WORKSHOP , R.MESIN NITROGEN , PEMBANGUNAN WORKSHOP MAINTENANCEE TERSUS DAN PEK. SPORADIS
PT.WHW-AR
RAB
ITEM UNIT PRICE (RAB) TOTAL PRICE (RAB)
NO URAIN PEKERJAAN QTY (ESTIMASI) UNIT
selisih harga
PROYEK PENAMBAHAN RETAINING
1.00 Harga Besi Angkur ± 3,403 /Btg Rp 120,000.00 Rp 408,360,000.00
WALL BATUBARA
Harga Bobok lantai beton (include ongkos angkut beton
± 35.36 m3 Rp 15,000,000.00 Rp 530,400,000.00
bobokan radius 5Km)
Harga Galian (include ongkos angkut radius 3 km) ± 1,100.00 m3 Rp 130,000.00 Rp 143,000,000.00
TOTAL I Rp 19,771,261,600.00
BANGUNAN WORKSHOP
2.00 Harga Bangunan Workshop Maintenance ± 1.00 Ls Rp 4,079,149,929.55 Rp 4,079,149,929.55
MAINTENANCE
TOTAL II Rp 4,079,149,929.55
PEKERJAAN SPORADIS (SALURAN,BAK Harga saluran (include galian, muat radius 2 km dan
4.00 ± 50.00 m' Rp 700,000.00 Rp 35,000,000.00
KONTROL,GALIAN, PENGELASAN PIPA penimbunan kembali)
harga instalasi dan las pipa besi (pipa besi suppyl pihak
± 27.00 m Rp 400,000.00 Rp 10,800,000.00
pertama)
TOTAL IV Rp 468,000,000.00
JUMLAH TOTAL Rp 25,000,591,815.71
FORM PENAWARAN PROYEK PENAMBAHAN RETAINING WALL BATUBARA GUDANG SODA ASH, BANGUNAN WORKSHOP , R.MESIN NITROGEN , PEMBANGUNAN
WORKSHOP MAINTENANCEE TERSUS DAN PEK. SPORADIS PT.WHW-AR
Harga Timbunan dan pemadatan ± 400.00 m3 Rp 250,000.00 Rp 100,000,000.00 443.56 M3 43.56 M3 10,889,000.00
BANGUNAN WORKSHOP
2.00 Harga Bangunan Workshop Maintenance ± 1.00 Ls Rp 5,211,918,053.96 Rp 5,211,918,053.96
MAINTENANCE
TOTAL II Rp 5,211,918,053.96
PEKERJAAN SPORADIS (SALURAN,BAK Harga saluran (include galian, muat radius 2 km dan
4.00 ± 50.00 m' Rp 700,000.00 Rp 35,000,000.00
KONTROL,GALIAN, PENGELASAN PIPA penimbunan kembali)
harga instalasi dan las pipa besi (pipa besi suppyl pihak
± 27.00 m Rp 400,000.00 Rp 10,800,000.00
pertama)
TOTAL IV Rp 468,000,000.00
RAB
ITEM UNIT PRICE (RAB)
NO URAIN PEKERJAAN QTY (GAMBAR) UNIT
TOTAL I
BANGUNAN WORKSHOP
2.00 Harga Bangunan Workshop Maintenance ± 1.00 Ls Rp 4,079,149,929.55
MAINTENANCE
TOTAL II
TOTAL III
PEKERJAAN SPORADIS (SALURAN,BAK Harga saluran (include galian, muat radius 2 km dan
4.00 ± 50.00 m' Rp 700,000.00
KONTROL,GALIAN, PENGELASAN PIPA penimbunan kembali)
harga instalasi dan las pipa besi (pipa besi suppyl pihak
± 27.00 m Rp 400,000.00
pertama)
TOTAL IV
JUMLAH TOTAL
ASH, BANGUNAN
AN PEK. SPORADIS
Rp 1,899,450,000.00
Rp 78,975,000.00
Rp 110,889,000.00
Rp 202,500,000.00
Rp 7,087,500,000.00
Rp 9,676,305,000.00
Rp 240,000,000.00
Rp 19,770,819,000.00
Rp 4,079,149,929.55
Rp 4,079,149,929.55
Rp 682,180,286.16
Rp 682,180,286.16
Rp 35,000,000.00
Rp 1,600,000.00
Rp 50,000,000.00
Rp 3,600,000.00
Rp 10,800,000.00
Rp 3,000,000.00
Rp 224,000,000.00
Rp 140,000,000.00
Rp 468,000,000.00
Rp 25,000,149,215.71
RENCANA ANGGARAN BIAYA
PROYEK : Bangunan Workshop Maintenance
LOKASI : Kendawangan, Kalbar
REKAPITULASI
A PEKERJAAN PERSIAPAN Rp 231,210,000.00
B PEKERJAAN TANAH & GALIAN Rp 43,288,693.00
C PEKERJAAN BETON BERTULANG Rp 2,207,373,050.21
D PEKERJAAN STRUKTUR BAJA Rp 589,108,800.00
E PEKERJAAN PASANGAN DINDIND & BATU KALI Rp 422,287,089.84
F PEKERJAAN SENG GELOMBANG Rp 177,838,080.00
G PEKERJAAN PLAFOND Rp 102,603,501.00
H PEKERJAAN TALANG Rp 11,119,500.00
I PEKERJAAN FINISHING Rp 103,346,068.00
J PEKERJAAN PINTU & JENDELA Rp 56,473,200.00
K PEKERJAAN ELEKTRIKAL Rp 98,109,000.00
