Toc Ppg01-E4 PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 29
At a glance
Powered by AI
The document discusses various topics related to construction contracts and claims management including contract administration, litigation, dispute resolution, and project audits.

Topics covered include contract types and provisions, risk allocation, change order management, claims avoidance techniques, alternative dispute resolution methods, the cost engineer as an expert witness, and more.

Chapter 18 discusses the cost engineer's role in legal proceedings.

PPG#1 CONTRACTS AND CLAIMS 4TH EDITION

Table of Contents

Introduction to the Fourth Edition

Introduction to the Third Edition

Introduction to the Second Edition

Introduction to the First Edition

Chapter 01: Contract Administration

1. Cost Interpretation of Contractual Terms, M. Viswanathan, AACE Transactions, 1974


2. Scheduling and Controlling Construction Sub-Contracts, James A. Bent, AACE Transactions,
1977
3. New Construction Management Emphasis Costs Cost and Schedule, Wesley R. Querns, CCE,
AACE Transactions, 1982
4. Contract Provisions That Ensure Complete Cost Disclosures, Curtis D. Sutliff, CCE; James G.
Zack, Jr., Cost Engineering Journal, 1987
5. Innovative Contract Documents and Progressive Project Management Yields Success, Donald
J. Fredlund, Jr.; Stephen J. Fortney; Stan A. Christopher, PE, AACE Transactions, 1989
6. An Analysis Of Construction Contracts: Types, Characteristics, and Applications, Robert S.
Ironmonger, CCE, Cost Engineering Journal, 1989
7. Are You Contracting for Success?, Serge Pressoir, PE, AACE Transactions, 1992
8. Achieving Cost And Schedule Goals: Contracting Approaches That Really Worked, AACE
International Planning and Scheduling Committee, Cost Engineering Journal, 1994
9. "Risk Sharing" - Good Concept, Bad Name, James G. Zack, Jr., AACE Transactions, 1995
10. A Contract Clause for Allocating Risks, Dr. George F. Jergeas, P.Eng.; Dr. Francis T. Hartman,
P.Eng., AACE Transactions, 1996
11. Best Value Contracting: Breaking the Low-Bid Paradigm, Dr. Douglas D. Gransberg, PE;
Michael A. Ellicott, PE, AACE Transactions, 1996
12. The Top Ten Lessons Learned in Construction Contracting, Dr. William W. Badger; Steven W.
Gay, Cost Engineering Journal, 1996
13. Change-Order Management, Bob M. McCally, AACE Transactions, 1997
14. Best-Value Contracting Criteria, Dr. Douglas D. Gransberg, PE; Michael A. Ellicott, PE, Cost
Engineering Journal, 1997
15. Cost/Schedule Management of Government Construction Subcontracts, Harry W. Jarnagan,
PE CCE, Cost Engineering Journal, 1997
16. Construction Contracts: Shifting Risk or Generating a Claim?, Donald F. McDonald, Jr., PE
CCE; John O. Evans III, AACE Transactions, 1998
17. RFIs - Use, Abuse, Control, James G. Zack Jr., AACE Transactions, 1998
18. Appropriate Risk Allocation in Lump-Sum Contracts - Who Should Take the Risk?, Dr. Francis
T. Hartman, PE; Patrick Snelgrove, P.Eng.; Dr. Rafi Ashrafi, Cost Engineering Journal, 1998
19. Value Engineering Incentive Clauses, George F. Jergeas; Vernon G. Cooke; Francis T.
Hartman, Cost Engineering Journal, 1999
20. Claims Avoidance Techniques: Best Practices for Contract Administration, Kathleen M.J.
Harmon; Bruce M. Stephan, AACE Transactions, 2001
21. Start Your Project the Right Way, Edward E. Douglas III, AACE Transactions, 2002
22. Reducing Contract Cost: The Trust Issue, Ramy Zaghloul; Francis T. Hartman, AACE
Transactions, 2002
23. Weather Derivatives Allow Construction to Hedge Weather Risk, Robert B. Connors, CCE,
Cost Engineering Journal, 2003
24. Contractor Default Insurance: A Key Issue for Estimators Budgeting Capital Projects, Robert
Seals, Cost Engineering Journal, 2003
25. Owner-Furnished Equipment: Savings or Potential Claims?, Talal Abi-Karam, PE CCE, AACE
Transactions, 2003
26. Make Liquidated Damages Work, Clark R. McCormick, PE, AACE Transactions, 2003
27. Understanding Risk to Mitigate Changes and Avoid Disputes, L. Adam Winegard; Stephen P.
Warhoe, PE CCE, AACE Transactions, 2003
28. Project Management Oversight: An Effective Risk Management Tool for EPC/Design-Build
Contracts, George E. Baram, P.Eng. CCE, AACE Transactions, 2003
29. Self-Perform Versus Subcontract Decision in Construction Contracts, Khaled Nassar, AACE
Transactions, 2003
30. False Claims on Public Projects: Don't Bet Your Business on It, Kayhan Fatemi; Matthew J.
Lankenau, CCE, AACE Transactions, 2004
31. Rules of Engagement for Construction Claims, Philip D. Barnard, PE, AACE Transactions, 2004
32. Guidelines for Specification Development, George Belev, AACE Transactions, 1989
33. Subcontract Administration and Control, James A. Bent, CCE, AACE Transactions, 1982
34. Uniform Proposal Form for the Subcontractor, Michael J. Cook, AACE Transactions, 1998
35. Financial Administration of Construction Contracts by Owners, W. Doug Creech, CCC, AACE
Transactions, 2006
36. Subcontractor Management for the General Contractor, Robert W. Fessler, AACE
Transactions, 1990
37. Lump Sum Contracting: An Owner's Perspective, Dwight R. Johnson, Jr., Cost Engineering
Journal, 1987
38. Subcontractor Status Reporting, Tom Mendel, AACE Transactions, 1985
39. Progress and Performance Control of a Cost Reimbursable Construction Contract, Moses Y.
Nkuah, CCC, Cost Engineering Journal, 2006
40. Construction Contract Administration in Kenya, Moses A. Nyakiongora, AACE Transactions,
2000
41. Team Approach for Evaluating Contract Administration Procedures, Serge Pressoir, PE, AACE
Transactions, 1989
42. The Effectiveness of the Construction Contract, Nathan Paul Slauson, AACE Transactions,
2005
43. LS-EPC From A Legal Viewpoint, Chris Thompson, Cost Engineering Journal, 1987
44. Construction Specifications - Their Impact on Construction Cost, William T. Trotter, AACE
Transactions, 1975
45. Managing International Contract Administration, Niall Reynolds, AACE Transactions, 2008

