Crashing Progarm: Estimation
Crashing Progarm: Estimation
Crashing Progarm: Estimation
Estimation
GROUP B
MORNING STUDIES
2019-2020
KADHIM FALAH Crashing progarm
Crashing (1)
refers to a particular variety of project schedule compression which is performed for the
purposes of decreasing total period of time (also known as the total project schedule duration).
The diminishing of the project duration typically take place after a careful and thorough analysis
of all possible project duration minimization alternatives in which any and all methods to attain
the maximum schedule duration for the least additional cost The objective of crashing a network
is to determine the optimum project schedule. Crashing may also be required to expedite the
execution of a project, irrespective of the increase in cost. Each phase of the software design
consumes some resources and hence has cost associated with it. In most of the cases cost will
vary to some extent with the amount of time consumed by the design of each phase .The total
cost of project, which is aggregate of the activities costs will also depends upon the project
duration, can be cut down to some extent. The aim is always to strike balance between the cost
and time and to obtain an optimum software project schedule. An optimum minimum cost
project schedule implies lowest possible cost and the associated time for the software project
management
Total project costs include both direct costs and indirect costs of performing the activities of the
project. If each activity of the project is scheduled for the duration that results in the minimum
direct cost (normal duration) then the time to complete the entire project might be too long and
substantial penalties associated with the late project completion might be incurred. At the other
extreme, a manager might choose to complete the activity in the minimum possible time, called
crash duration, but at a maximum cost. Thus, planners perform what is called time cost trade-off
analysis to shorten the project duration. This can be done by selecting some activities on the
critical path to shorten their duration. As the direct cost for the project equals the sum of the
direct costs of its activities, then the project direct cost will increase by decreasing its duration.
On the other hand, the indirect cost will decrease by decreasing the project duration, as the
indirect cost are almost a linear function with the project duration
KADHIM FALAH Crashing progarm
Direct cost : which comprises of expenditure, that is specific to a project, that is cost of
materials, labour and equipment
Indirect cost : includes expenditure like tariff for infrastructure facilities, rent
Since the direct and indirect costs are not necessarily expressible as linear functions, time–cost
trade-off relationships are made by searching for the lowest possible total cost (i.e., direct and
indirect) that likewise satisfies the region of feasible budgets. This method is shown in Figure1(3)
Example(4): The following table gives data on normal time and cost and crash time & cost for a
project
Table 1
Solution :
The above table indicates the optimum cost (5805) and optimum duration
(29 weeks) and also shows the maximum crashing after the project duration is
25weeks.
The all project duration is crashing is dependent in critical path (CPM) because
the duration is reduce in only crashing in critical path.
References
1. Production and Operations Management Systems Sushil Gupta and
Martin Starr
Kanpur