L PEKERJAAN HYDRAN & APAR Rp 36,392,947.50
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi dari Awal Pelaksanaan s/d selesai Ls 1.00 7,000,000.00 7,000,000.00
2 Pekerjaan Pengukuran Site Ls 1.00 10,500,000.00 10,500,000.00
3 Pagar Pengaman Proyek Ls 1.00 8,400,000.00 8,400,000.00
4 Papan Nama Proyek bh 1.00 1,050,000.00 1,050,000.00
5 Foto Proyek 3 phase Ls 1.00 1,260,000.00 1,260,000.00
6 Kantor Direksikeet Lengkap Pasilitasnya unit 1.00 42,000,000.00 42,000,000.00
7 Biaya Manajemen , Asbuilt Drawing & Dokumentasi ls 1.00 52,500,000.00 52,500,000.00
8 Listrik kerja ls 1.00 28,000,000.00 28,000,000.00
9 Air Kerja ls 1.00 10,500,000.00 10,500,000.00
10 Peralatan Keselamatan Kerja ( K3 ) Ls 1.00 17,500,000.00 17,500,000.00
11 Asuransi CAR Ls 1.00 52,500,000.00 52,500,000.00
Sub Total Pekerjaan Persiapan 231,210,000.00
G PEKERJAAN PLAFOND
Plafond gypsum tebal 9 mm + rangka hollo galvanis m2 313.20 327,600.00 102,603,501.00
Sub Total Pekerjaan Plafond 102,603,501.00
H PEKERJAAN TALANG
Pekerejaan talang + pipa pembuangan m 30.00 370,650.00 11,119,500.00
Sub Total Pekerjaan Talang 11,119,500.00
I PEKERJAAN FINISHING
a. Finishing cat besi ls 1.00 17,500,000.00 17,500,000.00
b. Finishing cat tembok, Lapex w. putih m2 2,197.80 39,060.00 85,846,068.00
Sub Total Pekerjaan Finishing 103,346,068.00
K PEKERJAAN ELEKTRIKAL
a. Instalasi lampu pabrik (dengan ballas hemat energi 250 watt) ttk 14.00 606,000.00 8,484,000.00
b. Instalasi stop kontak,2 & 3 lubang tanam 220V 10A ttk 33.00 445,000.00 14,685,000.00
c. Instalasi stop kontak AC 220V, 20A ttk 15.00 505,000.00 7,575,000.00
d. Instalasi saklar tunggal ttk 6.00 365,000.00 2,190,000.00
e. Instalasi saklar ganda ttk 2.00 393,000.00 786,000.00
f. Colokan internet RJ45 & RJ11 ttk 16.00 460,000.00 7,360,000.00
g. Switch board ttk 1.00 475,000.00 475,000.00
h. Kotak MEB ttk 1.00 380,000.00 380,000.00
i. Box panel lampu ttk 3.00 2,200,000.00 6,600,000.00
k. Box panel cadangan ttk 1.00 2,200,000.00 2,200,000.00
l. Lampu ceilling plafond, 30 V ttk 3.00 530,000.00 1,590,000.00
m. Lampu tunggal TL balok (ballast) 2 x 36 watt (di plafond) ttk 20.00 530,000.00 10,600,000.00
n. Saklar tombol tunggal ttk 1.00 360,000.00 360,000.00
o. Grounding m 140.20 120,000.00 16,824,000.00
p. Instalasi AC ttk 15.00 1,200,000.00 18,000,000.00
Sub Total Pekerjaan Elektrikal 98,109,000.00
b. Bawah sloof
DL1 0.10 x 0.50 x 67.50 =
b. Pedestal
Pedestal JC1 0.50 x 0.50 x 0.35 x 9.00 =
Pedestal JC2 0.60 x 0.70 x 0.35 x 2.00 =
Pedestal JC3 0.50 x 0.75 x 0.35 x 1.00 =
0.50 x 0.62 x 0.35 x 2.00 =
Pedestal JC4
0.70 x 0.75 x 0.35 x 2.00 =
0.50 x 0.55 x 0.35 x 1.00 =
Pedestal JC5
0.70 x 0.75 x 0.35 x 1.00 =
Pedestal JC2' 0.70 x 0.75 x 0.35 x 3.00 =
Pedestal JC3' 0.70 x 0.75 x 0.35 x 1.00 =
c. Sloof
DL1 0.30 x 0.60 x 210.70 =
GZ1 0.20 x 0.20 x 4.20 x 25.00 =
YPZ1 0.40 x 0.24 x 4.20 x 2.00 =
YPZ2 0.50 x 0.24 x 4.20 x 1.00 =
YPZ 0.20 x 0.40 x 4.20 x 4.00 =
4 Struktur Baja
a. GJ-01 (GJ-01a) 1,496.80 x 8.00 =
b. ZC1 606.20 x 2.00 =
c. SC1 Dia. 24 mm 9.50 x 2.00 x 4.00 / 12.00 =
d. GXG-01 Dia. 133 mm 7.50 x 15.00 x 1.00 x 16.70 =
4.20 x 6.00 / 12.00 x 1,128.00 =
e. GZ1 300x300
4.12 x 3.00 / 12.00 x 1,128.00 =
f. GL 300x180 7.50 x 12.00 / 12.00 x 595.20 =
g. Gording C 250x75x2x3 14.00 x 53.40 / 6.00 =
h. WYC (sambungan) 8.00 x 9.00 =
i. WLT Dia. 12 mm 1.20 x 10.00 x 14.00 / 12.00 =