Chapter 02: Management of Construction Schedules

1. Problems In The Implementation of Scheduling Systems, Gui Ponce-Campos, AACE


Transactions, 1975
2. Owner Approach to Planning and Scheduling, James A. Bent; John W. Hackney, AACE
Transactions, 1976
3. Scheduling Specifications for the 80's, Dr. Gui Ponce de Leon, AACE Transactions, 1983
4. CPM - Established and Then Some, Gary O. Glenn, AACE Transactions, 1985
5. Practical Specifications For Project Scheduling, John R. Clark, PE, Cost Engineering Journal,
1990
6. Schedule Games People Play and Some Suggested Remedies, James G. Zack, Jr., AACE
Transactions, 1991
7. New Directions in Schedule Management, Gui Ponce de Leon, PE, AACE Transactions, 1991
8. Contrasting Cost-Loaded CPM Scheduling Specifications, Dr. Gui Ponce de Leon, PE; Michael
J. Mix; Philip Spittler, AACE Transactions, 1994
9. Developing an As-Built Schedule From Project Records, John R. Knoke, PE; Gary H. Jentzen,
PE, AACE Transactions, 1996
10. A Scheduling Tool for Tunnel Construction, K.A. Pohrte; W.W. Edgerton, PE, AACE
Transactions, 1996
11. Activity Duration Quantification Under Uncertainty: Fuzzy Set Theory Application, Jong H.
Ock, Cost Engineering Journal, 1996
12. A Multiobjective Linear Program for Scheduling Repetitive Projects, Dr. Kamal Al-Subhi Al
Harbi; Dr. Shokri Z. Selim; Mazen Al-Sinan, Cost Engineering Journal, 1996
13. Practical Applications of Probabilistic Scheduling, Dr. Gui Ponce de Leon, PE; John R. Knoke,
PE, AACE Transactions, 1997
14. Optimized Scheduling for Highway Construction, Khaled El-Rayes; Osama Moselhi, PE, AACE
Transactions, 1997
15. Project Scheduling Under Limited Resources, Mohammed Moizuddin; Shokri Z. Selim, AACE
Transactions, 1997
16. Practical Risk Analysis in Scheduling, Abhi Basu, PE, AACE Transactions, 1998
17. The Case for Critical Path, Michael A. Hatfield; James Noel, Cost Engineering Journal, 1998
18. Soft Logic - An Overview, Dennis Read Hanks, PE CCE, Cost Engineering Journal, 1999
19. Industry Crisis: Construction Scheduling Software, Jon M. Wickwire; Stuart Ockman, AACE
Transactions, 2000
20. The Pitfalls of CPM Scheduling on Construction Projects, Ian A. Street, Cost Engineering
Journal, 2000
21. Schedule Review Basics, Craig L. Olsen, AACE Transactions, 2000
22. Baseline Schedule Approval, Zartab Q. Zafar; Dean Rasmussen, Cost Engineering Journal,
2001
23. Selecting Planning and Scheduling Specifications, Leaf A. Ballast; Calin M. Popescu, AACE
Transactions, 2001
24. Project Scheduling Enhancements for Avoiding Litigation, Anamaria Popescu; James T.
O'Connor; John D. Borcherding, AACE Transactions, 2002
25. Tripping Hazards in Schedules, Donald F. McDonald Jr., AACE Transactions, 2002
26. Computing Near-Longest Path, Ron Winter, Cost Engineering Journal, 2003
27. Computing Near-Longest Path - Part 2: Now That I have Longest Path Value, What’s It Good
For?, Ron Winter, Cost Engineering Journal, 2003
28. Effect of Multiple Calendars on total Float and Critical Path, Nestor J. Scavino, CCC, Cost
Engineering Journal, 2003
29. How to Befuddle a College Professor (Without Really Trying), Ronald M. Winter, Cost
Engineering Journal, 2003
30. Computing the Near-Longest Path, Ronald M. Winter, AACE Transactions, 2003
31. Contract Requirements for Construction Schedule, Win G. Li, PE CCE, AACE Transactions,
2003
32. Impact Of Uncertain Resources On Project Schedule And Cost, HN Ahuja; V Arunachalam,
Cost Engineering Journal, 1985
33. Critical Path Scheduling: Fundamentals And Concepts, William P. Allman, AACE Transactions,
1962
34. Implementing CPM With Cost Monitoring For Multitype Projects, Larry N. Allen, AACE
Transactions, 1965
35. Cost-Time-Risk Diagram: Project Planning and Management, Peerapong Aramvereekul, PSP
EVP; Daniel J. Seider, PE, Cost Engineering Journal, 2006
36. CPM Scheduling in Construction: A Case Study, Abhi Basu, AACE Transactions, 2003
37. Is Your Schedule Late at the Starting Gate?, Abhi Basu, PE, AACE Transactions, 2005
38. CPM Schedules - Why and How, Satinder Singh Baweja, CCE, AACE Transactions, 2006
39. Scheduling Specifications: A Lump Sum Contractor's Perspective, Martin J. Bradley, CCC,
AACE Transactions, 2005
40. PDM Scheduling at EPCOT Center, James Brownell, AACE Transactions, 1986
41. Scheduling Comparison of Engineering/Manufacturing to Engineering/Construction, Terry F.
Carlson, AACE Transactions, 1989
42. Line Of Balance Technology, Vincent C. Carnazza, AACE Transactions, 1965
43. Project Schedule Delay vs. Strategic Project Planning, Massimoluigi Casinelli, PE, CCE, AACE
Transactions, 2005
44. Have the Networks Fit the Project, Donald J. Cass, CCE, AACE Transactions, 1984
45. Reducing Time and Cost With Pre-facilitating Techniques, Allan D. Chasey PE; Neesha Regmi,
AACE Transactions, 2005
46. The Project Schedule: The Key to Project Communication, James M. Colvin; Larkin B. Breed,
AACE Transactions, 1976
47. Benefits of a Fixed Scheduling System, Cecil J. Bendy; Thomas E. Danz, AACE Transactions,
1979
48. Henry L. Gantt and Frederick Taylor: The Pioneers of Scientific Management, Peter B.
Darmody, PSP, AACE Transactions, 2007
49. Project Time Risk Analysis Through Simulation, Prasanta K. Dey; Stephen O. Ogunlana, Cost
Engineering Journal, 2001
50. Project Planning--Then Scheduling, Edward E. Douglas III, CCC, AACE Transactions, 2004
51. Planning and Scheduling Cost-Limited Projects, Edward E. Douglas III, CCC, AACE
Transactions, 1994
52. The Great Negative Lag Debate, Edward E. Douglas, III CCC PSP; Timothy T. Calvey, PE PSP;
Donald F. McDonald, Jr. PE CCE PSP; Ronald M. Winter, PSP, AACE Transactions, 2006
53. Project Management - Planning and Scheduling System, Gerald W. Duray, AACE
Transactions, 1976
54. The Adequacy of Initial Scheduling Estimates, John M. Dye; Dr. Irtishad U. Ahmad, PE, AACE
Transactions, 1998
55. Planning and Scheduling With Multiple Decision Points, Fritz Ehrenreich-Hansen, P.Eng. CCE;
S.W. (Bill) Wilson, P.Eng., Cost Engineering Journal, 1997
56. Project Management with Scheduling, Daniel P. Elliott, AACE Transactions, 1976
57. Recognizing and Avoiding Problems Inherent in Today's Scheduling Environment, David L.
Freidl, CCE, AACE Transactions, 1987
58. CPM Scheduling -- How Industry Views Its Use, Patricia D. Galloway, PE, Cost Engineering
Journal, 2006
59. Resource Allocation And Critical Path Techniques, W. C. Geoghan, AACE Transactions, 1965
60. Scheduling for Estimators, Robert R. George, CCC, AACE Document, 1998
61. Let’s Scrap the Precedence Diagramming Method, Earl T. Glenwright Jr., AACE Transactions,
2004
62. Modular CPM's or Detail CPM Schedules at a Barchart Price, Stephen Goodman, AACE
Transactions, 1992
63. Scheduling Practices and Project Success, Andrew F. Griffith, PE, AACE Transactions, 2005
64. Planning & Scheduling an International Project, Mark Grinberg, AACE Transactions, 1981
65. Scheduling for on Time Project, David H. Hamburger, PE, AACE Transactions, 1989
66. Soft Logic - Engineering, or "Seeing the Forest", Dennis Read Hanks, Cost Engineering
Journal, 1999
67. Soft Logic -- Construction, Dennis Read Hanks, Cost Engineering Journal, 2000
68. Conceptual Planning of Highway Construction Projects, Ahmed Hassanein, P.Eng., AACE
Transactions, 2006
69. BAL: An Algorithm for Scheduling and Control of Linear Projects, Tarek Hegazy; Osama
Moselhi; Dr. Paul Fazio, AACE Transactions, 1993
70. Certification Of Contract Progress Payments Using Critical Path Schedules, J. G. Hazan; B. J.
Swain, AACE Transactions, 1971
71. "Enhanced" PDM -- Concepts and Benefits, Scott C. Herold, PE, AACE Transactions, 2004
72. Repetitive Production Method (RPM) and CPM, Lawrence L. Humphries, CCE, AACE
Transactions, 1993
73. Up-front Project Scheduling in an Owner/Contractor Alliance, Murray W. Janzen, Cost
Engineering Journal, 1992
74. Approaches to Planning and Scheduling a Project, Ed Juracek, AACE Transactions, 1974
75. Critical Path Planning, W. G. Kast, AACE Transactions, 1963
76. Critical Path Scheduling Experience In Defense Contracts, William R. Kelley, AACE
Transactions, 1962
77. How to Reduce Risk in Project Schedules and Portfolios, Sarim Khan, Cost Engineering
Journal, 2007
78. The Perfect Plan, BE Kibler,, Cost Engineering Journal, 1985
79. Artificial Resource Loading for Schedule Review, Albert Joseph Kuhn, PSP, AACE
Transactions, 2007
80. CPM Not Working Well On Small Projects, Albert Joseph Kuhn, PSP, AACE Transactions, 2006
81. Factors Affecting Construction Planning, Dr. Alexander Laufer; Dora Cohenca, AACE
Transactions, 1986
82. Construction Scheduling Based on Resource Constraints, Yong-Il Lee; Thomas M. Gatton,
AACE Transactions, 1994
83. The Use of CPM Through Knowledge-Based Information Systems, Maris G. Lenss, AACE
Transactions, 1988
84. A Continuously Changing As-Planned Baseline?, John. C. Livengood; Mark I. Anderson, AACE
Transactions, 2005
85. Integrated Scheduling System - An Approach, Joseph R. Lorenzo; Dikshit Sharad, AACE
Transactions, 1975
86. A Comparison Between the Non-Mixed and Mixed Convention in CPM Scheduling, Gunnar
Lucko, Cost Engineering Journal, 2007
87. Planning and Scheduling for Success, Ignacio Manzanera, CCE, AACE Transactions, 1990
88. Automatic Resource-Bases Cost-Time Forecasts, VK Marston; RM Skitmore, AACE
Transactions, 1990
89. The CPM Technique in Construction - A Critique, Derek Mason, AACE Transactions, 1984
90. Program Scheduling: Not Exactly = Project Scheduling, Courtney James McCracken, PE;
Patricia J. Auger; John H. Baratta, PE, AACE Transactions, 1995
91. A Project Plan for Maximum Control, Thomas W. McKeown; Raymond A. Haarstick, AACE
Transactions, 1976
92. Scheduling Concerns in the Hazardous Waste Industry, Timothy C. McManus; Minosca V.
Alcantara, Cost Engineering Journal, 1996
93. Construction Scheduling - Don't Depend on a Textbook, Brett M. McPherson; Daniel J.
Whitecotton, AACE Transactions, 1991
94. Considerations in Planning and Scheduling, John K. Nabors, AACE Transactions, 1994
95. Integrated Network Planning and Scheduling with 3-D Construction Sequence Models, Daniel
P. Nevins; Ronald J. Zabilski; Bridget E. O'Reilly, AACE Transactions, 1993
96. Contemporary Controversies - Circa 2005, James J. O'Brien; Earl Glenwright, PE PSP, AACE
Transactions, 2005
97. Matrix Scheduling for Repetitive Residential Construction, Neil D. Opfer, CCE, AACE
Transactions, 1996
98. Schedule Risk Analysis Using Computer Simulation, Joseph J. Orczyk, PE; Dr. Donn Hancher,
PE, AACE Transactions, 1987
99. Parametric Project Scheduling of Milestones, Joseph Orczyk, PE; Luh-Maan Chang, AACE
Transactions, 1990
100. Construction CPM Scheduling - Precision Without Accuracy, Victor M. Ostrowski, PSP, AACE
Transactions, 2006
101. Studies in Planning and Scheduling, Gordon G. Peterman, CCE, AACE Transactions, 1978
102. Repetitive Activity Scheduling Process, F. Fred Rahbar; Dr. James E. Rowings, CCE, AACE
Transactions, 1992
103. Back To The Basics Of Planning And Scheduling, Gary W. Rastelli, Cost Engineering Journal,
1993
104. Breakthrough Planning Methodology, Joe Rizzo, AACE Transactions, 1992
105. The Role of Probability in Scheduling, Aaron Rose, CCE, AACE Transactions, 1981
106. Enhanced Project Management with Reference Schedules, Dr. James E. Rowings, Jr.CCE,
AACE Transactions, 1986
107. Project Planning and Scheduling and its Impact to Project Outcome: A Study of EPC Projects
in Canada, Janaka Y. Ruwanpura; Tanveer Nabi Ahmed; Karim Kaba; Gerald Patrick Mulvany,
AACE Transactions, 2006
108. Transparent CPM, Mark C. Sanders, PE CCE, AACE Transactions, 2005
109. A Systems Approach to Project Management Measurements of Productivity and Cost Control,
Howard M. Sanderson, AACE Transactions, 1976
110. CPM- Scheduling At An Existing Operating Airport, CJ Saper, AACE Transactions, 1986
111. CPM Techniques Really Can Be Applied to Major Mechanical and Technical Construction,
Peter J. Schappa, CCE; Dwight A. Zink, CCE, AACE Transactions, 1983
112. CPM - Pert Time Scaled Summary Network, Harold B. Shugar, AACE Transactions, 1985
113. Schedule Planning for Construction Projects, William A. Shunk, AACE Transactions, 1982
114. The Planning Engineer - A Human Element of Planning and Scheduling, Remo J. Silvestrini,
AACE Transactions, 1983
115. Multiproject Scheduling, Andrew Sipos, PE, Cost Engineering Journal, 1990
116. Benefits of Linear Scheduling, Gary Rock Spencer, PE; Rose Mary Lewis, AACE Transactions,
2005
117. Fundamentals Of Critical Path Planning And Scheduling, Anthony R. Stumpo, Jr., Cost
Engineering Journal, 1986
118. Critical Path Scheduling - Philosophy And Experience, Robert B. Vogeler, AACE Transactions,
1962
119. Utility Rate Case - Schedule Analysis, Anthony J. Werderitsch,PE CCE; Clive D. Francis, CCE,
AACE Transactions, 1987
120. Managing A Turnaround Using Computerized CPM, KW Woodcock, Cost Engineering
Journal, 1989
121. Linear Scheduling Fundamentals for Cost Engineers, Carla Lopez del Puerto CCC; Douglas D.
Gransberg PE CCE, AACE Transactions, 2008

