to generate electricity with the help of outside excitations which are often
called Static Exciter with Scroll Ring existing intermediaries in the shaft generator .
As a generator is equipped with a cooling medium Generator Stator Cooling with water media that
didionisasi make up water with conduktivity 0.5 µs/cm ~ 1.5 µs/cm , as for alarm 5 µs/cm and very
high alarm 9.5 µs/cm
For conditioning Generator ( Rotor ) Hydrogen gas is used media with 4.5 barg pressure ( 4.2 - 4.8
barg ) with temperatures ranging from 40- 48 °C and 50 °C alarm
Normal leaking H2 gas 0.14 m³/day ,when leaking more 0.57 m³/day this is caution may be throuble
by seal oil system and than leaking 11.3 m³/day the Generator mast be shut down.
To avoid leakage of gas H2 is also equipped with oil seal system with normal operation of the
channel Main Lube Oil Pump .
When the Generator and its associated equipment have been completely installed on site.
The following items will be adjusted and inspected prior on the commercial.
The Formula
V gen = x VG x ( - )
t 273 + T1 273 + T2
= x 98 x ( - ) = 1.677 m³/day
VG = generator volume m³ = 98 m³
Pe1 = the pressure of the system when begin testing = …4500.6m bars
Pe2 = the pressure of the system when ending testing = …4489.5 m bars
Pamb1= atmospheric pressure when began to test = 1011 mbar
T2 = gas temperature when end testing = (28.1+28.1+ 27.7 +28.3 )/4 = 28.05°C
If the air leakage is greater than 2.1 m³ 9stp ) ͒/24 h ,then there are existence of leak
*∆ P Gas H2 with oil seal 0.84 kpa range ( 0.5 kpa ~ 0.9 kpa )
Water quality
Normal limit values and reasonable achievable values in normal operation for Condensed steam
sample. Conductivity at 25 °C downstream of strongly acidic sampling cation exchanger continous
measurement at sampling point normal < 0.2 µs/cm for Power plant 0.1 µs/cm
PH 9.3 - 9.6
9 HP Feedwater PH
The steam blowing coefficients of Superheater and Reheater shall be greater than 1.0
The target width shall be 8 % pipe inside diameter at the installation point of target and not be less
than 25 mm, the thickness not less than 5 mmand the length is longitudinally through the pipe inside
diameter ,the target surface roughness shall reach to Ra 100
Acceptance critical for aluminium target plate , inspect each of two conditionous target plate no
spot above 0.8 mm, and total quantity of the spots between 0.2 mm- 0.8 mm should not be more
than 8
Target plate of steel , cooper or other materials ,the acceptance criteria shall refer to the
manufacturer’s requirement.
Parameter of cleaning
Concentration of Na3 PO4 ~ 0.2 % - 0.5 % = 3.5 t (chemical quantity) / 700 = 0.5 %
Concentration of Na2 PO4 ~ 0.1 % - 0.2 % = 1.4 t (chemical quantity) / 700 = 0.2 %
Concentration of anti foam ~ 0.04 % = 0.28 t (chemical quantity) / 700 = 0.04 %
Temperature water cleaning 50 ± 5 °C put the auxialiary steam into operating for heating
Water flushing PH ≥ 9
Condensor ~ Condensate Pump ~ Gland steam Condensor ~ LP Heater (water and steam side) ~
Deaerator ~ feed water Pump ~ HP Heater ( water and steam side ) ~ included the piping of
Condensate & feed water system
In order to get the expected movement at three different directions during the Boiler operation, the
fixed expansin center is setup ,which is symmetrically laid out from left to right ,and 915 mm away
from the rear wall center line. Physically ,this is the crossing of the axial line of expansion point fixed,
the hanger –buckstay system is developed, which is olso the basis of each pressure part expansion
,piping stress and flexibility analysis calculation
Fluid temperature change at the outlet of any furnace pass must not exceed
the rate 1.85-2.0℃/min. .
Caution: More sootblowing is not necessarily better. Excessive blowing frequency and pressure
beyond what is needed to keep unit clean, will result in erosion damage to tubes.