j. WXL Dia. 12 mm 1.60 x 8.00 x 7.00 / 12.00 =
k. WCG Dia. 12 mm 1.20 x 8.00 x 7.00 / 12.00 =
7 Pekerjaan Plafond
Plafond gypsum 9 mm 6.15 x 23.50 =
2.20 x 16.00 =
7.00 x 15.00 =
8 Pekerjaan Talang 15.00 x 2.00 =
9 Pekerjaan Finishing
a. Finishing cat besi =
b. Finishing cat tembok, Lapex w. putih 999.00 x 2.00 =
10 Pekerjaan Listrik
a. Instalasi lampu pabrik (dengan ballas hemat energi 250 watt, 6 m dari lantai) =
b. Instalasi stop kontak,2 & 3 lubang tanam 220V 10A (0,3 m dari lantai) =
c. Instalasi stop kontak AC 220V, 20A (1,3 m dari lantai) =
d. Instalasi saklar tunggal =
e. Instalasi saklar ganda =
f. Colokan internet RJ45 & RJ11 =
g. Switch board =
h. Kotak MEB =
i. Box panel lampu (1,6 m dari lantai nempel di kolom) =
j. Box panel lampu (1,6 m dari lantai nempel di kolom/dinding) =
k. Box panel cadangan (1,6 m dari lantai nempel di kolom) =
l. Lampu ceilling plafond, 30 V =
m. Lampu tunggal TL balok (ballast) 2 x 36 watt (di plafond) =
n. Saklar tombol tunggal (1,3 m dari lantai) =
o. Grounding =
39.33 m3
15.98 m3
7.99 m3
18.18 m3
9.09 m3
23.97 m3
7.99 m3
71.48 m3
194.01 m3
4.14 m3
1.68 m3
0.84 m3
1.91 m3
0.96 m3
2.52 m3
0.84 m3
7.52 m3
3.38 m3
23.80 m3
17.01 m3 35
7.29 m3 11
3.65 m3 5
8.37 m3 12
4.19 m3 6
10.94 m3 16
3.65 m3 5
55.08 m3 90 423.02
0.79 m3 6
0.29 m3 2
0.13 m3 1
0.22 m3 2 90.30
0.37 m3 2
0.10 m3 1
0.18 m3 1
0.55 m3 3
0.18 m3 1
2.81 m3 18
37.93 m3 253
4.20 m3 42
0.81 m3 4
0.50 m3 2
1.34 13
44.78 m3 314
200.25 m3
0.86 m3
0.24 m3
304.02 m3 423.02
11,974.40 kg
1,212.40 kg
269.80 kg 42.60
1,878.75 kg
2,368.80 kg
1,162.12 kg
4,464.00 kg
6,930 kg 55.62
72 set
149.80 kg 10.70
79.89 kg 10.70
59.92 kg 10.70
854.40 m2
75.00 m2
63.00 m2
992.40 m2
450.00 m2
549.00 m2
999.00 m2
35.74 m3
144.53 m2
35.20 m2
105.00 m2
284.73 m2
30.00 m
1.00 ls
1,998.00 m2
14.00 ttk
33.00 ttk
15.00 ttk
6.00 ttk
2.00 ttk
16.00 ttk
1.00 ttk
1.00 ttk
1.00 ttk
2.00 ttk
1.00 ttk
3.00 ttk
20.00 ttk
1.00 ttk
4.00 ttk
REKAPITULASI
A PEKERJAAN PERSIAPAN Rp 50,800,000.00
B PEKERJAAN TANAH & GALIAN Rp 10,248,900.00
C PEKERJAAN BETON BERTULANG Rp 350,920,546.16
D PEKERJAAN BOBOKAN LANTAI BETON Rp 40,680,000.00
E PEKERJAAN PASANGAN DINDING Rp 119,788,800.00
F PEKERJAAN SENG GELOMBANG Rp 26,624,000.00
G PEKERJAAN FINISHING Rp 45,963,040.00
H PEKERJAAN PINTU & JENDELA Rp 37,155,000.00
HARGA SATUAN
JUMLAH HARGA
NO URAIN PEKERJAAN SAT VOLUME
Rp.
Rp.
A PEKERJAAN PERSIAPAN
1 Pembersihan Lokasi dari Awal Pelaksanaan s/d selesai Ls 1.00 4,000,000.00 4,000,000.00
2 Pekerjaan Pengukuran Site Ls 1.00 1,500,000.00 1,500,000.00
3 Pagar Pengaman Proyek Ls 1.00 12,000,000.00 12,000,000.00
4 Papan Nama Proyek bh 1.00 1,500,000.00 1,500,000.00
5 Foto Proyek 3 phase Ls 1.00 1,800,000.00 1,800,000.00
6 Kantor Direksikeet Lengkap Pasilitasnya unit 1.00 5,000,000.00 5,000,000.00
7 Biaya Manajemen , Asbuilt Drawing & Dokumentasi ls 1.00 5,000,000.00 5,000,000.00
8 Listrik kerja ls 1.00 5,000,000.00 5,000,000.00
9 Air Kerja ls 1.00 5,000,000.00 5,000,000.00
10 Peralatan Keselamatan Kerja ( K3 ) Ls 1.00 5,000,000.00 5,000,000.00
11 Asuransi Ls 1.00 5,000,000.00 5,000,000.00
Sub Total Pekerjaan Persiapan 50,800,000.00
G PEKERJAAN FINISHING
a. Finishing cat besi ls 1.00 25,000,000.00 25,000,000.00
b. Finishing cat tembok, Lapex w. putih m2 499.12 42,000.00 20,963,040.00