Chapter 03: Schedule Control

1. Time Extension In Construction Contracts, Steven G. Revay, CCE, Cost Engineering Journal,
1979
2. Preliminary Time And Overhead Estimates By The One-Third Rule, Marvin Gates, PE CCE;
Amerigo Scarpa, PE, Cost Engineering Journal, 1980
3. Controlling Job Costs Through CPM Scheduling, Philip S. Inglis, AACE Transactions, 1987
4. Modified CPM - A Scheduler's Best Friend, James D. Stevens, PE, Cost Engineering Journal,
1988
5. CPM Schedules In Construction Claims, Robert B. McCullough, Cost Engineering Journal,
1989
6. ODOT's Construction And Control Process, Amir Tavakoli, PE CCE, Cost Engineering Journal,
1991
7. Owner's Reviews of Schedules - How Far Should They Go?, Donald J. Fredlund, Jr.; Fred King,
AACE Transactions, 1992
8. Duration Analysis, Andrew Sipos, PE, Cost Engineering Journal, 1992
9. Third-Party CPM Scheduling - Making It Work, Terry W. Towle, Cost Engineering Journal,
1993
10. Out-Of-Logic Progress, Saad A. Suhail, PE CCE, Cost Engineering Journal, 1993
11. Using Schedule Variance As The Only Measure Of Schedule Performance, Jim W. Short, CCC,
Cost Engineering Journal, 1993
12. Field Project Control - Back To Basics, Edward E. (Ted) Douglas III, CCC, Cost Engineering
Journal, 1993
13. The Effect of Resource Constraints on Project Schedules, Michael R. Just, CCE; James P.
Murphy, AACE Transactions, 1994
14. Project Time-Cost Optimization With the Purchase Time Method, Andrew Sipos, PE, Cost
Engineering Journal, 1998
15. Improving Productivity With Short-Interval Scheduling, Walter J. Strutt, AACE Transactions,
2001
16. Time-for Versus Time-of Performance, Ferdinand Fourie, AACE Transactions, 2003
17. Pre-planning Project Control, Alfred L. Dellon, AACE Transactions, 1969
18. Engineer-Constructor and Client Tools for Cost and Schedule Control, Trent O. Meacham;
Richard L. Patterson, AACE Transactions, 1974
19. Short Cycle Methods for Improved Construction Control, Gui Ponce-Campos; Edward E.
Pauley, AACE Transactions, 1977
20. Reverse Technique for Project Planning/Scheduling Controls, Duane A. Fuller, AACE
Transactions, 1978
21. Construction Control Schedule, Derek Mason, AACE Transactions, 1982
22. Cost-Schedule Integration: Alternatives, Raad H. Hermes, AACE Transactions, 1982
23. ADM or PDM?, Raymond G. Piper, Cost Engineering Journal, 1982
24. Meaningful Scheduling Summaries for Management, Robert R. Cook, CCE, AACE
Transactions, 1983
25. Modern Innovations in Scheduling Techniques, Dr. James E. Rowings, Jr.; John S. Bloess, AACE
Transactions, 1984
26. A Scheduling Tool for Smaller Jobs, Fred Rahbar, AACE Transactions, 1984
27. Back To Basics: Practical Scheduling Guidelines Using CPM Computer Programs, Shiela Toth,
Cost Engineering Journal, 1985
28. Using Milestone and CPM Scheduling Techniques to Decrease Network Size, James R. Walsh,
PE, Cost Engineering Journal, 1988
29. Scheduling Technique to Control Several Minor Modification Projects, Mark A. Andrews;
Kenneth L. Mortensen, PE; Edward J. Kaufmann, PE, AACE Transactions, 1988
30. Is Resource Constrained Project Management Software Reliable, BM Woodworth, Cost
Engineering Journal, 1989
31. Automation of the Scheduling Analysis Process, Dr. Gary Rock Spencer; F. Fred Rahbar, AACE
Transactions, 1989
32. A Mechanical Model for CPM Scheduling Calculations, Abhi Basu, AACE Transactions, 1990
33. Owners Specify Contractor's Estimating/Scheduling Systems, Thomas L. Goff, AACE
Transactions, 1991
34. Management of Networks of Projects, Roland Gareis, AACE Transactions, 1992
35. Automating the Schedule Review Process, John R. Knoke, PE; Jhan Schmitz, AACE
Transactions, 1992
36. A Statistical Evaluation Of The Impact Of Limited Resources On Project Scheduling, BM
Woodworth, Cost Engineering Journal, 1993
37. Improve Schedule Forecasting Via Earned Value, Donald J. Cass, CCE, AACE Transactions,
1994
38. The Cost of Chasing Unrealistic Project Schedules, Christopher F. Michalak, AACE
Transactions, 1997
39. Managing Schedule Changes at Rocky Flats, Todd Bilstein, AACE Transactions, 1999
40. Managing Hospital Design Using CPM, Agustin Dominguez-Larrea; Calin M. Popescu, PE,
AACE Transactions, 2002
41. Notes From Your Technical Board: What is Construction Schedule Control?, Satinder S.
Baweja, CCE, Cost Engineering Journal, 2003
42. Schedule Integration -- Communication Tool Par Excellence, Rohit Singh, CCE, AACE
Transactions, 2003
43. Project Schedules: Simple Checks for Accuracy, David L. Freidl, PE CCE, AACE Transactions,
2003
44. Contract Requirements for Construction Schedule, Win G. Li, PE CCE, AACE Transactions,
2003
45. Scheduling Results: Automation of Remaining Durations, Suhaib M. Anani, AACE
Transactions, 2003
46. Notes from your Technical Board: Managing the Project Schedule, Clive D. Francis, CCC, Cost
Engineering Journal, 2003
47. Contractor's Schedule Submittal: Catch-22, Earl T. Glenwright Jr., AACE Transactions, 2004
48. Construction Baseline Schedule Review and Submittal Timeframe, Win G. Li, PE CCE PSP;
David J. Carter, Cost Engineering Journal, 2005
49. Documenting the Schedule Basis, Edward E. Douglas III, CCC, PSP, AACE Transactions, 2005
50. Managing Multiple Milestones, Ron Winter, PSP, AACE Transactions, 2005
51. Predicting Building Construction Duration, Theresa Keoughan Burrows; Ian Pegg; Joe Martin,
AACE Transactions, 2005
52. Effective Use of Gantt Chart for Managing Large Scale Projects, Pankaja Pradeep Kumar, CCE,
Cost Engineering Journal, 2005
53. Evaluating CPM Reliability: A Linguistic Approach, Lee J. Hobb, Cost Engineering Journal,
2006
54. Proposed Specification Language Regarding Pacing, Kenji P. Hoshino, PSP, AACE
Transactions, 2006
55. Don't Create Variances During Planning, Leah V. Zimmerman, CCC PSP, AACE Transactions,
2006
56. Schedule Analysis Indices, Gary Rock Spencer, PE; Rose Mary Lewis, PE, AACE Transactions,
2006
57. Claims Analysis Nested in Schedule Updates, Christopher Willis Carson, AACE Transactions,
2006
58. RDM - Relationship Diagramming Method, Fredric L. Plotnick, PE, AACE Transactions, 2006
59. Scheduling: The Good, the Bad and the Ugly, H. Lance Stephenson, CCC, AACE Transactions,
2006
60. Making CPM More Transparent, Ronald M. Winter, PSP, AACE Transactions, 2006
61. Innovative Approaches to CPM Scheduling Management, Russell P. Vakharia, CCE PSP, AACE
Transactions, 2006
62. Predicting Construction Duration of Building Projects, Theresa Keoughan Burrows; Ian Pegg;
Joseph L. N. Martin, AACE Transactions, 2006
63. Scheduling Specifications for the 21st Century, Paul Levin, PSP, AACE Transactions, 2006
64. Managing Resource Leveling, Michael R. Nosbisch, CCC PSP; Ronald M. Winter, PSP, Cost
Engineering Journal, 2006
65. Scheduling Practices for Project Success, Andrew F. Griffith, PE, Cost Engineering Journal,
2006
66. How the Critical Chain Scheduling Method is Working for Construction, Jyh-Bin Yang, Cost
Engineering Journal, 2007
67. Applying Earned Schedule Analysis to EVM data for Estimating Completion Date, Ray W.
Stratton, EVP, AACE Transactions, 2007
68. Implications of Schedule Response, John C. Hildreth; Michael C. Vorster, AACE Transactions,
2007
69. Innovative Schedule Performance Measurements, Donna J. Nardella, PE PSP, AACE
Transactions, 2007
70. Scheduling Management: Classifications vs. Levels, H. Lance Stephenson, CCC, AACE
Transactions, 2007
71. Converting Linear Schedules to Critical Path Method Precedence, Douglas D. Gransberg, PE
CCE, AACE Transactions, 2007
72. 4D Modeling: Adding a New Dimension to CPM Scheduling, Vidya C. Dixit, CCE PSP, AACE
Transactions, 2007
73. 4D Scheduling – A Case Study, Abhimanyu Basu, PE PSP, AACE Transactions, 2007
74. Pangs of Progress: Transition From P3 to P5, Jeffery L. Ottesen, PE PSP; J. Scott Palmer, AACE
Transactions, 2007
75. Scheduling Management: Schedule Basis Memorandum, H. Lance Stephenson, CCC, AACE
Transactions, 2007
76. Business Rules in CPM Scheduling Software, Abhimanyu Basu PE PSP, AACE Transactions,
2008
77. Schedule Acceleration - What, Why and How, Sunu Mohan PSP EVP, AACE Transactions,
2008
78. Risk Review of Recovery Schedules, John J. Ciccarelli PE CCE PSP; Matthew Murch, AACE
Transactions, 2008
79. Schedule Constructability Review, Edward E Douglas III CCC PSP, AACE Transactions, 2008
80. Using the Contemporaneous Period Analysis During Projects, Mark F Nagata PSP; Brian
Furniss, AACE Transactions, 2008
81. Construction Scheduling: Keeping Relevance, Amit Sarkar, AACE Transactions, 2008
82. RP 53R-06, Schedule Update Review, Ronald M. Winter PSP, AACE Transactions, 2008

Chapter 04: Schedule Float Ownership

1. Who Owns Float?, Gordon G. Peterman, CCE, Cost Engineering Journal, 1979
2. Float Ownership: Specs Treatment, Dr. Gui Ponce de Leon, PE, Cost Engineering Journal,
1986
3. Qualitative Criteria Combination for Total Float Distribution, Suthi Pasiphol; Calin M.
Popescu, PE, AACE Transactions, 1994
4. Total Float Management in CPM Project Scheduling, Dr. Suthi Pasiphol; Dr. Calin M. Popescu,
PE, AACE Transactions, 1995
5. Schedule Density as a Tool for Pricing Compensable Float Consumption, Michael Ross Finke,
Cost Engineering Journal, 2000
6. Once Upon a Time: A Scheduler's Tale, Lee Hobb, Cost Engineering Journal, 2003
7. Total Float Management: Renovating a Misused and Abused Approach, Anamaria I Popescu
PE; John Jerz, AACE Transactions, 2008

Chapter 05: Cost Control

1. A Contractor's Costing System, J.J. Kelsall, Cost Engineering Journal, 1980


2. Cost Containment and Cost Reduction, Stephen C. Wexler, PE CCE, AACE Transactions, 1985
3. Controlling Project Costs Through Trending, Daniel Becker, CCE, AACE Transactions, 1988
4. Range Estimating: Measuring Uncertainty and Reasoning with Risk, Michael W. Curran, Cost
Engineering Journal, 1989
5. Project Cost Controls: Estimate Preparation Through Claim Defense, Del L. Younker, CCE, Cost
Engineering Journal, 1990
6. Tools of the Trade: Advances in Cost Control and Schedule Management for Commercial
Construction, Robert B. McCullough, PE CCE, AACE Transactions, 1997
7. Competitively-Bid Construction Contracts, Randy R. Rapp, PE, Cost Engineering Journal, 1997
8. Cost Control and Cash-Flow Management: A Simple Approach, Irving M. Fogel, PE, Cost
Engineering Journal, 1997
9. The Dual-Entry Cost Control Method: Why Cost Engineers Should Switch, Wieslaw J.
Jurkiewicz, PE, Cost Engineering Journal, 1997
10. Earned Value Programs for DOE Projects, Donald J. Cass, CCE, AACE Transactions, 1998
11. Optimization for Bidder Profitability and Contractor Selection, Dr. Amarjit Singh, P.Eng.; Max
M. Shoura, PE, Cost Engineering Journal, 1998
12. The Myth About General Conditions, Iftikhar K. Madni, Cost Engineering Journal, 1998
13. Improving the Cost and Schedule Control System, Mohammed S. El-Mashaleh; Allan D.
Chasey, PE, Cost Engineering Journal, 1999
14. Bid Markup Methodologies, Dr. Kwaku A. Tenah; Dr. Carleton Coulter III, PE, Cost
Engineering Journal, 1999
15. Analysis of Change Order Markup Allowances on Stipulated Price Building Contracts, Aminah
Robinson Fayek; Moses Y. Nkuah, Cost Engineering Journal, 2002
16. Up-Front Cost Estimating of Change Orders, Osama Moselhi; Ihab Assem; Khaled El-Rayes,
AACE Transactions, 2002
17. Estimating the Cost of Change Orders, Osama Moselhi, PE, Cost Engineering Journal, 2003
18. How Much is Too Much?, Michael C. Ray, PE, CCE, AACE Transactions, 2003
19. Cost Control Systems: Benefits Provided to Claims Analysis, John J. Ciccarelli, AACE
Transactions, 2003
20. Cost Control Or Complacency, Frederick H. Barnes, AACE Transactions, 1962
21. Capital Project Costs Can Be Controlled, John F. Lovett, AACE Transactions, 1963
22. Can The Application Of The Critical Path Method Assist Cost Control, Alex S. Traub; John R.
Bridgeman; Martin J. Gibson, Jr.; Thomas J. Monahan; Lars O. Soderberg; Robert E.
Templeton, AACE Transactions, 1963
23. Better Project Control Through Coordinated Estimating, Cost Control And Scheduling, J.
Alcabes, AACE Transactions, 1969
24. Cost And Schedule Control Of Engineering Work Using One Data Base & The Network
Technique: A Concept, G. Suhanic, Jr., AACE Transactions, 1969
25. Why Not Cost Control?, A. Patrascu; C. P. Rapier; A. Smolin; H. K. A. Solu, AACE Transactions,
1970
26. Cost Control As A Management Tool, F. Graham, AACE Transactions, 1971
27. Computerized Project Cost Control System Using CPM As A Basis, E. E. Faulkner; S. S. Sriram,
AACE Transactions, 1972
28. Cost Control and the Project Manager, A. E. Garred, AACE Transactions, 1973
29. Capital Cost Control Requires Cost Engineering - Plus!, Edward F. Hensley, AACE
Transactions, 1973
30. A Practical Cost Control System for Force Account Construction Projects, D. A. Zink, AACE
Transactions, 1973
31. Interrelating Project Estimates to CPM Schedules, Albert A. Badger, AACE Transactions, 1974
32. Managerial Attention to Cost and Schedule, John W. Strach, AACE Transactions, 1974
33. Can We Really Control Multi-Million Projects?, Joseph R. Lorenzo; D. Sharad, AACE
Transactions, 1974
34. Cost Control... Where It's At!, William G. Fischer; J. W. Hackney, AACE Transactions, 1975
35. Cost Control in Building Design - Determining the Right Strategy, Peter Brandon, AACE
Transactions, 1976
36. Cost Management Techniques for Construction Projects, Kenneth M. Guthrie, AACE
Transactions, 1976
37. Construction Project Planning and Cost Control, Arnold J. Quakkelaar, AACE Transactions,
1977
38. Cost Control Through Engineering Interface, Jack F. Browder; Collin J. Douthit, AACE
Transactions, 1977
39. Early Warning System Trending Techniques, Charles F. Johnson, CCE, AACE Transactions,
1978
40. Cost Control for the Common Man, Robert F. Smith, CCE; Joseph E. Strasser, AACE
Transactions, 1978
41. Cost Control on Multi-Contract Projects, Dick Sharad, CCE; W. W. Roney, AACE Transactions,
1979
42. Key Cost Control for Capital Projects, John W. Hackney, CCE, AACE Transactions, 1979
43. Cost/Performance Measurement, Melvin F. Rogers, AACE Transactions, 1979
44. Project Cost Control - Behavioral Considerations, Dr. Carl Wolf, CCE; Dr. Phillip F. Ostwald,
AACE Transactions, 1980
45. Cost Control of a Negotiated Contract, Norman H. Matthews, AACE Transactions, 1981
46. The System of Project Control, George Suhanic, AACE Transactions, 1981
47. Project Controls - A Force-Account Approach to CM, Thomas P. Roche, AACE Transactions,
1981
48. Project Control: An Integrated Approach to Construction Planning and Cost Control, Philip W.
Dixon, AACE Transactions, 1981
49. Integration of Cost and Scheduling Systems, Paul B. Shiring, Jr., CCE, AACE Transactions,
1981
50. Cost Controls Used Constructing A Nuclear Station, Yogesh V. Shah; Barnwell R. Linley, CCE,
Cost Engineering Journal, 1981
51. Applications of Cost and Schedule Integration, William R. Crean; Walter F. Adamczyk, AACE
Transactions, 1982
52. A Critique of Integrated Cost/Schedule Systems, William M. Sancho, CCE, AACE Transactions,
1982
53. Cost/Schedule Integration - Panacea or Poison?, Robert R. Cook, CCE, AACE Transactions,
1982
54. An Early Warning System, Paul B. Shiring, Jr., CCE, AACE Transactions, 1983
55. Early Warning Project Cost Control, William C. Hickey, AACE Transactions, 1983
56. Engineering Cost and Schedule Control, James A. Bent, CCE, AACE Transactions, 1983
57. How to Interface Cost and Planning in Offshore Projects, Pierre Boutineau; James-Jacques
Eldin, AACE Transactions, 1983
58. Integration of Cost and Planning: Myth or Reality?, Serge Pressoir, AACE Transactions, 1983
59. Construction Cost Control at the Corporate Level, Rupinder S. Rangar; Bevis A. Ostermann,
AACE Transactions, 1983
60. Cost and Schedule Integration in Process Plants Construction, Chandra S. Murthy, AACE
Transactions, 1983
61. Integration of Cost and Scheduling with Materials Management Function, John C. Cato;
Chandra S. Murthy, AACE Transactions, 1983
62. Cost Control And The Small Construction Company, Keith O. Thomas, Cost Engineering
Journal, 1983
63. Practical Cost Control: Techniques & Timing, J. Peter Bullis, AACE Transactions, 1984
64. Cost Controls for International Development Projects, Raymond H. Lennark, PE CCE, AACE
Transactions, 1984
65. Authority Over Cost Control of Construction, G. E. Ninos; S. H. Wearne, AACE Transactions,
1984
66. Project Cost Control by the Government of Canada, Jean-Guy Hache, AACE Transactions,
1984
67. Cost Control's Missing Link - Progress Measurement, James G. Buck, AACE Transactions,
1985
68. The Cost Control Tree, George Suhanic, PEng, Cost Engineering Journal, 1986
69. The Cost Control Banana, George Suhanic, P Eng., AACE Transactions, 1986
70. Cost Control in a Nutshell, H. K. A. Solu, PE, AACE Transactions, 1986
71. Determining Overrun Probabilities, John W. Hackney, CCE, AACE Transactions, 1986
72. Construction Cost Control Techniques in the United Kingdom, R.B. Watson, Cost Engineering
Journal, 1988
73. Cost Control: The Industrial Owner's View, Leland S. Riggs, Cost Engineering Journal, 1988
74. Capital Cost Control: The Owner's Perspective, Marc T. Richardson, PE CCE, AACE
Transactions, 1988
75. Cost Control and Project Accounting are Getting Married, Serge Pressoir, PE, AACE
Transactions, 1988
76. A System for Monitoring Cost and Schedule Performance of Professional Design Services, Luis
F. Suarez, CCE; Howard A. Green, AACE Transactions, 1988
77. Cost Control - The Tricks and Traps, Leslie E. McMullan, AACE Transactions, 1991
78. Implementing an Owner's Cost Control System, Ron F. Cagle, AACE Transactions, 1991
79. Project Control -- Back To Basics, Robert A. McKim, Cost Engineering Journal, 1990
80. Cost Control In Design/Build, JG Fish, Cost Engineering Journal, 1991
81. Aspects Of Cost Control, Bruce A. Martin, CCE, Cost Engineering Journal, 1992
82. Integrated Cost And Schedule Control, BE Kibler, Cost Engineering Journal, 1992
83. Joint Ventures - The Wave of the Future, F. Sam Griggs, Jr., CCE, AACE Transactions, 1992
84. Cost Control of Engineering Services in Buildings, R. Bruce Watson, AACE Transactions, 1992
85. Applied Cost Control, Don E. Stiner, CCE, AACE Transactions, 1992
86. Proactive Field Level Cost Control, Neil D. Opfer, CCE, AACE Transactions, 1992
87. Construction Cost Control Systems in Saudi Arabia, Dr. Ali A. Shash; Samer Ahmad Zamel,
AACE Transactions, 1993
88. The Project Trend Program, Harry W. Jarnagan, PE CCE, AACE Transactions, 1993
89. Biopharmaceutical Construction, Costs, and Cost Controls, Christopher Law, Cost Engineering
Journal, 1997
90. Improving the Cost and Schedule Control System, Mohammed S. El-Mashaleh; Allan D.
Chasey, PE, Cost Engineering Journal, 1999
91. Project Controls - Where It Fits In, Michael C. Ray, PE CCE, AACE Transactions, 1998
92. Integration of Schedule and Cost Risk Models, Robert V. Wendling; Randal B. Lorance, PE,
AACE Transactions, 1999
93. Project Controls in an International Arena, Desmond G. Pellicena, AACE Transactions, 2000
94. Project Controls: Getting Back to Basics, Michael R. Nosbisch, AACE Transactions, 2002
95. The Project Management Tools: Scheduling and Cost Control Systems, Chris Brous, AACE
Transactions, 1978
96. Cost Control - A Perspective Of Its Future, Marc S. Caspe, PE, AACE Transactions, 1978
97. Practical Cost/Schedule Modeling for CIP Management, John R. Knoke, PE; Jaime de la Garza,
AACE Transactions, 2003
98. Improving Cost Control for Skeptical Managers, Morris E. Fleishman, PE CCE, AACE
Transactions, 2004
99. Cost Management, Allen C. Hamilton, CCE, AACE Transactions, 2004
100. Cost and Schedule Control for Engineering Contracts, Kenneth R. Davey, CCE, Cost
Engineering Journal, 2004

