IENG300 Midterm Solution Fall 2017
IENG300 Midterm Solution Fall 2017
School of Engineering
Department of Industrial Engineering
In the table below, mark the following statements as either TRUE (T) or FALSE (F). If
you change your answer, scratch previous one and clearly re-write the new one.
Questions with a confusing answer will automatically get a zero mark. Wrong answers
do not penalize correct ones. The weight for each question is 1 point.
1. A major portion of the project work, both physical and mental, takes place during the
conceptualization stage of the Project Life Cycle.
3. There can be two or more parallel critical paths, all having exactly the same completion time.
4. The term "work breakdown structure" refers to a failure in the work structure.
5. When the client makes a change in the project, the baseline of the project should be changed
accordingly.
6. Control charts and Gantt charts are tools used to monitor the project’s time performance.
8. In an AoN network, if two activities have the same description, you can use the same
identification number for both.
9. A labor cost is usually a direct cost, while the project manager salary is a direct overhead cost.
10. The evaluation of the risk value must occur at the identification phase of the risk management
process.
Question 1 2 3 4 5 6 7 8 9 10
Answer F F T F T T F F T F
Choose the correct answer. Only one answer may be marked. Questions with more than
one answer will automatically get a zero mark. Wrong answers do not penalize correct
ones. The weight for each question is 2 points.
1. Projects:
a. Do not usually produce something new.
b. Do not have a specific duration.
c. Are not repetitive.
d. Do not have objectives.
3. After the government issued a new law forcing all universities to have 50% of their
electric power generated by solar panels by end of year 2020, LIU started sending
requests for proposals for the design & installation of a solar panels systems across all
its campuses. These projects are classified under:
a. Strategic projects.
b. Compliance projects.
c. Risky projects.
d. Operational projects.
5. You have been assigned as the Project Manager of an engineering project. One of the
project documents available to you lists down all the risks in a hierarchical fashion.
What is this document called?
a. Risk management plan.
b. List of risks.
c. Monte Carlo diagram.
d. Risk breakdown structure (RBS).
6. Projects are usually classified into all but one of the following categories. Which one is not
one of the typical classifications?
a. Strategic projects.
b. Compliance projects.
c. Political necessity projects.
d. Operational projects.
7. A series of coordinated, related, multiple projects that continue over extended time intended to
achieve a goal is known as a:
a. Strategy.
b. Program.
c. Campaign.
d. Venture.
9. Imad is the Project Manager of a team in charge of installing a new operating system
on a hospital IT network. Before implementing the project, Imad’s team tested the new
operating system on a smaller isolated network. By doing so, they discovered a variety
of problems and were able to come up with solutions prior to implementation. This
testing can be considered an example of:
a. Mitigating risk.
b. Avoiding risk.
c. Transferring risk.
d. Retaining risk.
10. During the definition phase of the project life cycle (PLC), it is important to:
a. Determine the project scope.
b. Develop the project plan.
c. Initiate change requests.
d. None of the above.
13. An important tool that is used in the change management process would be:
a. Risk request.
b. Change request.
c. Change creep.
d. Scope modification request form.
14. The Failure Mode Effect Analysis (FMEA) involves calculating the value of a project
risk through the multiplication of the following factors:
a. (Probability) x (detection).
b. (Probability) x (impact) x (detection).
c. (Impact) x (detection).
d. (Likelihood) x (trigger).
15. The table where project risks are tracked and controlled is referred to as:
a. Risks register.
b. Changes register.
c. Risks severity matrix.
d. Risks Breakdown Structure (RBS).
Your company has set up a weighted scoring matrix for evaluating potential
projects. Below are five projects under consideration:
Question 3 Solution
a) Using the provided scoring matrix, which project would you rate the
highest? Which project would you rate the lowest? (4 points)
b) If the weight for “Risk” is changed from 2 to 4, will the project selection
change? What are the three highest weighted project scores with this new
weight? (4 points)
The project office (PO) of your company is asking you to address the questions in the
solution section. The activities time estimates and their dependencies are summarized in the
following table:
Question 4 Solution
A,B,C,F,G,H
Critical activity
SL= 0
Burst
Merge
Parallel to E
WindPower assigned you as the Project Manager on this project, and provided you with the below
information:
The client, NorthBuild, wants the project to be completed by 27/07/2018.
The client, NorthBuild, wants to see time and cost details of the activities.
The 1.5 MW wind turbine should be delivered by 15/05/2018 from Spain.
WindPower does not have enough experience in installing wind turbines with capacities
above 1 MW. That’s why senior Management requested you to have a strong focus on the
project and to use all the expertise available in the functional departments of WindPower.
When connecting the power cables from the wind turbine to the residential complex, the
cables should be laid underground. This will involve Excavation, Cable Laying and
Backfilling over a distance of 1 Km.
The client, NorthBuild, is also hoping to sell renewable energy from this wind turbine to the
national power grid of Electricité du Liban (EDL), by providing cables connection between
the wind turbine and a nearby EDL substation. WindPower stated that they cannot execute
this part, because of its complexity.
Based on the presented facts, address the questions in the solution section.
Question 5 Solution
b. You were requested to participate in completing the project scope checklist below. Fill in the
blank items of the checklist below (Some items were already filled by other project team
members). (4 points)
c. What would be the recommended approach for cost estimations? Justify your answer.
A Bottom-Up approach is preferred because the client wants to see time and cost details of the
activities. Also, time is an important factor because the wind turbine will be delivered almost 2
months before the project completion date. This is why refined time and cost estimates should
be made using a bottom-up approach based on the elements of the WBS.
d. Identify 2 risk events that might impact the scope, cost, time, or quality of this project:
e. Propose a risk response (i.e. Avoid, Mitigate, …) along with planned action and contingency
for each one of the above risks. (8 points)
f. Would you include risk management plan in your baseline plan? Justify your answer. (5
points)
Is a proactive rather than a reactive approach which allows the PM to foresee risks before
they occur?
Reduces surprises and negative consequences.
Prepares the PM to take advantage of appropriate risks.
Provides better control over the future.
Improves chances of reaching project performance objectives within budget and on time.