Sub Total Pekerjaan Finishing 45,963,040.00
b. Pedestal
Pedestal JC1 0.45 x 0.56 x 1.10 x 2.00 =
Pedestal JC2 0.51 x 0.56 x 1.10 x 4.00 =
Grouting kaki kolom JC 1 0.45 x 0.56 x 0.35 x 2.00 =
Grouting kaki kolom JC 2 0.51 x 0.56 x 0.35 x 4.00 =
c. Sloof
JL 1 0.20 x 0.60 x 23.00 =
JL 2 0.20 x 0.60 x 14.00 =
d. Balok
QL 1 0.20 x 0.20 x 6.00 =
QL 2 0.20 x 0.20 x 11.90 =
QL 3 0.20 x 0.20 x 11.90 =
QL 4 0.20 x 0.20 x 14.80 =
e. Kolom
GZ 1 0.20 x 0.20 x 7.40 =
MZ 1 0.20 x 0.20 x 7.40 =
MZ 2 0.20 x 0.20 x 7.40 =
4 Struktur Baja
a. WF 244x175x7x11 (kolom) 7.40 x 3.00 / 12.00 x 308.40 =
b. WF 244x175x7x11 (kolom) 6.70 x 3.00 / 12.00 x 308.40 =
c. WF 244x175x7x11 () 7.40 x 3.00 / 12.00 x 308.40 =
d. XG 1 INP 120x58x5.1x7.7 11.50 x 3.00 / 12.00 x 133.20 =
e. ZC 1 L 75x75x8 9.18 x 32.00 / 6.00 x 54.20 =
f. GL 300x180 7.50 x 12.00 / 12.00 x 595.20 =
g. Gording C 250x75x2x3 14.00 x 53.40 / 6.00 =
h. WYC (sambungan) 8.00 x 9.00 =
i. WLT Dia. 12 mm 1.20 x 10.00 x 14.00 / 12.00 =
j. WXL Dia. 12 mm 1.60 x 8.00 x 7.00 / 12.00 =
k. WCG Dia. 12 mm 1.20 x 8.00 x 7.00 / 12.00 =
7 Pekerjaan Plafond
Plafond gypsum 9 mm 6.15 x 23.50 =
2.20 x 16.00 =
7.00 x 15.00 =
9 Pekerjaan Finishing
a. Finishing cat besi =
b. Finishing cat tembok, Lapex w. pu 0.00 x 2.00 =
10 Pekerjaan Listrik
a. Instalasi lampu pabrik (dengan ballas hemat energi 250 watt, 6 m dari lantai) =
b. Instalasi stop kontak,2 & 3 lubang tanam 220V 10A (0,3 m dari lantai) =
c. Instalasi stop kontak AC 220V, 20A (1,3 m dari lantai) =
d. Instalasi saklar tunggal =
e. Instalasi saklar ganda =
f. Colokan internet RJ45 & RJ11 =
g. Switch board =
h. Kotak MEB =
i. Box panel lampu (1,6 m dari lantai nempel di kolom) =
j. Box panel lampu (1,6 m dari lantai nempel di kolom/dinding) =
k. Box panel cadangan (1,6 m dari lantai nempel di kolom) =
l. Lampu ceilling plafond, 30 V =
m. Lampu tunggal TL balok (ballast) 2 x 36 watt (di plafond) =
n. Saklar tombol tunggal (1,3 m dari lantai) =
o. Grounding =
0.65 m3
1.29 m3
2.81
4.75 m3
2.04 m3 5.12
4.08 m3 10.24
6.12
0.55 m3 4.44
1.26 m3 9.42
0.18 m3 1.41
0.40 m3 3.00
2.39
2.76 m3 27.60
1.68 m3 16.80
4.44
0.24 m3 3.60
0.48 m3 7.14
0.48 m3 7.14
0.59 m3 8.88
1.78
0.30 m3 5.92
0.30 m3 5.92
0.30 m3 5.92
0.89
16.10 m3 7.40
14.09 m3 15.01
45.81 m3 144.96
570.54 kg
516.57 kg
570.54 kg
382.95 kg
2,654.54 kg
4,464.00 kg
6,930 kg 55.62
72 set
149.80 kg 10.70
79.89 kg 10.70
59.92 kg 10.70
104.00 m2
287.12 m2
35.74 m3
144.53 m2
35.20 m2
105.00 m2
284.73 m2
30.00 m
1.00 ls
0.00 m2
14.00 ttk
33.00 ttk
15.00 ttk
6.00 ttk
2.00 ttk
16.00 ttk
1.00 ttk
1.00 ttk
1.00 ttk
2.00 ttk
1.00 ttk
3.00 ttk
20.00 ttk
1.00 ttk
4.00 ttk
ITEM
NO URAIN PEKERJAAN
TOTAL I
BANGUNAN WORKSHOP
2.00 Harga Bangunan Workshop Maintenance
MAINTENANCE
TOTAL II
TOTAL III
TOTAL IV
JUMLAH TOTAL
YEK PENAMBAHAN RETAINING WALL BATUBARA GUDANG SODA ASH, B
OGEN , PEMBANGUNAN WORKSHOP MAINTENANCEE TERSUS DAN PE
PT.WHW-AR
RAB
URAIN PEKERJAAN QTY (ESTIMASI) UNIT
TOTAL I
TOTAL III
harga instalasi dan las pipa besi (pipa besi suppyl pihak
± 27.00 m
pertama)
TOTAL IV
JUMLAH TOTAL
RA GUDANG SODA ASH, BANGUNAN
NANCEE TERSUS DAN PEK. SPORADIS
Rp 19,313,623,000.00
Rp 4,079,149,929.55 Rp 4,079,149,929.55
Rp 4,079,149,929.55
Rp 682,180,286.16 Rp 682,180,286.16
Rp 682,180,286.16
Rp 700,000.00 Rp 35,000,000.00
Rp 1,600,000.00 Rp 1,600,000.00