Chapter 06: Management of Change

1. Change Orders Impact on Construction Cost and Schedule, George Suhanic, AACE
Transactions, 1980
2. Estimating and Negotiating Change Orders, Leonard A. McMahon, CCE, AACE Transactions,
1984
3. Cost Guidelines for Change Orders, Ronald F. Cilensek, CCE, AACE Transactions, 1986
4. Construction Projects: Change Order Management, Dr. Calin M. Popescu, AACE Transactions,
1986
5. The Role of the Cost Engineer and the Change Order Process, Alfred L. Dellon, CCE, AACE
Transactions, 1986
6. Change Orders: Causes, Prevention, Control, and Resolution, John H. DeFeis, Jr., Cost
Engineering Journal, 1986
7. Documentation And Verification In The Change Order Process, Alfred L. Dellon, CCE; Dr. Irene
J. Dellon, AACE Transactions, 1988
8. Direct Range Estimating for Change Orders, John R. Knoke, PE; John R. Spittler, PE, AACE
Transactions, 1991
9. Budgeting for Changes in Construction, Stephen F. Rusteika, Jr.; John L. Boomer, AACE
Transactions, 1992
10. Change Order Management For Construction Projects, Fritz Ehrenreich-Hansen, PE CCE, Cost
Engineering Journal, 1994
11. Forward Pricing Impact on Construction Projects, Brian E. Kasen; Victor C. Oblas, PE, AACE
Transactions, 1996
12. Estimating the Cost of Change Orders, Dr. Osama Moselhi, PE, AACE Transactions, 1998
13. Constructability in the Design Firm, James A. Young III, CCC, Cost Engineering Journal, 1998
14. Tracking Changes in Capital Improvement Budgets, John R. Knoke, PE, AACE Transactions,
1999
15. Managing Changes in Large Programs, Ashish Kumar, AACE Transactions, 2000
16. Project Trends and Change Control, Edward E. (Ted) Douglas III, AACE Transactions, 2000
17. Lookout For change Orders, Iftikhar K. Madni; Joseph M. Reed, Cost Engineering Journal,
2001
18. Change Order Evaluation and Resolution Approach, Joseph W. Wallwork, Cost Engineering
Journal, 2001
19. Analyzing the Cumulative Impact of Changes, David D. Reichard; Cheryl L. Norwood, AACE
Transactions, 2001
20. Projects Costing Too Much? Taking Too Long?, Dean Dahlen, AACE Transactions, 2001
21. Notes From Your Technical Board: Managing Change Orders, Sarwar A. Samad, CCE, Cost
Engineering Journal, 2002
22. Constructive Changes, Anthony J. Werderitsch; James E. Krebs, AACE Transactions, 2002
23. Deferred Work Impact: A Solution, Michael A. Hauser, CCC, AACE Transactions, 2003
24. Proactive Change Order Management, Frank Kettlewell, AACE Transactions, 2003
25. Coping with Changes, Stephen O. Revay, CCC, AACE Transactions, 2003
26. Effective Management of Project Change Orders, Edward E. Douglas III, CCC, AACE
Transactions, 2003
27. A Project Control to Meet Project Change, Mark W. Beyer, PE, AACE Transactions, 1988
28. Management Change in the Project Environment, Dr. M. Dean Martin; Dr. Stephen D. Owens,
AACE Transactions, 1988
29. Managing Change: Making the Most of Contingency, Daniel W. Jordan, CCE, AACE
Transactions, 1989
30. Designs: They Are A-Changin', Stanley L. Cohen, PE, AACE Transactions, 1992
31. Change Control and Tracking, Mark T. Chen, PE CCE, AACE Transactions, 1992
32. The Keys to Forecasting - #3 Change Control, James E. Baar; Stephen M. Jacobson, CCC, Cost
Engineering Journal, 2004
33. Controlling Design-Phase Scope Creep, John A. Kuprenas, PE; Elhami B. Nasr, AACE
Transactions, 2003
34. Accelerating Change in Construction Project Delivery, George F. Jergeas, P.Eng., AACE
Transactions, 2004
35. Systematic Contract Change Review, Mark C. Sanders, PE CCE, AACE Transactions, 2004
36. The Effect of Early Freezing of Scope on Project Schedule, Neil N. Eldin, PE, Cost Engineering
Journal, 2005
37. Project Scope Management, Asadullah Khan, Cost Engineering Journal, 2006
38. Change Management for Today's Projects - A Process Approach, Stephen E. Goodman, AACE
Transactions, 2006
39. "Root Causes": The Six Reasons for CHANGE, Robert L. Tichacek, PE, AACE Transactions, 2006
40. Six Steps for Successful Change Order Management, Katherine K. Molly, CCC, Cost
Engineering Journal, 2007
41. Performing Value Analysis on Construction Project Variation Orders, Jamal Al Duaij; Tareq
Awida; A.E. Kollarayam, Cost Engineering Journal, 2007
42. Skills and Knowledge of Cost Engineering: Change Management for EPC Contracting, Donald
F. McDonald, Jr. PE CCE PSP, AACE Transactions, 2007

Chapter 07: Cost Impacts

1. Pricing Construction Claims, Irv Richter, AACE Transactions, 1978


2. Minimizing The Cost Of Delay Related Construction Claims, Dwight A. Zink, AACE
Transactions, 1979
3. The Integration Of Labor Cost Distribution (LCD) & Network Scheduling, Stephen C. Wexler,
AACE Transactions, 1979
4. Escalation: Measuring Its Effect On Project Costs, Frederick L. Blanchard, Cost Engineering
Journal, 1980
5. Material Escalation Claim on an International Project - A Case Study, P. E. Ullmann, AACE
Transactions, 1981
6. Complex Claims: Cost Principles, Models and Behavior, Michael O'Connor, PE, AACE
Transactions, 1984
7. The Measured Mile: Proving Construction Inefficiency Costs, Dwight A. Zink, Cost Engineering
Journal, 1986
8. Proof of Damages in Construction Claims, Richard J. Long, AACE Transactions, 1988
9. Computing Construction Equipment Costs For Government Contracts, William W. Powell, PE,
Cost Engineering Journal, 1988
10. Recovering Added Costs When Superior Knowledge Is Undisclosed, LuRicka L. Kougl, Cost
Engineering Journal, 1990
11. Substantiation Of Costs In Construction Claims, Robert A. Dieterle, CCE; Stanley J. Maziarz,
Cost Engineering Journal, 1991
12. Understanding Contractor Overhead, Ron Cilensek, CCE, Cost Engineering Journal, 1991
13. The Cost of General Conditions, Daniel F. Becker, AACE Transactions, 1993
14. Liquidated Damages for Multi-Prime Projects, Gui Ponce de Leon, PE; Gerald P. Klanac;
William H. Edwards, AACE Transactions, 1993
15. Estimating Construction Claims - A Different Problem, Arthur Monsey, PE, AACE
Transactions, 1993
16. General Conditions Analysis - A Contracting Approach, Lorry T. Bannes, AACE Transactions,
1993
17. Fee Analysis - A Contractor's Approach, Lorry T. Bannes, PE, AACE Transactions, 1994
18. Windfall Profits, Dwight A. Zink, AACE Transactions, 1995
19. Indirect Rate Development for Government Contracts, David A. Norfleet, CCC, Cost
Engineering Journal, 1995
20. Consequential Cost Effects, Paul R. Heather, CCE; Michael D. Summers, CCE, AACE
Transactions, 1996
21. Equipment Compensation in US Government Construction Equitable Price Adjustments, Beni
Warshawsky, Cost Engineering Journal, 1996
22. A Spreadsheet Checklist to Analyze and Estimate Prime Contractor Overhead, Walter B.
Jones, CCC, Cost Engineering Journal, 1996
23. Analyzing the Impact of Change Orders on a Schedule, Jeffrey A. Veenendaal, Cost
Engineering Journal, 1998
24. Practical Analyses in Proving Damages, Jack W. Harris; Andrew Ainsworth, AACE
Transactions, 2003
25. Cost Validation Methodology: New Systems Implementation, Jack W. Harris, AACE
Transactions, 2004
26. Impacts of Modifications to the Change Order Process, G. Steve Gardner, PE; Roy W. Block,
AACE Transactions, 2004
27. Contingency! Who Owns and Manages It?, Peter W. Ripley, CCC, AACE Transactions, 2004
28. The Impact Of Modifications On Major Projects, Ronald A. Gillis, AACE Transactions, 1967
29. Impact: The Real Effect Of Change Orders, Carroll J. Collins, AACE Transactions, 1970
30. Cost Control land Lump Sum Contracting (Coping with all the Changes), John R. Healy, CCE,
AACE Transactions, 1981
31. Calculations of Lost Profits from Lost Business Opportunities, Kris R. Nielsen; Joseph J.
Galeno, AACE Transactions, 1984
32. "Mathews Curve" - A Model for Evaluating Impact, Paul R. Heather, CCE, AACE Transactions,
1989
33. Labor Cost Calculations in International Construction, Dr. Enno Koehn, PE; D. C. Regmi, AACE
Transactions, 1991
34. Predictive Model of Cost Overruns, Dr. Mark O. Federle; Steven Pigneri, AACE Transactions,
1993
35. Model Building Strategy for Construction Cost Overruns, Dr. Mohamed K. El-Choum, AACE
Transactions, 1995
36. Estimating the Cost of Change Orders, Dr. Osama Moselhi, PE, AACE Transactions, 1998
37. Analysis of Change Order Markup Allowances on Stipulated Price Building Contracts, Aminah
Robinson Fayek; Moses Y. Nkuah, Cost Engineering Journal, 2002
38. Estimating Change Orders, -- Cost or Opportunity?, Michael B. Carringer, AACE Document,
1998
39. Estimating Cost Growth From Schedule Changes: A Regression, John V. Bielecki; Edward D.
White, Cost Engineering Journal, 2005
40. Impacts of Project Change Management on Project Cost and Schedule Performances, Yi Zou;
Sang-Hoon Lee, AACE Transactions, 2006
41. The Cost of Change, Michael T. McKeeman; Kurt Rossetti, CCE, Cost Engineering Journal,
2007
42. The Cumulative Effect of Change, Bob M. McCally, AACE Transactions, 2006
43. Design Phase Influences on Construction Change Order Costs, John A. Kuprenas, PE, AACE
Transactions, 2007
44. Pricing Cumulative Impacts of Differing Site Conditions and Design Changes in Construction,
Danielle Bonhomme-Delprato, CCE, Cost Engineering Journal, 2008
45. Reviewing Change Orders 101, Brian S Clare CCC, AACE Transactions, 2008
46. Recommended Ways to Reduce the Number of Change Orders on School and Hospital
Building Projects, Jacqueline Therese Doyle; J Michael Molnar; Robert B Brown PE, AACE
Transactions, 2008
47. Change Management During FEED - Owner's Case Study, Vijay S. Jambhekar; Stephen D.
Weeks, AACE Transactions, 2008

Chapter 08: Productivity Impacts

1. Learning Curves: Theory And Practice, B. R. Elder, AACE Transactions, 1963


2. Learning Curves, Sal M. Kadri, AACE Transactions, 1963
3. Estimating Capital Equipment Construction Costs With The Learning Curve, W. B.
Hirschmann, AACE Transactions, 1965
4. Measurement of Engineering Productivity: An Approach, Sharad Dikshit, AACE Transactions,
1973
5. Effect Of Scheduled Overtime On Construction-Projects, RM Blough, Cost Engineering
Journal, 1973
6. Overtime In Construction, Weldon McGlaun, Cost Engineering Journal, 1973
7. The Use of the Learning Curve, Jack H. Chellew, AACE Transactions, 1974
8. Productivity in Construction - With Relation to Union and Nonunion Operation, John P.
Trimmer, AACE Transactions, 1974
9. Extended Overtime and Construction Productivity, John Smith, AACE Transactions, 1975
10. Factors Affecting Productivity, Leon Morrison, AACE Transactions, 1975
11. Productivity Analysis - A Case Study, Charles J. Peles, AACE Transactions, 1977
12. Construction Productivity and Progress Control, Robert E. Sheffield, CCE, AACE Transactions,
1978
13. Factors Which Influence Productivity on Large Projects, Dr. John D. Borcherding, AACE
Transactions, 1978
14. Developments in Firm-Level Productivity Measurement, Jerry L. Hamlin, CCE, AACE
Transactions, 1978
15. Productivity--An Updated Concept of Management, H. Murray Hohns, AACE Transactions,
1979
16. Major Factors Influencing Craft Productivity in Nuclear Power Plant Construction, John D.
Borcherding; Scott J. Sebastian, AACE Transactions, 1980
17. Analysis of Working Space Congestion from Scheduling Data, Dr. Paviz F. Rad, CCE, AACE
Transactions, 1980
18. Motivation and Productivity of Craftsmen and Foremen on Large Projects, John D.
Borcherding; Douglas F. Garner, AACE Transactions, 1980
19. A More Effective Program to Monitor Productivity, Fred S. Griggs, Jr., AACE Transactions,
1980
20. Construction Labor Productivity During Nuclear Power Plant Construction, William B. Murray,
AACE Transactions, 1980
21. Productivity Control on Large Power Projects, Jude P. Laspa, AACE Transactions, 1980
22. Worker Productivity: Characteristics and Measurement, Ira B. Gregerman, AACE
Transactions, 1981
23. Productivity Defined, Jean-Claude Huot, AACE Transactions, 1981
24. Using Pay to Motivate Construction Job Performance, Alexander Laufer; John D. Borcherding,
AACE Transactions, 1981
25. The Productivity Measurement of Construction Labor Using Work Sampling, Ira B.
Gregerman, AACE Transactions, 1981
26. A Program to Improve Productivity of Field Directed Construction Operations, Michael H.
Casten, AACE Transactions, 1981
27. The Correction Curve, Marvin Gates, CCE; Amerigo Scarpa, AACE Transactions, 1982
28. Understanding the Word "Productivity": What It Means And What Is Behind It, Marjatta
Strandell, AACE Transactions, 1982
29. Improving Construction Productivity: The Case for Motivation, G. Douglas Jenkins, Jr.;
Alexander Laufer, AACE Transactions, 1982
30. Work Sampling And Unit Man-hours, Enno Koehn, Cost Engineering Journal, 1983
31. Significant Elements of Construction Productivity, Dr. Carleton Coulter III; Victor F. Spruill,
AACE Transactions, 1983
32. Construction Productivity Management, R Cardell, Cost Engineering Journal, 1986
33. Learning Curves and Work Interruptions in Construction, Vassilios Frantzolas, AACE
Transactions, 1984
34. Craftsman Questionnaire Sampling for Construction Productivity, Luh-Maan Chang; Dr. John
Borcherding, AACE Transactions, 1984
35. Predicting Productivity, James M. Neil, CCE; Lee E. Knack, AACE Transactions, 1984
36. Management Development Leads to Increased Productivity, Karl W. Haavind, AACE
Transactions, 1984
37. Construction Industry Factors Impairing Productivity, P. Fazio; Don Chutter; G. Bourassa; Dr.
Alan D. Russell, AACE Transactions, 1984
38. The Megaproject And Productivity, MA Muspratt, Cost Engineering Journal, 1984
39. Dollars And Sense Of Productivity, M. R. Goodes, Cost Engineering Journal, 1984
40. Labor Productivity and Manpower Forecasting, Forrest D. Clark, CCE, AACE Transactions,
1985
41. Criteria And Techniques For Meaningful Work Sampling Productivity Studies, James B.
Scarfuto, Cost Engineering Journal, 1985
42. The Measured Mile: Proving Construction Inefficiency Costs, Dwight A. Zink, Cost Engineering
Journal, 1986
43. Labor Productivity in Third World Environments, Dr. James E. Rowings, Jr.CCE; Hashiem,
AACE Transactions, 1986
44. Estimating Labor Productivity, Joseph A. Brown, CCE, AACE Transactions, 1986
45. Methods for Construction Productivity Measurement, Jeffrey S. Russell; Dr. Luh-Maan Chang,
AACE Transactions, 1987
46. Construction Site Operations Perceptions of Tradesmen, Dr. Enno Koehn; Cpt. Michael W.
Pratt; Ryan Cook, AACE Transactions, 1987
47. Increasing Onsite Production, Andrew G. Smith, CCE, AACE Transactions, 1987
48. Activity Survey Impact on Construction Productivity, Stephen G. Goranson, AACE
Transactions, 1988
49. Analytical Techniques to Improve Construction Productivity, Dr. Luh-Maan Chang, AACE
Transactions, 1988
50. Impact of Overtime on Construction, Irwin Bromberg, PE, AACE Transactions, 1988
51. Development and Application of Learning Curves, John F. Synan; Frederick K. Larson, AACE
Transactions, 1989
52. Labor Productivity Factors for Hazardous Waste Sites, Donald J. Cass, CCE, AACE
Transactions, 1989
53. Productivity Improvement Through Communications: C O G, A. Larry Aaron, AACE
Transactions, 1989
54. Productivity Committee Meeting and Productivity - Guess It or Measure It, Ralph P. O'Neal, Jr.
CCE, AACE Transactions, 1989
55. Can the Mystery of Productivity be Solved?, Ralph P. O'Neal, Jr., CCE, AACE Transactions,
1990
56. An Estimate-Independent Productivity Measurement System, A. Larry Aaron; Dr. H. Randolph
Thomas, AACE Transactions, 1990
57. Multiple Improvement Curve Effects Upon Productivity, Dr. Robert C. Creese; B. P. Madhu
Sudhan, AACE Transactions, 1991
58. Impacts And Construction Inefficiency, Dwight A. Zink, Cost Engineering Journal, 1990
59. Determining Labor Productivity: A Case Study, TG Mendel, Cost Engineering Journal, 1991
60. Measuring Construction Productivity, LM Chang, Cost Engineering Journal, 1991
61. The Creation and Use of Labor Productivity Standards among Specialist Subcontractors in the
Construction Industry, John D. Gilleard, Cost Engineering Journal, 1992
62. A Method to Calculate the Productivity Factor, Juan Fornino Gaeta; Robert R. Ruiz Gomez,
AACE Transactions, 1993
63. Productivity: Measurement and Management, Vic Alby, PE, CCE, AACE Transactions, 1994
64. Construction Production Factors in International Areas, Dr. Enno Koehn; Chih-Shing Pan; Jen-
Yuan Liu; Rana P. Pingili; Sirichai Tanratanawong, AACE Transactions, 1995
65. Crew Synchronization in Construction, Anamaria I. Popescu; George E. Gibson, Jr., PE; John D.
Borcherding, PE, AACE Transactions, 1995
66. Labor Productivity Modeling With Neural Networks, Dr. James E. Rowings Jr., PE CCE; Rifat
Sonmez, AACE Transactions, 1996
67. Productivity of Construction in Developing Areas: India, Enno Koehn, PE; V. R. Ganapathiraju,
AACE Transactions, 1996
68. Construction Productivity: Continuous Improvement Is Normal, Dr. Richard E. Larew, PE CCE,
AACE Transactions, 1996
69. TVA's Continuous Outage Productivity Measurement/Improvement, Dr. Hans E. Picard; C.
Robert Seay Jr., AACE Transactions, 1996
70. Shiftworker Fatigue: The $77 Billion Problem, Ed Coburn, Cost Engineering Journal, 1997
71. Production Rates for International Projects in Asia, Dr. Enno Koehn, PE; Moin U. Ahmed,
AACE Transactions, 1998
72. Construction Productivity as a Competitive Edge, Dr. Hans E. Picard, AACE Transactions, 1998
73. Variation in Construction Productivity: Developing Countries, Enno "Ed" Koehn; Sheikh Arif
Ahmed; Satyanarayana Jayanti, AACE Transactions, 2000
74. Productivity Improvement through Work Sampling, James L. Jenkins; Daryl L. Orth, AACE
Transactions, 2003
75. Improving Construction Process Capability, Hans E. Picard, AACE Transactions, 2003
76. Mechanical and General Construction Productivity Results, Daryl L. Orth; James L. Jenkins,
AACE Transactions, 2003
77. Project Productivity Analysis: What Is 1.0?, Charles P. Woodward, PE CCE, AACE
Transactions, 2003
78. Impact of Overtime on Construction Labor Planning, Awad S. Hanna, PE; Kenneth T. Sullivan,
Cost Engineering Journal, 2004
79. Performance Measurement in the UK Construction Industry, Joe Martin, AACE Transactions,
2004
80. Analyzing Construction Productivity, Joseph J. Orczyk, PE, AACE Document, 1999
81. A Case Study: Schedule Forecast Verification With Productivity Assessment, Win G. Li, PE CCE
PSP, AACE Transactions, 2005
82. Construction Productivity in Developing Global Regions, Enno Koehn, PE; Sanjay A. Jagushte,
AACE Transactions, 2005
83. Modeling Labor Productivity in Steel Fabrication, Lingguang Song; Simaan M. AbouRizk,
P.Eng., AACE Transactions, 2006
84. Construction Productivity, James D. Whiteside, II PE, AACE Transactions, 2006
85. Scheduled Overtime and Loss of Productivity: Fact or Fiction? A Business Roundtable Report,
Robert Seals, PSP; Josette Rodriguez, Cost Engineering Journal, 2006
86. Productivity Claims: Beyond ‘Smoke and Mirrors’, John Gerard Boyle, AACE Transactions,
2007
87. The Measured Mile - A Better Way Of Utilizing An Old Tool, Glen R. Palmer, PSP, AACE
Transactions, 2008
88. Monitoring the Adequacy of the Amount and Productivity of Engineering and Construction
Manpower, Dwight A. Zink, CCE, AACE Transactions, 1980
89. An Improved Technique of Productivity Measurements, Steven G. Revay, CCC, AACE
Transactions, 1984
90. Construction Industry Factors Impairing Productivity, P. Fazio; Don Chutter; G. Bourassa; Dr.
Alan D. Russell, AACE Transactions, 1984
91. Construction Productivity: Major Causes of Impact, Charles A. Leonard; Dr. Paul Fazio; Dr.
Osama Moselhi, AACE Transactions, 1988
92. Variance Analysis Labor Cost Report, Joseph Orczyk, PE, AACE Transactions, 1989
93. Impacts And Construction Inefficiency, Dwight A. Zink, Cost Engineering Journal, 1990
94. A Methodology for Measuring Construction Productivity, Foster M. Burton, AACE
Transactions, 1991
95. Use of Productivity Factors in Construction Claims, Robert Dieterle, CCE; Alfred DeStephanis,
AACE Transactions, 1992
96. Labor Productivity Impact of Varying Crew Levels, Donald J. Cass, CCE, AACE Transactions,
1992
97. A Model for Analyzing Jobsite Productivity, David D. Chitester, PE, AACE Transactions, 1992
98. Are Any Construction Overtime "Studies" Reliable?, Dr. Richard Lerew, PE, AACE
Transactions, 1995
99. Labor Productivity, Disruptions, and the Ripple Effect, Dr. H. Randolph Thomas, PE; Dr. Amr
A. Oloufa, PE, Cost Engineering Journal, 1995
100. Use of Statistical Control Charts in Construction, Satinder S. Baweja, CCE, AACE Transactions,
1997
101. Demonstrated Labor Efficiency: An Effective Labor Cost Control and Analytical Tool, Bob M.
McCally, AACE Transactions, 1998
102. Measuring Construction Labor Productivity by Daily Visits, Dr. Iqbal Noor, PE CCE, AACE
Transactions, 1998
103. Quantifying the Effect of Change Orders on Electrical Construction Labor Efficiency, Dr. Awad
S. Hanna, PE; Dr. Jeffrey S. Russell, PE; David Thomack, Cost Engineering Journal, 1998
104. The Effect of Hot Weather on Construction Labor Productivity and Costs, Donn E. Hancher;
Hesham A. Abd-Elkhalek, Cost Engineering Journal, 1998
105. Are Any Construction Overtime "Studies" Reliable?, Richard E. Larew, Cost Engineering
Journal, 1998
106. Statistical Evaluations of Measured Mile Productivity Claims, Michael Ross Finke, Cost
Engineering Journal, 1998
107. Simplified Spreadsheet Solutions: Models for Critical Path Method and Time-Cost-Tradeoff
Analysis, Tarek Hegazy; Amr Ayed, Cost Engineering Journal, 1999
108. Construction Productivity: A Survey of Industry Practices, George F. Jergeas; Mohammad S.
Chishty; Marko J. Leitner, AACE Transactions, 2000
109. Labor Productivity Impacts: A Case Study, Robert D. Kelly, AACE Transactions, 2000
110. Measured Mile Analysis and International Mega-Projects, Dan Crowley; John C. Livengood,
AACE Transactions, 2002
111. Construction Productivity: An Auditing and Measuring Tool, George F. Jergeas; Robert
McTague, AACE Transactions, 2002
112. Productivity Issues, Melanie L. Longmore; Doug Major; Jose L. Maldonado, AACE
Transactions, 2002
113. "Measured Mile" Process Project Controls to Support Equitable Recovery of Production
Inefficiency Claims, Thomas W. Presnell, CCC, Cost Engineering Journal, 2003
114. Assessing Methodologies for Quantifying Lost Productivity, Mark C. Sanders, PE; Mark F.
Nagata, AACE Transactions, 2003
115. Inefficiency, Zartab Z. Quraishi, PE CCE, AACE Transactions, 2003
116. The Productivity Baseline, Ronald Gulezian; Frederick Z. Samelian, AACE Transactions, 2003
117. Measured Mile Labor Analysis, Timothy T. Calvey, PE; William R. Zollinger III, PE, AACE
Transactions, 2003
118. Loss of Learning in Disruption Claims, David A. Norfleet, CCC, AACE Transactions, 2004
119. Going the Extra Mile, Walter Bauer, P.Eng., AACE Transactions, 2004
120. Quantifying Disruption through Simulation and Heuristics, Kenneth G. Cooper; Kimberly Sklar
Reichelt; Jonathan Moore, AACE Transactions, 2004
121. Estimating Lost Labor Productivity in Construction, AACE International, AACE International
Recommended Practice, 2004