Rp 50,000,000.00 Rp 50,000,000.00
Rp 300,000.00 Rp 3,600,000.00
Rp 400,000.00 Rp 10,800,000.00
Rp 3,000,000.00 Rp 3,000,000.00
Rp 6,400,000.00 Rp 224,000,000.00
Rp 3,500,000.00 Rp 140,000,000.00
Rp 468,000,000.00
Rp 24,542,953,215.71
133.56
M3 353,700,000.00
M3 -64,025,000.00 4,300,000,000.00
M3 10,889,000.00 3,388,975.58
M3 -142,500,000.00
M3 87,500,000.00
M3 0.00 6,607,000.00
M3 0.00
312,404,000.00 19,451,572,000.00
837.76
4,371,286,109.78
710,162,974.56 Rp 89.36
-502,801.74
25,000,000,000.00
-457,046,784.29
-502,801.74
###
###
###
###
###
###
###
###
###
STRUKTUR ORGANISASI
PROYEK PENAMBAHAN RETAINING WALL BATUBARA GUDANG SODA ASH, BANGUNAN WORKSHOP , R.MESIN NITROGEN , PEMBANGUNAN
WORKSHOP MAINTENANCEE TERSUS DAN PEK. SPORADIS PT.WHW-AR
PROJECT MANAGER
KRISTIAN YUSUF
WAKIL PROJECT
MANAGER
WIDA
SITE MANAGER
NO URAIAN PEKERJAAN TOTAL BIAYA BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7
1 FEE MANAJEMEN & TRANSPORTASI TENAGA KERJA Rp 1,100,000,000.00 Rp 250,000,000.00 Rp 150,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 170,000,000.00 Rp 230,000,000.00 Rp 100,000,000.00
3 PEKERJAAN WORKSHOP MAINTENANCE Rp 953,162,800.00 Rp 7,500,000.00 Rp 167,652,500.00 Rp 263,732,500.00 Rp 231,872,150.00 Rp 250,959,650.00 Rp 31,446,000.00 Rp -
JUMLAH TOTAL Rp 4,434,750,442.10 Rp 696,730,729.60 Rp 1,304,483,726.25 Rp 1,319,258,186.25 Rp 331,872,150.00 Rp 420,959,650.00 Rp 261,446,000.00 Rp 100,000,000.00
NO URAIAN PEKERJAAN VOLUME BIAYA TOTAL BIAYA BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7
3 Biaya Fee Manajemen bln 7.00 Rp 100,000,000.00 Rp 700,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00 Rp 100,000,000.00
A UPAH BORONGAN
KASBON TENAGA TAHAP 1
= 75 ORG X Rp. 1.000.000 ORG 75.00 Rp 1,000,000.00 Rp (75,000,000.00) Rp (75,000,000.00) Rp 25,000,000.00 Rp 25,000,000.00 Rp 25,000,000.00
3 Upah Bobokan lantai beton & Muat Bobokan ke Truck ± 148.00 m3 Rp 200,000.00 Rp 29,600,000.00 Rp 14,800,000.00 Rp 14,800,000.00
6 Upah Borongan Beton C15 (Lantai Kerja) ± 138.00 m3 Rp 180,000.00 Rp 24,840,000.00 Rp 18,630,000.00 Rp 6,210,000.00
7 Upah Borongan Pengecoran + Perawatan Beton C30 ± 3,088.80 m3 Rp 180,000.00 Rp 555,984,000.00 Rp 277,992,000.00 Rp 277,992,000.00
NO URAIAN PEKERJAAN VOLUME BIAYA TOTAL BIAYA BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7
A UPAH BORONGAN
1 PEKERJAAN PERSIAPAN
Upah Pembersihan Lapangan ± 810.00 m2 Rp 15,000.00 Rp 12,150,000.00 Rp 12,150,000.00
Upah Pembuatan direksi Keet ± 32.00 m2 Rp 350,000.00 Rp 11,200,000.00 Rp 11,200,000.00
Upah Pembuatan pagar pengaman ± 150.00 m2 Rp 25,000.00 Rp 3,750,000.00 Rp 3,750,000.00
1 PEKERJAAN TANAH & GALIAN
Upah Pek Galian Tanah ± 195.00 Rp 25,000.00 Rp 4,875,000.00 Rp 4,875,000.00
Upah Timbunan dan pemadatan ± 64.00 Rp 55,000.00 Rp 3,520,000.00 Rp 3,520,000.00
2 PEKERJAAN BETON BERTULANG
Upah Pengecoran Beton ± 358.00 m3 Rp 180,000.00 Rp 64,440,000.00 Rp 21,480,000.00 Rp 21,480,000.00 Rp 21,480,000.00
Upah Bekisting ± 425.00 m2 Rp 195,000.00 Rp 82,875,000.00 Rp 41,437,500.00 Rp 41,437,500.00
Upah pembesian ± 89,500 kg Rp 1,800.00 Rp 161,100,000.00 Rp 80,550,000.00 Rp 80,550,000.00
3 PEKERJAAN STRUKTUR BAJA
Upah pemasangan Baja ± 21,375.00 kg Rp 11,000.00 Rp 235,125,000.00 Rp 11,756,250.00 Rp 58,781,250.00 Rp 47,025,000.00 Rp 117,562,500.00
Upah borongan Pondasi Batu kali ± 39.31