Chapter 09: Management and Analysis of Delay


1. Construction Delay Claims - Assessment Defense, A. J. Werderitsch, CCE; Shah Firoozi, AACE
Transactions, 1983
2. How to Save a Delayed Project, Wesley R. Querns, CCE, AACE Transactions, 1986
3. Delay Analysis: A Systematic Approach, Joseph S. Reams, Cost Engineering Journal, 1989
4. Weather-Related Delays on Government Contracts, Michael R. Finke, AACE Transactions,
1990
5. Delay Evaluation Using "Record Schedules", Donald J. Fredlund, Jr.; Gui Ponce de Leon, PE,
AACE Transactions, 1990
6. Substantiation And Use Of The Planned Schedule In A Delay Analysis, Joseph S. Reams, CCE,
Cost Engineering Journal, 1990
7. Selecting As-Planned Base in Project Disputes, Calin Popescu, PE, AACE Transactions, 1991
8. A Cost-Effective Delay Analysis Technique, Mireille Battikha; Sabah Alkass, PE, AACE
Transactions, 1994
9. Delay Analysis - Issues Not for Granted, George E. Baram, CCE, AACE Transactions, 1994
10. Responsibility for Delays After the Expiration of the Contract Time, Gary H. Jentzen, PE; Philip
Spittler; Dr. Gui Ponce de Leon, PE, AACE Transactions, 1994
11. Proving and Pricing Constructive Acceleration Claims, Craig C. Halvorson, CCC, AACE
Transactions, 1995
12. Remedies for Delays in Architectural Construction, Timothy C. McManus; Daniel R. Tishman;
Lisa R. Turnbaugh, AACE Transactions, 1995
13. Construction Delay Analysis Systems, Dr. Janet K. Yates; Hisham Aoude, AACE Transactions,
1995
14. Quantifying and Apportioning Delay on Construction Projects, Lee Schumacher, PE, Cost
Engineering Journal, 1995
15. Construction Project Delay Analysis, Zartab Q. Zafar, PE CCE, Cost Engineering Journal, 1996
16. The Reliability of Critical Path Method (CPM) Techniques in the Analysis and Evaluation of
Delay Claims, Gasan G. Kallo, Cost Engineering Journal, 1996
17. Construction Documentation Used as Indicators of Delays, Hala Elnagar; Janet K. Yates, Cost
Engineering Journal, 1997
18. Contemporaneous Analyses of Excusable Delays, Michael Ross Finke, PE, Cost Engineering
Journal, 1997
19. Delay Damages - Some Owner Defenses, James G. Zack Jr., AACE Transactions, 1998
20. The Five Commandments of Construction Project Delay Analysis, Hamed A. Al-Saggaf, Cost
Engineering Journal, 1998
21. Pacing Delays - The Practical Effect, James G. Zack Jr., AACE Transactions, 1999
22. CPM Schedules in Construction Claims From the Contractor’s Perspective, Robert B.
McCullough, PE CCE, AACE Transactions, 1999
23. But-For Schedules - Analysis and Defense, James G. Zack Jr., AACE Transactions, 1999
24. Interruptible or Continuous Activity Durations?, Dr. Joseph J. Orczyk, PE, AACE Transactions,
1999
25. Delay Claims Management in Construction - A Step-By-Step Approach, M.A. Baki, Cost
Engineering Journal, 1999
26. Delay Analysis - Eliminating the Smoke and Mirrors, Eric Z. Fruchtman, AACE Transactions,
2000
27. The Window Methods of Analyzing Delay Claims, George E. Baram, AACE Transactions, 2000
28. Weather Delays and Impacts, Donald F. McDonald Jr., Cost Engineering Journal, 2000
29. Schedule Delay Analysis, George R. Stumpf, PE, Cost Engineering Journal, 2000
30. But-For Schedules -- Analysis and Defense, James G. Zack Jr., Cost Engineering Journal, 2001
31. Software Review: Schedule Analyzer Pro - An Aid in the Analysis of Delay Time Impact
Analysis, E. Douglas Lucas, Cost Engineering Journal, 2002
32. Analyzing Weather-Related Construction Claims, Osama Moselhi, P.Eng.; Khaled El-Rayes,
Cost Engineering Journal, 2002
33. Schedule Delay Analysis: Modified Windows Approach, Kirk D. Gothand, CCC, Cost
Engineering Journal, 2003
34. Daily Delay Measure: A New Technique to Precisely Identify Delay, John C. Livengood; Brian
G. Laush, AACE Transactions, 2003
35. Business Interruption Claims -- Delay Analysis Considerations, Donald J. Fredlund Jr.; Robert
B. Brown, PE; Frank DeLessio, AACE Transactions, 2003
36. Construction Delay Analysis Method, Jae-Seob Lee, AACE Transactions, 2003
37. Claims Schedule Development and Analysis: Collapsed As-Built Scheduling for Beginners, Vera
A. Lovejoy, CCC, Cost Engineering Journal, 2004
38. Continuous Delay Measurement and the Role of Daily Delay Values, Robert Seals, AACE
Transactions, 2004
39. Calculating Imaginary Numbers: Time Quantification in Acceleration, John C. Livengood;
Christopher R. Bryant, AACE Transactions, 2004
40. Is Noncritical Progress Critical?, William R. Zollinger III, PE; Timothy T. Calvey, PE, AACE
Transactions, 2004
41. Determining the Actual Critical Path, Ronald M. Winter, AACE Transactions, 2004
42. Notes From Your Technical Board: Draft Framework for Recommended Practice for Forensic
Schedule Analysis at the 48th Annual Meeting, Kenji Hoshino, Cost Engineering Journal, 2004
43. Forensic Schedule Analysis, AACE International, AACE International Recommended Practice,
2007
44. Utilities' forced Delays - Controllable or Uncontrollable?, Patricia D. Galloway; Kris R. Nielsen,
AACE Transactions, 1986
45. Project Commencement Delays on Architectural Projects, Stephen F. Rusteika, Jr., AACE
Transactions, 1991
46. Interdependent Analysis of Construction Project Cost and Time, Tadeusz Kasprowicz, AACE
Transactions, 2001
47. Is Noncritical Progress Critical?, William R. Zollinger III, PE; Timothy T. Calvey, PE, AACE
Transactions, 2004
48. The Case of US Projects in Europe - Guidelines to Mitigate Schedule Delay, from the Owner's
Viewpoint, Massimoluigi Casinelli, PE CCE, Cost Engineering Journal, 2005
49. System Dynamic Modeling of Delay and Disruption Claims, William Ibbs; Min Liu, Cost
Engineering Journal, 2005
50. Window Analysis: The Method and the Myth, John J. Ciccarelli, PE, CCE; Mark W. Cohen, PE,
AACE Transactions, 2005
51. Retrospective As-Built Schedule Development, Anamaria I. Popescu, PE; Andrew Avalon, PE,
AACE Transactions, 2005
52. The Link Between Planning and Programming Practice and the Analysis of Delay and
Disruption Claims, Nuhu Braimah; Issaka Ndekugri, AACE Transactions, 2006
53. Current Delay Analysis Techniques and Improvements, Satish B. Mohan; Khalid S. Al-Gahtani,
AACE Transactions, 2005
54. Concurrent Delay Analysis in Litigation, Victor M. Ostrowski, PSP; Michael T. Midgette, PSP,
Cost Engineering Journal, 2006
55. Concentrated Window Analysis Results, Jeffery L. Ottesen, PE PSP, AACE Transactions, 2006
56. Measuring Delay Using the Contemporaneous Period Analysis, Mark F. Nagata, PSP, AACE
Transactions, 2006
57. Delay Analysis Considering Productivity, Jae-Seob Lee, AACE Transactions, 2006
58. Identifying As Built Completion Drivers, Robert B. McCullough, PE CCE; Satinder Singh
Baweja, CCE, AACE Transactions, 2006
59. Total Float Management for Delay Analysis, Khalid S. Al-Gahtani; Satish B. Mohan, Cost
Engineering Journal, 2007
60. Performing Forensic Delay Analyses From Deep Within the Black Tent, Thomas F. Peters, PE
CFCC, AACE Transactions, 2007
61. The Great Debate—TIA vs WINDOWS A Better Path for Retrospective Delay Analysis?, Bruce
Evans Hallock, PSP CFCC; Pradip M. Mehta, AACE Transactions, 2007
62. Additional Practical Applications of the Window Analysis, John J. Ciccarelli, PE CCE PSP, AACE
Transactions, 2007
63. Retrospective TIAs: Time to Lay Them to Rest, John C. Livengood, PSP, AACE Transactions,
2007
64. How Claims Happen When Schedules Become Political – An Actual Court Case Study, Michael
W. Leary, PE; Craig D. Hutchison, AACE Transactions, 2007
65. Delay Analysis Using Linear Schedule in Construction, Jae-Seob Lee, AACE Transactions, 2007
66. Delay Analysis Under Multiple Baseline Updates, Tarek M. Hegazy, P.Eng.; Wail Menesi, AACE
Transactions, 2007
67. Daily Specific As-Built in As-Planned vs. As-Built Schedule Analysis, Svetlana Lyasko, Cost
Engineering Journal, 2008
68. Use of Relational Databases in Forensic Delay Analysis, Faik Burak Evrenosoglu CCE PSP,
AACE Transactions, 2008
69. Delay Analysis Considering Dynamic Resource Allocation and Multiple Baselines, Tarek M
Hegazy P.Eng.; Wail Menesi, AACE Transactions, 2008
70. A Synthesis of Forensic Schedule Analysis Techniques, J Scott Lowe; Mark F Nagata PSP, AACE
Transactions, 2008
71. Forensic Schedule Analysis: Example Implementation, Mark C Sanders PE CCE PSP, AACE
Transactions, 2008
72. Primavera Project Management Software and the Claims Consultant, Anne Marie Tombros;
Sunu Mohan PSP EVP, AACE Transactions, 2008
73. When is the "Critical Path" Not the Most Critical Path?, Murray Woolf, AACE Transactions,
2008

Chapter 10: Concurrent Delay Issues

1. Theories of Concurrent Delays, Gui Ponce de Leon, PE, AACE Transactions, 1987
2. Concurrent Delays in Construction Litigation, Dr. David Arditi; Mark A. Robinson, PE, Cost
Engineering Journal, 1995
3. Concurrent Delays - What Are They and How to Deal With Them?, George E. Baram, AACE
Transactions, 2000
4. Dissecting the Doctrine of Concurrent Delay, Thomas F. Peters, PE, AACE Transactions, 2003
5. Analyzing Concurrent Delay when Using the “Lean” Approach to Scheduling, John R. Spittler,
PE, AACE Transactions, 2003
6. Management of Concurrent Delay in Construction, Abdulaziz A. Bubshait; Michael J.
Cunningham, Cost Engineering Journal, 2004
7. Concurrent Schedule Delay Between Main Contractor and Subcontractor, Massimoluigi
Casinelli, PE CCE; Aldo De Angelis, AACE Transactions, 2007
8. Concurrent Delay Analysis for Litigation, Victor M. Ostrowski, PSP; Michael T. Midgette, PSP,
AACE Transactions, 2005
9. Pacing: An Excuse for Concurrent Delay?, Ronald J. Rider; Thomas E. Finnegan, AACE
Transactions, 2005

Chapter 11: Pricing of Delay

1. The Cost Of Delay In Construction, Daniel M. Uman, AACE Transactions, 1975


2. Construction Delay Claims: Treatment of Extended Overhead, Ronald F. Parisi; Robert J.
Schlunt, AACE Transactions, 1983
3. Minimizing Costs of Delay Construction Claims, Dwight A. Zink, AACE Transactions, 1987
4. Home Office Overhead - Recovery in Construction Delay Claims, Michael R. Just, CCE; Michael
J. Grdgon, Jr., CCE, AACE Transactions, 1992
5. An Alternative to Eichleay, Gui Ponce de Leon, PE, AACE Transactions, 1992
6. Extended Overhead Costs: When Should They Be Paid?, Gary H. Jentzen, PE; Robert S. J.
Berry; Philip Spittler, AACE Transactions, 1995
7. Estimating Delay Damages, Gary H. Jentzen, PE; Robin A. Collins, PE; Dr. Gui Ponce de Leon,
PE, AACE Transactions, 1996
8. Unabsorbed Overhead: Meaning and Method, Beni Warshawsky, Cost Engineering Journal,
1997
9. Determining Shop Burden, Dr. Mark O. Federle, PE CCE; Dr. James E. Rowings Jr., PE CCE,
Cost Engineering Journal, 1997
10. Calculation and Recovery of Home Office Overhead, James G. Zack Jr., AACE Transactions,
2001
11. Alternative Estimation of Home Office Overhead, Jefferey L. Ottesen, PE; Jack L. Dignum,
AACE Transactions, 2003
12. Owner Caused Delay - Field Overhead Charges, Matthew J. Lankenau, CCE, Cost Engineering
Journal, 2003
13. The Real Cost of Mitigating Delays, John J. Ciccarelli, PE CCE, AACE Transactions, 2004
14. Eichleay Update, Paul E. Makris, PE, AACE Transactions, 2004
15. New Ideas in Overhead Recovery, Michael R. Just, CCE; James P. Murphy, AACE Transactions,
1995
16. The Time Value of Project Change, David Chick, Cost Engineering Journal, 1999
17. Forensic Estimating and Impact Cost Determination, Robert H. Pratt, AACE Document, 1998
18. Eichleay and Qualifying Costs, Robert D. Kelly, PSP, AACE Transactions, 2005
19. Liquidated Damages Court Pulls Plug on Utility Contractor's Case, Kurt Rossetti, CCE; Michael
T. McKeeman, Cost Engineering Journal, 2007
20. The Theory of Indirect Costs, David A. Norfleet, CCC, AACE Transactions, 2007
21. Analysis of Delay Damages for Site Overhead, William Ibbs; Long D. Nguyen, Cost
Engineering Journal, 2008
22. The Eichleay Formula - Is Standby the Standard?, Robert A Dieterle CCE, AACE Transactions,
2008

Chapter 12: Mitigation of Claims

1. The Cost Engineer's Role in Construction Claims and Claims Prevention, R. P. Vanden Bosche,
CCE, AACE Transactions, 1981
2. Claims Control/Cost Control - Working Together, Thomas P. Roche, AACE Transactions, 1983
3. Improving Project Management for Claims Reduction, John J. Yanoviak, CCE, AACE
Transactions, 1987
4. The Cost Engineer and Claims Prevention, H. D. Casner, Jr., PE, AACE Transactions, 1988
5. Claims Avoidance and Resolution, William G. Clark, CCE, AACE Transactions, 1990
6. The Ultimate ADR, Roy L. Wilson, PE CCE, AACE Transactions, 1992
7. Practical Dispute Management, James G. Zack, Jr., AACE Transactions, 1994
8. The Benefits Of Constructability Reviews During The Design Of Environmental Capital
Projects, Henry C. Pepper III, PE CCE, Cost Engineering Journal, 1994
9. Claims Prevention: Offense Versus Defense, James G. Zack Jr., AACE Transactions, 1996
10. Constructability in the Design Firm, James A. Young III, CCC, AACE Transactions, 1996
11. An Integrated and Proactive Approach for Avoiding Delay Claims on Major Capital Projects,
Lee Schumacher, PE, Cost Engineering Journal, 1996
12. Measuring Partnered Project Performance, Dr. Douglas D. Gransberg, PE CCE; Howard L.
Reynolds; Jack W. Boyd, AACE Transactions, 1998
13. Partnering in Public Works Construction, Talal S. Abi-Karam, PE, AACE Transactions, 1999
14. The Project Achilles Heel: Misalignment, Gregory J. Skulmoski; Francis T. Hartman, Cost
Engineering Journal, 2000
15. Stakeholder Management on Construction Projects, George F. Jergeas; Erin Williamson;
Gregory J. Skulmoski; Janice L. Thomas, AACE Transactions, 2000
16. Key Partnering Success Factors, Jennifer L. Krahn; George F. Jergeas; Sami Fahmy, AACE
Transactions, 2001
17. Partnering Construction Contracts: A Conflict Avoidance Process, Richard B. Fisher, AACE
Transactions, 2004
18. Construction Process Risk Allocation, Carl A. Erikson; Leroy T. Boyer; Michael J. O'Connor,
AACE Transactions, 1978
19. Pipeline Projects Can Result In Construction Claims - Be Prepared, Roy L. Wilson, PE, Cost
Engineering Journal, 1982
20. Claims And Their Prevention, Howard A. Feldman, Cost Engineering Journal, 1993
21. Effective Risk Management for Remediation Projects, Timothy C. McManus; Robert Goltz, PE;
Lisa R. Turnbaugh, AACE Transactions, 1996
22. ...Project Risks and Risk Allocation, John A. Rutgers; H. Dean Haley, Cost Engineering Journal,
1996
23. How to Reduce Your Project Cost, Ramy Zaghloul Mohamed; Francis T. Hartman, AACE
Transactions, 2000
24. Managing Risk in Design-Build, Talal Abi-Karam, AACE Transactions, 2001
25. Overcoming “Gotchas” Clauses in Construction Contracts, Donald F. McDonald Jr., PE CCE,
AACE Document, 1999
26. Identifying Risk Transfer Traps, Sidney J. Hymes, AACE Transactions, 2005
27. Front-end Specifications: Tool or Trouble?, Sidney J. Hymes, AACE Transactions, 2006
28. How Design Documents Create Claims and What to Do About It, Bryan Payne, PE CCE, AACE
Transactions, 2007
29. A Structured Approach To Least Cost Recovery Scheduling, Christopher W. Carson, PSP, AACE
Transactions, 2007
30. The New Scheduling CPM: Claims Protection Methods, Edward E. Douglas, III CCC PSP, AACE
Transactions, 2007
31. Exculpatory Clauses in Construction Contracts: The Effect of the Use of Exculpatory Clauses
On Contractors Bid Price, Bashar Haddad, AACE Transactions, 2007

Chapter 13: Documentation and Claims Management

1. Document Management for Construction Claims Prevention, John J. Yanoviak, CCE, AACE
Transactions, 1989
2. Construction Claims - Documenting the Facts, George E. Baram, CCE, AACE Transactions,
1992
3. Integrity And Credibility In Construction Dispute Resolution - Documenting And Presenting
The Facts, George E. Baram, CCE, Cost Engineering Journal, 1994
4. Applying Multimedia Technology to Mitigate Claims, Dr. Liang Y. Liu; John R. Knoke, PE, AACE
Transactions, 1995
5. Effective Claims Presentations: Making Your Point, Michael R. Just, CCE; Bill Ogden, AACE
Transactions, 1998
6. Construction Claims: Making It Simple, Michael Marenghi; Anthony J. Werderitsch, PE CCE,
AACE Transactions, 1999
7. Electronic Project Documentation: Legal and Practical Problems, James G. Zack Jr., AACE
Transactions, 2002
8. What Construction Management Seeks in Pictorial Documentation, R. Dennis Foster, AACE
Transactions, 1982
9. Construction Project Document Management Aided by Microcomputers, Donald F.
McDonald, Jr. CCC, AACE Transactions, 1987
10. The Daily Report As A Job Management Tool, DA Pogorilich, Cost Engineering Journal, 1992
11. Notes from your Technical Board: Construction Document Control, Edward E. Douglas III, Cost
Engineering Journal, 2003
12. Project Documents and How They Influence Damages, Patrick Steven Ray, CCC, AACE
Transactions, 2006
13. Electronic Databases for Claims Analysis, Joseph W. Wallwork, PE CCE PSP; Thomas S.
Sinacore, CCE PSP; Eric Schatz, AACE Transactions, 2006
14. Is the Theory of Cumulative Impact a Provable Reality?, Stephen P. Warhoe, PE CCE CFCC,
Cost Engineering Journal, 2007
15. Lost Profits Analysis — Lost Business Opportunities, Jack W. Harris; Louise B. DiCiesare, AACE
Transactions, 2007
16. Causation - How is it Proved?, James E Krebs PE CCE; Michael J Reynolds, AACE Transactions,
2008
17. Managing Evidence Preservation at a Construction Accident Site, John R. Spittler PE; Robert B
Brown PE; John F Lattyak PE, AACE Transactions, 2008

Chapter 14: Claim Recognition and Analysis

1. Identifying Construction Claims, Richard Vanden Bosche, AACE Transactions, 1978


2. Recognition And Documentation Of Construction Claims, Harvey L. Kornbluh, Cost
Engineering Journal, 1982
3. Improve Your Profits by Understanding Claim Analysis, Ignacio Manzanera, CCE; Khaled
Bubshait, AACE Transactions, 1991
4. Analysis Of Construction Disputes And Strategies For Cost Minimization, Thomas R.
Henderson, CCE, Cost Engineering Journal, 1991
5. Claimsmanship - A Current Discussion, James G. Zack, Jr., AACE Transactions, 1992
6. Is Your Project Heading For Trouble? - How To Recognize The Signs, Donald R. Boyken, CCC,
Cost Engineering Journal, 1993
7. Contractors' Protection Against Construction Claims, Dr. George F. Jergeas, PE; Francis T.
Hartman, PE, AACE Transactions, 1994
8. Construction Defects Claims Analysis and Mitigation, Neil D. Opfer, CCE, AACE Transactions,
1997
9. One More Time... Why Design Professionals Are Not Liable to Contractors, Talal S. Abi-Karam,
PE, AACE Transactions, 1999
10. Appraisal of Contractual Claims, Gianluca di Castri, AACE Transactions, 2000
11. Claim Evaluation for Combined Effect of Multiple Claim Factors, Amarjit Singh, Cost
Engineering Journal, 2001
12. Early Warning Signs of Troubled Projects, Donald B. Giegerich, AACE Transactions, 2002
13. Confronting Mold Damage Claims, Neil D. Opfer, CCE, AACE Transactions, 2003
14. Proving Causation, Paul E. Makris, PE, AACE Transactions, 2004
15. Understanding Building Contractor's Claims for Extras, Jerome Reiss, AACE Transactions,
1975
16. Is Your Project Heading For Trouble? - How To Recognize The Signs, Donald R. Boyken, CCC,
Cost Engineering Journal, 1993
17. Claims in the Design/Build Arena, James G. Zack, Jr., AACE Document, 2000
18. Allocating Damages in Construction Defect Cases, David A. Norfleet, CCC, AACE Transactions,
2006
19. False Claims: Road Embankment Construction Proves to Be a Slippery Slope for Contractors,
Kurt Rossetti, CCE; Michael T. McKeeman, Cost Engineering Journal, 2007
20. How to Prove/Disprove “Cumulative Impact” Claims, Anamaria Popescu, PE; Jeffrey L.
Ottesen, PE PSP; Glen R. Palmer, PSP, AACE Transactions, 2007
21. Risk Assessment For Scheduling Acceleration, Khalid S. Al-Gahtani, AACE Transactions, 2007
22. Contractors’ Tort Claims Leave Design Professionals Wondering if Liability is Spiraling Out of
Control, Michael T. McKeeman; Kurt Rossetti, CCE, Cost Engineering Journal, 2007