4 PEKERJAAN PASANGAN DINDIND & BATU KALI
Upah Pasangan Dinding hebel ± 1,098.90 m2 Rp 64,000.00 Rp 70,329,600.00 Rp 35,164,800.00 Rp 35,164,800.00
Upah borongan Pas Pondasi Batu Kali ± 39.31 Rp 250,000.00 Rp 9,827,500.00 Rp 9,827,500.00
5 PEKERJAAN SENG GELOMBANG
Upah borongan Pas Atap & Dinding Seng ± 992.30 m2 Rp 35,000.00 Rp 34,730,500.00 Rp 17,365,250.00 Rp 17,365,250.00
6 PEKERJAAN PLAFOND
Upah Borongan Pemasangan Plafond ± 313.20 m2 Rp 63,000.00 Rp 19,731,600.00 Rp 9,865,800.00 Rp 9,865,800.00
7 PEKERJAAN TALANG
Upah Pemasangan Talang ± 30.00 m2 Rp 72,000.00 Rp 2,160,000.00 Rp 2,160,000.00
8 PEKERJAAN FINISHING
Upah Borongan Cat Besi ± 21,375.00 kg Rp 500.00 Rp 10,687,500.00 Rp 5,343,750.00 Rp 5,343,750.00
Upah borongan Cat Dinding ± 2,197.80 m2 Rp 4,500.00 Rp 9,890,100.00 Rp 4,945,050.00 Rp 4,945,050.00
9 PEKERJAAN PINTU & JENDELA
Upah pas Pintu double alumunium M1524, 1500 X 2400 mm 3.00 unit Rp 700,000.00 Rp 2,100,000.00 Rp 2,100,000.00
Upah Pas Pintu tunggal alumunium M0924, 900 x 2400 mm 7.00 unit Rp 600,000.00 Rp 4,200,000.00 Rp 4,200,000.00
Upah Pas Jendela double C1518, 1500 x 1800 mm 7.00 unit Rp 450,000.00 Rp 3,150,000.00 Rp 3,150,000.00
10 PEKERJAAN ELEKTRIKAL
upah pemasangan Elektrikal ± 795.00 m2 Rp 115,000.00 Rp 91,425,000.00 Rp 4,571,250.00 Rp 22,856,250.00 Rp 18,285,000.00 Rp 45,712,500.00
PEKERJAAN HYDRAN & APAR
upah pemasangan Hydrant & APAR ± 795.00 m2 Rp 8,800.00 Rp 6,996,000.00 Rp 6,996,000.00
B BIAYA PERALATAN
NO URAIAN PEKERJAAN VOLUME BIAYA TOTAL BIAYA BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6 BULAN KE-7
Upah Bobokan lantai beton & Muat Bobokan ke Truck ± 36.00 m3 Rp 200,000.00 Rp 7,200,000.00 Rp 3,600,000.00 Rp 3,600,000.00
harga instalasi dan las pipa besi (pipa besi suppyl pihak pertama) ± 27.00 m Rp 72,000.00 Rp 1,944,000.00 Rp 1,944,000.00
harga instalasi valve DN3000 (pipa besi disupply pihak pertama) ± 1.00 bh Rp 540,000.00 Rp 540,000.00 Rp 540,000.00
JUMLAH TOTAL Rp 4,434,750,442.10 Rp 696,730,729.60 Rp 1,304,483,726.25 Rp 1,319,258,186.25 Rp 331,872,150.00 Rp 420,959,650.00 Rp 261,446,000.00 Rp 100,000,000.00
RINCIAN ESTIMASI BIAYA MATERIAL PELAKSANAAN PROYEK KALIMANTAN & JADWAL PENGIRIMAN
OKTOBER NOVEMBER
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN TOTAL BIAYA
MINGGU KE-3 MINGGU KE-4 MINGGU KE-1 MINGGU KE-2 MINGGU KE-3 MINGGU KE-4
A PEKERJAAN DINDING RETAINING WALL
6 Besi Beton D19 - 12M FULL 1,382.00 BTG Rp 255,000.00 Rp 352,410,000.00 Rp 352,410,000.00
7 Besi Beton D16 - 12M FULL 3,295.00 BTG Rp 195,000.00 Rp 642,525,000.00 Rp 642,525,000.00
8 Besi Beton Ø13 - 12M FULL 531.00 BTG Rp 125,000.00 Rp 66,375,000.00 Rp 66,375,000.00
9 BESI Beton Ø12 - 12M FULL 1,201.00 BTG Rp 105,000.00 Rp 126,105,000.00 Rp 126,105,000.00
10 Besi Beton Ø8 - 12M FULL 2,971.00 BTG Rp 48,000.00 Rp 142,608,000.00 Rp 142,608,000.00
11 kawat bendraat / 25 KG 70.00 ROLL Rp 365,000.00 Rp 25,550,000.00 Rp 25,550,000.00
7 Besi Beton D16 - 12M FULL 577.00 BTG Rp 195,000.00 Rp 112,515,000.00 Rp 112,515,000.00
8 Besi Beton D13 - 12M FULL 338.00 BTG Rp 125,000.00 Rp 42,250,000.00 Rp 42,250,000.00
9 BESI Beton Ø10 - 12M FULL 407.00 BTG Rp 75,000.00 Rp 30,525,000.00 Rp 30,525,000.00
10 Besi Beton Ø8 - 12M FULL 41.00 BTG Rp 48,000.00 Rp 1,968,000.00 Rp 1,968,000.00
11 Wiremesh M8 159.00 LBR Rp 750,000.00 Rp 119,250,000.00 Rp 119,250,000.00