Chapter 15: Claims Management

1. The Construction Claim, Roy L. Wilson, Cost Engineering Journal, 1979


2. Anatomy of a Construction Claim, R. P. Vanden Bosche, CCE, AACE Transactions, 1981
3. Construction Claims: Justification and Negotiation, William G. Clark, CCE, AACE Transactions,
1984
4. Planning And Scheduling Concepts In The Containment Of Contract Claims, Dr. Gui Ponce de
Leon, PE, Cost Engineering Journal, 1985
5. Issues Related To Construction Claims, Thomas J. Watts, Cost Engineering Journal, 1987
6. Construction Claims And The Problems Of Cost Management, Irvin E. Richter, Cost
Engineering Journal, 1987
7. Public Agency Construction Claims Costing - An Analysis, Michael C. Ray, CCC, Cost
Engineering Journal, 1989
8. Claims Management, Gasan Kallo, Cost Engineering Journal, 1990
9. Claims Management in the Contract Startup Phase, Gui Ponce de Leon, PE, AACE
Transactions, 1991
10. Proactive Defense Against Total Cost Claims, John A. Smith, AACE Transactions, 1992
11. Claims - What and When to Claim, Rosa C. Sotelo, CCE; Ramon Vazques Del Mercado, AACE
Transactions, 1993
12. Dispute Resolution Using Innovative Project Controls, Robert A. Dieterle, CCE; Michael V.
Griffin, PE, AACE Transactions, 1995
13. Managing Changes and Claims on Design Contracts, Stephen F. Rusteika, Jr.; Gary H. Jentzen,
PE, AACE Transactions, 1995
14. Developing Construction Claims for Arbitration: An Arbitrator’s Viewpoint, Dr. Douglas D.
Gransberg, PE CCE; Charles A. Joplin, AACE Transactions, 1999
15. What to Do on Receipt of a Notice of Termination of US Government Contracts, Richard E.
McCracken, Cost Engineering Journal, 1999
16. Claims Avoidance -- A Project Management Primer, Anthony J. Werderitsch; James E. Krebs,
AACE Transactions, 2000
17. Be Prepared for Construction Claims -- Globally, Rohit Singh, AACE Transactions, 2000
18. Claims and Disputes in the Construction Industry, George F. Jergeas, AACE Transactions,
2001
19. Managing Design Errors and Omissions in Construction Projects, George W. Davie; Carl Wolf,
AACE Transactions, 2001
20. Total Cost Construction Claims Tactics, Charles R. McDuff; Michael C. Ray, AACE
Transactions, 2002
21. CPM as a Tool in Claims Management, Rohit Singh, AACE Transactions, 2002
22. Communicating the Dispute, Joseph W. Wallwork, PE CCE, AACE Transactions, 2003
23. Charting a Successful Dispute Resolution, Osmond F. Belcher, AACE Transactions, 2003
24. Disputes and Construction Industry Cultures, Raufdeen Rameezdeen; Nishanthi Gunarathna,
AACE Transactions, 2003
25. Constructive Acceleration: Waking the Sleeping Giant, Thomas F. Peters, PE, AACE
Transactions, 2004
26. Spearin Doctrine’s Effect on the A/E Construction Process, Jean-Paul Prentice, CCE, AACE
Transactions, 2004
27. Charting a Successful Global Dispute Resolution, Osmond F. Belcher, AACE Transactions,
2004
28. Staking Your Claim: Effective Claim Resolution, Philip D. Barnard, PE, AACE Transactions,
2005
29. Daily Observation Reports Prevent Unwanted Costs, William J. Bender, PE, AACE
Transactions, 2006
30. Construction Claims Practice: USA versus Brazil, Joao Otavio Goulart Brizola, AACE
Transactions, 1994
31. You’re Fired!, Timothy T. Calvey, PE, AACE Transactions, 2005
32. Using Artificial Neural Networks for Predicting the Outcome of Canadian Construction
Litigated Claims, Amir Camille Chehayeb; Mohamed Al-Hussein, P.Eng., AACE Transactions,
2006
33. Construction Claims in Egypt: Contrasts and Similarities With Published Literature, Amr A.G.
Hassanein; Waleed M. El Nemr, AACE Transactions, 2007
34. Cost Engineering Applications for Performance Bond Surety Defaults, Lin B. Heath, CCE, Cost
Engineering Journal, 2004
35. The Claims Consultant as a Peacemaker, George F. Jergeas, P.Eng; Stephen O. Revay, CCC,
AACE Transactions, 2006
36. A Critical Analysis of a Roof Dispute With an Emphasis on Project Management, Paul S.
Kupakawana, Cost Engineering Journal, 2006
37. Getting Paid on Private Work Projects, Michael T. McKeeman; Rossetti, Cost Engineering
Journal, 2007
38. Appraisals Resulting from Negligence of Others, James P. Miller, AACE Transactions, 2005
39. Structuring Win-Win Proposal Strategies: Trials and Tribulations, Iqbal Noor, PE CCE; Shankar
Narayan, PE; Matthew Grumo; Tod Hubbard, AACE Transactions, 2007
40. Displaying Complex Technical Data Graphically, John C. Potter, PSP, AACE Transactions, 2006
41. Phased Root Cause Analysis -- A Distinctive View on Construction Claims, L.S. Sandlin; James
R. Sapple; R.M. Gautreaux, Cost Engineering Journal, 2004
42. Subcontract Management Through a Bankruptcy, Retta M. Sandoval; Paul Edwards, PE;
Michael Peek, AACE Transactions, 2005
43. Dispute Resolution - Is There a Right Way?, L. Lee Schumacher, PE, Cost Engineering Journal,
2004
44. Calpine’s Effective Use of Project Control Minimizes and Eliminates Disputes, Christopher B.
Stimpson, Cost Engineering Journal, 2004
45. Determining the Cost to Complete, Joseph W. Wallwork, PE CCE PSP, AACE Transactions,
2007
46. Does Sharing Project Data Create Claims?, William R. Zollinger III, PE; Michael W. Leary, PE,
AACE Transactions, 2005
47. Impact Costs Litigation in Montreal’s Mega-hospitals, Jean-Claude Huot PE, AACE
Transactions, 2008
48. Put Some Punch in Your Pen, Jeffery L. Ottesen PE PSP CFCC, AACE Transactions, 2008
49. The Use of Forensic Animations in Resolving Complex Disruption Claims - A Case Study, Keith
Pickavance, AACE Transactions, 2008

Chapter 16: Negotiation Process

1. How to Successfully Negotiate and Administer Contracts, James A. Bent, CCE, AACE
Transactions, 1985
2. Negotiation - Important in Project Management, Tom E. Krieg, CCE, AACE Transactions, 1986
3. Construction Disputes: A Negotiated Resolution, Anthony J. Werderitsch, PE CCE, AACE
Transactions, 1986
4. Dispute Resolution: Managing Construction Conflict with Step Negotiations, John R.Spittler,
PE; Gary H. Jentzen, PE, AACE Transactions, 1992
5. Organizing the Negotiation Process: Techniques and Factors to Consider When Negotiating
Lump Sum Changes on Behalf of the Owner, Darrel D. Field, PE; Michael Harvey, PE; John
Spittler, PE, AACE Transactions, 1993
6. Negotiation of Settlements - A Team Sport, James G. Zack, Jr., AACE Transactions, 1993
7. How to Lose Money Negotiating a Construction Claim, Michael R. Just, CCE; Brian Torone,
AACE Transactions, 1997
8. Behind-the-Scenes Hurdles to Settlement, Stephen O. Revay, AACE Transactions, 2000

Chapter 17: Alternative Dispute Remedy Process

1. Alternate Methods to Resolve Contract Disputes: Approaches to Effective Prevention,


Management, and Settlement of Construction Contract Claims, S. Leonard Didonato, AACE
Transactions, 1993
2. How To Use Dispute Review Boards For Claims Settlement During Contracts, John A. Smith,
Cost Engineering Journal, 1993
3. Mediation - The Process, Stephen O. Revay, CCC, Cost Engineering Journal, 1993
4. A New Twist on Construction Arbitration Rules, Gordon Beveridge, Cost Engineering Journal,
1996
5. Construction Claims Preparation Under ADR, Douglas A. Findley, AACE Transactions, 1997
6. Resolution of Disputes: The Next Generation, James G. Zack Jr., AACE Transactions, 1997
7. How To Select A Mediator, Zela G. Claiborne, Cost Engineering Journal, 1998
8. Mediative Conciliation, Ifeanyi Tim Anago, AACE Transactions, 2000
9. Are You Prepared for Mediation?, James G. Zack Jr., AACE Transactions, 2000
10. Alternate Dispute Resolution: The Mini-Trial Approach, Michael C. Ray, AACE Transactions,
2000
11. Dispute Review Boards - One View, Juan E. Duran; Janet K. Yates, Cost Engineering Journal,
2000
12. Developing Construction Claims for Arbitration: Two Arbitrators' Viewpoint, Douglas D.
Gransberg, PE CCE; Charles A. Joplin, Cost Engineering Journal, 2000
13. Mock Arbitration: Catfish Contractors Versus NYET County Airport Board, Case No. AACE
2000 SIG001, Robert B. McCullough; Donald F. McDonald Jr., AACE Transactions, 2000
14. Awarding Damages in Construction Claims Arbitration, Douglas D. Gransberg, AACE
Transactions, 2001
15. Arbitration of Disputes in International Construction, Talal Abi-Karam, AACE Transactions,
2001
16. Using the Project Neutral« Process to Resolve Contentious Disputes, Robert A. Dieterle; Alann
M. Ramirez, AACE Transactions, 2001
17. Mapping Dispute Resolution Mechanism with Construction Contract Types, Sai-on Cheung,
Cost Engineering Journal, 2002
18. Dispute Review Boards Help Settle Disputes During Construction, Adele McKillop, P.Eng.,
AACE Transactions, 2003
19. Adding A Neutral Third Part To ADR Process Can Reduce Exposure To Construction Litigation,
Donald R. Cruver, Cost Engineering Journal, 1994
20. Partnering and CE: A Construction Attorney's Perspective, Marc T. Richardson, PE, AACE
Transactions, 1995
21. Partnering Construction Projects - Worth the Time?, Ken A. Rice, AACE Transactions, 1995
22. Partnering: An Innovative and Effective Project Organization Concept, Abdulaziz A. Bubshait,
Cost Engineering Journal, 2001
23. Dispute Review Board Effects on Bid Prices, Kathleen M. J. Harmon, Cost Engineering
Journal, 2004
24. Dispute Resolution Strategy and Decision Analysis, Jon Hoogenboom, PE; W. Stephen Dale,
AACE Transactions, 2005
Chapter 18: Litigation and the Cost Engineer

1. The Cost Engineer As An Expert Witness, Ram L. Bashambu, Cost Engineering Journal, 1981
2. Cost Engineers as Construction Claims Expert Witnesses, Sidney Numerof, AACE
Transactions, 1986
3. Cost Estimates in Litigation Disputes, Donald F. McDonald, Jr., PE CCE, AACE Transactions,
1992
4. Preparing Litigation Estimates For Public Improvements Correction In Land Development,
John D. Bledsoe, PE CCE, Cost Engineering Journal, 1992
5. Expert Witnessing - In Court and Out, David Rosoff, CCE, AACE Transactions, 1994
6. Discovery - Where Does It Fit Into The Adjudication Process?, Michael C. Ray, AACE
Transactions, 2002
7. Depositions - From the Deponent's Perspective, Michael C. Ray, AACE Transactions, 2001
8. Surviving a Daubert Challenge: A CPM Expert’s Perspective, Kenji P. Hoshino, AACE
Transactions, 2003
9. The Liability Labyrinth: How Will Cost Engineering Respond to the Increasing Liability
Problem?, John W. McManus, AACE Transactions, 1978
10. Liability: A New Cost Trap For Architectural/Engineering And Construction Firms, Glenn E.
Hayes; William G. Hundt, Cost Engineering Journal, 1980
11. Testimony Of Expert Witness Upheld, AACE, Cost Engineering Journal, 1982
12. Damage Issues In Construction Claims, Robert A. Dieterle, Cost Engineering Journal, 1985
13. The Cost Engineer's Role in Legal Proceedings, Otto Mendel, CCE, AACE Transactions, 1985
14. Adversarial Cost Engineering, Gideon Samid, Cost Engineering Journal, 2000
15. Forensic Estimating of Project Owner Damages, Robert H. Pratt, AACE Document, 1999

Chapter 19: Project Audits

1. "Here Come the Auditors", Deborah Flannagan, AACE Transactions, 1988


2. Preaward Contract Audits - A Claims Avoidance Procedure, Sherry M. Rice, AACE
Transactions, 1991
3. Government Requirements for Estimating System Audits, Frank D. Postula, PE CCE, AACE
Transactions, 1993
4. EVMS Internal and DCAA Audit Recommendations, Sean T. Regan, CCE, AACE Transactions,
2006
5. Construction Audit - An Essential Project Controls Function, Alexia Nalewaik, CCE, Cost
Engineering Journal, 2007

Appendix A: CFCC Certification Information

1. Certified Forensic Claims Consultant (CFCC), AACE International, Certification Information,


2007

Author Index

Chronological Index

About the Editor

You might also like