12 kawat bendraat / 25 KG 10.00 ROLL Rp 365,000.00 Rp 3,650,000.00 Rp 3,650,000.00
JUMLAH 2 Rp 1,641,086,709.00
NOTE :
jumlah 2,240,000,000.00
VOLUME TERHITUNG KEBUTUHAN LAPANGAN
PASIR = 3,029.00 X 190,000.00 = 575,510,000
BATU = 2,799.00 370,000.00 = 1,035,630,000
jumlah 1,611,140,000.00
SELISIH 628,860,000
PEKERJAAN
NO URAIAN PEKERJAAN SAT BOBOKAN
PEKERJAAN A
MATERIAL
1 Semen @50 KG ZAK
2 Pasir Cor M3
3 Batu Pecah 2/3 / split M3
4 Air bersih M3
5 Pasir batu / Sirtu 4:6 M3
12 Multiplek 18 MM LBR
13 Kayu kaso 5/7 M3
14 Paku Kg
PERALATAN
1 Mesin Las unit
2 Jack Hammer set 8.00
3 Lori bh 10.00
4 Sekop bh 5.00
5 Mesin Bor Hilti bh
6 Carmix unit
7 Pompa beton unit
8 Vibrator unit
9 Exavator Pc100 unit
10 Dumptruck unit
11 Watertank unit
12 Karung Goni bh
13 Tandon 1000 ltr bh
PEKERJAAN PEKERJAAN GA
NO URAIAN PEKERJAAN SAT PERSIAPAN URUGAN
MATERIAL
1 Semen @50 KG ZAK
2 Pasir Cor M3
3 Batu Pecah 2/3 / split M3
4 Air bersih M3
5 Pasir batu / Sirtu 4:6 M3
12 Multiplek 12 MM LBR
13 Kayu kaso 5/7 M3 8.00
Papan 3x200 M3 2.00
14 Paku Kg 8.00
PERALATAN
1 Cangkul bh 10.00
2 Molen set
3 Lori bh
4 Sekop bh
5 Stamper unit
13 Tandon 1000 ltr bh
PEKERJAAN
PEKERJAAN PEKERJAAN BETON PEKERJAAN BETON PEK. PASRI BATU
PEKERJAAN ANGKUR BETON C30
GALIAN C15 C30 4:6
TULANGAN
1,382.00
3,295.00
531.00
219.00 982.00
2,971.00
70.00
264.60
102.06
270.00
6.00
2.00
Rp 5.00
2.00
1.00
2.00
1.00
2.00
1.00
1,000.00
PEKERJAAN GALIAN & PEKERJAAN BETON PEK, DINDING & PEKERJAAN SENG PEK TALANG &
PEK PLAFOND
URUGAN TULANGAN BATU KALI GELOMBANG PIPA
3,181.52 857.14
236.53 642.86
276.23
769.98
577.00
338.00
407.00
41.00
159.00
9.63
103.64
39.98
105.76
Rp 10.00
1.00
10.00
10.00
Rp 2.00
PEK. PASRI BATU
TOTAL
4:6
30,620.25
2,148.88
2,521.97
6,868.82
240.00 240.00
-
1,382.00
3,295.00
531.00
1,201.00
2,971.00
70.00
-
264.60
102.06
270.00
-
6.00
-
-
-
-
-
2.00
8.00
10.00
5.00
5.00
2.00
1.00
2.00
1.00
2.00
1.00
1,000.00
2.00
4,038.66
879.39
276.23
769.98
-
-
577.00
338.00
407.00
41.00
9.63
-
103.64
47.98
2.00
113.76
-
123.00
-
-
-
-
20.00
1.00
10.00
10.00
2.00
-
-
BACKUP KEBUTUHAN MATERIAL
1.00 URAIAN
2.00 ANGKUR
VOL = 607.50 M3
4.00
VOL = 607.50 M3
B VOLUME PONDASI
PONDASI TAPAK = 204.12 M3
=2,8*((0,3+0,78)/2)*135M
DINDING = 33.75 M3
=0,5*0,5*135
= 237.87 M3
VOL TIMBUNAN
= 607.50 -237.87 = 369.63 M2
= KOIFISIEN TIMBUNAN = 1,2*3= 443.56 M2
5.00
BETON C15
VOL = 40.50 M3
VOL = 40.50 M3
VOLUME A+ B = 81.00 M3
5.00
BETON C30 TANPA PEMBESIAN
VOL = 1,903.50 M3
VOLUME A+ B = 2,025.00 M3
6.00
BETON C30 DENGAN PEMBESIAN
VOL = 81.00 M3
VOL = 71.28 M3
LEBAR = 0.90 M
PANJANG = 0.40 M
JUMLAH : 92.00 BH
VOL = 79.49 M3
D PONDASI RW BARU
TINGGI = 1.04 M
LEBAR = 2.80 M
PANJANG = 135.00 M
VOL = 393.12 M3
VOL = 189.00 M3
total a + b = 116,654.06 kg
SUPPLY BY OWNER
BESI D19 = (10,690) KG
BESI Ø8 = (8,000) KG
TOTAL PENGADAAN = 97,964.06 KG
BEKISTING DINDING
RETAINING WALL EXISTING = 1,080.00 M2
BEKISTING DINDING BARU = 1,080.00 M2
2,160.00 M2
PENGERJAAN PENGELASAN
EXISTING
DINDING
PANJANG LAS = 0.20 CM
BANYAK LAS = 2,700.00 BH
PLAT
PANJANG LAS = 0.20 CM
BANYAK LAS = 2,700.00 BH
PILAR
B BOUWPLANK
B pemadatan
B BETON C 40
Sloof = 49.26 M3
BESI BETON
PONDASI
PEDESTAL
SLOOF
PLAT LANTAI
BESI Ø8 = 167.85 KG
REKAP
BESI Ø8 = 167.85 KG
WIREMESH M8 = 159.00 KG
BEKISTING
VOLUME = 423.02 M2
VOLUME GAMBAR RAB ANALISA RAP PELAKSANAAN
URAIAN
= 16.20 M3
TENAGA
MANDOR
TUKANG BOBOK
TUKANG BUANG BERANGKAL
= 11.88 M3
ALAT BANTU
JACK HAMMER / HAMMER DRILL
SEWA DUMPTRUK INCLUDE
= 101.25 M3
URAIAN
= 2,700.00 BTG
TENAGA
MANDOR
TUKANG BESI
TUKANG BOR BETON EX HILTI INC
ADHESIV perekat
= 1,260.00 BTG
MATERIAL
BESI BETON Ø12 - 12M FULL
TARGET PENCAPAIAN PEKERJAAN BOBOK PER HARI
RENCANA TARGET ANGKUR PLAT
RENCANA ANGKUR PILAR
TOTAR PER HARI TARGET 7 HARI
URAIAN
=
TENAGA
MANDOR
TUKANG GALI
= 607.50 M3
ALAT
MOBILISAS & DEMOB EXAVATOR
SEWA EXAVATOR INCLUDE
SEWA DUMPTRUCK INCLUDE
URAIAN
= TENAGA
MANDOR
TUKANG
= ALAT
URAIAN
= TENAGA
MANDOR
KEPALA TUKANG
TUKANG
KENEK
=
= MATERIAL
81.00 M3
URAIAN
= TENAGA
MANDOR
KEPALA TUKANG
TUKANG
KENEK
=
= MATERIAL
2,025.00 M3
ALAT BANTU
Sewa Self Loading Congcrete Mixer
include Operator
Insentif Operator
N URAIAN
= TENAGA
MANDOR
KEPALA TUKANG
TUKANG
KENEK
= 81.00 M3
= MATERIAL
231.77
SEMEN @50 KG / 10 ZAK
PASIR COR
BATU PECAH 2/3 / SPLIT
= 71.28 M3 AIR BERSIH
= ALAT BANTU
PEMBESIAN
= 393.12 M3
Upah
=
material Besi
BESI BETON
KAWAT BENDRAAT
= 189.00 M3
=
BEKISTING
= 95.68 M3
multi 18 mm
kaso 5/7
paku
minyak bekisting
97,964.06 kg
PASIR
ANALISA PENGELESAN /M' - 10 CM
ITEM
= 102.00 m2 1.00 Ls
= 102.00 m2 MATERIAL
Seng Gelombang
Kayu 5/7
Paku
= 258.68 m2 Ls
= 258.68 m2 MATERIAL
900.00 m2
= Ls
MATERIAL C20
SEMEN @50 KG
PASIR COR
BATU PECAH SPLIT 2/3
AIR BERSIH
BESI BETON
Besi D16
Besi D13
BESI Ø10
BESI Ø8
WIREMESH M8
KAWAT BENDRAAT
multi 18 mm
kaso 5/7
paku
minyak bekisting
PELAKSANAAN KEBUTUHAN MATERIAL KEBUTUHAN ALAT
7.00 HK
JACK HAMMER
SEWA DUMPTRUCK
1.00 OH
8.00 OH
6.00 OH
8.00 UNIT
2.00 UNIT
209.00 BTG
RJAAN BOBOK PER HARI
EXAVATOR
DUMPTRUCK
1.00 OH
15.00 OH
3.00 UNIT
3.00 UNIT
15.00 UNIT
RJAAN GALIAN :
=
EXAVATOR
1.00 OH DUMPTRUCK
6.00 OH STAMPER
3.00 UNIT
2.00 UNIT
RJAAN TIMBUNAN & PE :
=
=
81.00 M3
7.05 ZAK
0.52 M3
0.76 M3
215.00 LTR
10.00 ZAK
0.72 M3
0.84 M3
215.00 LTR
2,025.00 M3
1.00 Unit
1.00 bln
1,088.80 M3
0.50 UNIT
0.50 Unit
0.50 bln
0.50 unit
116,654.06 kg
97,964.06 Kg
1.05 KG
122.40 lbr
5.81 m3
6.12 kg
1.60 m3
1.60 m3
1.68 kg
PERALTAN
PERALTAN
172.53 ZAK
14.63 M3
51.16 M3
3,008.99 ZAK
224.00 M3
261.60 M3
718.81 M3
577.00 BTG
338.00 BTG
407.00 BTG
41.00 BTG
159.00 LBR
9.63 ROLL
103.64 lbr
39.98 m3
105.76 kg
0.20 l
KEBUTUHAN ALAT
JUMLAH SAT
8.00 UNIT
2.00 UNIT
KEBUTUHAN ALAT
JUMLAH SAT
1.00 UNIT
1.00 UNIT
4.00 SET
KEBUTUHAN ALAT
JUMLAH SAT
1.00 UNIT
1.00 UNIT
JUMLAH SAT
1.00 UNIT
1.00 UNIT
2.00 UNIT
JUMLAH SAT
1.00 UNIT
1.00 UNIT
12.00 M
JUMLAH SAT
1.00 UNIT
1.00 UNIT
2.00 UNIT
JUMLAH SAT
1.00 UNIT
1.00 UNIT
2.00 UNIT
1.00 UNIT
1.00 UNIT
REKAP ESTIMASI BIAYA MATERIAL PELAKSANAAN PROYEK KALIMANTAN
NO URAIAN PEKERJAAN NILAI BOBOT BULAN KE-1 BULAN KE-2 BULAN KE-3 BULAN KE-4 BULAN KE-5 BULAN KE-6
3 PEKERJAAN WORKSHOP MAINTENANCE Rp 1,631,251,538.09 16.313% Rp 326,250,307.62 Rp 326,250,307.62 Rp 326,250,307.62 Rp 326,250,307.62 Rp 326,250,307.62
ITEM RETAINING TOTAL TOTAL BEKISTING BESI BETON KUBIKASI PER M'
RETAINING WALL BARU M2 KG M3
PONDASI RW 1 0,3 X 2,80 X 188,36 = 158.22 M3 686.03 M3 180.83 47,647.55
1.63
PONDASI RW 2 0,48 X (2,80+0,5)/2 X 188,36 149.18 M3
PILAR KOLOM BAJA 1,30 X 0,80 X 6,50 X 17 TTK = 114.92 M3 464.10 13,273.26 6.76
DINDING RW 4,0 X ((0,5+0,2)/2) X 188,36 = 263.70 M3 1,506.88 29,505.14 1.40
###